w2 Battery Ups and Earthing

Embed Size (px)

Citation preview

  • 8/20/2019 w2 Battery Ups and Earthing

    1/36

     

    EEEEEETTTPPP / / /BBBSSS N N NL L L  

    SILVER

    CERTIFICATION COURSETELECOM SUPPORT INFRASTRUCTURE 

    BATTERY UPS AND EARTHINGVersion 2 June 2014

  • 8/20/2019 w2 Battery Ups and Earthing

    2/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 1 of 36

    For Restricted Circulation

    BATTERY UPS & EARTHING

    INDEX

    2.1  Introduction ..................................................................... 2 

    2.2  Objective ........................................................................... 2 

    2.3  Different methods of working of a battery .................... 3 

    2.4  Secondary cells (conventional) ....................................... 8 

    2.5 

    Maintenance free battery (VRLA) ................................. 9 

    2.6  Working and maintenance of UPS............................... 17 

    2.7  Earthing system in telecom ........................................... 22 

    2.8  Summary ........................................................................ 33 

    2.9  Self Assessment questions ............................................. 34 

    2.10  References and suggested further readings ................ 34 

  • 8/20/2019 w2 Battery Ups and Earthing

    3/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 2 of 36

    For Restricted Circulation

    2  BATTERY UPS & EARTHING

    STRUCTURE 

    2.1  INTRODUCTION 

    2.2  OBJECTIVE 

    2.3  DIFFERENT METHODS OF WORKING OF A BATTERY 

    2.4  SECONDARY CELLS (CONVENTIONAL) 

    2.5  MAINTENANCE FREE BATTERY (VRLA) 

    2.6  WORKING AND MAINTENANCE OF UPS 

    2.7  EARTHING SYSTEM IN TELECOM 

    2.8  SUMMARY 

    2.9  SELF ASSESSMENT QUESTIONS 

    2.10  REFERENCES AND SUGGESTED FURTHER READINGS 

    2.1  INTRODUCTION

    The secondary cell batteries can be utilized in many ways. However presently

    float working is adopted. The two type of batteries used are Conventional batteries and

    Maintenance Free VRLA batteries. Maintenance free, valve-regulated lead-acid (VRLA) batteries ensure a reliable, effective and user friendly source of power. It is spill proof,

    leak proof and explosion resistant and there is no need to add water or to clean terminals.

    Uninterrupted Power Supply (UPS) is required to provide stable AC in the event

    of failure of Mains. It comprises of Battery banks coupled with inverter. An inverter is an

    electrical device that converts direct current (DC) obtained from battery to alternating

    current (AC); the converted AC can be at any required voltage and frequency with the use

    of appropriate transformers, switching, and control circuits.

    Earthing is an essential part of any electric /electronic system to prevent damage

    and for proper operation of telecom equipment. Utmost care is required to be taken for

     provision of proper and effective earthing for various telecom installations.

    2.2  OBJECTIVE

    The objective of this chapter is:

      To know the different methods of battery working

      To understand operating procedure of of float scheme

      To explain initial charging and discharging

      To enumerate different meters used

      To explain the VRLA battery construction

     

    To enumerate the chemical reactions

  • 8/20/2019 w2 Battery Ups and Earthing

    4/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 3 of 36

    For Restricted Circulation

      To explain the method used for charging

      The principle of working of UPS system

      The alarms in the UPS System

      To list the objective of Earthing

      To explain the requirement of Effective Earthing

     

    To know the Earthing System for Electrical Installation

     

    To know the Earthing System for Telecom Installations

    2.3  DIFFERENT METHODS OF WORKING OF A BATTERY

    The secondary batteries can be utilized in any of the following ways:

    The charge discharge system:

    In this system the electrical energy derived from the supply mains is first

    converted into chemical energy and stored in the battery Subsequently the chemical

    energy is reconverted into electrical energy when the battery discharges into the exchange

    load. In the charge discharge system the entire DC supply for the equipment is taken from

    the battery.

    ii) Standby battery system: 

    In this system, the DC electrical energy for the operation of the equipment is

    drawn directly from the public AC power supply system through mains conversionequipment and the standby battery is kept fully charged and idle, i.e. not connected to the

    load. Whenever there is mains failure the equipment load is immediately transferred from

    the mains conversion equipment to the standby battery.

    Fig1. Charge discharge system

  • 8/20/2019 w2 Battery Ups and Earthing

    5/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 4 of 36

    For Restricted Circulation

    (iii) Float System:

    It is a variation of the standby battery scheme as in this system also, the battery

    supplies only the emergency reserve requirements of the equipment during mains failure.

    Unlike the standby battery scheme, the battery is always kept connected across the load in

    the float system in a fully charged state. But the operating conditions are so maintained

    that the floated battery does not discharge into the load as long as the mains power supply

    is available. The main distinction between the floating battery scheme and the standby

     battery scheme is that in the float scheme, there is absolutely no break in the DC power

    supply when the mains supply fails as the emergency battery takes over the load

    instantaneously. It is not the case for the standby scheme.

    In this system the battery is always kept connected across the load in the float

    system in a fully charged state. But the operating conditions are so maintained that the

    floated battery does not discharge into the load as long as the mains power supply is

    available. There is absolutely no break in the DC power supply when the mains supply

    fails as the emergency battery takes over the load instantaneously.

    The charge/discharge system was the standard system for manual exchange and

    telegraph power plant operation for a number of years but has been superseded by float

    systems for all the installations from late 60’s onwards. 

    The float system can be worked on a fully automatic basis or on a semiautomatic

     basis with a minimum of maintenance attention. Float systems are economical since

    Fig2. Standby battery system

    Fig3. Float Working

  • 8/20/2019 w2 Battery Ups and Earthing

    6/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 5 of 36

    For Restricted Circulation

     practically all the DC power requirements are taken directly from the public AC mains

    supply through converters. With the battery connected in parallel almost full battery

    capacity is available to carry the equipment load under mains failure conditions. It is

    usually to provide a battery capacity equivalent to six times the busy hour load in float

    systems.

    2.3.1 

    Operating procedure

    The operating procedure for floating batteries depends to a great extent on the

    floating voltage. The floating voltage cannot be higher than 2.35 volts per cell since

     beyond this limit, overcharging and vigorous gassing of the battery occurs. The lower

    limit for the floating voltage of a lead acid cell is 2 volts, since below this voltage, the

     battery will discharge. Within the permissible range of floating voltage from 2.0 to 2.35

    volts per cell, three distinct types of full float schemes have been evolved. They are as

    follows:-

    Batteries floated between 2.02 to 2.07 volt per cell or divided battery float system.

    Batteries floated between 2.15 to 2.20 volt per cell or parallel battery float system.

    Batteries floated between 2.24 to 2.30 volt per cell or end cell switching system.

    2.3.2  Requirements of float scheme

      Voltage should be maintained between prescribed limits.

      The capacity of the battery should be adequate to meet emergency.

