6/11/2015 1 West Commercial MultiModal Corridor & Martin’s Point Shared Use Path Studies Public Workshop June 11, 2015 Tonight’s Agenda Welcome and Introductions Meeting Overview Complete Streets 101 W. Commercial Purpose & Need W. Commercial Issues & Options Martin’s Point Purpose & Need Martin’s Point Issues & Options Next Steps Questions Workshop

W Comm-MP Path.pdf

Embed Size (px)

Citation preview

  • 6/11/2015

    1

    WestCommercialMultiModalCorridor&MartinsPointSharedUsePathStudies

    PublicWorkshopJune11,2015

    TonightsAgenda WelcomeandIntroductions MeetingOverviewCompleteStreets101W.CommercialPurpose&Need W.CommercialIssues&Options MartinsPointPurpose&Need MartinsPointIssues&Options NextSteps Questions Workshop

  • 6/11/2015

    2

    ProjectSchedule AprilMay:Fieldwork,siteanalysis

    andStakeholdermeetings June:PublicWorkshop#1 JuneAugust:Developmentand

    RefinementofAlternatives September:PublicWorkshop#2 SeptOctober:Recommendations

    andCostEstimates NovDecember:FinalReport JuneDecember:UrbanInteractive

    platform/website

    Context: MultimodalTransportationConnectionsandGaps

  • 6/11/2015

    3

    CompleteStreets101

    WhatareCompleteStreets?SafeComfortableConvenient

  • 6/11/2015

    4

    IncompleteStreetsareUnsafe

    Morethan40% ofpedestriandeathsin2007and2008occurredwherenocrosswalkwasavailable.

    andInadequateNosidewalksorcrosswalksforwalkers Unsafe forpeopleonbicycles

    Uninvitingforbusriders Inaccessibleforwheelchairusers

  • 6/11/2015

    5

    CompleteStreetsinCommercial/IndustrialCorridors: MaintainRoadwayCapacity AccommodateTrucksandEmergencyVehicles ImproveSafetyforAllUsers ImproveAccessibilityforAllUsers EncourageHealthierLifestyles ReduceAirandWaterPollution ReducePersonalTransportationCosts ImproveQualityofLife Provideamoregreen,attractivestreetscape

    IndustrialCompleteStreetsStrategiestomaintaintruckaccessandimprovewalking& bicyclingsafety Mountableaprons Maintainsidewalkgrade Hivisibilitycrosswalks

    andmedianislands 11travellanesfor

    bicycleaccess 3035mphspeedlimits

    Crosswalkmedianisland

    Mountableapronandraisedcrosswalk

  • 6/11/2015

    6

    WestCommercialStreetPurposeandNeedSummary

    The purpose of the West Commercial Multi-Modal Corridor is to recommend a configuration for the corridor that safely accommodates all modes of transportation and accommodates current land uses and future development projects. Changes proposed along the corridor will create an enhanced gateway to Portlands waterfront.

    Goals: Balance truck access and staging with ped/bike safety and mobility Serve divergent land uses and the widest number of roadway users Create an attractive gateway to Portlands waterfront.Needs: Reduce high vehicle speeds Create better defined areas for truck parking and staging Extend the shared-use path network and provide on-road bike

    accommodations Enhanced pedestrian accessibility along and across the street

    WestCommercialSt.KeyIssues

    1.Truckaccessandstaging3.Onstreet

    BikeLanes

    5.Sidewalks&Crosswalks

    2.DevelopmentandParking

    4.SharedusePathAlignment

  • 6/11/2015

    7

    1.TruckAccessandStaging

    MaineDOT designforBeachStreetintersection

    2.DevelopmentandParking

  • 6/11/2015

    8

    2.DevelopmentandParkingWhatisthebestroadwaydesigntosupportdevelopment?

    WestCommercialStreetcrosssection,westofStarMatchbuilding

    Marine Industrial

    Zone

    Whatisthebestroadwaydesigntosupportdevelopment?

    WestofStarMatch:Currentconditions

    Marine Industrial Zone

    Marine Industrial Zone

  • 6/11/2015

    9

    Whatisthebestroadwaydesigntosupportdevelopment?

    WestofStarMatch:Option1,Parkingon

    BothSides,NoHarborSideSidewalk

    Marine Industrial Zone

    Marine Industrial Zone

    Whatisthebestroadwaydesigntosupportdevelopment?

    WestofStarMatch:Option2,

    Parking/sidewalkonHarborSideOnly

    Marine Industrial Zone

    Marine Industrial Zone

    Potential sidewalk to serve commercial uses along harbor side

  • 6/11/2015

    10

    Whatisthebestroadwaydesigntosupportdevelopment?

