Upload
anonymous-8ooqmmons1
View
217
Download
0
Embed Size (px)
Citation preview
7/27/2019 Wastewater - Primary
1/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
1
TOPIC 3: WASTEWATER SYSTEMS
TABLE OF CONTENTS
PREVIEW ......................................................................................................................... 2Introduction ................................................................................................................ 2Objectives ................................................................................................................... 2Readings ..................................................................................................................... 2
3.1 COMPONENTS OF WASTEWATER SYSTEMS .................................................... 33.2 CHARACTERISTICS OF WASTEWATER .............................................................. 3
3.2.1 Quantity - Wastewater Flow Determination...................................................... 43.2.2 Water Quality .................................................................................................... 83.2.3 Variations in Wastewater Quantity and Quality ................................................ 9
3.3 OUTLINE OF A WASTEWATER TREATMENT PLANT .................................... 113.4 PRELIMINARY TREATMENT ............................................................................... 13
3.4.1 Screens ............................................................................................................. 133.4.2 Grit Chambers ................................................................................................. 223.4.3 Other ................................................................................................................ 35
3.5 PRIMARY TREATMENT ........................................................................................ 353.5.1 Primary Sedimentation Tanks ......................................................................... 35
7/27/2019 Wastewater - Primary
2/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
2
PREVIEW
Introduction
This topic introduces the main principles of wastewater systems focusing particularly on
technologies of waste water treatment systems.
Objectives
After completing this topic you will be able to:
understand functioning of wastewater systems, particularly wastewater
treatment plants;
conceptually outline several types of wastewater treatment plants:
conventional, modern and alternative;
design a conventional wastewater treatment plant; and
understand interaction between wastewater systems and other UWM systems
(e.g. water supply systems and stormwater management systems).
If you are not convinced that you can achieve each objective after studying the
materials, you should re-read the relevant parts of the Study Guide and associated
reading.
Readings
This summarises the suggested readings for the topic.
SUGGESTED
Tchobanoglous,Wastewater Engineering:
Treatment and Reuse, Metcalf & Eddy, 2002
Environmental Engineering, Gerard Kiely,McGrow Hill, 1997
Introduction to Environmental Engineering,
Mackenzie Davis & David Cornwell, McGrow
Hill, 1991
http://www.pub.gov.sg/research/Pages/default.
aspx?
7/27/2019 Wastewater - Primary
3/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
3
3.1 Components of Wastewater Systems
Municipal wastewater is collected from our homes and industrial plants via a sewage
collection system. In this context, it is defined as everything from the point of a
wastewater discharge in urban areas to the point of its disposal into a receiving water
body (e.g. the wastewater system of Melbourne is presented in Figure 3.1 to the left).
The system comprises of the following:
collection in households municipal sewage pipes and pumps, wastewater treatment plant, disposal of treated water into receiving water bodies, disposal of sewage sludge.
Figure 3.1: Diagram of wastewater system and separate stormwater system in
Melbourne.
In Australia, stormwater and municipal wastewater are collected in separate systems(Fig. 3.1), while in Europe combined systems are more common (stormwater and
wastewater are collected in one pipe).
3.2 Characteristics of Wastewater
Sewerage systems are designed to collect, transport, treat, and discharge sewage. These
requirements involve hydraulicprocesses and treatmentprocesses. Therefore, before
we start designing the systems, we have to determine the sewage quantity (flow rate)
and its water quality.
7/27/2019 Wastewater - Primary
4/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
4
In most cases, the hydraulics is reasonably basic. Nevertheless, a sound understanding
of the hydraulic processes is necessary to ensure efficient, economical, and safe
operation.
3.2.1 Quantity - Wastewater Flow DeterminationThe main components of municipal wastewater are:
Domestic wastewater - discharged from residences, commercial, institutional,and other facilities.
Industrial wastewaterdischarges from industrial plants. Inflow/infiltration - stormwater runoff which finds its way into the sewer, and
steady leakage from groundwater.
Average Dry Weather Flow (ADWF) in litres/day, that presents flow in pipes without
any infiltration, is calculated as:
ADWF=Domestic + Industri al [l /day] (3.1)
Domestic Wastewater
Principal sources are residential and commercial districts. Other sources include human
waste from institutional and recreational facilities.
Domestic discharge is usually expressed as:
Domestic = PE (F low discharged per capita) [l/day] (3.2)
where PE is Population Equivalent.
Currently, it is assumed that
Flow discharged per capita = 225 l/day/capita (3.3)
General PE values for different establishments are presented in Table 3.1
I ndustrial Wastewater
Industrial use varies widely, according to the nature of the manufacturing process. There
is no foolproof procedure for predicting industrial discharges. Consequently, careful
measurements are required.
Flow rates vary depending on:
type of industry,
size of industry,
degree of water re-use, and
on-site wastewater treatment methods.
7/27/2019 Wastewater - Primary
5/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
5
Table 3.1: Recommended PE values for different establishments.
Wastewater flow projections may be based on water use. However, it is usually
estimated according to some of the following assumptions:
the typical design value for industrial districts with no wet process industries is
30 m3/ha/day;
the same for light industry is 20 m
3
/ha/day;for industries without internal re-use programmes 85-90% of water used will
become wastewater; for large industries with internal water re-use programmes,
separate estimates must be made;
average domestic wastewater contributed from industrial activities may vary
from 30 to 95 l/capita/day;
special attention needs to be given to projections of future industrial flows; and
industrial flows are particularly troublesome in small sewage treatment plants
where there is limited capacity to absorb shock loadings.
7/27/2019 Wastewater - Primary
6/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
6
Infiltration
Sewers are not watertight. They may be damaged by ground movement, traffic & road
construction, tree roots, age, or illegal connections. Therefore, due to infiltration during
wet weather, flow rates in sewage pipes are much higher than the Average Dry Weather
Flows. As a consequence of the above, infiltration may be present even during dry
weather; it occurs mainly through seepage into sewers laid below the water table.
It is impossible to entirely avoid faulty joints, cracked sewer pipes, and damaged
manhole connections. However, infiltration is greatly reduced by use of proper
materials, construction techniques, supervision, and field testing.
Inflow/infiltration has a number of components as follows:
Surface infiltration rain water entering a sewer system from the ground
through defective pipes, pipe joints, connections, or manhole walls;
Steady inflow - water discharged from cellar and foundation drains, cooling-water discharges, and drains from springs and swampy areas. It is a steady flow
and is identified and measured along with infiltration;
Direct inflow - inflows that have a direct stormwater runoff connection to thesewer and cause an almost immediate increase in wastewater flows. Possible
sources are: roof leaders, yard drains, manhole covers or cross-connections from
storm drains.
Figure 3.2 presents different types of flow in sewage pipes. A part of the terms
described above flowrate also shows the following:
Total inflow - sum of the direct inflow at any point in the system plus any flowdischarged from the system upstream through overflows, pumping station
bypasses, etc.
