Water. Ecuador. 2. Team 11 . Josiah Dobson Brett Nicholson Travis Befus. Objective. To develop an elevated water storage and pumping system that can be implemented in rural communities worldwide - PowerPoint PPT Presentation

Citation preview

Page 1: Water

Water2Ecuador

Josiah Dobson Brett Nicholson Travis Befus

Team 11

Page 2: Water

Objective To develop an elevated water storage and

pumping system that can be implemented in rural communities worldwide

Focus on providing a reliable system for two communities in Ecuador through HCJB

Page 3: Water

Design Norms Stewardship-Use only materials local to Ecuador

-Efficient use of all resources

Transparency-maintain open communication with our client, HCJB

-Make sure the communities we are serving are aware of developments

Page 4: Water

Locations Washintsa-15 family community-Currently has no water system-Requires a complete distribution system, tower and pump design

Iniayua-25 family community-Current tower is on the verge of collapse due to lack of maintenanceand poor material construction-Tower does not meet capacity requirements

Page 5: Water

DesignTower-Tower will be built using steel or wood materials-Modeling will be conducted using StaadPro and RAM Steel-Must provide sufficient storage capacity and pressure to meet the demands-Must withstand the climate elements

Pump-Solar powered pump must meet average daily flow conditions-Determine optimum number and size of solar panels based on user demand and weather conditions

Distribution System-A complete distribution system will be design for Washintsa-Modeling will be conducted using EPANET

Page 6: Water

Constraints Weight and Size Constraints-Materials not from village must fit in a small aircraft-Maximum material length is 6 feet-Cannot exceed 800 pounds per plane load-largest hard plastic tank that can fit is 145 gallons

Simple Construction-Constructed without the use of electricity-Constructed with unskilled labor force

Cost

Page 7: Water

Travel to Ecuador Team plans to travels to Ecuador in January for 9

days

Visit the two sites to meet with the end users and collect data