    EvaluationMatrixexample

    3.OnStreetBicycleAccess

    W.CommercialatStarMatch:

  • 6/11/2015

    11

    3.OnStreetBicycleAccess

    W.CommercialatStarMatch:

  • 6/11/2015

    12

    4.SharedusePathAlignmentPotentialoffroadpathalignment

    Useoftunnelforpotentialoffroadalignmentoption

    5.SidewalksandCrosswalks

    ExistingsidewalksandcrosswalkalongW.Commercial

    SidewalkontheapproachtoBeckys

  • 6/11/2015

    13

    5.SidewalksandCrosswalksKeyLocation:crosswalkfromIMTtoHarborViewMemorialPark

    Facingwest

    Facingsouth

    The primary purpose of the Martins Point Path Study is to recommend short and long-term options for improved non-motorized connections between the Back Cove & East End paths with the Martins Pt. Bridge and points north. Ultimately, the improved links will serve the transportation and recreation needs of the East Deering neighborhood and of people throughout the City.

    Goals: Enhance the East Coast Greenway route through Portland to points north Increase pedestrian and bicycle capacity for the route between Tukeys

    Bridge and the Martins Point Bridge

    Needs: In short-term, enhance bicycle connectivity along the Veranda St. corridor Improve pedestrian crossings at various intersections along the Veranda

    Street corridor Increase capacity on the Tukeys Bridge congested pathway Increase safety by reducing vehicle speeds along Route 1

    MartinsPointPathPurposeandNeedSummary

  • 6/11/2015

    14

    MartinsPointKeyIssues

    1.EastCoastGreenwayConnectivity

    2.PathCongestiononTukeysBridge

    4.HCLsatI295On/OffRamps

    5.VerandaSt.ShortTerm

    3.I295RightofWay

    1.EastCoastGreenwayConnectivity

    MartinsPoint

    Bridge

    Downtownviathe

    BaysideTrail

    BackCoveTrail

  • 6/11/2015

    15

    2.PathCongestiononTukeys

    Walkers,runnersandbicyclistscompeteforspaceonthe810path

    Solution:MultipleOptions

    Potentialnewshareusepathalignment

    Possibleconnectionbelowbridge

  • 6/11/2015

    16

    ConnectionBelowBridge

    WestsideofTukeys bridgelookingsouth

    PotentialNewPathAlignmentCurrentConditions

    Existing Path

  • 6/11/2015

    17

    Option1: Cantileveredpathoneastside

    PotentialNewPathAlignment

    Existing Path

    PotentialNewPathAlignmentOption2: Useofbridgestructurefornewpath

    Existing Path

  • 6/11/2015

    18

    PotentialNewPathAlignment

    RecentlyattachedpathstructureontoI279bridgeinPittsburgh

    PotentialNewPathAlignmentOption3: Separatestructurefornewpath

  • 6/11/2015

    19

    PotentialNewPathAlignment

    EugeneORDesMoinesIA

    MinneapolisMN

    3.I295ROWAlignment

  • 6/11/2015

    20

    4:HCLsatI295On/OffRampsPotentialofframplaneconversiontoshareusepathw/barrier

    Highspeedtraffictoonramp

    Potentialrealignmentofofframp

    4a.I295OffRamp

    Viewoftwolane,I295northboundofframptoRoute1

  • 6/11/2015

    21

    4b.I295OnRamp

    IntersectionofVerandaStreetandtheI295southboundonramp

    5.VerandaStreetShortTerm

    CurrentconditionsonVerandaStreetfacingnorthwest

  • 6/11/2015

    22

    Istherealogicalshorttermimprovementforbicyclists?

    VerandaStreet:CurrentConditions

    Istherealogicalshorttermimprovementforbicyclists?

    VerandaStreet:Option1 Enhanced

    SharedLaneMarkings

  • 6/11/2015

    23

    Istherealogicalshorttermimprovementforbicyclists?

    VerandaStreet:Option2 CycleTrack

    oneastside

    NextSteps Consolidationofcomments Refinementofroutingand

    alternativesdesigntreatments PublicWorkshop#2topresent

    draftrecommendations PreferredAlternativeswithCost

    Estimates TrafficanalysisandInterchange

    ModificationReport(ifneeded) Draft/Finalreport

  • 6/11/2015

    24

    Questions

    Workshop

  • 6/11/2015

    25

    WestCommercialMultiModalCorridor&MartinsPointSharedUsePathStudies

    PublicWorkshopJune11,2015