    AHMEDABAD MUNICIPAL CORPORATION

    (HOUSING PROJECT DEPARTMENT)

    TENDER

    FOR

    CONSTRUCTION OF NEW BUILDING FOR FIRESTATION AND RESIDENTIAL QUARTERS AT

    THALTEJ, AHMEDABAD

    VOLUME-I (TECHNICAL BID) PART-II SPECIFICATION

    Municipal Commissioner AhmedabadMunicipal Corporation. Sardar Patel Bhuvan,Danapith, AHMEDABAD - 380 001

  • 7/25/2019 Volume-i Part II Specification

    2/118

    2

    Construction of New Building for Fire Station and

    Residential Quarters at Thaltej, Ahmedabad

    GENERAL STANDARD TECHNICAL SPECIFICATIONS

    (A) A printed Booklet for GENERAL TECHNICAL SPECIFICATION FORBUILDING WORKS.

    (B) A printed Booklet for VLOUME "B" LIST OF THE APPROVED PRODUCTSSCHEDULE OF RATES (GOVT. OF GUJARAT, ROADS AND BUILDINGS

    DEPARTMENT, ELECTRICAL WING).

    (C) A Printed Booklet forTENDER FOR ELECTRIC WORKfor Roads and Building

    Department Government of Gujarat.

    The above may be referred of the printed booklets of PWD which may also be

    available from Gujarat Book Stores, Sector-21, Gandhinagar 382 021.

    Note:

    01. The work shall be carried out in accordance with the relevant

    specifications contained in PWD Hand Book Vol. I & II with the

    correction slips from time to time or the latest addition.

    02 The reference as indicated with page Nos. are as per the above referred Booklets

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    1 Excavation in all sorts of Hard Soil includingsoft murram, for any activity

    General Technical Specificationfor building work Booklet

    (Technical Specification forbuilding work is attached withtender documents in references)Item No. 4.00 (a) p.21+ It4.001(A) p. 25 + 4.24 P.28 (up to

    5 Km lead)

    2 Filling the river sand in plinth / Trenches orwhere necessary

    - do - Item No 4.24 P.28

    3 Filling in foundation and plinth with murram

    or selected soil (Brought from Out side)

    - do - Item No 4.004 P.28

    4 Providing and injecting Chemical emulsionsfor preconstruction ant termite & Fungaltreatment(Note: measurement on plinth area shall be

    paid )

    As per separate attached sheet

    5 Provide. & laying cement concrete 1:3:6 - do - Item No 5.3.14(A) P. 30

    6 Providing & laying cement concrete 1:4:8 in(A) Foundation & plinth

    - do - Item No 5.3.3 (B) P. 31

  • 7/25/2019 Volume-i Part II Specification

    3/118

    3

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    7 Reinforced Cement Concrete work gradeM25/M20/M15 of IS-456,2000

    (A) Foundations, Footings, base of columns,

    and mass concrete in M25

    - do - Item No 5.8.3(A)

    P.40+9.1(A)P.54(B) Walls ( Retaining wall, Lift Pardi, WaterTank Pardi, Shear wall All types of Pardi /

    Wall etc ) from top of foundations in CementConcrete M25 Grade

    - do - Item No 5.8.3.(B) +(F)P.40+9.1(C)P.56

    (C) Slabs, shelves, Balconies, Loft and

    Cantilever member etc in Cement ConcreteM20 Grade

    - do - Item No 5.8.2.(C)

    P.39+9.1(B)I P.56

    (D) Columns, pillars, posts, and stoutest inCement Concrete M25 Grade

    - do - Item No 5.8.3 (D)P.40+9.1(G)P.56

    Beams:(E) (i) All size and shape Tie Beams / Ground

    Beams in M25,

    - do - Item No 5.8.3 (C)P.40+9.1(H) I P.56

    Beams:(E) (ii)All size and shape Beams,Bracket, Cantilever Beam all floor etc in

    M20

    - do - Item No 5.8.2.(C)P.39+9.1(H) I P.56

    (F) Staircase with steps/ Kadi Tappa, waistslab and landing in Cement Concrete M20Grade

    - do - Item No 5.8.2.(E),P.39+9.1(M) P.56

    (G) For Lintels in Cement Concrete M20Grade

    - do - Item No 5.8.2.(C)P.39+9.1(H) I P.56

    (H) For any Type of Chajja in CementConcrete M20

    - do - Item No 5.8.2.(C)P.39+9.1(B)I P.56

    (I) For Floor Concrete / Grade Slab / tre mixConcrete in cement Concrete M20 Grade

    - do - Item No 5.8.2.(A) P.39

    8 Providing thermo Mechanically treated bars(T.M.T) As per separate attached sheet

    9 Providing and constructing brick masonry230mm thick and above 230mm thick, in CM1:6

    ( A ) For Foundations and plinth - do - Item No 6.13(B) P. 44

    ( B ) For Ground Floor - do - Item No 6.19(B) P. 46 but inCM (1:6)

    ( C ) For First Floor - do - Item No 6.19 (B) + 6.20, P.

    46 but in CM (1:6)

    ( D ) For Second Floor - do - Item No 6.19 (B) + 6.20, P.46 but in CM (1:6)

    ( E ) For Third Floor - do - Item No 6.19 (B) + 6.20, P.

    46 but in CM (1:6)10 Providing and constructing 115mm / 90mm

    thick brick masonary in partition walls

    ( A ) For Ground Floor - do - Item No 6.30 I (B) P. 46

    ( B ) For First Floor - do - Item No 6.30 I (B) P. 46 +6.33(B) P.48

    ( C ) For Second Floor - do - Item No 6.30 I (B) P. 46 +

    6.33(B) P.48( D ) For Third Floor - do - Item No 6.30 I (B) P. 46 +

    6.33(B) P.48

  • 7/25/2019 Volume-i Part II Specification

    4/118

  • 7/25/2019 Volume-i Part II Specification

    5/118

    5

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    22 Providing and laying GROUP-5 RUSTICCERAMIC (PREFERRED "ENDURA PEI-

    5) tiles

    - do - Item No 14.29 P.84 ,Except

    White/colored/ printed tiles ofsize 300 x 300 mm /600mm x

    600mm or any size of Bell

    /Somani / Johnson / Gold Coin,

    or equivalent group-5 tiles shall

    be used instead of 150 x

    150mm. White glazed tiles.

    23 Providing and laying White / Color shadeapproved by consultants glazed tiles 6 mm.ofsize 600 x 325/400x250mm thick in skirting,risers of steps and dedo on 10 mm. thick

    cement plaster 1:3

    - do - Item No 14.32 P.84,exceptthat tiles as per BOQ and approved

    by Architect /Engineer in charge

    24 Providing and laying polished Kota stone slab(Polished, Green color) flooring over 25 mm.

    (average) thick base of cement mortar 1:6

    -- do - Item No 14.43 (A) P. 86

    25 Providing and laying polished Kota stone slab25 mm. thick in Tread, riser of steps, dado,Skirting, window sill, jams, Threshold and

    pillars laid on 10 mm. thick cement mortar1:3

    - do - Item No 14.44 P. 87

    26 Providing and fixing 18mm thick kesariyajiGreen marble( approved by Architect) gangsaw cut mirror polished (premoulded and

    prepolished) machine cut for Doors&window sills,Doors & Window Jams,(One Piece)