      It should last longer.

     

    The energy losses should be minimum.

    2.3.3  Details of float schemes

    In automatic telephone exchanges the permissible range of voltage is from 46 to52 V. Instead of referring these float schemes by the floating voltage per cell, they are

    often named after the total number of cells in each set of the floated battery. From this

    standpoint these float scheme are usually referred as the 25 cell, 24 cell and 23 cell

    schemes.

    The 24 cell float scheme or parallel battery float scheme has now been prescribed

    as the standard method of supplying power to telephone exchanges. It is also adopted for

    60V plus and minus supply in telegraph offices and telex exchanges.

    In this scheme the battery voltage is maintained within very close limits (51.5  

    0.5). The required battery capacity, (ordinarily for 6 to 8 busy hours ) is provided equally

    in two sets of batteries to facilitate maintenance attention to any one battery set. Both the battery sets are floated in parallel simultaneously. Ref. Fig.3. as the floating voltage of

    2.15 V per cell is within the trickle charging range, a steady trickle charge current flows

    and recoups all capacity losses due to local action, partial discharge on peak loads etc.,

    incurred during the floating periods. Thus the floated battery is maintained at its full

    capacity, which is available as reserve for mains failure conditions. Refresher charges at

    three monthly intervals and yearly reconditioning cycle are given to the battery to ensure

    that the battery is kept in a healthy condition. Under mains failure conditions the battery

    voltage drops down to 48 volts for 24 cells and the lower operating voltage of exchanges

    is limited to 46 volts thus the end point for the discharge of the cells has to be limited to

    1.92 volt per cell. Thus only about 52% of the rated capacity of the cell is available for

    use. Therefore higher capacity batteries are required.

  • 8/20/2019 w2 Battery Ups and Earthing

    7/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 6 of 36

    For Restricted Circulation

    2.3.4  Initial Charging

    Initial charging is the charge received by any battery for the first time after

    installation. The following procedure is a general guideline for the first or initial charge.

    The instructions given by the manufacturer is to be followed strictly.

     

    General:Make sure that the battery room is well ventilated. Install batteries so that they are

    not exposed to direct rays from the sun and are away from steam pipes, radiators and

    other heat generating equipment, as a warm battery tends to have a self discharge at an

    accelerated rate, increasing the load on the power supply and shortening life of the

     battery. Align the cells and make sure all connections are tight.

      Initial Charge

    Before placing the battery on charge, check and record the open circuit voltage of

    every cell. After this connect the battery for charging continuously at the rate specified

    for 80 hours or as specified by the manufacturer by using direct current. The voltage

    output from the charger should be minimum 2.7 volts per cell. Another method of

    charging prescribed is start the charging @ 14% of AH capacity and as the cells start

    gassing reduce the rate of charge to 7% till the end of the charge.

    As soon as the battery is put on charge, take another set of voltage readings and

    enter these readings opposite to open circuit voltage readings. This is to check if there are

    any reversed cells and to avoid reverse connection of the entire battery. If the battery is

    connected properly and there are no reversed cells, proceed with charging. During first

    charge take individual cell voltage, S. G. and temperature readings for every eight hours

    and record

    The cells are considered to be fully charged when values of cell voltage and S.G.of electrolyte corrected to 27o C remain constant for three consecutive hours at the end of

    approximately 80 hours of charging. However in spite of achieving constancy of S.G. and

    voltage readings, initial charge has to be continued for 80 hours (in the case of 80 hrs of

    charge method). The voltage at the end of initial charge will be 2.65 to 2.7 volts per cell

    The temperature of electrolyte in the cells at any period of charge should not be

    allowed to rise beyond 50o C

    At the end of charging the S.G. of electrolyte is to be adjusted to 1.200  0.005 at

    27 o C. If the S.G. at the end of charging is above 1.200, add distilled water and if it is

     below 1.200 add 1.400 S.G. acid. If any of the cells show abnormally low S.G. / voltage

    at the end of 80 hours initial charging inform the supplier.After ensuring that the cell isfully charged, give a rest of 12 to 24hrs and conduct test discharge to ensure the

    following.

      The capacity of the battery.

      The efficiency of the battery.

      The specific gravity range of the battery.

     Normally the capacity does not reach 100% until 4 or 5 cycles of charge

    discharges.

    2.3.5  Test Discharge

    Test discharge is conducted at 10 hr rate.

  • 8/20/2019 w2 Battery Ups and Earthing

    8/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 7 of 36

    For Restricted Circulation

    Instruments and accessories required

    (i) Artificial resistance load

    An artificial resistance load made up of lamp resistance or coils of wires is used in

    case of low capacity batteries. For large cells electrodes immersed in water with little acid

    or wire coils (300 lbs GI) are used. Care is taken to avoid contact between the electrodes.(ii) Voltmeter

    Two voltmeters with suitable ranges are required to measure the terminal voltages

    across the individual cells and the battery. The voltmeter should have a resistance of not

    less than 1000 ohms per volt and an accuracy of 1% of the full scale reading. AVO meter

    / Digital Multi meter can be used in place of voltmeter.

    (iii) Ammeter

    Each division of the ammeter scale should denote not more than 1% of the full

    scale reading. It should be accurate to 1% of the full scale reading. The scale of the meter

    should be so chosen that the value of the currents to be measured comes to 2/3rd of thefull scale of the meter.

    (iv)Hydrometer

    The hydrometer should be capable of indicating S.G. reading in the steps of 0.002

    (2 points) . In any event the steps should not be at intervals longer than 0.005 (5 points)

    (v)Thermometer

    A thermometer capable of reading correct to 0.5c or 1F should be used.

    2.3.6  Discharging procedure

     

    Connect cable lugs to the cable for connecting artificial load to the battery.  Prepare artificial load.

     

    Connect the connecting cable to the artificial load.

     

    Disconnect the battery from the float /charger.

      Connect the connecting cable to the ammeter in the circuit.

      Take the open circuit voltage of the battery and of each individual cell.

      Connect the connecting cable to the battery fuse output by nut and bolts in

     battery room.

      Adjust the artificial load to get 10hour discharge rate. Adjust the artificial

    load frequently to maintain constant current.

      The total voltage of the battery, the voltage, specific gravity and

    temperature of each cell should be read at the beginning of the discharge

    and at hourly intervals up to the 8th hour and these readings are taken

    every 15 minutes after 8-1/2 hours of discharge. These readings should be

    recorded in the form given.

      Stop discharge if the electrolyte temperature exceeds 37.8 c (100F) and

    start discharge when the temperature falls sufficiently below 35 c.

      The test discharge shall be stopped as soon as the overall battery voltage

    reaches a value equivalent to 1.85 V x no. Of cells in series (44.4 V for 24

    cell Battery) or when the voltage across any cell falls to 1.70V whichever

    is earlier.