Delayed inflow - Stormwater runoff which my require several days or more todrain through the sewer system. This can include the discharge of sump pumps
from cellar drainage as well as the slowed entry of surface water through
manholes in ponded areas.
Infiltration may vary during the year in response to groundwater levels. Normally, it is
estimated during the early morning hours when water use is at a minimum and the flow
consists essentially only of infiltration. This is particularly suitable for small systems
where travel times through the system are short, however not so suitable for largesystems where travel times may be long.
Inflow rates are determined by using a network of continuous flow meters operating
before and during a significant storm event. It is determined from the flow hydrograph
by subtracting the normal dry-weather domestic and industrial flow and the infiltration
from the measured flow rate.
For design purposes, the maximum infiltration rate for well constructed sewers is
I nfi ltration = 50 l/mm/km/day D L [l /day] (3.4)
7/27/2019 Wastewater - Primary
7/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
7
whereD is the pipe diameter, andL is the pipe length. Although design values are given
in the standards, there are many factors which can affect infiltration: length of sewers,
area served, soil and topographic conditions, population density (which affects the
number and total length of house connections).
Sewers first built in a district usually followed water courses in the bottom of valleys.
They are often close to (or even below) the bed of the stream. As a result, these old
sewers can receive large infiltration flows. Newer sewers are often built at higher
elevations and receive comparatively less infiltration
It is usually found that:
only a small part of the collection system contributes most of theinflow/infiltration;
typically about 75% of the inflow comes from 20 - 30% of the system; andtypically about 75% of the infiltration comes from 40% of the area.
There is an attempt to produce watertight sewer systems. They are sometimes known as
Smart sewers. The benefits of a leak-free or tight system include:
no overloaded or surcharged sewers and the associated problems of wastewater
backups and overflows,
more efficient operation of wastewater treatment facilities, and
use of sewer hydraulic capacity for wastewater instead of inflow/infiltration.
Figure 3.2: Components of wastewater flow
7/27/2019 Wastewater - Primary
8/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
8
3.2.2 Water Quality
NOTE: Water quality depends on the source!
Domestic Wastewater
Typical data on the individual constituents found in domestic water are reported in
Table 3.2. Main water quality characteristics of domestic waters are: BOD5
(biochemical oxygen demand) and SS (suspended solids). Some other constituents
that are important for biological treatment should be also determined (Ca, Cu, Fe, Mg,
Zn, Mn, Sulphates). If the inflow from industrial wastewater is high the characteristics
of municipal waters (collected by the drainage system) could be different from those
presented in Table 3.2.
Table 3.2: Main water quality characteristics of domestic wastewater
Concentration
Constituent Strong Medium Weak
Solids, total :
Dissolved, total
Fixed
Volatile
Suspended, total
Fixed
Volatile
Settleable solids, mL/LBiochemical oxygen demand, 5-day, 20C
(BOD5, 20C)
Total organic carbon (TOC)
Chemical oxygen demand (COD)
Nitrogen (total as N) :
Organic
Free ammonia
Nitrites
Nitrates
Phosphorus (total as P) :Organic
Inorganic
Chloridesb
Alkalinity (as CaCO3)b
1200
850
525
325
350
75
275
20400
290
1000
85
35
50
0
0
15
510
100
200
150
720
500
300
200
220
55
165
10220
160
500
40
15
25
0
0
8
35
50
100
100
350
250
145
105
100
20
80
5110
80
250
20
8
12
0
0
4
13
30
50
50a
mg/L = g/m3
bValues should be increased by amount in domestic water supply
I ndustrial Wastewater
Numerous materials can be found in industrial waste that can cause pollution. The most
common are: anorganic salts, acids or alkalis, organic matters, suspended solids,
7/27/2019 Wastewater - Primary
9/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
9
floating solids and liquids, colour, heated water, toxic chemicals, radioactive materials,
foam-producing matter, and microorganisms.
Quality of industrial wastewatervaries widely with the type of industry and it usually
includes:process waste from manufacturing,
water from heating and cooling,
wash water, and
employees sanitary waste products.
Typical quantities for process wastewater from four different manufacturing industries
are presented in Table 3.3. The wastewater is more specific for each industry and can
range from wastewaters with high BOD5 (meat, food industry) to inorganic and toxic
waste (textile, chemical and plating industry).
Table 3.3: Industrial process wastewater quality
Parameter Food Meat Plating Textile
Volume (L)/capita/day - - - -/tonne prod. 10,000 12,000 - 100,000% runoff - - - -
MPN (106
/100mL) 0 - 0 0
BOD5
1,200 640 0 400
COD - - - -TOC - - - -Susp Solids 700 300 0 100Diss Solids - 200 - 1,900Total N 0 3 0 0Total P 0 - 0 0pH - 7.0 4 or 10 10Copper 0.29 0.09 6 0.31Cadmium 0.006 0.011 1 0.03Chromium 0.15 0.15 11 0.82Nickel 0.11 0.07 12 0.25Lead - - - -Zinc 1.08 0.43 9 0.47
Food: canning factory (pickles, beets tomatoes, pears);Meat: meat processing (poultry plant with no manure or blood recovery);
Plating: wastes are acidic with chromate baths, alkaline with cyanide baths;
Textile: textile mill (spun cotton yarn processed into cotton goods)
3.2.3 Variations in Wastewater Quantity and Quality
The principle factors for loading variations are the following:
(i) established daily people habits (short-term variations);
(ii) seasonal activities (longer-term variations); and
(iii) industrial activities (both short and long term, plus shock loads).
7/27/2019 Wastewater - Primary
10/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
10
Daily variations due to established people habits are presented in Figure 3.3. A double-
peaked diurnal pattern is common, depending on the mix of commercial, industrial, and
domestic connections. Diurnal patterns are regular because of:
the same daily pattern for Monday to Friday flows;the weekend patterns differ from weekdays; and
Saturdays and Sundays may be different from each other.
Figure 3.3: Daily diurnal patterns
Both quantity and quality
of industrial wastewater
may vary significantly
throughout the day.
Problems with short-term
loading from one
particular part of the
manufacturing processcan cause problems to
treatment plants. Seasonal
variations are typical for
food industry, as shown
in Figure 3.4.
When industrial wastes
are to be accommodated in municipal collection and treatment facilities, special
attention should be given to developing adequate characterisations and projections.
Figure 3.4: Seasonal variations of flow in a small town
with a large peaches cannery plant.
7/27/2019 Wastewater - Primary
11/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
11
Peak Flows
Peak hourly flow must be used in design of sewers, pumping stations, and treatment
plant components. It is determined as:
Peak Flow = PFF ADWF (3.5)
where ADWF is the Averaged Dry Weather Flow (domestic + industry) and PFF is the
Peak Flow Factor. The PFF depends on the size of the development and is generally
calculated as:
1000
7.4 11.0
PEPwhere
PPFF
(3.6)
where PE is the Population Equivalent (Table 3.1) and P is the population equivalent inunits of 1,000. Thus, the PFF for different sizes of a development is:
PE = 1,000 PFF = 4.7
PE = 10,000 PFF = 3.6
PE = 300 PFF = 5.4
If commercial, institutional, and/or industrial wastewaters make up > 25% of all flows
(excluding infiltration) consideration should be given to estimating PFFs for each flow
category.