    As per separate attached sheet

    27 Providing & laying 80mm thick grey or

    colored Reflective Rubber Mould M-30(Lacquer coated ) paver block

    As per separate attached sheet

    28 Providing , fixing, threading or plaster drip &molding R.C.C. Precast molded Curbing ofsize 350mm. X 100mm X 150mm. Height

    with molded edges as per design, and mix of1:2:4

    As per separate attached sheet

    29 TRIMIX CONCRETE WITH EXPANSTIONJOINTS.: Controlled cement concrete inGrade M20

    As per separate attached sheet

    30 Construction of granular sub-base As per separate attached sheet

    31 Wet Mix MacadamSub- Base/ Base Course As per separate attached sheet

    32 Providing & Fixing 4mm Aluminumcomposite panel manufactured with a

    poluthelene laminated in two sheets of0.5mm. aluminum colored sheet

    As per separate attached sheet

    33 Providing and laying Rough chiseled dressed(kota stone green) stone flooring over 25 mm.thick base of cement mortar 1:5

    - do - Item No 14.44 P. 87

    34 Providing and laying Cement concreteflooring for I.P.S. 1:2:4

    - do - Item No 14.71 (B) P. 89

    35 Providing & laying sandwitch Kitchenplatform

    As per separate attached sheet

  • 7/25/2019 Volume-i Part II Specification

    6/118

    6

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    A) 18mm thick Granite Top Sandwich typeplatform

    B) 25mm thick Kota stone Top Sandwich

    type platform

    36 Providing and Fixing 25mm thick polish kotastone Shelves ( Both side Polishing) below

    platform, store or in cupboards

    - do - Item No 14.44 P. 87

    37 Providing and laying Water Proofingtreatment on terrace

    As per separate attached sheet

    38 Providing & laying China mosaic flooring As per separate attached sheet

    39 Providing and applying 3-coats of Acrylicpolymer cementations based with fiber glass

    net will reinforce in the sandwich waterproofing on gutter

    As per separate attached sheet

    40 Ceiling plastering work: Provdg. 10 mm.thick cement plaster in single coat on fair sideof brick concrete walls for interior plasteringup to floor two level and finished even and

    smooth in for (I) Cement mortar 1:3

    -do - Item No 17.58 I +17.69+17.91+17.94 P. 104+106+107

    41 Provdg. 15 mm. thick cement plaster in singlecoat on fair side of brick concrete walls forinterior plastering up to floor two level and

    finished even and smooth in (II) Cementmortar 1:4

    - do - Item No 17.58

    II+17.69+17.94 P. 105+106+107,Thi of plaster is 15mm instead of

    10mm

    42 20 mm. thick sand face cement plaster onwalls up to height of 10 mt. and above ground

    level consisting of 12 mm. thick backingcoating of C.M. 1:3 (1 cement : 3 sand) and 8

    mm. thick finishing coat in C.M. 1:1 (1cement :1 sand)

    - do - Item No 17.95 P. 107

    43 Providing and laying 15 mm thick cementwater proofing plaster to slabs / Sunk

    portion

    - do - Item No 17.58

    I+17.69+17.94 +17.70P. 104+105+106+107,Thi of

    plaster is 15mm instead of 10mm

    44 Providing /applying Heritage Fine RotoFinish Two- Part coating System of Bakelite

    Hylam Ltd.

    As per separate attached sheet

    45 Providing cement vata /coving (10 cms x 10cms) size quarter round in cement mortar 1:1

    - do - Item No 17.0.0.1, P.109

    46 Providing Applying Wall & Ceiling paintingWith Plastic emulsion paint incl. Birlawhite puttyor equivalent putty

    As per separate attached sheet

    47 Providing & applying External 100% AcrylicPaint "Apex "of desired shed from Asian

    paint or equivalent in minimum three coats

    As per separate attached sheet

    48 Providing, laying and fixing heavy duty (toASTM D2846) CPVC PIPE SDR 13.5 pipes

    with screwed socket joints

    As per separate attached sheet

    (A) 15 mm

  • 7/25/2019 Volume-i Part II Specification

    7/118

    7

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    (B) 20 mm

    (B) 25 mm

    (C) 40 mm

    (D) 50 mm

    49 Providing, fixing, Laying & Jointing Highpressure UPVC plumbing pipe schedule -80and fittings.ConcealedInstallation

    As per separate attached sheet

    (A) 15 mm

    (B) 20mm

    (B) 25 mm

    (C) 32 mm

    50 Providing and fixing UPVC Higher Gradetype-B soil, waste, rain water and vent pipe(IS: 13592-92 IS: 14735-99 IS: 5382

    IS: 4985)

    As per separate attached sheet

    (A) 75 mm dia O/D

    (B) 100 mm dia O/D

    51 Providing . & fixing in position uPVC cowlwent to pipes

    As per separate attached sheet

    (i) 75mm dia

    (ii) 100 mm dia

    52 Provdg. and fixing UPVC(Spuun) Nahni trap As per separate attached sheet

    53 Providing & fixing Floor mountingEuropean Closet

    As per separate attached sheet

    54 Providing & fixing white vitreous Flat backurinal of size 440x315x265mm withFlushing System

    As per separate attached sheet

    55 Providing & fixing Wash basin As per separate attached sheet56 Providing & fixing Imported Stainless Steel

    (Grade -304)Kitchen sink of Carysil/Nirali/Cera or equivalent make of size

    535mm X 457mm X 203mm standard

    As per separate attached sheet

    57 Provdg.& fixing C.P. Brass Imporatedoverhead shower rose with 15 mm inlet.

    Hindware -F160004 or Equivalent make)

    - do - Item No 23.141 (A),P.149,shower rose as per BOQ

    58 Provdg. & fixing 600mm x 450 mm devellededge mirrorof superior glass mounted of .6

    mm th. A.C. sheet or plywood sheet and fixedto wooden pluge with C.P. brass screws andwashers.

    - do - Item No 23.143, P.150

    59 Provdg. & fixing C.P..Brass Towal railcomplete with C.P. brass brackets fixed towooden plugs with C.P. Brass screws.(B) 600

    mm x 20 mm size (Hindware - F805001 orEquivalent make)

    - do - Item No 23.144 (B), P.150,

    towel rail as per BOQ

    60 Providing and fixing a CP brass Napkin-ringof ISI make(hindware make -F 805002 orequivalent) with concealed type brackets

    fixed to the wall with CP brass screws, etc.,complete.

    as specified in the Bill of

    Quantities

  • 7/25/2019 Volume-i Part II Specification

    8/118

    8

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    61 Providing and fixing SS or brass chromiumplated double Robe hook of Hindware -

    F805005 or Equivelent complete as approved

    by architect and Engineer - Incharge.

    as specified in the Bill ofQuantities

    62 Providing and fixing a surface type soap dish/ trayof Hindware - F 805003 or Equivelentcomplete with clean surface to original

    conditions, etc., complete.

    as specified in the Bill of

    Quantities

    63 Providing & fixing Bib-Cock with Foam flowof following size ( 15mm dia (hindware -

    F200003 or Equivalent make)

    - do - Item No 23.92 (A) (1) P. 150except that the bib cock shall be as

    specified in the Bill of Quantities

    64 Providing & fixing Concealed 15mm stopcock for Shower control of Hindware -F200007 or Equivelent complete as perinstruction by architect or engineer.