     

    Cells have to be recharged soon after discharge

  • 8/20/2019 w2 Battery Ups and Earthing

    9/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 8 of 36

    For Restricted Circulation

    2.3.7  Recharging

    Recharging is done at two rates. The staring rate being maintained till the cells

    reach 2.4 Volts per cell, after which at the finishing rate till end of charge. The high rate

    of charge is normally 14 % and finishing rate is 7 % of battery capacity. Charging should

     be completed at 7% of the capacity till full charge. Alternatively, the cells can be charged

    at 10 hour rate till constancy. The battery is considered fully charged when all the cells

    gas freely for 2 hours and the cell voltage and S.G. remain constant for 3 consecutive

    hours thereafter.

    It is recommended to conduct cycles of discharge and charge as above before

    connecting to the associated equipment. Find out the efficiency of the battery. If 100%

    capacity is attained in the 1st discharge itself then there is no need to discharge it for a

    second time. Strict adherence to the instructions and maintenance manual supplied by

    manufacturer is a must for making any complaint to the supplier. All records as per the

    supplier’s is instructions must be maintained. 

    2.4 

    SECONDARY CELLS (CONVENTIONAL)One of the primary requirements of any telephone system is that service shall be

    available to the subscribers at all times. The electrical energy required for signaling,

    switching, speech transmission etc. in telephone exchanges is derived either directly or

    indirectly from the public electricity system. In order to provide uninterrupted service, the

    exchange power supply system is designed to give continuous energy to the system. So

     provision is also made for alternate source of supply in the event of mains failure. This

    emergency energy is derived from Batteries of secondary cells or a combination of

     battery and prime mover generator sets.

    The secondary cells in general use in our dept. are of lead acid type. Secondary

    cells are electrolytic cells for generation of electric energy. These cells can be restored toits original condition after they are discharged. This restoration is done by passing a

    current in a direction opposite to the flow of current in the cell during the discharge.

    2.4.1  Type of secondary cells

    There are three types of storage (secondary) cells in use. They are (1) lead-lead-

    acid type (2) Nickel-iron-alkaline and (3) Nickel-Cadmium alkaline type. In telecom only

    lead-lead-acid type is used. They are commonly known as lead acid type cell. These cells

    have electrodes of lead immersed in an electrolyte of dilute sulphuric acid in a suitable

    container

    There are two lead-acid designs in use today: the flooded and the valve regulated

    (VRLA). Of the two designs, the flooded battery is the more reliable and should be the battery of choice for mission critical applications. VRLA batteries have the advantage of

    lower cost and lower space requirements

  • 8/20/2019 w2 Battery Ups and Earthing

    10/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 9 of 36

    For Restricted Circulation

    2.5  MAINTENANCE FREE BATTERY (VRLA)

    Maintenance free, valve-regulated lead-acid (VRLA) batteries ensure a reliable,

    effective and user friendly source of power. It is spill proof, leak proof and explosion

    resistant and there is no need to add water or to clean terminals. It has low self-discharge

    rate which eliminates the need for equalizing charges.

    2.5.1  VRLA Technology

    The container of VRLA Battery is made of polypropylene. Each plate is

    individually wrapped by a highly absorbent, micro porous glass separate developed

    specially for VRLA batteries. The chemically inert glass ensures lifelong service. The

    absorbed electrolyte ensures that there is no spillage even in the unlikely event of

     puncture of the cell. Gas evolution under float conditions is negligible. The water loss

    throughout life due to gassing is roughly 0.1% of the total electrolyte present in the cell.

    This will in no way affect performance and also eliminate the need for specially

    ventilated battery room and acid resisting flooring. As the batteries can be installed in

    stacks, there will be considerable space saving also.

    Various capacities of Batteries are 120 AH, 200 AH, 400 AH, 600 AH, 1000 AH,

    1500 AH, 2000 AH, 2500 AH, 3000 AH, 4000 AH and 5000 AH.

    2.5.2  A brief review of Chemical Reaction

    The electrode reaction in all lead acid batteries including VRLA battery is

     basically identical. As the battery is discharged, the lead dioxide positive active material

    and the spongy lead negative active material react with the sulphuric acid electrolyte to

    form lead sulphate and water. During charge, this process is reversed. The Columbic

    efficiency of the charging process is less than 100% on reaching final stage of charging or

    under over charge conditions, the charging energy is consumed for electrolytic

    decomposition of water and the positive plates generate oxygen gas and the negative

     plates generate hydrogen gas.

    Fig4. Secondary Cell (Conventional)

  • 8/20/2019 w2 Battery Ups and Earthing

    11/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 10 of36

    For Restricted Circulation

    Under typical charging conditions, oxygen at the positive plate occurs before

    hydrogen evolution at the negative. This feature is utilized in the design of VRLA

     batteries. In flooded cells, the oxygen gas evolved at the positive plate bubbles upwards

    through the electrolyte and is released through the vents. In MF-VRLA batteries the

    oxygen gas evolved, at the positive plate, instead of bubbling upwards is transported in

    the gas phase through the separator medium to the negative plate. The separator is ahighly absorbent glass matrix type with very high porosity, designed to have pore volume

    in excess of the electrolyte volume (starved electrolyte design), due to which the oxygen

    gas finds an unimpeded path to the negative plate.

    The oxygen gas gets reduced by reaction with the spongy lead at the negative

     plate, turning a part of it into a partially discharged condition, there by effectively

    suppressing the hydrogen gas evolution at the negative plate. This is what is known as the

    oxygen recombination principle. The part of negative plate which was partially

    discharged is then reverted to the original spongy lead by subsequent charging.

    Thus, a negative plate keeps equilibrium between the amount which turns into

    spongy lead by charging and the amount of spongy lead which turns into lead sulphate byabsorbing the oxygen gas generated at the positive plate. The oxygen recombination

     principle can be shown by the following reaction:

    Reaction at positive plate:

    H2O = ½ O2 + 2e –   … (1) 

    Reaction at negative plate :

    Pb + 1/2O2 = PbO … (2) 

    PbO+H2SO4 = PbSO4 + H2O … (3) 

    To reaction (1)

    PbSO4 + 2H+ + 2e –   = Pb + H2SO4 … (4) 

    To reaction (3)

    To reaction (2)

    The total reaction at negative plate

    ½O2 +2H+ = H2O

    Thus, the oxygen recombination technology makes the battery virtually

    maintenance Free.

  • 8/20/2019 w2 Battery Ups and Earthing

    12/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 11 of36

    For Restricted Circulation

    2.5.3  Freshening Charge

    Batteries lose some charge during transportation as well as during the period prior

    to installation. A battery should be installed and given a freshening charge after receipt as

    soon as possible. Battery positive (+) terminal should be connected to charge positive (+)

    terminal and battery negative (-) terminal to charger negative (-) terminal.

    The charge intervals for storage are given below.

    Temp in centigrade Charging interval in months

    32 6.0

    37 4.5

    42 3.0

    47 2.25

    52 1.5

    Storage beyond this period without freshening charge can result in excessive

    sulphation of the plates.

