Wake Bus Rapid Transit System Standards
New Bern Avenue Final Design
Transportation - Transit
City Council June 2, 2020
Slide 2
Agenda
• Wake Transit Plan
• Wake BRT Program Project Status
• New Bern Avenue 30% Design
• Final Design Team
• Scope and Fee Highlights
• Recommended Action
Slide 3
Wake Transit Plan – Four Big Moves
Slide 4
Project Development Overview
FEDERAL TRANSIT ADMINISTRATION (FTA) SMALL STARTSTotal Cost: <$300 millionFunding: <$100 million
STEP 1: FTA APPROVALProject Development (PD)• PD Application• Review Alternatives• Locally Preferred Alternative (LPA)• Environmental Review• Funding Commitment • Complete Engineering
STEP 2: FTA EVALUATION, RATING AND APPROVAL Full Funding Grant Agreement• Construction
NEW BERN
SOUTHERN &WESTERN CORRIDORS
Slide 5
Project Sponsor Designation Process
• Capital Area MPO Executive Board is responsible for fixed guideway project sponsor designations
• Major Investment Study Consultants developed a memo recommending the City of Raleigh as BRT Project Sponsor
• On August 15th, 2018 the Capital Area MPO Executive Board voted unanimously to request the City of Raleigh to become the Project Sponsor for one or more BRT projects
• On September 4, 2018, City Council authorized the mayor to accept the City’s project sponsor designation for the Wake BRT projects
Slide 6
Project Sponsor Responsibilities
• Takes the primary responsibility for project implementation • Coordinates and makes project-level decisions with other impacted
jurisdictions, for example: o Station design and station area plans o Technology decisionso Street (ROW) use assignments
• Bike and pedestrian facilities• Sidewalk widths• BRT runningways• Parking • Curbspace use
• Complies with the Wake Transit Plan policies and processes
Slide 7
Wake BRT Program - Project StatusWake BRT: New Bern Avenue
STATUS: 30% Design Complete (WSP) NEXT STEP: 30-100% Design and System Standards (HNTB)
Wake BRT: Southern CorridorWake BRT: Western Corridor
Wake BRT: Northern Corridor
STATUS: Route Selection kicked off in February 2020 (WSP)
STATUS: Route Selection Kicked off in November 2019 (WSP/Western Corridor Blvd Study)
STATUS: Pre-Planning Complete
Slide 8
Wake BRT: Western Corridor Update• Western Boulevard Corridor Study ongoing - LPA memo (technical recommendation)
• Project Development Application draft
• Monthly meetings with partner municipalities and NCDOT
• Next Steps: Contract for 0 – 30% design and NEPA with WSP (target date June 16th)
BOTH ALIGNMENTS WOULD REQUIRE CONSTRUCTION OF NEW ROADWAY (WESTERN BLVD. EXTENSION)
Slide 9
Wake BRT: Southern Corridor Update
• LPA Selection ongoing
• Public engagement February-March 2020
• Project Development Application draft
• Monthly meetings with partner municipalities and
NCDOT
• Next Steps: Contract for 0 – 30% design and
NEPA with WSP (target date June 16th)
Slide 10
Wake BRT: New Bern Avenue Update
Previous Council PresentationsFeb 11, 2020• Discussed New Bern Avenue BRT and Pedestrian
Improvements projects consolidation
March 17, 2020 • Provided Wake BRT: New Bern Avenue 30% design
overview • Summarized public engagement completed since
project initiation
Slide 11
New Bern Avenue – Current Design 30%
Slide 12
Wake BRT: New Bern Avenue
SUMMERSPRING FALL WINTER SUMMERSPRING FALL WINTER SUMMERSPRING FALL WINTER2019 2020 2021 2023 2024
Project Development
30% Design Complete(WSP)
Final Design Complete
ConstructionBRT Service late 2023Small Starts
Ratings Application
Final Design Team Selected/HNTB
WE ARE HERE
HNTB Contract Recommendation
30% -100% Design and System Standards Begins/HNTB
WSP team HNTB team
Project Status
Slide 13
Selection Committee Members:
• CAMPO, GoTriangle, NCDOT, Town of Cary, Town of Garner, Wake County and various City of Raleigh departments.
Submittals were independently reviewed and scored, selection committee held
interviews and developed final recommendation.
Final Recommendation: HNTB
RTA Reviewed on May 14, 2020: Recommended Approval
Wake BRT: New Bern AvenueFinal Design Team Selection Process
Slide 14
HNTB Scope Highlights: Focus Areas
Wake BRT: New Bern Ave Final Design
Wake BRT: System Standards
• Geospatial Survey
• Final Design
• Public Engagement
• Utility Coordination
• Right-of-Way (ROW)
• Construction
• FTA Coordination
• System Standards
• User Experience
• Branding
• Public Engagement
• System-Wide Policies
Estimated Fee: $7.7M | Period of Performance: July 2020 – December 2023
FINAL DESIGN - HNTB
FINAL DESIGN - SUBS
FINAL DESIGN - RALEIGH WATER
SYSTEM STANDARDS - HNTB
SYSTEM STANDARDS - SUBS
$1.5M
$0.5M
$0.2M
$2.5M
$3.0M
Slide 15
FTA DBE Goal: 13% | HNTB Team DBE Participation: Approx. 30%
HNTB – Subconsultants
Name Focus DBE Designation Location
SRF Consulting Group System Design/FTA None Minneapolis, MN
Neighboring Concepts Architecture DBE, MBE, HUB, SPSF Charlotte, NC
PR Pros Branding DBE, MBE, HUB, SPSF Raleigh, NC
Public Participation Partners Public Engagement DBE, MBE, SBE, HUB, SPSF Raleigh, NC
CH Engineering Survey, ROW, Utility DBE, WBE, HUB, SPSF Raleigh, NC
Susan Hatchell Landscape Architecture DBE, WBE, SBE, HUB, SPSF Raleigh, NC
Falcon Engineering Geotech DBE, WBE, SBE, HUB, ACDBE, SPSF Cary, NC
Slide 16
Wake BRT Program Milestones
Item Date Status
New Bern 30% Design Review March 17, 2020
New Bern Final Design Contract June 02, 2020 Today
WSP Contracts and Project Development Application (Southern and Western corridors) June 16, 2020
Transit-Oriented Development Overlay Discussion July 7, 2020
Western and Southern Corridor LPA Recommendation Fall 2020
New Bern 65% Design Review and Approval December 2020
Council Updates and Decision Points
Slide 17
Authorize City Manager to execute Wake BRT System
Standards and New Bern Avenue BRT Final Design
Contract with HNTB
Recommended Action