    - do - Item No 23.92 (A) (1) P. 150except that the cock shall be asspecified in the Bill of Quantities

    65 Providing & Fixing the C. P Wall Mixurewith provision of over head Shower with

    115mm LB pipe & wall Flange. Of Hindware-F200020 or Equivelent complete as per

    instruction by Architect or Engineer-in-charge.

    as specified in the Bill ofQuantities

    66 Supply, installation, testing andcommissioning of gunmetal, male or femalethreaded isolation control valve (Ball Valve),

    As per separate attached sheet

    (A) 25 mm dia

    (B) 40 mm dia

    (C ) 50 mm dia

    (D) 60 mm dia

    67 Providing and Fixing Handle Valve of ISI ofZALOTO or Equivalent brand

    As per separate attached sheet

    (A) 15 mm

    (B) 25 mm

    (C) 40 mm

    (D) 50 mm

    68 Providing, supplying & fixing to wall, ceilingand floor rigid un plasticised PVC pipes of

    ISI -13592 /92 for Rain water pipe

    - do - Item No 23.8 P. 144 exceptthat the rigid un plasticised PVC

    pipes hall be as specified in theBill of Quantities

    (A) 75mm

    (B) 110 mm dia

    69 Supplying Rotationally moulded HDPEstorage tank of approved make( A ) (Each in required capacity (Sintex orEquivalent )

    As per separate attached sheet

    70 Providing. & laying (two level or slopes) &jointing with stiff, mixture of cement mortarin proportion 1 :1, dia salt glazed stoneware

    pipe(A) 100 mm dia(B) 150 mm dia

    Item 24.1 (A, B) P.155

  • 7/25/2019 Volume-i Part II Specification

    9/118

    9

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    71 Provdg. & laying S.W. Gully trap with C.I.garting brick masonry chamber & water tight

    C.I. cover with frame of 300 mm x 300 mm

    size ( inside) with standard weight.(I) Squaremouth trap(A) 150 mm x100 mm size P-Trap

    -Item 24.19 (I) P.156 (RCC Coverinstead of C I Cover)

    72 Construction brick masonry chamber forunderground C.I. inspection chamber in C.I.1:5 C.M. FRC cover.

    (I) Inside Dimensions 455mm x 610 mm &450 mm deep for single pipe line

    - do Item 24.44(I) + (II) P.163

    Except P/F P/F FRC H D coverinstead of C I Cover

    73 Extra over above item for every additionaldepth 0.1 M or part thereof beyond 450 mm.

    depth for brick masonry chamber. (I) for 455mm x 610 mm size

    - do Item 24.46 P.163

    74 Construction of Manhole

    (1) A- type depth 0.90 metre for 150 mmdiameter sewer

    - do Item 24.27 P.157 ExceptP/F P/F FRC H D cover instead

    of C I Cover

    75 (I) Extra rate for costing B. B. masonry orevery additional depth of 0.1 M. or part thereof over item (I) for depth from 0.90 M to 1.5M.

    - do Item 24.28 P.158

    76 Providing. & laying 18 mm. thick polishedSelected color & pattern Granite Cladding onfront wall or in risers & tread of steps laid on

    12 mm th. Cement mortar 1:3

    As per separate attached sheet

    77 Designing (Aesthetically ) and constructingR.C.C ground service reservoirs / RCCSUMPS (Capacity 4.0 lac litr) IN M-250 mixof required Capacity REFER THE

    ATTACHED TENDER DRAWING.

    As per separate attached sheet

    78 Providing and layiong non pressure humepipes of Np2 1

    - do Item 24..22 P.156

    For 150 mm Dia BFor 250 mm Dia CFor 300 mm Dia DFor 450 mm Dia EFor 600 mm Dia G

    79 Supplying, Testing & commissioningHYDRO-PHEUMATIC SYSTEMS for U. Gtank to O. H tank filling systems.

    As per separate attached sheet

    80 Providing, making, fixing & anchoring ofreinforcing bars or dowel

    As per separate attached sheet

    8 mm

    10mm

    12mm

    16mm

    20mm

  • 7/25/2019 Volume-i Part II Specification

    10/118

    10

    Sr. No.

    of the

    Item in

    the

    Schedule

    -B of

    Tender

    Description of items

    Sr. No. and page no of the applicable

    specifications in General Technical

    Specification for building work Booklet

    25mm

    81 Providing & constructing 20 mm wide & fulldepth Expansion joint including providing20mm th Expansion board (or equivalent

    brand ) painted with bitumen on both sidesand filling the joint with polysulphide sealantmaterial

    As per separate attached sheet

    82 Supplying and fixing Standard steel Rollingshutters partly grilled for a height of 450 mmin between and partly with laths made out of

    8 mm dia round bars

    As per separate attached sheet

    83 Providing & laying sandwitch Sittingarrangement sandwich type of 20/25 mm thk

    Kota fine polish of approved shade andsample on top and 25 mm thick kota in

    bottom with 30 mm thk screed of (1:2:4) inbetween)with sandwich supports of 25 mmthk two kota on sides and screed in between

    and 75 mm raised platform with kota on topas per Architectural design and approved

    sample for all floors / all levels / all heights.

    As per separate attached sheet

    84 Percolation well of 150 mm ( 6") dia As per separate attached sheet

    85 Providing spreading and leveling Goradufield soil of approved quality on site.

    As described in BOQ

    86 Providing Farm yard Manure on site Incl.Labor for spreading and mixing farm yardManure and leveling the same.

    As described in BOQ

    87 Providing pure doob ( Dharo ) grass suckers

    and planting the same at a distance of 8 to 10Cm. Both ways and maintain till well

    establishment.

    As described in BOQ

    88 Excavation pits of 30 X 30 X 30 Cm. andrefilling the same by providing mixing farm

    yard Manure @ 2.02 Cmt, per pit. Providingand planting well grown saplings of specified

    variety and maintain till well established(about 45 days. )

    As described in BOQ

    89 Excavation in any soil up to 30 cm. depthbreaking clods removing unwanted stuff such

    as brickbats, stone, grass roots, etc, andrefilling the same , preplan ting, watering,

    weeding, top digging, reveling, and bringingthe earth to fine tilt and ready for

    As described in BOQ

    90 Providing and laying Name plate of differentSize on S.S.316 grade,18 gauge molded edges

    plate with engravings alpha bate latter of size4" with filling radium - black color in letters,

    As per separate attached sheet

    91 Providing and fixing POP. board ceiling As per separate attached sheet

    92 Providing and fixing standard qualityvertical blinds complete as per instruction

    of architect or engineer in charge.

    As per separate attached sheet

  • 7/25/2019 Volume-i Part II Specification

    11/118

    11

    Separate sheet of detailed specification

    Item No. 4.Providing and injecting Chemical emulsions for pre-construction anti-termite & Fungal

    treatment and creating continuous chemical barrier under and all around the columns pits, wall

    trenches, basement excavation, top surface of plinth filling, junctions of wall & floors, along the

    external perimeter of building, Expansion joints, over the top surface of the consolidated earth

    on which plinth protection is to be laid, surrounding pipes and conduits etc. complete. in first

    stage of work, & furniture, & necessary floors in second stage of construction work in

    accordance with IS:6313 ( Part-II) with using Chloropyriphos Emulsifiable concentrate 1.00%. (

    IS.: 8944-1978), Lindens 1.00% ( IS.: 632), Imidacloprid 0.075% with relevant IS: code ( Rates

    are Incl. proposed Furniture & Plinth area of the building at ground floor level shall Only. be

    measured.).

    Anti termite specification

    Chemicals used during treatment

    Imidacloprid 30.5 % SCCloropyriphose 20 % EC

    Providing & injecting emulisifiable concentrate lmidacloprid 30.5 SC with (0.075%)

    concentration chemical emulsion by Avitus India Pest Management Pvt. Ltd. for antitermite & Fungal treatment & creating chemical barrier under & around the column

    pits, wall trenches, basement, excavation, top surface of plinth filling junction of wall

    & floor along the external perimeter of the building expansion joints surrounding of

    pipes conduits etc, in the first stage of work and using Chloropyriphos Emulsifiableconcentrate 1.00%. ( IS.: 8944-1978) for wooden fixed furniture ( Wooden frames

    and doors). Complete plinth area of the building shall be measured in square mtr on

    the basis of basement area of the building.

    METHOD OF TREATMENT FOR TERMITE CONTROL

    AVITUS INDIA PEST MANAGEMENT PVT. LTD. is using a New Generation

    Insecticide for Termite Control that contains IMIDACLOPRID as active ingredient. Itis an appropriate insecticide for the control of Termites in building and premises,which can be used both for PRE & POST construction treatments.