For industrial wastewater the PFF is estimated on the basis of:
average water use;
number of shifts worked; and
pertinent details of plant operation.
3.3 Outline of a Wastewater Treatment Plant
The products of a wastewater treatment plant are:
an effluent of accepted quality in relation to a receiving water course, and
a sewage sludge that contains all pollutants.
There are the following major categories for municipal wastewater treatment:
(1)Preliminary (or pre-treatment);(2)Primary treatment;(3)Secondary treatment;(4)Tertiary (or advanced treatment), and(5)Sludge treatment.
Efficiencies of the main categories are listed below:
7/27/2019 Wastewater - Primary
12/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
12
Primary treatment: Removal of 60% of TSS and 35% of BOD5. It removes the
pollutants that either settle or float by screening and sedimentation methods.
Secondary treatment: Removal of 85% of BOD5 and more than 85% of TSS. Itremoves BOD5 and SS by biological processes.
Tertiary treatment: 99% of BOD5 and phosphorus, all TSS, and bacteria, 95%of nitrogen are now removed. The pollutants are removed by chemical treatment
and filtration, or by land infiltration treatment.
Traditional treatment plants have no tertiary treatment as shown in the case of the
Melbourne Eastern Treatment Plant in Figure 3.5. They treat wastewater usually to
TSS=30 mg/l and BOD5 = 20 mg/l. However, modern treatment plants have a tertiary
treatment for further removal of pollutants as shown in Figure 3.6.
Figure 3.5: Diagram of a typical secondary treatment plant (Melbourne).
7/27/2019 Wastewater - Primary
13/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
13
Figure 3.6: Diagram of a tertiary treatment plant.
3.4 Preliminary treatment
Preliminary or pre-treatment is aimed to provide protection to the wastewater treatment
plant, but it has little effect on the reduction of BOD5 and nutrients. The main devices
used in the preliminary treatment are discussed below. However, be aware that some of
these devises could also be used at other stages of the treatment process chain.
The most common devices used in preliminary treatment are screens and grit chambers.
3.4.1 Screens
Screening of sewage is one of the oldest treatment processes. Although used mostly in
the preliminary treatment they are also used in other stages of treatment. Therefore,
screens are classified as:
primary screens,
secondary screens, and
microstrainers.
In this section, primary and secondary screens are discussed, while microstainers are
discussed later (they are used in the secondary treatment stage).
7/27/2019 Wastewater - Primary
14/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
14
Primary Screens
Primary screens (Fig. 3.7) are typically located
at the inlet to sewage treatment plants and also
at the inlet to pumping stations. They are
designed to remove coarse debris such as rags,
solids, and sticks which could cause damage by
damaging pump impellers or interfering with the
downstream performance in sewage treatment
plants. They have to be cleaned either manually
or mechanically.
Primary screens are normally classified as:
Coarsewith openings of 50-150 mm;
Mediumwith openings 20-50 mm.
The following factors need to be taken into account in screen design:
the strength of the screen material and its resistance to corrosion,
the clear screen area (this is related to cleaning),
the maximum flow velocity through the screen to prevent dislodging ofscreenings,
the minimum velocity in the approach channel to prevent sedimentation of
suspended matter, and
the head loss through the screen.
Secondary Screens
Secondary screens have smaller openings than primary screens and are installed after
the pumping section and ahead of the grit chamber. Their purpose is to remove material
such as paper, plastic, cloth, and other particles which may affect the treatment process
downstream; and to minimise blockages in sludge handling and treatment facilities.
Secondary screens are analysed and designed in the same way as primary screens. The
only difference is in the maximum clear spacing of bars. This is typically around 12
mm, although openings as small as 6 mm have been used in practice.
Hydraul ics of Screens
The analysis of a screen involves the determination of the head loss across it. The head
loss is primarily a function of the flow velocity and the screen openings, but may also
be dependent on bar size, bar spacing, and the angle of the screen from the vertical.
Several equations have been developed, but only those most widely used are considered
here.
Figure 3.7: A primary screen.
7/27/2019 Wastewater - Primary
15/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
15
Figure 3.8: Schematic of Sloping Bar Screen
Figure 3.8 shows a schematic of a sloping bar screen. Application of Bernoullis
equation yields:
lossesg
vhg
vh 22
2
2
2
2
1
1 (3.7)
where
h1 is the upstream depth of flow
h2 is the downstream depth of flow
g is the acceleration due to gravity
v1 is the upstream velocity
v2 is the downstream velocity
For a clean or partially blocked screen, the losses are usually incorporated into a
coefficient and Equation (3.7) is expressed as:
losses h h hgC
v vd
sc1 2 2
2
1
21
2(3.8)
where vsc is the velocity through the screen
Cd is a discharge coefficient with a typical value of 0.84.
Alternatively, an orifice equation may be applied in the form:2
2
2
2
1
2 AC
Q
ggC
vh
dodo
sc (3.9)
where Q is the flow rate,
A is the effective open area of the submerged screen,Cdo is a discharge coefficient.
It should be noted that the discharge coefficient in Equation (3.9), Cdo is different from
that in Equation (3.8). In the latter equation, the value of Cdo is dependent on screen
design parameters and is supplied by the screen manufacturer or by experimentation.
If the screens are to be manually cleaned, the effective open area should be taken as 50
% of the actual open area, representing the half-clogged condition. The head loss should
be estimated under conditions of maximum flow.
v1
7/27/2019 Wastewater - Primary
16/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
16
If the bar screen is clean, Kirschmers equation may be used for estimating the head loss
as follows:
hW
bhv
1 33.
sin (3.10)
where is a bar shape factor, as given in Table 3.4
W is the total transverse width of the screen
b is the total transverse clear spacing between bars
hv is the upstream velocity headv
g
1
2
2
is the angle of the bars to the horizontal
Table 3.4: Bar Shape Factor for Kirschmers Equation
Bar TypeSharp-edged rectangular 2.42
Rectangular with semicircular upstream face 1.83
Circular 1.79
Rectangular with semicircular upstream and
downstream face
1.67
Tear shape 0.76
It should be noted that Kirschmers equation is a general form of the standard head loss
equation:
h Kv
g
2
2 (3.11)
where v is identified as v1
K is given by KW
b
1 33.
sin
It should be noted that the expressions developed above are of use in determining the
minimum energy losses through screens, but are of little value in determining the energy
loss once material begins to accumulate behind the screen.
The screen design should take into account the maximum increase in head loss likely tooccur under the conditions of maximum flow rate and minimum cleaning frequency. It
is especially important with manually raked screens that sufficient freeboard is provided
in the upstream channel to avoid the danger of spills at high flows.
