Washington Avenue Reconstruction Project City of Chelsea Public Informational Meeting May 31, 2011

Washington Avenue Reconstruction Project City of Chelsea Public Informational Meeting May 31, 2011

Embed Size (px)

Citation preview

Washington Avenue Reconstruction Project

Washington Avenue Reconstruction Project

City of ChelseaPublic Informational Meeting

May 31, 2011

Why Project is Occurring

Poor Roadway Conditions Separation of Sewer and Stormwater Replacement of Water Replacement of Gas (by National Grid)

What Does the Project Entail?

Project Details Geographic Scope of the Work

Heard St to Route 16 Back of Sidewalk to Back of Sidewalk Reconfiguration of Cary Square

Full-Depth Roadway Reconstruction Explanation1. New Street Surface2. New Sidewalks3. Streetscape Amenities (Benches, Bike Racks, Trees,

Etc.)

What Does the Project Entail?

Funding Sources Municipal Borrowings through General Obligation Sewer and Water Bonds Chapter 90 Funds Community Development Block Grant Funding MWRA Grant and Zero Interest Loans

Total of $6M+

What Does the Project Entail?

Project Construction Schedule Water, Sanitary & Drain - Spring/Summer/Fall 2011

Streetscape – Spring/Summer/Fall 2012

Completion – Spring 2013

Project Schedule

• Contract has been awarded to J. Marchese and Sons

• Work starts Monday June 6th

• Work hours approximately 7 AM to 3:30 PM, Monday through Friday

Construction Schedule

Construction Schedule

June Construction

July Construction

August Construction