    Mode of Action

    We create a non detectable treated zone that function not as a repellent barrier, but

    as a killing field whose effects may be transmissible to other Termites and leads to

    eradication of the colony. It acts by interfering with the transmission in the nervous

    system and resulting in their death.

    We are injecting concentrated Chemical Emulsion for Anti Termite treatment for

    creating chemical barrier under & around column pits, wall trenches, basement,excavation, top surface of plinth filling junction of wall and floor along external

    perimeter of the building, expansion joints, surrounding of pipes conduits etc.

    PRE CONSTRUCTION TREATMENT

    1. Bottom surface and side pits up to a height of 30 cm will be treated @05(Five) Ltr. Chemical Emulsion per Sq. Mtr. of surface area.

  • 7/25/2019 Volume-i Part II Specification

    12/118

    12

    2. Back fill earth in immediate contact with the foundation structure will betreated @ 7.5 Ltr. per Sq. Mtr. of the vertical surface of substructure of each

    side.

    3. Treatment of RCC foundations: Treatment should start at depth of 50 cmbelow ground level @ 7.5 Ltr. per Sq. Mtr.

    4. Treatment of top surface of plinth filling: The top surface of the earthconsolidated within plinths wall shall be treated with Chemical Emulsion @

    05(Five) Ltr. per Sq. Mtr. of the surface before the sand bed or sub grade is

    laid.

    5. Soil treatment along external perimeter of building: Earth along the externalwalls of the building should be treated at an interval of 15 cm and to a depth of30 cm exposing the wall surface. Chemical Emulsion will be poured along the

    wall @ 7.5 Ltr. per Sq. Mtr of vertical surface.

    POST CONSTRUCTION TREATMENT

    The treatment comprises of drilling holes at the wall and floor junction level andfilling it after pumping in sufficient quantity of chemical.

    This ensures a continuous chemical barrier for termites to make an entry and protect

    the treated structure.

    1. Treatment to wall and floor junction:

    Holes of diameter 12 mm (1/2" approx.) are drilled at approximately 30 cm (12

    inches) intervals along the inner junction of wall and floor in the entire premise.

    Water based chemical will be injected under pressure into these holes, to create abarrier against termite.

    2. Treatment to soil under floor:

    If the subject premises on the ground floor and if cracks are noticed on the floorbecause of construction joints, expansion joints or shrinkage, the soil below floor

    needs to treated. Holes of 12 mm (1/2" approx.) dia 30 cm apart will be drilled along

    the cracks and water based chemical will be injected under pressure into these holes.

    3. Treatment to wooden fixtures:

    Holes of diameter 12 mm (1/2" approx.) will be drilled at the base of wooden works

    such as window frames; door frames etc. inset in the flooring and chemical will be

    injected. A oil based chemical will be sprayed on all the wooden work infested bytermites within the premise.

    4. Treatment to termite tubes:

    Visible shelter mud tubes will be removed and the infested area treated with Waterbase chemical.

    5. All the drilled holes will be sealed and made good using cement

    In the case Soil Treatment along External Perimeter of a Building is done as:-

  • 7/25/2019 Volume-i Part II Specification

    13/118

    13

    Item No-8Providing thermo Mechanically treated bars (T.M.T) confirming to IS 786/FE 415 for R.C.C

    works including bending, binding and placing in position complete for All Floor

    MOST specification section 1600 shall be followed with relevant provision ofrespective IRC/IS specification as well as IRC 21 2000 and IS 1786

    The payment shall be made on Kg. basis for completed work. Unit rate including costof all materials, labour, tools, plants, equipment machinery and cutting, bending, binding, &

    placing in position required to complete the job for all the floor levels.

    Mode of measurement and payment:Reinforcement shall be measured in length including overlaps, separately for

    different diameters as actually used in the work. Standard laps of length as shown on thedrawings or as instructed at site shall be admissible; Laps provided due to the Contractor'sown faults or because of use of short bars shall not be paid for. From the length so measured,the weight of reinforcement shall be calculated in tones on the same basis of as per M-18.Wastage and annealed steel wire for binding shall not be measured and the cost of these itemsshall be deemed to be included in the rate for reinforcement. Cutting, bending, placing;

    binding and fixing in position as shown on the drawings and as directed. It shall also includeall devices for keeping reinforcement in approved position, cost of joining as per approvedmethod and all wastage and spacer bars. The rate shall be for a unit of one Kg.

    Item No-11Providing and Fixing 12cm x7cm First Class teak wood door frame (Gana Teak) including MS

    hold fast with providing and fixing ISI marked 35mm thick flush door shutters conforming to

    IS: 2202 (Part I) non-decorative type, core of block board construction with frame of 1st class

    hard wood and well matched commercial 3 ply veneering with vertical grains or cross bands and

    face veneers on both faces of shutters including fixing with laminated sheet on both side of

    approved make & shade by architect. All Necessary fixtures should be pure Stainless Steel butt

    hinges, Door stop, Aldrob, Handles, latch, stopper, fixing by Stainless Steel screws & fixing with

    best workmanship and as per the instruction by architect or engineer in charge.

    The teak wood (Ghana or equivalent) shall be of good quality as required for the item to beexecuted.

    Teak wood (Ghana or equivalent) generally br free from large, loose, dead or cluster knots,flaws, shakes, warps, twists bends, or any other defects. It shall generally be uniform in

    substance and of straight fibres as far as possible. It shall be free form rot, decay, harmfulfungi and other defects of harmful nature which affect the strength durability of itsusefulness for purpose for which it is required. The colour shall be uniform as far as

    possible. Any effort like painting, using any adhesive or resin materials made to hide thedefects shall render the pieces liable to rejection by the Clerk- Of- Work or Engineer-in-

    Charge

    All Scantlings, planks etc. shall be sawn in straight lines and planes in the direction of grainsand of uniform thickness.The tolerances in the dimensions shall be allowed at the rate of 1.00mm per face to be

    planed.

    Second class teak wood shall have no individual hard and sound knots shall be more than 15sq. cms. In size and aggregate area of such knots shall not exceed 2 % of the area of piece.

    MODE OF MEASUREMENT:Dimensions is computed in square meter, rounded to two places of decimal

  • 7/25/2019 Volume-i Part II Specification

    14/118

    14

    Item No-12Providing, Fabricating and fixing Special Double Glazed Aluminum doors, windows and

    ventilators with sections, 70 microns pure polyester powder coated, as specified by the architect

    drawings from the colors available, Containing profiles of a minimum thickness of 1.5mm

    Exterior walls. For a double glazed unit the total thickness is a maximum of 28mm. The Profiles

    will consist of the Standard Company(JSP/PERFECT GLAZING Aluminum or Equivalent and

    shall use EPDM Gaskets, rated to withstand up to 80C varying from 1.5mm to 7.5mm thickness

    for the larger sizes of glass used in the glazing. All Glass should be sourced from AIS India or

    saint Gobain. Both open able vent frame and fixed outer frame and the fixed outer frame below

    the glazing gasket pocket shall exist to insert a stainless steel chevron. The crimp shall be securedusing a revolutionary cleat inserted in to a pocket specially designed in both the open able vent

    frame and fixing outer frame. All the structure will be bolted using stainless steel screws and

    sealed for waterproofing by silicon (Dow Corning make or equivalent). All Structure will be as

    per approved architect drawings and as directed by engineer incharge. Shop drawings will need

    to be provided by the contractor. Note: above item is including cost of material like aluminum

    sections, Glazing Glass, EPDM Gaskets desiccant/hygroscopic substance, spacer bars & labour

    (Fabrication and site installation) etc.

    Tender specification for Double Glass Glassing Windows.