ExampleA mechanically cleaned wastewater bar screen is constructed using 6.5 mm wide bars
with a clear spacing of 5.0 cm. The wastewater flow velocity in the channel
immediately upstream of the screen will vary from 0.4 m/sec to 0.9 m/sec.
Determine the design head loss for the screen at the two extremes of flow. Assume that
the discharge coefficient Cdhas a value of 0.84.
7/27/2019 Wastewater - Primary
17/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
17
Solution:
Energy Equation: Head Loss1
2 22
1
2
gCv v
d
sc
Ifv1 is given, vsc can be calculated, knowing the screen geometry.
Continuity Equation:)(1111 clearscsc whvwhv
where w1 is channel width in front of the screen,
wsc is the total width of clear openings of the screen.
w
wsc clear
1
( )
bar spacing + bar width
bar spacing
50 6550
. = 1.13
vsc = 1.13v1
h v v1
2 9 81 084113
2
2
1
2
1
2
x xx
. .. = 0.02v1
2
v1 = 0.4 m/sec h = 3.2 mm
v1 = 0.9 m/sec h = 16.2 mm
Design of Screens
The velocity in the approach channel is normally kept between about 0.3 m/sec and 1m/sec. The lower limit is designed to prevent the settling of coarse matter while the
upper limit is designed to prevent the screens being carried away by the flow.
Screens may be manually cleaned or mechanically raked. Manually cleaned screens are
only fitted in small treatment plants, typically servicing a population equivalent, PE of
less than 5,000. Mechanically raked screens are recommended for all plants servicing a
PE greater than 2,000.
Figure 3.9 shows a schematic of a manually raked screen. The maximum clear spacing
between bars is typically set at 25 mm, although American practice permits spacings up
to 50 mm. To facilitate cleaning, the bars are normally set at 30 45 from the vertical.
The screenings are manually raked on to a perforated plate where they drain, prior to
removal. Cleaning must be frequent to avoid clogging. Infrequent cleaning may result in
significant upstream backwater caused by the buildup of solids. When cleaning is
carried out, the sudden release of the ponded water leads to flow surges.
7/27/2019 Wastewater - Primary
18/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
18
Figure 3.9: Schematic of Manually Raked Screen
A schematic of a mechanically raked bar screen is shown in Figure 3.10. Typically, the
maximum clear spacing between bars is 25 mm, although American practice permitsspacings up to 38 mm. A spacing of 18 mm is considered satisfactory for the protection
of any downstream equipment.
Figure 3.10: Schematic of Mechanically Raked Bar Screen
Mechanically raked screens are normally set at between 0 and 45 from the vertical. The
use of such screens leads to reduced labour costs, improved flow conditions, and
improved capture of screenings. A large number of proprietary screens with mechanicalrakes are available. Manufacturers will normally provide design charts to facilitate
selection of the correct screen size for a particular service.
Figure 3.11 shows a schematic of another type of screen a drum screen. Screenings
naturally fall from the screen as it rotates above the hopper. A water spray assists in
removing screenings.
7/27/2019 Wastewater - Primary
19/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
19
Figure 3.11: Schematic of Drum Screen
An example illustrating the design technique for a screen and screen chamber is
presented in an example below..
ExampleDesign a screen and screen chamber and determine its hydraulic characteristics for a
loading of 10,000 PE. All material larger than 12 mm is to be screened out. The screen
is a bar screen with rectangular bars of 5 mm transverse dimension. At the peak design
flow, the velocity through the screen should be 0.9 m/sec
The water level downstream of the screen is controlled by a downstream long-throated
flume which gives a depth of 400 mm at the peak design flow and 175 mm at ADWF.
In particular, a) determine the head loss across screen;
b) determine the screen chamber width;
c) check the velocities; and
d) if the screen is 50 % blocked, calculate the head loss across it.
Solution:
Estimate loads
ADWF = 225l/day/PE
Peak flow factor (PFF) = 4.7 (PE)
-0.11
(PE in thousands)
7/27/2019 Wastewater - Primary
20/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
20
Load = 10,000 PE
ADWF = 2.25Ml/day = 26l/sec
Peak flow factor = 4.7 10-0.11
= 3.65
Peak flow = 3.65 26 = 95l/sec
Choose the screen:
Bar spacing = 12mm (will screen out all larger material)
Bar thickness = 5mm
If screen velocity is 0.9m/sec for peak flow, calculate v1
bar widthspacingbar
spacingbar1 scvv 0 9
12
17. = 0.64m/sec
a) Determine head loss
2
1
2
22
1vv
gCh sc
d
1
2 9 81 0 840 9 0 642
2 2
. .. .
m029.0h
Depth upstream of screen mhg
v
g
vhh 43.0
22
2
1
2
221
b) Determine screen chamber width.
From continuity, required clear screen width ( Wsc clear( ) ) is
Q h W vsc clear sc1 ( )
Wsc clear
0095
0 429 09
.
. .= 0.246m
Required screen chamber width
7/27/2019 Wastewater - Primary
21/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
21
w 0 24617
12. 0.349m or 350mm
(CHECK against approach velocity)
429.0349.0
095.0
1
1hw
Qv =0.64m/sec
c) Check velocities
ADWF = 0.026m3/sec
Associated h2=175mm
350.0175.0
026.02v 0 426. m / sec
Now, because the flow is lower, we would expect a reduced head loss as well.
The upstream depth will be less than 0.175 + 0.029 < 0.204m
v1
0026
0 204 0 349 0365
.
. . . m / sec >0.3m/sec
O.K. (we could calculate v1exactly, but the above argument removes
the need to do so)
d) Head loss with screen half blocked
Energy equation: hv
g
hv
g
hL11
2
2
2
2
2 2
For peak flow Q = 0.095m3/sec
Upstream from the screen (Section 1):
11
1
271.0
35.0 hh
Qv
On the screen:
Wsc (clear) = * 0.246m = 0123 m
7/27/2019 Wastewater - Primary
22/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
22
11
77.0
123.0
095.0
hhvsc
After the screen (Section 2):
h2 0 4. m smwh
Qv /679.0
35.04.0
095.0
2
2
Losses: h v vL sc1
2 9 81 0 842
2
1
2
. .
Substitute for v h v vsc1 2 2, , , in energy equation
2
1
2
2
1
2
2
2
2
1
2
1
271.077.0
84.06.19
1
6.19
679.0
4.06.19
271.0
hhhh
hh1 1
2
0 003750 4235 0
..
Solve by trial
h1 0539. m
Head loss = 539400 139mm
vQ
hsc 0124
0 095
0124 0 5391.
.
. .=1.42m/sec
vh1 1
0 271 0 271
05390503
. .
.. / secm
3.4.2 Grit ChambersWithin sewage treatment plants, gritcomprising sand, egg shells, coffee grounds and
other non-putrescible materialmay cause severe problems in pumps, sludge digestion
facilities, and de-watering facilities. In addition, it may settle out in downstream pipes
and processes.