    Fig5. Power Stack Cell –  Cut Section

  • 8/20/2019 w2 Battery Ups and Earthing

    13/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 12 of36

    For Restricted Circulation

    2.5.4  Constant Voltage Method

    Constant voltage is the only charging method recommended. Most modern

    chargers are of the constant voltage type.

    Determine the maximum voltage that may be applied to the system equipment.

    This voltage, divided by the number of cells connected in series, will establish themaximum volts per cell (VPC) that may be used.

    Table B lists recommended voltages and charge times for the freshening charge.

    Select the highest voltage the system allows but not exceeding 2.37 volts per cell to

     perform the freshening charge in the shortest time period. The charging current should be

    limited to a maximum of 20% of the rated capacity in Amps.

    Table 1

    Cell Volts Time

    2.25 30 hrs

    2.30 12 hrs

     Note: Time periods listed in Table 1 are for temperatures from 15oC to 40°C. For

    temperatures below 15°C double the number of hours. Charging

    The charging current should be limited to a maximum of 0.2 times of AH

    Capacity. Widely accepted charging methods use a current of 0.1xC10 (C10 = AHCapacity when discharged at 10 hr rate) Example:

    A 2000 AH VRLA battery is to be charged as under

    0.2 x 2000

    0.2 x 2000 = 400 Amps or

    0.1 x 2000 = 200 Amps ( as per TEC recommendation)

    Raise the voltage to the maximum value not exceeding 2.37 volts per cell

     permitted by the system equipment. When charging current has tapered and stabilized (no

    further reduction for three hours), charge for the hours shown in the above table or until

    the lowest cell voltage ceases to rise. Correct charge time for the temperature at the time

    of stabilization. To determine lowest cell, monitoring should be performed during the

    final 10% of the charge time. All POWER STACK batteries are rated to an end cell

    voltage of 1.75 VPC at all rates of discharge.2.5.5  Floating Charge Method

    In this type of operation, the battery is connected in parallel with a constant

    voltage charger and the critical load circuits. The charger should be capable of

    maintaining the required constant voltage at battery terminals and also supply normal

    connected load where applicable. This sustains the battery in a fully charged condition

    and also makes it available to resume the emergency power requirements in the event of

    an AC power interruption or charger failure.

  • 8/20/2019 w2 Battery Ups and Earthing

    14/36

  • 8/20/2019 w2 Battery Ups and Earthing

    15/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 14 of36

    For Restricted Circulation

    temperature compensated voltage  –   regulated charger after a discharge provides thealternate method for determining the full state of charge. The temperature compensation

    factor is – 3 mV per cell °C rise from ambient temperature of 27°C.

    Under normal conditions the batteries are floated at around 2.25 volts per cell, i.e.

    in a DOT System 24 cells are floated at 53.5 volts. During charging as the cells approach

    full charge, the battery voltage rises to approach the charger output voltage, i.e. 53.5 volts

    and the charging current decreases to the float current value of around 50 mA/100 AH for

    VRLA batteries. So, when the charging current has stabilized at the float current for three

    consecutive hours or the voltage across the battery bank terminals is constant for six

    consecutive hours, then the battery bank can be considered as having reached full state of

    charge.

    If the charging voltage has been set at a value higher (but equal to or less than

    2.30 VPC) than normal float voltage (so as to reduce charging time), it is normal practice

    to reduce the charging voltage to the float value of 2.25V after 12 hrs. Then the float

    current will soon stabilize and the above methods can be adopted for determining the state

    of charge.

    C10 0.43

    C5 0.58

    C3 0.68

    CAUTION:

    It was noticed in some of the exchanges during the normal course of day to day

    working, the exchange failing due to low voltage condition even though the batteries

    appear to be in healthy condition while they are on float as indicated by the daily readings

    recorded. To avoid this it is recommended that the batteries be discharged periodically;

    say once in a month by switching off the FR and the exchange load may be allowed to be

    taken by the battery for half an hour. The individual cell readings are to be taken and no

    cell voltage should fall below 2.10 V. Some cells which are faulty, may show negative

    values with reference to the other cells. If the voltage of any individual cell differs from

    others in this manner it is recommended that the cell be replaced.

    Table 3

    % State of Charge Open Circuit Voltage

    100 2.15

    90 2.13

    80 2.11

    70 2.09

    60 2.07

  • 8/20/2019 w2 Battery Ups and Earthing

    16/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 15 of36

    For Restricted Circulation

    50 2.05

    40 2.03

    30 2.01

    20 1.97

    0 1.95

    Float charging is at 2.23 VPC and the recommended boost charge voltage is 2.30

    VPC. If the charger does not have a float cum boost mode, it is important to switch over

    to float after boost not later than 24 hours under steady current conditions.

    2.5.8  Safety precautions

    In normal use, VRLA batteries will not release hydrogen and oxygen gasses, will

    not release acid mist and will not leak acid. Thus they are safer than conventional leadacid batteries. However, under abnormal conditions, or as a result of damage, misuse or

    abuse, these potentially hazardous conditions can occur. Hence the instructions given by

    the supplier is to be strictly followed.

      Stacking limitation- The recommended limits on stacked battery

    configurations are as follows.

    Module arrangements Max Modules

    Horizontal single stack 8 High

    Horizontal multiple stack 8 High

      Module assembly- This design is arranged to provide the shortest connections

     between modules using rigid lead coated copper strip connectors to maximise

    system performance Modules are identified with a label located at the end of

    the module. Each module is provided with a protective cover to prevent

    accidental contact with module live electrical connections.

    2.5.9  Monitoring Of VRLA Batteries

    The points to be taken care to observe the health of the battery and expectedresidual capacity

      Periodic physical inspection of each cell of the battery for cracks and leaking etc.

      Discharge of battery for a short duration and recording the voltages of each cell

    in the string.

      Measurement of a mark deviation (>30%) in the impedance or conductance ofthe cell as compared to the one recorded at the time of commissioning.

      Measurement & recording of cell temp periodically.

      Float Voltage of cells & its comparison with the midpoint voltage.

      Float current in fully charged battery.

  • 8/20/2019 w2 Battery Ups and Earthing

    17/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 16 of36

    For Restricted Circulation

      Periodic Physical Inspection

      Check for any crack or leakage every month. If not every month, at least once in

    two months.

      Battery Partial Discharge Test- Put battery to a test discharge for 30 minutes

     by shutting power plant so that 20% of the battery is discharged. This can be

    decided by the table supplied by the manufacturer. Record the Voltage of eachcell. Any cell showing more than 5% variation compared to voltage of other cell

    can be potential weak cell.

      Impedance Measurement- Take impedance measurement when the charger is

    on and the battery is on float. Any change in impedance/conductance of the cell

    more than 40% shows imminent failure of the battery/cell. A change of

  • 8/20/2019 w2 Battery Ups and Earthing

    18/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 17 of36

    For Restricted Circulation

      Do not mix the batteries of different capacities or makes.