    Providing, fabricating and fixing aluminium doors, windows and ventilators with

    sections, 70 microns pure polyester powder coated, as specified by the architect

    drawings from the colours available, containing profiles of a minimum thickness of

    1.5mm exterior walls. The open able vent frame shall be 45mm wide and a totalheight of 69mm, additionally it should able to accommodate both multi-point lockingsystem as well as single point even though the latter shall be used, the fixed outer

    frame shall be 45mm wide and a total height of 45mm. The glazing bead shall strictlycontain one plane at 45. Measures should be in place in the system to allow for

    drainage of rainwater. Any transoms used shall have a flat exterior surface to ensure

    aesthetical and symmetry properties are maintained. All glass should be sourced from

    AIS India or Saint Gobain. Both operable vent frame and fixed outer frame shall be

    strictly pneumatically corner crimped and not screwed. To ensure a precise 45 mitre,

    crimped correctly a secondary pocket in both the openable vent frame and the fixedouter frame below the glazing gasket pocket shall exist to insert a stainless steel

    chevron. The crimp shall be secured using a revolutionary cleat inserted into a pocket

    specially designed in both the open able vent frame and fixed outer frame. This cleat

    should be a minimum of 42mm wide. The sealed unit for double glazed windows will

    be a minimum total thickness of 28mm. The profiles will consist of the

    JSP/PERFECT GLAZING OR Equiv. Aluminium systems and shall use EPDM

    gaskets, rated to withstand up to 80C varying from 1.5mm to 7.5mm thickness for

    the different thickness of glass sheets used in the glazing. Whatever the structure, willbe screwed using a combination of stainless steel and zinc oxide screws and sealed for

    waterproofing by silicon (Dow Corning make or equivalent). Structure will be as per

    approved architect drawings and as directed by engineer in charge. Shop drawings

    will need to be provided by the contractor. Note: above item is including cost of

    materials such as aluminium sections, glazing glass, EPDM gaskets,

    desiccant/hygroscopic substance, spacer bars and labour (fabrication and siteinstallation) etc.MODE OF MEASUREMENT:

    Dimensions is computed in square meter, rounded to two places of decimal

    Item No-13

    Providing and fixing FRP frame size 125x65mm and 35mm thick FRP shutter with wood grain

    raised panel design finish shutter having extra reinforcement on side and edges and in GEL coat

    finish. The core of shutter is to be filled up with injected fiber extinguishing grade polyurethane

    foam done in situ along with embedded wooden pieces for stiffening and also for taking hinges

  • 7/25/2019 Volume-i Part II Specification

    15/118

    15

    and fixtures. The whole FRP frame and shutter is to be waterproof , weatherproof, termite proof

    and resistance to mild acid/ Alkali resistance including S.S. hinges with necessary screws and

    aluminum fixtures and fastening.(Product should have 3-years performance guarantee)

    Material35 mm. thick shutter in depressed panel design shall be having 1.5 to 2mm. Thickness

    fire extinguishing grade F.R.P. skin, Sandwich panel of 4mm. Plywood and embedded

    wooden pieces for stiffing as well as holding hinges and fixture, all molded into a one

    piece shutter, Core material shall be injected fire extinguishing grade rigidpolyurethane foam done in situ having density 32 to 36 Kg. /m3 compressive strength

    1.8 to 2 Kg./Cm2 flexural strength 3.5 to 4.5 Kg. Cm2. Whole shutter shall beweather proof, water proof, termite proof and mild Acid / Alkali resistance. As well as

    same material for frame section of detailed size.

    Shutter

    35 mm. thick depressed panels F.R.P. shutter shall be join less, It shall be straight and

    smooth and of standard shape finish in jell coat. All necessary fixture and fastening

    shall be fixing where wooden pieces are provided.

    Workman ship

    Shutter shall be fixed in true line, level and proper manner having 2.0 to 3.0 mm. ply

    that is Air space for smooth and easy working three S.S. hinges shall be fixed

    properly with necessary screws.Fixtures and fastening.

    All others fixture likes aluminum Aldrops - tadi / Baby latch - handles shall be fix

    with shutter in usual manner.

    Tolerance

    1.5 mm. tolerance will be allowed in thickness of shutter

    Mode of measurement and paymentRate of shutter & Frame includes the cost of Aluminum fixtures and Fastening with

    necessary Screws for fixing in position and payment shall be made on a unit of Smt.

    Basis.

    Item No-14

    Providing and fixing Colour Anodised Aluminium work for doors, windows ventilators(Two

    Track, Three Track, Four Track, Fix-Partition, etc), with Extruded built up standard tubular

    sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and

    IS: 1285 fixed with rawl plugs and screws or with fixing clips or with expansion hold fastners

    including necessary filling up of gaps at junctions at top , bottom and sides with required

    PVC/EPDM/neoprene felt etc .Aluminium sections shall be smooth, rust free, straight, and

    jointed mechanically wherever reuired including cleat angle , Aluminium snap beading for

    glazing/ panelling, CP brass /stainless steel screws, fitting and Neccesory fixture, like Bearings, ,

    American Handle, Conceled lockgodrej or equivalent, stopper, hinges, all complete as per

    architectural drawings and the directions of Engineer-in-Charge.(Glazing and panelling to be

    paid for separately.)

    MATERIALS:(1) Approved door, windows, and ventilator sections as per drawing using 'Jindal'

    or equivalent Aluminum Sections.(2) Fixtures and fastenings including handles, stoppers, locking arrangement, tie

    road rubber and felt gaskets for stopping leakage of water and air.PROCEDURE:

    Aluminum door, windows, and ventilator s should be prepared from selected 'Jindal'or equivalent sturdy aluminum sections for outer frame as well as shutter frame, as perdrawing. The frame shall be fixed to the jams and sill with appropriate Rubber Gasket to

  • 7/25/2019 Volume-i Part II Specification

    16/118

    16

    prevent any leakage of water. The shutters shall be fitted to framing with appropriate hingesfixed by riveting. A felt gasket be fixed between the shutters for preventing leakage of airfrom the room.

    Approved Anodized aluminum handles, adjuster stoppers and locking mechanism beused.

    INCLUSIONS:Cost of All aluminum sections, screws, fasteners and all labour for making and

    fixing are included.

    MODE OF MEASUREMENT:Measurement of lengths of all Aluminum sections in outer window frame and

    shutter frame are recorded, weight is computed from standard section-weights. Weight of allfixtures, fastenings, screws, handles, hinges, adjuster stoppers, panels etc. are excluded.

    No increase be permitted due to anodizing. Payment is done by weight computed up to twodecimals in kg. Glass/wooden panels are paid separately.

    Item no-15

    Providing and fixing boards / sheets as specified below including cutting to required size and

    shape, fixing with aluminum glazing clips or triangular beading including screws, putty etc.,

    complete, Using 12mm thick flat pressed three layered wood based melamine faced prelaminated

    particle board bonded with Phenol formaldehyde with a decorate laminate of same colour onboth sides - NOVOPAN PLT / BHUTAN BOARD - Exterior grade or equivalent.

    The density of particle boards should be medium.These boards are manufactured from particles of agro waste and wood.

    The material is blended with adhesives and formed into solid panels with the help of heat,moisture, pressure etc.

    The particle boards are flat pressed with single, three or multi layers.

    Both surfaces of the boards are sanded to get a smooth finish.Adhesives: Adhesives are used for bonding. They are BWP(Boiling Water Proof) typesynthetic resin.

    Thickness and Tolerance:

    The thickness of the particle boards should be between 6mm to 40mm.

    Tolerance in thickness is +5% for boards having 25 mm thickness.Tolerance in thickness is +2.5% for boards having thickness above 25mm.

    The thickness of every board should be uniform.

    Testing:

    One sample of every 100 sq m is taken and tested.If the total requirement of particle boards in a work is less than 30 sq m, no testing is

    required.

    All the tested samples should meet the requirements of physical and mechanical propertiesof particle boards.