The grit removal process is carried out in grit chambers (Figure 3.12) at an early stage
of treatment because the grit particles cannot be broken down by biological processes
and the particles are abrasive and wear down the equipment. Because the grit material is
non-putrescible, it requires no further treatment following removal from the sewage
treatment process and ultimate disposal.
7/27/2019 Wastewater - Primary
23/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
23
It should be noted, however, that the location of grit chambers upstream of the sewage
pumps at the entrance to the sewage treatment plant would normally involve placing
them at a considerable depth involving substantial expense. Therefore, it is usually more
economical to pump the sewage, including the grit, to grit chambers located at a
convenient position upstream of the treatment plant units. It is recognised that thepumps may require greater maintenance as a result.
Figure 3.12: A grit chamber
Grit chambers are designed to remove inorganic solids of sizes greater than about 2 mm.
Removal is commonly effected using settlement, separation using a vortex, or
settlement in the presence of aeration (in the latter process, aeration keeps the lighter
organic particles in suspension). There are important hydraulic principles associated
with each of these three processes.
In this section, the choice of grit removal process is first discussed. The three main
types of grit chamber are then described and the hydraulic aspects of the operation of
each are described qualitatively and, where appropriate, quantitatively. Design aspects
are also discussed.
Choice of Gr it Removal Process
The choice of grit removal process depends largely on the size of the sewage treatment
plant:
For a PE < 5,000 (small treatment plants), a horizontal flow (constant velocity)
settling chamber is commonly used.
For PE of between 5,000 and 10,000 (medium-sized treatment plants), a vortextype grit chamber is commonly used.
7/27/2019 Wastewater - Primary
24/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
24
For PE > 10,000 (large treatment plants), an aerated grit chamber is often
specified, although the vortex type chamber may also be used.
Whichever type is used, it is vital that the unit must operate effectively over the full
range of expected flows.
Other non-hydraulic considerations include grit removal from the unit, which may be
manual or mechanical; handling, storage, and disposal of grit, and the provision of
standby or bypass facilities.
Horizontal F low (or Constant Velocity) Gri t Chamber
The horizontal flow grit chamber is basically an open channel with a detention time
sufficient to allow design particles to settle. Additionally, the velocity must be
sufficiently high that organic materials are scoured so that they pass through the gritchamber for subsequent biological treatment.
The Camp-Shields equation is commonly used to estimate the scour velocity required to
re-suspend settled organic material. This equation is expressed as:
vkgd
fs
p8(3.11)
where vs is the velocity of scour
d is the particle diameterk is an empirical constant (typically 0.040.06)
f is the Darcy-Weisbach friction factor (typically 0.02)
p is the particle density
is the fluid density
Typically, this equation yields a required horizontal flow velocity of 0.15 0.3 m/sec.
This compares well with the Malaysian design standard of 0.2 m/sec.
The primary hydraulic design issue for the horizontal flow grit chamber is the
maintenance of the constant velocity in the channel, despite large variations in the flow
rate, based on a typical diurnal flow pattern.
The problem is illustrated in the following.
Consider a rectangular chamber with the
flow passing over a low rectangular weir
placed at its end (Figure 3.13).
The discharge relationship for the weir is:
Q C B gH d 23
2 (3.12)
where
Figure 3.13: A chamber with a weir
7/27/2019 Wastewater - Primary
25/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
25
Cd is a discharge coefficient,
B is the channel width,
H is approx = the channel depth (if the weir height is very small).
(The derivation of Equation 3.12 is presented in the Study Guide of CIV2262).
Now, the horizontal velocity, vh, is related to the flow rate, Q, and channel geometry by:
vQ
BH
C B g H
BHC g Hh
dd
22
32 1
2 (3.13)
Substituting forH1
2 from Equation (3.12) yields:
v C gQ
C gBh d d2
2
13
(3.14)
v
v
Q
Q
h
h
max
min
max
min
13
(3.15)
Now, a typical value for the ratio of maximum to minimum flow rates (Qmax/Qmin) is
about 5. Substitution of this ratio into Equation (3.15) yields a corresponding value for
the ratio of maximum to minimum velocities (vh(max)/vh(min))of:
71.15
3/1
min
max
h
h
v
v
If 0.2 m/sec is chosen for the value ofvh(min), the corresponding value forvh(max) would
be 0.342 m/sec, which would be unacceptably large.
Therefore, the shape of either the channel or the weir must be modified to
maintain a constant and satisfactory horizontal velocity.
Modification of Channel Shape
The issue to be resolved is whether or not it is possible to develop a channel shape such
that the horizontal velocity remains constant for all flow rates. It is assumed that the
channel discharges into a rectangular control section, such as a long-throated or Parshall
flume. Such a device acts as a water level control and a flow measurement device (see
CIV2262 Study Guide; a flume is shown in Figure 3.14 to the right).
The analysis that follows is generally applicable to any rectangular cross-section. The
analysis specifically makes use of the properties of a long-throated flume because it is
widely used in practice.
The flow through a long-throated flume may be expressed in the form:
7/27/2019 Wastewater - Primary
26/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
26
Q g b H c2
3
2
31
32 (3.16)
where bc is the throat width,
H1 is the upstream head.
Differentiation of Equation (3.16) yields:
dQ gb H dH c2
31
12
1 (3.17)
Now, within the channel, the horizontal velocity, vh, is given by:
vQ
wHh
1
(3.18)
or:Q v wH h 1 (3.19)
where w is the channel width.
Differentiation of Equation (3.19) yields the flow through an elemental horizontal strip
of width w in the channel in the form:
dQ v wdHh 1 (3.20)
Equating the right hand sides of Equations (3.17) and (3.20) yields:
2
31
12
1 1gb H dH v wdHc h (3.21)
Solving Equation (3.21) forw yields:
w gb
vHc
h
2
31
12 (3.22)
If we want vh to be constant for any depth in the channel (i.e. any flow rate), the channelshould have the width determined as a function of its height:
w Hconstant x 11
2 (3.23)
Equation (3.23) describes a parabola, indicating that a parabolic shape for the channel
cross-section will ensure a constant value of velocity, vh, regardless of flow rate. To
reduce construction costs, the parabolic shape is normally approximated with a
trapezoid.
7/27/2019 Wastewater - Primary
27/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
27
Design Aspects
Figure 3.14 presents a layout of a typical design grit chamber with a flume for depth
control at its downstream end. The individual chambers have a trapezoidal shape with a
grit storage channel at their bottom for collection of deposited grit.
Figure 3.14: Schematic of Channel-modified Horizontal Constant Velocity Grit
Chamber
As a minimum, one channel and a bypass should be installed. However, usually at least
two are designed for operational reasons (maintenance, etc). When the number of
channels is determined, the maximum, average, and minimum flows in an individual
channel can be determined (i.e. Qemergency, Qmaximum, Qaverage, and Qminimum, are used to
design the shape and length of the grit channel).
