Upload
phamnga
View
219
Download
0
Embed Size (px)
Citation preview
Waddle Road Interchange Project
Patton Township
Board of Supervisors MeetingDecember 11, 2013
Insert Project Area Image
Project Area Map
Ø Relieve Existing Congestion
Ø Replace Functionally Obsolete Bridge
Ø Accommodate Regional Growth and Development
Project Objectives
Waddle Road InterchangeProject
Alternative 1Conventional Diamond
Waddle Road InterchangeProject
Alternative 2Partial Cloverleaf
Waddle Road InterchangeProject
Alternative 3Diverging Diamond
Waddle Road/I-99 Interchange Project Alternative Analysis2040 BUILD IMPROVEMENT ALTERNATIVESPreliminary Overall Level of Service Results
As Presented in December 2012
Intersection Conventional Diamond Partial Cloverleaf Diverging Diamond(DDI)
Multi LaneRoundabouts
Single Point UrbanInterchange
(SPUI)AM PM SAT AM PM SAT AM PM SAT AM PM SAT AM PM SAT
Waddle Road /I-99 SB– Rt. 322 WB Ramps C(20.1) C(29.1) C(24.3) A (0.7)2 A (0.9)2 A (0.5)2 B
(15.5)B
(19.9) B (13.2) B(13.4)1 F(61.1)1 C(17.1)1
C(26.1) C(34.6) C(29.5)Waddle Road/ I-99 NB– Rt. 322 EB Ramps B(16.7) B(11.3) A(9.4) B (16.4) B (12.3) B (12.3) C(22.3) C(30.4) C(31.7) B(14.8)1 C(19.3)1 B(12.7)1
Waddle Road/Colonnade Boulevard C(21.6) D(43.4) D(37.2) C (23.1) E (57.3) D (47.6) C
(22.9)D
(54.9) D (49.2) B(15.0)1 D(30.4)1 C(19.6)1 C(23.3) D(49.6) D(43.5)
Waddle Road/Strouse Avenue A(4.5) A(3.8) A(4.7) A (4.5) A (4.3) A (4.9) A (4.4) A (3.8) A (4.9) A(4.5) A(4.2) A(4.7) A(4.5) A(4.0) A(4.7)
Waddle Road/Clearview Avenue A(8.4) B(11.4) B(10.3) A (8.4) B (11.1) B (10.8) A (8.8) B
(11.1) B (11.0) A(8.4) B(10.1) B(10.3) A(8.5) B(11.2) B(10.1)
1 Multi-Lane Roundabout2 No Traffic Signal Control
Ø Awaiting Confirmation of Traffic Analysis Results fromPennDOT
Ø Preparing Contract to Complete Preliminary EngineeringPhase (Anticipated NTP Feb. 2013)
Ø Complete Environmental Clearance Document
Next StepsAs Stated in December 2012 Presentation
Ø Additional Coordination with Centre County
Ø Supplemental Traffic Counts Conducted
Ø Analysis Methodology Change
Traffic Analysis Updates
Traffic Simulation ModelSingle SB Through Lane at Colonnade
Traffic Simulation ModelSingle SB Through Lane at Colonnade
Note the traffic stacking on the westbound off ramp
Traffic Simulation ModelIncludes Auxiliary SB Through Lane
Traffic Simulation ModelIncludes Auxiliary SB Through Lane
Widening Option A
SRR rt lane merge.pdf
Widening Option B
Widening Option C
Widening Option D – Preferred Option
Looking north along Waddle Road, between Colonnade and Strouse
Bridge Elevation
Ø Conventional Diamond - $ 10.4 Million
Ø Partial Cloverleaf - $12.5 Million
Ø Diverging Diamond - $ 11.7 Million
ConceptualConstruction Cost Estimate
As presented December 2012
NOTE: Does not include Right-of-Way or Utility Relocation CostsBridge cost = $4 Million for each alternative
Ø Additional Widening Colonnade to Strouse - $500,000
Ø Additional Utility Impacts (5 Utility Poles)
Ø Additional R/W from Oakwood Centre andWilliamsburg Square
Ø Revised Conventional Diamond - $ 11.0 Million
ConceptualConstruction Cost Estimate
December 2013
NOTE: Does not include Right-of-Way, Utility Relocation Costs, orRe-profiling Eastbound Route 322Bridge cost = $4 Million
Ø Awaiting Confirmation of Traffic Analysis Results fromPennDOT
Ø Complete Preliminary Engineering Phase (Spring 2014)
Ø Complete Environmental Clearance Document(Spring 2014)
Next Steps
Waddle Road Interchange Project
Questions?