      Do not combine ordinary conventional batteries with VRLA batteries.

      Do not install physically damaged cells.

      Do not dump any waste materials in the battery room.

    2.6 

    WORKING AND MAINTENANCE OF UPSUPS stands for Uninterrupted Power Supply. It is required for providing

    uninterrupted and stable power supply, even during the failure of Mains.

    An inverter is an electrical device that converts direct current (DC) to alternating

    current (AC); the converted AC can be at any required voltage and frequency with the use

    of appropriate transformers, switching, and control circuits. Solid-state inverters have no

    moving parts and are used in a wide range of applications, from small switching power

    supplies in computers, to large electric utility high-voltage direct current applications that

    transport bulk power. Inverters are commonly used to supply AC power from DC sources

    such as solar panels or batteries. The inverter performs the opposite function of a rectifier.

    There can be different types of inverters. Modified sine wave Pure sine wave & Grid tieetc.

    2.6.1  DC power source utilization

    An inverter converts the DC electricity from sources such as batteries, solar

     panels, or fuel cells to AC electricity. The electricity can be at any required

    voltage; in particular it can operate AC equipment designed for mains operation,

    or rectified to produce DC at any desired voltage.

    1.  Micro-inverters convert direct current from individual solar panels into

    alternating current for the electric grid. They are grid tie designs by default.2.  Uninterruptible power supplies

    An uninterruptible power supply (UPS) uses batteries and an inverter to supply

    AC power when main power is not available. When main power is restored, a

    rectifier supplies DC power to recharge the batteries.

    3.  Induction heating

    Inverters convert low frequency main AC power to higher frequency for use in

    induction heating. To do this, AC power is first rectified to provide DC power.

    The inverter then changes the DC power to high frequency AC power.

    4. 

    HVDC power transmissionWith HVDC power transmission, AC power is rectified and high voltage DC

     power is transmitted to another location. At the receiving location, an inverter in a

    static inverter plant converts the power back to AC.

    5.  Variable-frequency drives

    A variable-frequency drive controls the operating speed of an AC motor by

    controlling the frequency and voltage of the power supplied to the motor. An

    inverter provides the controlled power. In most cases, the variable-frequency drive

    includes a rectifier so that DC power for the inverter can be provided from main

  • 8/20/2019 w2 Battery Ups and Earthing

    19/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 18 of36

    For Restricted Circulation

    AC power. Since an inverter is the key component, variable-frequency drives are

    sometimes called inverter drives or just inverters.

    2.6.2  Principle of UPS system

    The Block diagram of UPS is given above single phase A.C. supply is first

    rectified to 120V D.C. supply. Across these 2 sets of 40 AH, 120 volts battery sets

    are floated. The combined D.C is then fed to the inverter, which converts into A.C

    of 220 volts. During the available period of input AC mains, the battery sets will

     be trickle charged and the load will be taken by rectifier only. During the absenceof input A.C. mains, the battery set will be taking the load. Another type of UPS

    system used is designed to work on -48 V D.C supply fed from the exchange

     power plant.

    2.6.3  Circuit Description

      Basic designs

    In one simple inverter circuit, DC power is connected to a transformer through the

    centre tap of the primary winding. A switch is rapidly switched back and forth to

    allow current to flow back to the DC source following two alternate paths through

    one end of the primary winding and then the other. The alternation of the directionof current in the primary winding of the transformer produces alternating current

    (AC) in the secondary circuit..

    The electromechanical version of the switching device includes two stationary

    contacts and a spring supported moving contact. The spring holds the movable

    contact against one of the stationary contacts and an electromagnet pulls the

    movable contact to the opposite stationary contact. The current in the

    electromagnet is interrupted by the action of the switch so that the switch

    continually switches rapidly back and forth. This type of electromechanical

    inverter switch, called a vibrator or buzzer, was once used in vacuum tube

    automobile radios. A similar mechanism has been used in door bells, buzzers and

    Rectifier

    / chargerInverter

    Battery

    AC mains DC DC AC Output

    Fig6. Block diagram of UPS System

  • 8/20/2019 w2 Battery Ups and Earthing

    20/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 19 of36

    For Restricted Circulation

    tattoo guns. As they became available with adequate power ratings, transistors and

    various other types of semiconductor switches have been incorporated into

    inverter circuit designs.

    UPS units are divided into categories based on which of the above problems they

    address and some manufacturers categorize their products in accordance with the

    number of power-related problems they address.

      Specifications Of UPS Systems

    a) Input 230V, 1 , A.C. supply

     b) Input BTY 120V, 40 AH, two sets of

    Batteries.

    c) Output 220 volts, A.C

    d) Output current For 5 KVA it is 21.5 Amps.

      Alarms In UPS System

    1) Low Battery - If the battery voltage falls below a specific voltage.

    2) Over load - If the load on UPS is more than its capacity UPS will be tripped

    and overload alarm comes

    Fig7. 

    Basic design of UPS

  • 8/20/2019 w2 Battery Ups and Earthing

    21/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 20 of36

    For Restricted Circulation

    3) Output High - When output voltage becomes high UPS will be tripped and this

    alarm comes.

    4) Output low When output voltage becomes low UPS will be tripped and this

    alarm comes.

    5) Trip This LED glows once if the inverter trips.

    2.6.4  UPS Maintenance

    Maintenance of the UPS consists of preventive and corrective maintenance.

    Preventive maintenance consists of a scheduled list of activities. Performing these

    activities keeps the UPS in good working order and helps to prevent failures.

    Corrective maintenance is performed as a result of a failure. Corrective

    maintenance fixes the problem and gets the unit working again.

    A general guide for the maintenance requirements of the UPS systems modules,

    static switches, and controls is provided. Although electronic components are not

    subject to wear in the same degree as electromagnetic (EM) components, they do

    require systematic maintenance.

     

    Preventive maintenance

    Periodic maintenance is required to maintain the integrity and lifetime of the

     battery. Power electronic equipment also requires scheduled maintenance even

    though solid-state devices are used. Preventive maintenance may require that the

    UPS system be shut down. A transfer of the critical load which may not provide

    the power enhancement capabilities of an UPS system is something that the usermust tolerate in order to obtain maximum reliability and minimize downtime and

    repair costs.

      Equipment record

    This record should list the basic information on the equipment itself, e.g.,

    manufacturer’s identification, style, serial, size, location, etc., and incorporateinventory-control data for spare parts. Warranty requirements covering

    uninterruptible operating conditions should be abstracted from the user’s manual. 

     

    Repair cost record

    This record should provide a history of repair and associated costs of maintenancefor the UPS system. It is an essential diagnostic record for avoiding future

    difficulties, especially for systems determined to be of poor quality, misapplied, or

    marginal for the application.

