Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Waste Heat Recovery & Renewable Energy Projects in Aluminium production
Opportunities & Challenges
Debasish Ghosh Hindalco Industries Limited [email protected] 16.12.16
1
Contents
• Waste Heat sources in Aluminium Production
• Waste Heat Recovery - Opportunities & Challenges
• Renewable Energy - Opportunities & Challenges
2
Power Plant Co-generation
WH WH
WH
WH
Aluminium Production & Waste Heat
WH – Waste Heat
3
Smelter
4
CFD Model in Smelter
Relation – Duct Flow & Energy Consumption Duct flow : If can be decreased from 5900 to 4000 [Nm3/h] Duct temp : 20.5°C higher (168°C).
Constant : Current (180.7 kA), ledge thickness and shell heat flow Possibility : ACD squeeze Energy : 14.090 to 13.401 [kWh/kg Al]
5
Smelter - Other Cell Material Flow Energy loss
Around 0.35 [kWh/ kg Al] (2%-3%) of cell energy is consumed by parallel materials heat up and reactions
reduce time spent per anode change, improve the cover practices to
generate less sludge, reduce gross and net carbon consumptions.
6
Smelter – Waste Heat Recovery
Typical Gas duct in Smelter
7
Smelter – Waste Heat Recovery
Off Gas temp : 150 – 200 deg C Hydro smelters are utilizing the recovered heat in space and district heating schemes. heat exchangers (HXs) have been set up downstream of the dry scrubbers,
With HXs upstream of dry scrubber Advantages Better heat availability Lower size of HXs Potential for reducing the exhaust fan power consumption Extending the filter-bag life in the dry scrubber (temp below 135°C)
Concern fouling and corrosion of heat exchange Utlisation of the heat energy Power Generation through ORC ? Other Area : Anode Baking Furnace
8
Waste Heat Recovery– An example Belgaum Refinery • In-house fabrication of the air pre-heater at minimum cost • Flue gas temp brought down to 145 deg C and savings 9.3 MT Oe /month
FLUE GAS TO APH
FD FAN
BOILER & ECON (INTEGRAL)
COLD AIR IN
BY-PASS DAMPER
TO STACK
NEW AIR PRE-HEATER
Status : Implemented
9
Waste Heat Recovery - Refinery
Waste Heat Recovery in KILN > Hydrate Drying(7 to 8 % moisture) /Preheating > 9000m3/Hr flue gas at 200-210 Deg C > Investment Rs 72.0 Lakhs > Savings : fuel oil 10 Kg/T
Status : Not yet implemented
10
Waste Heat Recovery - Remelting
A typical Example Heat Source : Remelting Furnace Flue Gas Utilisation : Ingot Preheating Mode : Initial heating by Waste Heat Final Heating by Electricity Savings : 70 kWh/t Drawback : Cy time increase from 12 to 17 Hrs
1) Recuperators 2) Regenerative Burners 3) Additional potential
Status : Implemented but not in use now due to cycle time/productivity concern
11
Waste Heat Recovery - Aluminium Production
Sources Smelter Duct Gas Anode Baking Furnace Refinery Calciner Remelting Furnace
Utlisation Hot water application Air preheating Preheating of Charge/Raw material Refrigeration/Chillers through VAM Power Generation through ORC ?
Challenges High grade heat – available in batches Low grade heat – Technology & Economics Fouling of Heat Exchanagers
12
Renewable Energy
13
Sun Pipe light Installation at Belur FRP Plant
Machine Shop Shop floor
In its simplest form :
Status : Implemented
14
Solar Power
First MW scale Solar project for Hindalco
Alupuram, Kerala Solar 1 MW - commissioned 31.03.16 Seasonal Tilt, synchronised at 11 kV Consumption : 100% Captive Monthly PLF : upto 18% Performance Ration (PR) : @ 78% Daily Generation : 5,800 kWh (max) Monthly Generation : 1,50,000 KWh (max)
Status : Implemented
15
30 MW Solar
Substitute part thermal power by solar in Smelter Plant with CPP
Land requirement @ 140 – 150 Acre
Cannot synchronise at 11 kV & 33 kV for plant reliability/stability
To synchronise at 220 kV
Some loss of PLF in CPP resulting in PHR increase by 2 kcal/kWh (BEE Method : Design efficiency curve validated by operating data)
Need to regulate CPP generation with hour of the day/sunshine
Requires Operational control to restrict both Import/Export of Power
Status : In progress
16
Renewable Power for Captive consumption
Infirm in nature / Alternate source also required
Some efficiency loss in existing Thermal Power Plant
Available location may not be the ideal
States like Odisha do not have wind potential
Country Green corridor not yet ready
Interstate Renewable power transfer not yet established
Banking of power not allowed in most states
Govt. Policy & Regulations are constantly evolving
Concerns
Favourable Falling Prices of Solar Panels/Projects
17
Aluminium sector (12 units with CPP totalling approx. 6660 MW)
Unique sector with high ratio of electricity to thermal energy
Large power plants to meets its own electricity need.
High renewable % high capacity/ratio of Renewable energy in overall mix
unfavourable operational/reliability/efficiency/feasibility
Increases cost of production substantially
LT Renewable Trajectory set by MoP will need 3400 MW of RE Power for Al sector
Appears technically difficult & detrimental
There are constraints, we need to progress to the maximum feasible
From BEE PAT consultation document
18
Thank You