    Clear dimensions of PLPB Board rounded off to nearest centimeter are recorded and areacomputed in square meters, rounded to 2 places of decimal.

    Item No-16

    Providing and fixing glazing in aluminum door, window, ventilator shutters and partitions etc

    with PVC/neoprene gasket etc. complete as per the architectural drawings and the directions of

    engineer-in-charge. (Cost of aluminum snap beading shall be paid in basic item).With Clear glass

    panes of 5.00mm thickness (weight not less than 13.75 Kg/sqm).Note: clear area should be

    measured only.

  • 7/25/2019 Volume-i Part II Specification

    17/118

    17

    All glass shall be Tinted best quality, free from specks, bubbles, smokes, veins, air holesblisters and other defect. The kind of glass to be used shall be mentioned in the item or

    specification or in special provisions or sawn in detailed drawings. Thickness of glass panelsshall be uniform. The specifications of different kind of glass are as under. :

    Sheet Glass. :-

    1. Glass shall be weighing In absence of any specified thickness or weight in the item ordetailed specification of the item of work, sheet 13.75 K.G. /Sq.m. shall be used

    2. Sheet glass shall be patent flattened glass of best quality and for glazing & framingpurpose shall conform to I.S.1761-1960. Sheet glass of the specified color, style, shape& design shall be used, if shown in detailed drawing or so specified. For important

    buildings and for panels with any dimension over 900mm. plate glass of specifiedthickness shall be used.

    Plate Glass: -

    When plate glass is specified, it shall be Polished patent plate Glass of best quality.It shall have both the surface ground flat and parallel & polished obtain clear undisturbedvision and reflection. The plate glass shall be of thickness mentioned in the item or as sawn indetailed drawing or as specified. In absence of any specified thickness, the thickness of plat

    glass to be supplied 6mm. and a tolerance of 0.20 mm. shall be admissible.

    Clear dimensions of glass rounded off to nearest centimeter are recorded and areacomputed in square meters, rounded to 2 places of decimal.

    Item No-17

    Item description is same as item no -16 above, only use of material frosted glass instead of

    clear glass.

    Item No-18

    STRUCTURAL STEEL AND IRON WORK:

    Providing, fabricating, assembling, hoisting / erecting and fixing in position at all hights/ all levls/ all floors / all shapes and sizes with all leads and lifts structural steel hollow box sections RHS,

    SHS, tubular of TATA / Asian Structural box sections, (square, rectangular, tubular hollow

    sections as per IS 4923 & 1161) confirming to latest IS:808 for the work of , rolled steel, channels,

    angles, angle cleats, gusset plates, chequred plate, position hips and jack lifters,Trusses,

    purlins,etc. including cutting,straightening, Bending and welding, the members as per detailed

    drawing and design. The rate shall include 2 coat of zinc chromate yellow oxide primer and 2

    coats of synthetic enamel paint of approved make over all the surfaces of the steel sections. (Only

    standard measurements will be paid for as actual cut length used at site). Shop drawings for the

    connection details shall be prepared for the approval of the architect..

    (a) Canopy & Trusse with suspended cable work as per structural element design by consultants

    including toung & bukkle wire joints

    MATERIALS:

    (1) Fe-310 Closed Structural Steel of Tata or equivalent complying with IS:4923,Minimum Yield Stress of 310 N/mm2, Ultimate Tensile Stress of 450 N/mm2,and min. elongation 10%.

    (2) Advani High-Strength Welding rods,(3) G.I. Bolt-nuts as required,(4) Zinc-Chromate Primer,(5) Enamel Paint

    PROCEDURE:

  • 7/25/2019 Volume-i Part II Specification

    18/118

    18

    Samples selected from each lot should be tested at designated laboratory. Materialsbrought on site should be inspected for straightness, distortion, rusting and other defects. If the

    material is found defective, excessively rusted or if it does not comply with the test requirement it

    will be rejected and shall be immediately removed from site.

    Material shall be cut, bent and welded as per given profile on drawings. For weldingHigh Strength Advani Welding Rods of diameter 4mm and above should be used. Welded jointsshould be provided with sleeves, slots, plugs as per drawing. All weld slag should be carefullyremoved, and total weld size specified on drawing be made with multiple runs of weld, takingcare to avoid distortion during and after welding. All protrusions from welded junctions will beground off for smooth appearance. For cutting the member, use sawing or shearing machine. Gascutting be resorted only as a last resort. All bearing plates should be profile cut and machined. Allholes be drilled and files smooth for easy bolting. For foundation bolts and other connections, nogas-cut holes are permitted.

    Provide a cover plate min. 3 mm thickness for closing all open ends of hollow sections.Alternatively PVC stoppers made to size for snug fitting on the section might be provided to closethe ends. All bolt-heads, stems and nuts be protected by covering with appropriate rust-proofcoating.

    Prior to transportation to site for erection, two coats of Zinc-Chromate Primer shouldbe applied to all fabricated steel, after scrapping all rust, dirt, stains and weld slag. For members

    inaccessible to application of paint after erection should be given two coats of approved EnamelPaint of selected shade, prior to erection. Final touch up might be done after erection.

    All fabrication should be got inspected at fabrication site prior to application of primerand transportation to site. Corrections, if any, be incorporated before application of primer.

    All fabricated elements be transported to site, lifted to the required level and placed in

    position, connected with the structure with anchor fasteners, bolts etc. as per design and asdirected on site. Final coat of enamel paint shall be given either after fixing other elements like

    sheets, glass or prior to it as directed.

    INCLUSIONS:

    Cost of all materials, including steel, connectors, welding, primer, paint and alllabour for fabrication, transportation and erection etc. are included. Cost of providing,laying and dismantling templates, bending, wastage, erection jigs, anchor fasteners etc.are included.

    MODE OF MEASUREMENT:

    Number and Length of each section used will be recorded and weight computedas per standard steel tables. When plates are used for connections, they are measured andrecorded as per actual dimensions. No deduction is done for minor triangular cutouts.Weight of welds, bolts, nuts and other fasteners are not recorded, however an increasein total weight up to a maximum of 2% be allowed to compensate cost of fasteners.Weight is not to be derived by actually weighing fabricated elements.

    Item No-19

    Providing & Fixing Decorative M.S. gril, Pipe Clamp, M.S. Stair Railing / Balcony Railing as per

    architectural design as per design made from flats, bars Recagular, round,squae pipe etc., including

    cutting welding, Two coats of painting & one coat of primer etc, complete as per architectural

    Drawing. No extra payments pay for architecture design

    MATERIALS:(1) Mild Steel angles, square, flats, polished round bars, square/round pipe etc. as perdesign.

  • 7/25/2019 Volume-i Part II Specification

    19/118

    19

    (2) Fastenings like Screws, bolts etc. (3) Primer & Paint

    PROCEDURE:Mild steel grills be prepared from fresh rolled structural steel sections (not re-rolled or

    scrap materials) as per design, using angles, flats, square bars, & Polished round bars usingriveted joints as far as possible, minimizing use of welding. The design and dimensionsshould be matched with those in the existing structure, or modified as directed.

    The fabricated grills be inspected at the manufacturing premises prior toapplication of primer. All joints should be neatly finished. Welding slag should be removedfully and finished with grinder prior to application of red-oxide or zinc chromate primer.Holes be drilled appropriately in the steel frame for fixing with framing in the existingstructure. Grills should be fixed in position as directed, using fasteners or site welding, andtwo coats of approved enamel paint shall be applied.

    INCLUSIONS:Cost of all materials, including steel, connectors, welding, primer, paint and all

    labour for fabrication, transportation and erection etc. are included.

    MODE OF MEASUREMENT:Number and Length of each section used will be recorded and weight computed as

    per standard steel tables. Bolts, nuts, fasteners and welds are not recorded. Payment is done in

    weight, measured in kilogram.