     

    Inspection check list

    This list should provide necessary and pertinent information on points to be

    checked and establish the recommended recurring dates when these checks should

     be made. Since shutdown may require a sliding window period, the amount of

    time for which this request must precede the shutdown window should also be

    stated.

  • 8/20/2019 w2 Battery Ups and Earthing

    22/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 21 of36

    For Restricted Circulation

      Periodic maintenance schedule

    This schedule provides a complete listing of the day-to-day, weekly, monthly, and

    annual duties which should be reviewed on the same periodic time basis so that

     potential trouble situations can be investigated and corrected as soon as possible.

     

    Maintenance inspection and repair records

    These necessary and vital documents should be completed in detail by the

    inspector or an assigned individual in the maintenance department. Maintenance

     personnel usually report their findings and corrective action on assignment sheets

    or job cards. Permanent records are a useful guide to each UPS system’s generalcondition and reliability. It is important to know the frequency and type of repair

    and how often there is a need for a complete overhaul.

      Use of records

    These records provide for a workable preventive maintenance program. The

    information obtained from the necessary periodic inspections can be quickly lost.

    This is particularly true when test results are required. Unless records and data on

    the test and performance of equipment are retained, the maintenance program will

     be defeated. Unless records are updated at each succeeding test period, valuable

    information is lost. Comparative test data materially assists an UPS specialist in

    defining problems, especially when test results differ from manufacturers’recommended settings or actual factory test data. Significant changes in

    comparative test data can, in general, be related to the equipment’s condition. 

      Scheduling

    Scheduling of UPS and battery maintenance is normally based on the

    manufacturers’ recommendations. Since an UPS system is vital to the operation ofcritical loads, it may be considered advisable to provide more inspections thanthose the manufacturer recommends. Certain items on the UPS should be

    inspected daily or weekly. This inspection can be done by operating personnel, but

    data should be recorded and sent to the appropriate maintenance point not more

    than 5 days after being recorded. Battery maintenance should be done by

    maintenance personnel. Visual monitoring data should be recorded daily for the

    UPS, and if recorded for the battery, the recorded data should be handled and sent

    on to the maintenance department on a weekly basis.

      Periodic system status checks

    The continued monitoring of the operating status of any electronic equipmentgreatly enhances the probability that failure of that equipment will be prevented.

    Daily observation is advised but do not provide less than weekly checks.

    Personnel involved in status monitoring should be those most concerned with the

    equipment’s proper functioning. 

    2.6.5  UPS Maintenance Checklist

    Regular equipment testing should be part of a facility’s UPS maintenanceschedule. Such a schedule might include the following elements:

     

    Quarterly:

  • 8/20/2019 w2 Battery Ups and Earthing

    23/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 22 of36

    For Restricted Circulation

    Visually inspect equipment for loose connections, burned insulation or any other

    signs of wear.

      Semiannually:

    Visually check for liquid contamination from batteries and capacitors.

    Clean and vacuum UPS equipment enclosures.

    Check HVAC equipment and performance related to temperature and humidity.

      Annually:

    Conduct thermal scans on electrical connections to ensure all are tight and not

    generating heat, which is the first and sometimes only indication of a problem. A

    non-evasive diagnostic tool helps technicians identify hot spots invisible to the

    human eye. Technicians should retorque if thermal scan provides evidence of aloose connection. Provide a complete operational test of the system, including a

    monitored battery-rundown test to determine if any battery strings or cells are near

    the end of their useful lives.

      Biannually:

    Test UPS transfer switches, circuit breakers and maintenance bypasses. If a

    generator is part of the building’s emergency-power system and feeds the UPS, italso will need to be tested monthly or quarterly. Most facilities have a generator-

    maintenance schedule in place in which testing frequency is defined. A UPS

    typically is sized to carry the load for a short period of time. Longer outages

    require backup-power generation to maintain critical services. Each facility isunique, and managers need to develop a maintenance schedule to suit each site’sspecific needs.

    2.7  EARTHING SYSTEM IN TELECOM

    Earthing is an essential part of any electric /electronic system. Utmost care is

    required to be taken for provision of proper and effective earthing for various

    telecom installations. This chapter discusses about various types of earthing which

    are used in telecom installations.

    The objective of Earthing system may be summarized as follows:-

     

    Reduction of Crosstalk and Noise is achieved through proper Earthing System in theTelecom Network.

      Earthing is used to afford convenience & reliability, in the operative path of thecircuits involved in the switching apparatus of telecom circuits.

      Used as return path in telegraph and voice circuits.

      Earthing is used for protection of costly apparatus and persons against foreign

    voltages and leakage currents.

     

    Earthing is used for protection of buildings and equipments from lightening strikes.

  • 8/20/2019 w2 Battery Ups and Earthing

    24/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 23 of36

    For Restricted Circulation

      Earthing in power supply systems is used to effect reliability of power as it helps to

     provide stability of voltage regulations, preventing excess fluctuations and provides a

    measure for protection against lightening.

      To divert stray RF energy from sensitive audio, video control and computer

    equipments.

    2.7.1 

    REQUIREMENTS FOR EFFECTIVE EARTHING

    An earthing system must meet the following specifications:-

    The resistance to the earth must be within allowable limit for the particular

    application.

    The electrode buried in ground must be:

      Having good electrical conductivity to carry highest specified load current.

      Immune to the corrosive action of the soil all along its path.

     

    Of sufficient mechanical strength to enable them to install without any

    damage.  Inert i.e. must not be a source of corrosion within the system to be

     protected.

     

    The earth electrode must provide as much as area of contact as possible

    with the soil to reduce the resistance of the current path.

      The resistance of the earth connection must remain within the allowablelimits.

    2.7.2  EARTHING SYSTEM FOR ELECTRICAL INSTALLATION

    Earthing or grounding means to connect the equipment or electrical system to the

    general mass of the earth. There are two types of earthing.

     

    System earthing.

     

    Equipment earthing.

    2.7.3  System Earthing:-

    It means connecting to the earth, the neutral point i.e the star point of generator,

    transformer, rotating machines, and of grounding transformer. If neutral point of a

    system is earthed, the phase to ground voltage under earth fault condition do not

    rise to high value

    Let us consider a system in which neutral is not earthed. If there is Earth fault on

    B-phase, the voltage of R and Y (wealthy) phases to the earth becomes equal to

    the line voltage. The rise in voltage causes stress on the insulation. Earthing

     provides protection against such rise.

  • 8/20/2019 w2 Battery Ups and Earthing

    25/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 24 of36

    For Restricted Circulation

    It constitutes the connecting of non-current carrying metal parts of a equipment to

    the earth. It provides protection to operating personnel and equipment by ensuring

    operation of protective control gear.

    Advantages of Neutral Earthing:-

      Connecting the neutral of an electrical system to earth has following

    advantages.

      Arcing grounds are eliminated.

      Voltage of healthy phases with respect to earth does not rise √3 times tonormal value.

     

    Insulation is prevented from stress of high surge voltage and hence provides long life to insulation & equipment.