The system should be designed such that, when one channel is out of service, its flow is
diverted to the other channels. The resulting emergency flow for each channel is based
on the maximum flow into the set of grit chambers with one out of service.
Other practical aspects are associated with the turbulence which occurs in the inlet and
outlet zones of the chamber. These zones are similar as in any sedimentation tank, and
are illustrated schematically in Figure 3.15.
Turbulence occurs in the inlet zone as the flow is established. A similar phenomenon
occurs in the outlet zone as the flow streamlines turn upwards. To allow for this
disturbance, a 2550 % increase in the calculated settling length is applied.
Typical design criteria for a channel-modified horizontal grit chamber are presented in
Table 3.5.
7/27/2019 Wastewater - Primary
28/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
28
In the case of a flume being
used for flow regulation in the
chamber, the cross-section area
of the chamber is defined
according the followingprocedure. Equation 3.16 for the
flume is:
23
1
23
3
2HbgQ c
where bc is the
considered
width, and H1
the water depth.
Table 3.5: Typical design criteria for Channel-Modified Grit Chambers
Design Parameter Typical Values Comments
Water depth (m) 0.61.5 Dependent on channel area and
flow rate
Length (m) 325 Function of channel depth and
grit settling velocity
Extra for inlet and outlet 2550 % Based on theoretical length
Detention time at peak flow
(seconds)
1590 Function of velocity and
channel lengthHorizontal velocity (m/sec.) 0.150.3 0.2 m/sec is Malaysian
Standard
Equation 3.22 expresses the chamber width at the surface, w, as:
21
13
2H
v
bgw
h
c or
21
13
2Hg
wvb hc
Combining Eqs. 3.16 and 3.22 the flow can be expressed as:
hvwHQ 13
2
Since Q=Avh, the cross-sectional area of the chamber, A is:
13
2wHA (3.24)
The design procedure for a channel-modified grit chamber is illustrated in the following
Example.
Figure 3.15: Schematic of Settling Process in Grit
Chamber
7/27/2019 Wastewater - Primary
29/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
29
Example:Design a horizontal/constant velocity grit chamber for a hydraulic load of 2,000 PE.
Consider only the ADWF and the peak flow. The water level within the chamber iscontrolled by a downstream long-throated flume which gives a depth of 205 mm at the
peak design flow and 80 mm at ADWF. The following should apply:
Maximum horizontal velocity is v=0.2 m/sec
Channel length > 18 times maximum water depth
Grit quantity is estimated as 0.03 m3/ML of wastewater
Grit collection channel to be cleaned out twice per week
Solution
Average dry weather flow
ADWF = 225 2,000 = 0.45 ML/day
ADWF = 5.2l/sec
Peak flow factor PFF 4 7 2 0 11. . = 4.35
Peak flow PF= 4.35 5.2
PF= 23 l/sec
The long-throated flume gives depth of
205 mm at peak flow and 80 mm at ADWF
Therefore, cross-sectional areas of the trapezoidal cross-section should be:
ADWF :0.2
0.0052
v
ADWF=Area 0026
2. m
Peak: Area =0.023
0.2 0115. m2
Surface widths at each flow are now calculated.
7/27/2019 Wastewater - Primary
30/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
30
At average dry weather flow
Surface width12
3
HA
0 026 3
2 0 08
.
.
049. m
At Peak Flow
Surface width0115 3
2 0 205
.
.
=0.84m
Length of chamber:
> 18 max. depth
> 18 0.205
Use 3.7m
Grit quantity is based on ADWF
Grit quantity = 0.45 0.03 = 0.014m3
/day
At twice weekly cleanout, grit accumulation
0 014 4. ~ 0056. m3
Required cross-sectional area of grit collection channel
0056
37
.
.0015. m2
Use grit collection channel 150mm wide 110mm deep
(gives some margin). Allow for freeboard (say, 200mm)
Parabolic section to be approximated by trapezoid.
Modification of Downstream Control Weir
The chamber can have a rectangular cross-section, only if the flow is controlled by a
special device at the downstream end.
7/27/2019 Wastewater - Primary
31/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
31
For a rectangular grit chamber, the flow rate is given by:
BhvQ h (3.25)
where B is the chamber widthh is the flow depth in the chamber
The form of Equation (3.25) indicates that forvh to be constant, regardless of flow rate,
the flow rate should be linearly proportional to the depth, h. This may be assured by
using a downstream control weir characterised by a linear relationship between flow
rate and head on the weir crest.
Such a weir is the Sutro weir which is described and analysed in CIV2262 (see
CIV2262 Study Guide).
Sutro weir
Vortex Grit Chamber
A schematic of a typical vortex grit chamber is shown in Figure 3.16.
With reference to this figure, grit-laden flow enters the unit tangentially at the top. The
resulting spiral flow pattern tends to lift the lighter organic particles while the
mechanically induced vortex captures grit at the centre. The grit is then removed by air-lift or through a hopper. It should be noted that the grit sump has a tendency to become
compacted and will potentially clog. Sometimes provision is made for the use of high-
pressure agitation water or air to clear the sump.
The adjustable rotating paddles maintain the proper circulation within the unit for all
flows. Attention should be paid to the tendency for these paddles to collect rags.
7/27/2019 Wastewater - Primary
32/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
32
Figure 3.16: Schematic of Typical Vortex Grit Chambers (a) PISTA Unit (b) TeacupUnit
Vortex grit chambers are highly energy-efficient. The head loss across the unit is
minimal when operating correctly and unclogged. American practice indicates a value
of 6 mm, although an allowance of 100 mm is recommended.
Vortex grit chambers have the great advantage that they are very compact. Their design
is usually proprietary so that manufacturers will usually produce a suitable unit to
accommodate stated performance specifications. Manufacturers specifications will
provide information on the maximum water depth within the chamber.
Aerated Grit Chamber
Aerated grit chambers are commonly used in medium to large sewage treatment plants.
The introduction of air through a diffuser, located on one side of the tank, induces a
spiral flow pattern in the sewage as it moves through the tank, as shown in Figure 3.17.
Correct positioning of the tank inlet and outlet directs the flow perpendicular to the
spiral roll pattern. Inlet and outlet baffles are normally installed to dissipate energy and
minimise short-circuiting. Head loss across the chamber is minimal.
7/27/2019 Wastewater - Primary
33/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
33
Figure 3.17: Helicoidal Flow Pattern in an Aerated Grit Chamber
The roll velocity is set so that it is sufficient to maintain lighter organic particles in
suspension while allowing heavier grit particles to settle. Because conditions change
with flow rate, the air supply is adjustable to provide the optimum roll velocity.
A further advantage of the introduction of air is that the sewage is freshened, leading to
a notable reduction in odour. If desired, the chamber can be used for chemical addition,
mixing, and/or flocculation ahead of primary treatment. Grease removal may be
achieved with a skimmer.
