Upload
hoangkhue
View
219
Download
2
Embed Size (px)
Citation preview
Pretreatment Facility
High-Level Waste Facility
Analytical Laboratory
Low-Activity Waste Facility
www.hanfordvitplant.com • www.twitter.com/HanfordVitPlant • www.facebook.com/HanfordVitPlant
Hanford Vit Plant
February 2015
2014 ACCOMPLISHMENTS
• Received authorization to resume full production engineering for the High-Level Waste Vitrification Facility (HLW)
• Completed 18 concrete placements in HLW
• Received recertification of Voluntary Protection Program Star Status
• Completed the safest year in project history
• Achieved “Analytical Laboratory ready for systemization” milestone
• Completed conceptual design of direct feed of waste to the Low-Activity Waste Vitrification Facility (Direct Feed LAW)
• Completed phase 1 testing of the pulse jet mixer controls
• Completed the plan and schedule for resolving the Pretreatment Facility technical decisions
• Made significant progress on installing components of two, 300-ton melters for LAW
• Completed placement of the standby diesel generator
WASTE TREATMENT PLANT2014 ACCOMPLISHMENTS
Bechtel National Inc. is designing and building the world’s largest radioactive waste treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern Washington state. The Waste Treatment Plant, also known as the Vit Plant, will use a process called vitrification to solidify the radioactive liquid waste stored in 177 underground tanks.
Vitrification involves blending the waste with glass-forming materials and heating it to high temperatures. The molten mixture is then poured into stainless steel canisters to cool and solidify. In this glass form, the waste is stable and impervious to the environment, and its radioactivity will dissipate over hundreds to thousands of years.
The Vit Plant will cover 65 acres with four major facilities – Pretreatment, Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical Laboratory – as well as operations and maintenance buildings, utilities, other support facilities, and office space.
Aerial of the WTP Site
Pretreatment Facility
High-Level Waste Facility
Analytical Laboratory
Low-Activity Waste Facility
FACTS AND FIGURES• 2,700 employees
HLW and LAW stainless steel canisters
TP1501_06
Commodities To Date Concrete.................................230,000 yard3 Steel .......................................21,000 tons HVAC......................................896 tons Cable tray...............................52,000 feet Conduit ...................................278,000 feet Cable & wire ...........................928,000 feet
Procurements Small Business...................... $1.4 billionLarge Business...................... $2.3 billion Total ...................................... $3.7 billionTri-Cities Area* ...................... $1 billion Washington/Oregon............... $1.6 billion*Benton/Franklin Counties
2014 Engineering DeliverablesCalculations ................................. 397Engineering Studies ..................... 25Reports ......................................... 730Drawings ...................................... 3,506Specifications ............................... 55Datasheets ................................... 603Material Requisitions .................... 57
Test Vessel
Full-scale vessel testing at the EnergySolutions Engineering Laboratory
Placing the standby diesel generator
Placing refractory brick in one of the Low-Activity Waste Vitrification Facility melters