      Stable neutral point.

     

    Earth fault relay function becomes simple & reliable.

     

    Greater safety to personnel & equipment.

    2.7.4  Types of Earthing:-

    Sub-station earthing is mainly of two types

    a)  Mesh earthing

     b)  Electrode earthing

    a) Mesh Earthing :-

    It is formed by steel rods (30 to 40 cm dia) laid horizontally at a depth of about

    0.5 meter below ground surface to give a shape of mesh. The length and breadth

    are formed by welding of steel rods.

     b) Multiple Electrode system

    Where the required earth resistance cannot be obtained by a single driven

    electrode, it will be necessary to install additional electrodes and connect them

    together. To obtain the best results, multiple earth rods must be separated by a

    distance at least equal to their depth in the ground. Drive the rod head to 100 mm

     below the ground surface and connect together with earth wire buried at least 300mm below ground. Hand tools are generally suitable in light soils and the

    situations where it will not be necessary to drive the rods deeper than four meters.

    For harder driving conditions and greater depths power tools provide quicker and

    more effective means of installing the rods.

    Good quality earth wires (stainless steel or copper) are used to connect together

    the earth electrodes to the equipment, which must be earthed. Wherever possible

    the earth wires should be run without joints between electrode positions. Sharp

     bends should be avoided in the earth wires as these could be the source of faults

    under lightning discharge conditions.

    Fig8.  Neutral Earthing

  • 8/20/2019 w2 Battery Ups and Earthing

    26/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 25 of36

    For Restricted Circulation

    2.7.5  Earth Electrode:-

    Earth electrodes, which are in use, are

    a) Rod & pipe electrode

     b) Strip electrode

    c) Plate electrode

    a) Rod or Pipe Electrodes:-

    Pipe electrode shall not be smaller than 40 mm internal diameter if of galvanized

    iron. The length of the pipe electrode shall be minimum 4.5 meter. If one

    electrode fails to give the required resistance, no. of such electrodes shall not be

    less than twice the length electrodes. The G.I. Pipe shall be cut tapered at bottom

    and provided with holes of 12 mm dia drilled not less than 7.5 cm. from each

    other up to 2 mt length from bottom.

     b) Strip Electrodes:-

    It shall not be smaller in size than 40 Sq.mm section if of copper and 25x4 mm if

    of galvanized iron. For round conductors it should be not less than 3 mm2 in case

    of copper and 6 mm2 if of galvanized iron. The length of buried conductor shall

    not be less than 15 meter laid in trench not less than 0.5 meter depth.

    c) Plate Electrode:-

    In it, the plate is made of either copper or galvanized iron. This type of earthing

    (as shown in Fig.) is mostly used in our department. Size of copper plate shall not

     be less than 600 x 600 x 3 mm. And that of G.I. be 600 x 600 x 6 mm. Plate shall

     be 3 meter. Where earth resistance is not sufficient with one plate, two or more

     plate electrodes may be connected in parallel. This type is most suited forgenerating stations & sub-stations.

    2.7.6  Earthing Conductor :-

    The conductor from Earth Electrode to Earth shall be of the material as Earth

    electrode i.e. G.I. or copper and be in the form of strip or wire size of Earthing

    conductor which shall not be less than the following

      Four mm dia copper wire.

      Five mm dia G.I. Wire.

      25 x 4 mm the power of 2 G.I. Strip.

     

    20 x 3 mm the power of 2 Copper Strip.However Earthing conductor, shall not be more than 150 Sq. mm in Case of G.I.,

    or 100 Sq. mm in case of copper, unless otherwise specified.

    2.7.7  Types of Telecom Earthing

    The various types of earthing practices adopted for earthing the Telecom

    Equipments as per the relevant Engineering instructions are listed below:

      Ring earthing

      Plate earthing

      Spike Earthing

  • 8/20/2019 w2 Battery Ups and Earthing

    27/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 26 of36

    For Restricted Circulation

      Mesh earthing

      Static earthing

      Ring Earthing

    A GI strip of 50 x 3mm is laid in a trench 30 cm wide and depth 1 to 1.5m.

    The trench to be minimum 1m away from the building.

    The layout of ring earth is shown in fig. (9)

      The ring earth

    The ring earth to be provided in all transmission and switching system where

    space is available. This type is mainly used for tower earthing.

    In case of new bldg. ring earth to act as equipotential bonding and all earthing

    equipments to be extended from ring earth.

    Fig9. 

    Ring earth

  • 8/20/2019 w2 Battery Ups and Earthing

    28/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 27 of36

    For Restricted Circulation

    Commoning of Earths for Equipotential Bonding

    For Telecom Installation the existing earths are to be commoned i.e. tower earth,

     bldg.earth, lightning earth, equipment earth, power plant earth, engine alternator

     body earth, etc., to bring equipotential situation.

    The sheath / armour of underground cable bringing the LT supply inside the building should be connected to the ring earth of building.

    Frame of EA set is to be connected to ring earth. Neutral of alternator should be

    extended to power board and connected to ring earth through a link.

    DC positive from the power plant as well as LT lightning arrestors are to be

    connected to ring earth.

      Earthing of roof top antenna / Tower

    Roof top tower to be earthed through 50 x 3mm GI strip down leads.

    The leads are bonded to any two opposite tower legs and brought down along

    outside of the building and connected to ring earth /plate earth.

    Each leg of the tower is to be separately connected to ring earth by 50x3 mm GI

    strip.

    The sheath of warning light cable is to be connected to ring earth.

  • 8/20/2019 w2 Battery Ups and Earthing

    29/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 28 of36

    For Restricted Circulation

      Plate Earth

    Plate earth is to be done as illustrated in fig 11

     Nos. of 600x600x6.5mm GI plate are buried in a pit of size 2m x 2m at a depth of

    3m and interconnected by 4 No, 50mmx3mm GI strips using GI bolts & nuts.

    50 x 3mm GI strips are used to connect to various equipments for earthing.

    The bends in GI srtip should not be sharp but with a radius of 1m.

    The Earth electrode to be placed in position and all interconnections made .

    The pit should be filled with fine ash and finely sieved good quality soil in layer.

    Fig10.  Tower mounted on top of building

  • 8/20/2019 w2 Battery Ups and Earthing

    30/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 29 of36

    For Restricted Circulation

    The soil and ash to be rammed so as to make it compact and cohesive.

      Spike Earth

    Fig11.  Method of plate earthing

    Fig12.  Plate earth

  • 8/20/2019 w2 Battery Ups and Earthing

    31/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 30 of36

    For Restricted Circulation

    The earthing system consists of 20 Nos. of 25mm or 38mm GI pipes, each of

    275cm. or 375 cm. long, driven into the ground as shown in fig.

    Each pipe is used as earth spike and is so driven into the ground that its top

    remains at some depth below the ground surface.

    The spacing between 2 spikes is not less than 375cm and in no case less than250cm.