If correctly designed, an aerated grit chamber with a minimum hydraulic detention time
of 3 minutes will capture about 95% of grit larger than 0.2 mm when operating at its
peak flow. The usual range of design specifications is given in Table 3.6.
Table 3.6: Typical Design Specifications for an Aerated Grit Chamber
Design Parameter Range of Values Comments
Depth 25 m Varies widelyLength 820 m
Width 2.57 m
Width:Depth Ratio 1:15:1 2:1 typical
Length:Width Ratio 3:15:1
Minimum Detention Time 25 minutes 3 minutes typical
Air Supply 0.250.75 m /min/m 0.45 m /min/m typical
Diffuser Distance from
Bottom
0.61.0 m
Transverse Roll Velocity 0.60.75 m/sec
7/27/2019 Wastewater - Primary
34/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
34
Example:Design an aerated grit chamber for a hydraulic load of 20,000 PE. The following is
chosen:
The minimum detention time at peak flow is 3 minutes,
The width to depth ratio is 2:1,
The length to width ratio is 2:1,
Grit quantity is estimated as 0.03 m3/ML of wastewater,
The aeration requirement is 10 litres/sec/m length of tank.
Solution
ADWF = 20,000 225l/day= 4,500m3/day=52l/sec
PFF= 4.7 20-0.11= 3.38
Peak flow = 52 3.38 = 176 l/sec
Grit chamber volume:
Minimum detention time at peak flow = 3minutes
= 3 60 = 180seconds
Required volume = 0.176 180 = 31.7 = 32m3
W
D
L
W2 2,
Volume = D W L = 32
W = 2D, L = 2W = 4D
D 2D 4D = 32
Dimensions D = 1.6m
W = 3.2m
L = 6.4m
Aeration requirement
10l/sec/m length = 10 6.4 = 64 l/sec
Means should be provided to vary the air flow rate to control grit removal
rate and grit cleanliness
Grit quantity
Based on average flow rate,
= 4.5ML/day 0.03m3/ML = 135 l/day
7/27/2019 Wastewater - Primary
35/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
35
3.4.3 Other
Comminutors
Comminutors mince wastewater solids (rags, paper, plastic, etc) by revolving cuttingbars. They are used instead of fine bar racks (after grit chambers).
EqualizationThe purpose of equalization is to dampen flow variations so that wastewater can be
treated at a nearly constant flow rate. It is achieved by constructing large basins.
3.5 Primary Treatment
After preliminary treatment, the wastewater contains light organic solids, some of which
can be removed by gravity or screening.
3.5.1 Primary Sedimentation TanksSedimentation tanks (also known as clarifiers) are used as a part of both primary
treatment and secondary treatment processes. Here only preliminary sedimentation
tanks will be discussed.
Sedimentation tanks may be rectangular, square, or circular in shape. A schematic of a
typical rectangular clarifier is shown in Figure 3.18, of a circular clarifier in Figure 3.19,
and a square one in Figure 3.20.
Rectangular tanks (Fig. 31.18) are commonly used for primary sedimentation. They
occupy less space than circular tanks and can be economically built side by side with
common walls.
Figure 3.18: Schematic of Rectangular Sedimentation Tank
In the case of a circular, the flow enters at the centre and settlement takes place as the
flow moves outwards and rises. The effluent is collected in a channel or launder, which
7/27/2019 Wastewater - Primary
36/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
36
then conveys the flow to an exit channel or pipe. Circular tanks require a careful design
of the inlet stilling well to achieve a stable radial flow pattern without causing excessive
turbulence in the vicinity of the central sludge hopper. Inlet design is considered in
subsequent paragraphs.
Figure 3.19: Schematic of Circular Clarifier
Square or upflow tanks (Fig. 3.20) typically have deep hopper bottoms and are common
in small treatment plants. Their primary advantage is that sludge removal is carried out
entirely by gravity. The steeply sloping sides typically 60concentrate the sludge atthe bottom of the hopper. A significant disadvantage is that hydraulic overloading may
cause major problems because any particles with a settling velocity less than the surface
loading rate will not be removed, but will escape with the effluent.
This section emphasises the hydraulic aspects of the design of clarifiers. The basic
design procedure is reviewed and design guidelines are presented. The important
procedure for the design of the launder is then discussed. Finally, a design example is
presented to aid understanding.
7/27/2019 Wastewater - Primary
37/45
7/27/2019 Wastewater - Primary
38/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
38
where Q is inflow;
A is surface area;
Detention Time
The detention time is given by the equation:
SLR
H
Q
Volumet (3.25)
where H is depth of the tank.
Following the specification of these parameters, the dimensioning of the tank then
proceeds as follows:
SLR
QAArea,SurfaceTank (3.26)
ADL orDiameter,orLengthTank (3.27)
whereL
4for rectangular tanks
4for circular tanks
Clarifiers are normally designed to provide a detention time of between 1.5 and 2.5
hours, based on the peak flow rate. It is noted that the design criteria for Malaysian
systems incorporate a time of 2 hours based on the peak flow rate.
The Forward Velocity
The forward velocity is also an important aspect of the design of rectangular tanks. If
this is excessive, scouring and re-suspension of the sludge will result.
The forward velocity is given by:
vQ
WHh (3.28)
Incorporating Equation (3.26) for the detention time,
vL
th (3.29)
It is evident from Equations (3.28) and (3.29) that the forward velocity influences the
choice of length to width ratio. The maximum forward velocity to avoid the risk of
scouring settled sludge is 10 to 15 mm/sec, indicating that the ratio of length to width
should preferably be about 3:1.
7/27/2019 Wastewater - Primary
39/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
39
Values of L/W in practice range between 3 and 6. The Malaysian Draft Guidelines
specify a value of 3.
Weir Loading RateThe weir loading rate is defined as
WLR = Q/Lw (3.30)
where Lw is the length of the outlet weir.
If this value is too high, the approach current generated by the weir will extend
upstream into the settling zone, creating a potential disruption of the flow pattern. A
weir loading rate of between 100 and 200 m3/m/day is typically specified. Achieving
this value is a particular problem for rectangular tanks which is usually overcome by
utilising multiple suspended weir troughs.
In circular tanks, the weir loading rate associated with a perimeter weir is normally
satisfactory at high flows. At low flows, however, difficulties may arise from a weir
loading rate which is too small because the consequent very small flow depths over the
weir make the tank flow pattern very sensitive to errors in weir levelling. This problem
may be overcome by constructing the perimeter weir as a saw-tooth weiror multiple
V-notchto increase the flow depth.
Design Guideli nes
Design guidelines for clarifiers vary significantly from country to country. Typical
guidelines from American practice are presented in Table 3.7.