    Item No-20

    Providing and Fixing 8mm thick of Full body Vitrified tiles in various finish of 605mm x 605

    mm Size and 10mm thk ( Marbito or their equivalent) as per detail, in floor of approved make

    and of approved colour of first quality, even shade, set in cement slurry over minimum 50 mm

    thick cement mortar 1:3 laid to proper slope, line and level, as specified including using white

    cement with or without colour mixing as per shade of approved quality in pointing of joints also

    joint fill with acrylic grout Filler and applying neat cement paste about 3 kg/sq.Mtr., curing and

    cleaning complete as directed by Clerk - of- Work For all, lift, levels and leads. Note: No extra

    payment pay for architectural Design.

    No tile shall be set on a surface where other work is specified or detailed to be

    embedded in the tile work until such work has been installed and approved.

    The surface on which the tiles are to be fixed shall be rough, clean, free of dust andthoroughly wetted. The tiles shall be soaked in water for a minimum period of six hour before

    fixing. A layer of 1:3 cement mortar bed of thickness up to 50mm thick. Shall be evenlyspread according to the slope required. The tiles shall then be laid in a neat thin cement paste,gently tapped with a wooden mallet and pressed in position.

    The pattern of fixing the tiles shall be as per the drawings. The floor tiles shall always go

    under the dado tiles. All joints shall be uniform and as thin as possible. Dado shall be for aheight as specified on drawings. Where full tiles are not possible, the same shall be cut or

    sawed to the required size and their edges rubbed smooth to ensure straight and true joints.After the tiles are laid, the extra cement grout shall be removed. The joints shall then be

    cleaned with a wire brush and the joints shall then be pointed with cement of a matchingcolor, and cured. The entire dado shall be cleaned and polished alter the work has beencompleted. The contractor shall protect all work until it is handed over to the Owner.

    The dado shall be in line, level, and plumb. Wherever necessary, holes shall be made in thetiles for pipes, conduits, etc. and then finished neat. Nothing extra shall be paid for making

    these holes and finishing the joints smooth, cutting the tiles and for making jaries or filling thejaries between the top of the tiles and the plaster. The top of the tiles for dado shall be truly

    horizontal. Measurements shall be in square meters. The tile work shall not sound hollow

  • 7/25/2019 Volume-i Part II Specification

    20/118

    20

    when tapped with a wooden mallet. Inner and outer corners (curved pieces) and specials oftiles, if specified by the Architects/Consultants. shall not be paid for separately.

    Note: For wall cladding/ dado the rate shall be included in the item of 12mm to 20mm

    plaster bedding (baking coat) as per required.

    MODE OF MEASUREMENT:Dimensions is computed in square meter, rounded to two places of decimal

    Item No-21

    Providing & laying 600mm x 600mm Anti skid Vetrified 8mm thick tile flooring (Any colour

    shade aproved bt Consultants) over 20mm ( ave ) base of C.M. 1:6 on new surface finished with

    flush pointing & cleaning the surface etc. comp. for antiskid ( For flooring, landing, skirting,

    dedo in desired colours, finishes fully polished, Matt, Satin, Satin Guard with flush pointing in

    white cement & pigment with residue and skirting, incl. curing, polishing & cleaning with mild

    oxalic acid etc. complete for all floors / all levels etc. ) Light & Dark colour

    Same as above item no-20 except that the tiles are antiskid vitrified tiles described in Item above.

    Item No-22

    Providing and laying GROUP -5 RUSTIC CERAMIC ( PREFERRED "ENDURA PEI-5 ) tiles

    of light color range specified in specification of size 300 x 300 mm /600mm x 600mm. laid on up

    to 6 mm on floors, tread of steps landings on a bed of 25 mm average thickness of C.M 1:3 (1

    cement : 3 sand) Jointed with neat cement slurry mixed with pigment to match the shade of tiles

    including buffing and polishing complete as detailed design and directed by consultant / engineer

    in charge.

    Specification for this item shall conform to item No. 14.29/P. No. 84 of General Technical

    specifications for building work. (Except hydrofluoric acid it's derivatives. Hence,commercially available detergents and cleaning agents also can be use for regularmaintenance)Except White/colored/ printed of size 300 x 300 mm /600mm x 600mm or any size of Bell/Somani / Johnson / Gold Coin, or equivalent group - 5 tiles shall be used instead of 150 x

    150mm. White glazed tiles.Rate shall be paid for a unit of one sq.mt.

    Item No.26

    Providing and fixing 18mm thick kesariyaji Green marble (approved by Architect) gang saw cut

    mirror polished (premoulded and prepolished) machine cut for Doors &window sills, Doors &

    Window Jams, (One Piece) as and similar locations of required size of approved shade, colour

    and texture laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with joints

    treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing,

    curing moulding and polishing to edge to give high gloss finish etc. complete at all levels.The rate

    includes rounding, champhering and mirror polishing of edges, facias of kesariyagi green

    marble, including necessary bonding adhesive like Araldite or equivalent.

    Providing and fixing kesariyaji Green marble ( approved by Architect) slab of 18 mm thick(Uniform Thickness), machine cut edges in sill and jambs /shelves (in single piece) as perdetail, including, making zaries in brick wall and fixing with cement mortar (1:4) etc.,Finishing and polishing with all respect, etc. complete.

    MODE OF MEASUREMENT:

    Dimensions is computed in square meter, rounded to two places of decimal

  • 7/25/2019 Volume-i Part II Specification

    21/118

    21

    Item No. 27. Paverblock

    Providing & laying 80mm thick grey or coloured Reflective Rubber Mould M-30( Lacquer

    coated ) paver block over a bed of sand (min 75 mm thickness) Job Includes spreading sand on

    existing driven way, compacting sand bed by ramming and interlocking them with the use of a

    suitable plate vibrator, job includes all incidental work like cleaning the site of debris etc. The

    paver blocks supplied by the party must confirm to following notes and completed as directed by

    architect or engineer incharge. (No extra payment shall be made for architectural detail.)

    Paver Block Specification

    Material : 80mm thick Rubber Mold Reflective Paver blocks lacquered coated of M-30

    Grade heavy duty paver blocks. of Alcock or Equivalent.

    Scope work:

    Excavation and compaction up to 25 cm in height for around road and landscaping area

    paving in all sorts of soil murrum including sorting out and stacking of useful materials

    stuff up to 50 mtr. lead from excavated place and same shall be carted. Up to 5 km. The

    scope of work includes supplying and lying of precast paver blocks at site, as mentioned

    in the Item. All relevant provisions of IS 15658:2006 shall apply. Laying of paver blocks

    at site as per requirement in technical specification, within shortest possible time. The site

    is public place hence care should be taken to ensure that the routine activities shall not be

    disturbed. The job of laying may required to be carried out during night also. The work

    shall be executed in perfect line and level as per instructions of Engineer in charge.

    Colored concrete paver blocks shall be manufactured as per specifications using approved

    color pigment. The color shade shall Be as selected by AMC before commencement of

    the work...

    The contractor shall guarantee that all material and components designed, fabricated,supplied and laid by him shall be free from any type of defect due to faulty material and/

    Workmanship/erection For a period of One year from the date of completion of work.

    The Contractor shall render free Maintenance for One year. If the contractor fails to

    execute the repair Works in time, the same shall be carried out at his risk and cost.The mode of measurement shall be on Smt. basis.

    Item No: 28Providing , fixing, threading or plaster drip & molding R.C.C. Precast molded

    Curbing of size 350mm. X 100mm X 150mm. Height with molded edges as per

    design, and M20 reinforced 1.6 mm. dia. Mild steel wire incl. roughening, cleaning

    fixing and finishing in cement mortar 1:3 and curing etc. complete. as per detail and

    directed by consultant / engineer in charge.