    The spikes shall be connected together by a continuous main earth conductor of

    size 19 x 1.6mm bare tinned copper protected by PVC pipe.

    The earth conductor is brought into the building and terminated at a height of

    30cm. above floor.

    It may be used for MBM Exchanges equipment earthing.

      Mesh type earthing

    The radio and Multiplexing equipments are to be connected by means of mesh

    earth with copper strips 20x1.5mm running on top of the bays and forming a

    mesh. Each bay may be connected by means of copper cables to the copper strip.

    The mesh to be connected to external ring earth in a shortest distance possible at

    two opposite points of the mesh.

    Fig13.  Spike earth

  • 8/20/2019 w2 Battery Ups and Earthing

    32/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 31 of36

    For Restricted Circulation

      Static Earthing

    The primary source of electrostatic charge is contact electrification, where two

    dissimilar metals are brought into contact and then separated. The two metals

     become oppositely charged due to charge transfer. Whenever charged object

    makes contact with uncharged object, the charge is shared between them to the

    extent that their conductivities allow. Materials having surface resistivity more

    than 1012 Ohm m are capable of retaining charge for longer period. These are

    readily charged by contact electrification.

    Fig14. 

    Earth distribution

  • 8/20/2019 w2 Battery Ups and Earthing

    33/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 32 of36

    For Restricted Circulation

    The human body has a low enough volume resistivity to act as a conductor and

    if insulated from earth it can accumulate electrostatic charge. A troublesome

    consequence of the electrostatic potential on charged personnel is that it can be

    high enough to cause damage to electrostatic sensitive devices, such as

    semiconductors, when these are being handled or assembled. Antistatic or

    conductive type materials can be used to avoid retention of static electricity. Ifantistatic floor is not provided, anti static wrist strap, which is properly earthed,

    shall be used while working on such equipments. In NT Exchanges with false

    floor the jack s below the false floor are earthed for protection against static

    electricity.

    2.7.8  GENERAL CONSIDERATIONS FOR ELECTRICAL EARTH AND

    TELECOM EARTH

      General considerations for Electrical Earth

    Since material resistivity does not play a part in the resistance of earth electrode to

    earth and the GI pipe electrode offers comparatively lower resistance than even acopper plate electrode, GI / CI pipe earthing may be preferred to plate earthing

    wherever possible. Also to improve the earth resistance further, as per

    requirements, Bentonite mixture can be used with GI pipe earthing in places

    where continuous attention is available .In such places, the condensate water from

    air conditioners may be directly taken to the earth pit to keep the pit constantly

    wet. This earthing with Bentonite powder can be preferred to some chemical

    earthing since this Bentonite method is cost effective and gives the same results of

    low resistance. This Bentonite earthing may not be used for BTS Stations or in

    remote areas where continuous attention is not available.

    The disadvantage with Bentonite is that if it is allowed to dry, it becomes hard and

    revival by addition of water becomes difficult. Since resistance to corrosion ofcopper is better than any other material, the existing method of copper plate

    earthing may be adopted in the areas where the effect of corrosion is high. The

    method of chemical earthing adopted by private operators can also be tried at one

    or two places on experimental basis. It is learnt that this has been already

     practiced at one or two places. The feedback received from this place is not

    encouraging. The problem indicated was that the earth resistance shot up with

     passage of time. This may probably require periodical maintenance such as

    keeping the earth pit wet by pouring water.

      General considerations for Telecom Earth

    The engineering instructions issued by T&D Circle, Jabalpur in the Issue III

    dt.30.04.2005 specifies that ring earthing is to be used for all transmission and

    switching system.

    It is gathered that the ring earthing is specifically used for tower earthing by

    Telecom Wing. The engineering instructions further specifies that all the

    equipments are to be connected to this ring earth for equi -potential bonding.It is

    recommended that the ring earthing may be particularly used for tower earthing

    and related BTS Station earthing with all the equipments connected to this ring

    earth. Spike earthing requires lot of space. It is comparatively costlier. Hence the

    method of spike earthing can be adopted in exceptional cases where very low and

  • 8/20/2019 w2 Battery Ups and Earthing

    34/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    EETP/ BSNL Silver Certification Course /Ver.02/June’ 2014 Page 33 of36

    For Restricted Circulation

    reliable earth resistance values are required and this system of spike earthing is

    not recommended for normal applications. Static earthing using anti-static floor

    tiles in switch rooms of electronic exchanges are invariably being adopted and

    hence no change is recommended.

    RECOMMENDATIONS FOR EARTHING SYSTEM

    Type of Exchange Telecom earthing Electrical earthing

    Ground Based

    Tower & BTS

    Ring earthing with

    all equipments

    connected to ring.

    For neutral & lightning conductors

    separate GI pipe earthing.

    Other equipments can be extended to

    ring earthing.

    Roof Top Tower

    & BTS

    04 Nos. GI plate

    earthing.

    For neutral & lightning conductors

    separate GI pipe earthing.

    Other equipments separate GI pipe

    earthing.

    Rural Exchanges

    like CDOT SBM

    04 Nos. GI plate

    earthing.

    For neutral & lightning conductors

    separate GI pipe earthing.

    Other equipments separate GI pipe

    earthing.

     New tech

    Exchanges (LT

    connection)

    04 Nos. GI plate or

    spike earthing.

    For neutral & lightning conductors

    separate GI pipe earthing and bentonite

    mixture wherever required.

    Other equipments separate GI pipeearthing with bentonite mixture

    wherever required.

     New tech

    Exchanges (HT

    connection)

    04 Nos. GI plate or

    spike earthing.

    For neutral & lightning conductors

    separate Copper plate earthing.

    Other equipments separate Copper plate

    earthing (fault current density

    consideration) .

     Note: Where soil is corrosive, G.I pipe/plate earthing can be replaced by copper plate earthing.

    2.8  SUMMARY

    This unit explains the different methods of battery working. This unit covers the

    different types of inverters like modified sine wave, pure sine wave, grid type, etc. It also

    gives a basic idea about the circuit diagram of inverters and the UPS. The chapter also

    gives the maintenance schedule for preventive and corrective maintenance of the

    uninterrupted power supply.

  • 8/20/2019 w2 Battery Ups and Earthing

    35/36

  • 8/20/2019 w2 Battery Ups and Earthing

    36/36

    Telecom Support Infrastructure (TSI) Battery, UPS & Earthing

    SELF ASSESMENT ANSWERS

    1.  Float

    2. 

    2 times3.  False

    4. 

    False

    5.  Voltage

    6. 

    Recombination

    7.  AH

    8.  2.35

    9. 

    Earthing

    10. True

    11. 

     Neutral Earthing

    12. 5 Ohms

    13. 

    Ring

    14. Copper Plate

    15. Saw-Tooth Wave Inverter

    16. 220V AC

    17. Output High

    18. 

    True

    19. 230V AC

    20. 

    AC, DC