Table 3.7: Typical Design Guidelines for Circular Primary Clarifiers
Parameter Value
Detention time
For average weather flow 1.5 and 2.5 hours
Surface loading rate = Q/Surface area
For average dry weather flow
For peak flow conditions
32 - 49 m3/m2/day
49 - 122 m3/m2/daySidewater depth 2.15 m
Weir loading rate = Q/Weir length 125500 m /m/day
Primary clarifiers are designed more conservatively if sedimentation is the only
treatment and if activated sludge is being returned to the primary clarifier. Rectangular
clarifiers are generally designed under the same criteria as circular clarifiers. Typical
length to width ratios for rectangular primary clarifiers range from 3:1 to 5:1, although
many existing tanks are characterised by ratios of between 1.5:1 and 15:1.
A well-designed and operated primary clarifier should be capable of removing between
50 and 65% of the total influent suspended solids.
7/27/2019 Wastewater - Primary
40/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
40
The issues of surface loading rate, detention time, and weir loading rate are illustrated
by the example below.
ExampleTwo primary clarifiers are 26 m in diameter with a 2.1 m side water depth. Single
effluent weirs are located on the peripheries of the tanks. For a wastewater flow of
26,000 m3/day, calculate:
a) the surface loading rate,
b) the detention time, and
c) the weir loading rate.
Solution
Surface area of each clarifierD2 2
4
26
4530 2m
Total surface area = 530 2 = 1,060m2
Total volume = 1,060 2.1 = 2,230m3
a) Surface loading rateQ
A
26 000
1060
,
, 245. m / m / day3 2
b) Detention timeVolume
Flow rate
2 230
26 00024
,
,2 06. hours
c) Weir loading rateflow rate
weir length
26 000
2
,
D
26 000
2 26
,
159m / m / day3
Tank I nlets
Sedimentation tank inlets must be designed to distribute the flow as uniformly aspossible so that the best possible flow pattern is maintained. The influent jet has a high
amount of kinetic energy that must be dissipated.
For rectangular tanks, various baffled inlet arrangements have been used which are
effective for energy dissipation and flow distribution. Typical arrangements are shown
schematically in Figure 3.21.
With circular tanks, the radial flow from the inlet is inherently less stable than the
horizontal flow in a rectangular basin. Careful design is needed to achieve a stable
radial flow pattern. Typical arrangements are shown in Figure 3.22 for (a) side feed, (b)
7/27/2019 Wastewater - Primary
41/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
41
vertical pipe feed, and (c) slotted vertical pipe feed. In all cases, the primary design
principles are that energy must be dissipated and the flow distribution must be uniform.
Figure 3.21: Schematics of Typical Rectangular Sedimentation Tank Inlets
Figure 3.22: Centre-feed Inlets for Circular Clarifiers: (a) Side Feed, (b)
Vertical Pipe Feed, (c) Slotted Vertical Pipe Feed
Ef fl uent L aunder Design
Rising wastewater in a clarifier flows over a weir into a channel or launder which, in
turn, conveys the collected effluent to the exit channel. Flow in the launder is classified
as spatially varied because the flow rate increases with distance along the launder. This
7/27/2019 Wastewater - Primary
42/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
42
characteristic requires the use of the momentum equation for its analysis, rather than the
energy equation.
The basic flow condition is illustrated schematically in Figure 3.23 which shows the
flow spilling over the multiple V-notch weir into the launder. A full momentumanalysis, including the effects of friction are needed. A simplified approach is usually
adequate and is presented herein.
The first issue is the size of V-notch weir required. The individual V-notches are
typically set out with a centre-to-centre spacing of between 150 and 300 mm. With the
number of V-notches consequently established, the flow through each notch can be
determined from:
NperV notch
(3.31)
where N is the number of V-notches.
The maximum height, h, over the weir is then determined from the standard V-notch
weir equation (see Study Guide CIV2262):
25
2tan2
15
8hgCQ dnotchperV (3.32)
The discharge coefficient, Cd, is a function of the notch angle, . For = 90
0
, Cd has avalue of 0.58.
The head over the weir, calculated from Equation (3.32), should be increased by a
safety factor of 15%.
The next stage in the hydraulic design is to determine the maximum depth in the
launder. First, the critical depth at the discharge point of the launder is calculated from:
yqL
b gc
2
2
13
4(3.33)
Figure 3.23: Definition Sketch for Flow in a Launder and image of a completed design.
7/27/2019 Wastewater - Primary
43/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
43
where LwQq / is discharge per unit weir length,
Lw is the length of weir,
L is the length of the launder (circumference of the tank),
b is the width of the launder.
The depth at the upstream end of the launder is then calculated from:
H yq x
gb yc
c
22 2
2
122
(3.34)
where x=L/2 for a circular basin.
The depth, H, calculated from Equation (3.34) should be increased by a factor of safety
of 50% to allow for friction loss, freeboard, and a free fall allowance.
The design of a launder is illustrated by the example below.
ExampleDesign the overflow weirs and launders (collection channels) for two identical circular
clarifiers that treat a design flow of 20,000 m3/day, and a peak hourly flow of 32,000
m3/day. They are 18 m in diameter each. The critical condition is when the peak flow
occurs with one clarifier out of service. The launder must be able to cope with the
corresponding flow.
Solution
Weir design
One clarifier must handle peak flow.
Peak weir loading rate32,000m / day
2 18m
3
where: 2 represents the inflow on both sides
18 represents the diameter
WOR /m/daym2833
Assume that weir comprises V-notches with spacing of 25cm centre to centre (this may
need adjusting).
Total number of V-notches 20 25
D
.
Take D as 18m, even though it will be less for the inner ring and more for the outer.
Total number of V-notches 218
0 25.= 452
7/27/2019 Wastewater - Primary
44/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
Department of Civil Engineering, Monash University
04-2012
MONASHU N I V E R S I T Y
44
Flow per notch /sm00082.0452
1
24600,3
000,32 3
Now, for each V-notch, notch angle is =900 and Cd=0.58.
25
2tan2
15
8hgCQ d
mh 051.06.1958.08
00082.015 52
A safety factor of 15% is normally appropriate.
Allow for water depth over notch of 1.15 0.051= 0.059m
= 60mm
Width of V-notch at the top = 60mm 2 = 120mm.
Weir design as follows:
Launder design
q is discharge/unit weir length = weir loading rate 2
(because launder is fed from both sides)
q283
3 600 24
2
,
m / m / sec3
0 0066. m / m / sec3
Assume a launder width
Try 500mm
Calculate depth at launder discharge point
7/27/2019 Wastewater - Primary
45/45
Unit CIV3264: Urban Water and Wastewater SystemsTopic 3 Wastewater
45
m0.24381.95.04
180066.0
4
31
2
231
2
2
gb
qLyc
Calculate maximum depth in launder at upstream end
H yq x
gb y
2
2 2
2
0 52
.
(Note: xD
2)
mH 419.0243.05.081.9
2
180066.02
243.0
21
2
2
2
2
Increase this depth by 50% to allow for friction loss in the launder, freeboard, and free-
fall allowance.
Total depth to be provided in launder
= 0.419 1.5
= 0.629, say 0.65m
Launder depth below vertex of V-notch weirs = 0.65m
Launder width = 0.50m