    Material : R.C.C. Precast molded Curbing of size 350mm. X 100mm X 150mm. Height

    with molded edges as per design, M20 grade Curbing

    Fixing: The pits of the size 0.15 M in width and required depth shall first be excavated, trueto line and level. The relevant specifications of item A- 1 shall be followed for excavationwork. The pits shall be filled with a layer of 0.05 M. thick sand bedding. The curbs then shall

    be placed in position of which 50mm shall be below road. Care should be taken to maintain

  • 7/25/2019 Volume-i Part II Specification

    22/118

    22

    proper line and level. The joints between the kerbs shall be pointed with C.M. 1:3 and curedfor minimum seven days.

    Precast Kerb Stones:The relevant specifications of concreting as per item above shall befollowed except that work shall be carried out for precast concrete kerb stones as specified inthe item. All Precast members shall be cast at workshop. Sufficient curing shall be done

    before placement of the same the method of transporting and placing the precast membersshall be as approved by the Engineer-in-charge. Members shall be so transported that no

    breakage or undue stresses are induced in them.

    The contractor shall guarantee that all material and components designed, fabricated, suppliedand laid by him shall be free from any type of defect due to faulty material and/Workmanship/erection For a period of One year from the date of completion of work. TheContractor shall render free Maintenance for One year. If the contractor fails to execute therepair Works in time, the same shall be carried out at his risk and cost.

    The rate shall be for Rmt of work carried out.

    Item No. 29.

    The use of "TRIMIX VACCUM DEWATERING SYSTEM" for spreading, screeding,

    dewatering, floating and troweling with the help of power trowelling floater of concrete floor as

    directed and specified using necessary steel form work with M.S. Channels including providing

    & laying sepration layer of 125 micron expanded polythin foam sheets . Rate includes forming

    construction & contraction joints 4 mm to 6 mm wide by cutting the floor upto % 5th depth of

    thickness of the concrete depth using mechanical saw up to full depth of cutting including

    providing & fixing M.S. dowells bars with bitumen painted of full length as shown in drawing as

    to form the bays not exceeding 6.0 m X 4.5 m etc. complete as per directed by Architect or Clerk-

    of-Work. For all level.( NOTE: Concrete item pay under respective item)

    TRIMIX

    How to place high-quality durable Industrial floors the requirements on the quality ofIndustrials floors have rapidly become more exacting during the few years. The reason for

    this is mainly the use of fork-left trucks and other modern transport equipment. The increasedwheel loads require higher compressive strength and wear resistance of the floor than before.

    With increasing lift heights higher accuracy as to the fines of the floors becomes aprerequisite.

    These demands of cause lead to a further checking of traditional floor placing methods and todevelopment of new building methods. The TREMIX Vacuum Dewatering Technique. Which

    is described here satisfies these high quality requirements. In addition, this method offersseveral advantages .e.g. Lower manufacturing costs.

    Traditional floor placing: several courses.

    According to traditional floor placing methods, a base course is first placed. This base is thencovered with a topping. This topping, which may consists of one or several courses, must be

    placed very carefully. Therefore, it is quite a hard work. The topping must have good bond tothe structural concrete if it is to function in operation and in traffic. Problems like break away

    of the topping are usual on this type of floors.

    In spite of similar initial materials, the physical properties of concrete and topping aredifferent. Both layer be have differently at varying temperature-weather-and environmentconditions. This may lead to stresses in the floor. For bimetals, such stresses are desirable but

    not for industrial floors, as they cause separation of the topping from the base concrete,

  • 7/25/2019 Volume-i Part II Specification

    23/118

    23

    cracking and finally breakaway. A repair is then inevitable Repairs are not only expensive butalso associated with costly interruptions in production and cause dust and noise problems.

    Modern floors: single course.

    The considerations to avoid the problems involved with traditional floor placing lead tomonolithic industrial floors. The structural concrete needs no topping.

    The monolithic method is successfully used in road building since decades. Extensive

    research and practical experience from the placing of thousands of kilometers of concreteroads have brought these up to their present high quality level. The Monolithic concrete roadsare placed with heavy building machines. Very stiff concrete consistency class K-1 with avery low water/cement ratio used. Road building owes its high quality to this technique.

    The great weight of the machines and the hardly workable concrete do not however, ingeneral allow the used of this technique for industrials floors.

    Monolithic industrial floors, which have the same high quality as concrete roads, are thereforenowadays-placed according go the TRIMIX Vacuum Dewatering Method.

    The advantage of this method is that a plastic and easily workable concrete can be placed with

    light equipment, and after that great part of the surplus water is extracted from the concrete,and the desirable quality y improvement is achieved.

    The TRIMIX Vacuum Dewatering Method has been used with great success for high-qualityIndustrial floors for many years.

    The use of the TRIMIX Vacuum Dewatering Method.

    This method follows the well-known laws of concrete technology and construction. For full

    utilization of the advantages of the advantages of the TREMIX Vacuum Dewatering system,the following points should be observed already at the planning stage.

    Base

    If the Industrial floors are placed directly on the ground, the base must have a sufficientbearing capacity. If necessary, frost protection layers are placed on free surfaces orappropriate filling materials for floors in halls or hangars.

    At this work and also at the ensuing concrete placing careful attention should be paid to the

    calculation of the expected traffic loads keeping in mind also those often-bigger ones, whichoccur during the construction work.

    If industrial floors are placed as suspended floors, the usual conditions regarding formworkand static loads are valid.

    Installations

    The position of the pipes for water and drainage, heating, eclectics supply and telephones

    must be fixed before concreting starts, so they not hinder the concreting work.

    Through vacuum processing shrinkage is reduced by 50.75 % compared to that of normalconcrete. Correspondingly, Joint spacing can be increased on vacuum dewatered industrial

    floors. Joint less bays 20x20 m are possible.)New condition for this is however that stabilityof the bars and the construction including reinforcement is calculated with regard to future

    traffic loads.

    Also on suspended floors the joint distance can be increased. At the execution, howeverattention must be paid to the stresses of the construction. The joints must be expansion joints

  • 7/25/2019 Volume-i Part II Specification

    24/118

    24

    which give enough room for the movement of concrete. Expansion joints can as a rule belocalized on fixed bases for flat industrial floors.

    Dummy joints are working joints, the placing of which is determined by daily production e.g.400 Sq.mt. at 20x20 m for heavy traffic the joints must be carried out as for highways withgrooved joints.

    Contraction joints to of the slab thickness are cut afterwards. They give clear and stresses.Their construction is easier and cheaper than from removal their function faultless and

    reliable.

    SlopeConcrete floors can have star shaped or roof shaped slopes Roof shaped slopes preferable.

    Separation layerBefore placing concrete on ground, a plastic sheet must be placed on the gravel or sand bed as

    a separation layer for protection against humidity and water. It also works as a sliding layerwhich prevents concrete from sticking to the sub base and allows the working of the concrete,in order to avoid cracking.

    This separation layer is not needed for suspended floors Concrete is placed directly on

    ordinary from and special preparation are not necessary.

    Reinforcement

    Reinforcement depends on the static constructional demands on the floors. A careful

    estimation of the expected traffic loads on the floor and the base is necessary.

    Important:Vacuum concrete should be made according to standards DIN 1045 With regardto concrete quality you must not use so much water that it runs on its own into the for work.

    Even if the excess water is then extracted during to vacuum treatment the quality of theconcrete would suffer. Therefore the exacting demands of the standard DIN 1045 should beobserved.

    Admixture:A pre-test of the admixtures, if used is to the carried out on order to determine

    their suitability for vacuum dewatering.

    Standards: DIN 1045 is also valid for vacuum impermeability high frost resistance, high

    resistance against chemical, high wear resistance is required, the prescriptions of paragraph6.5.7 of the standard are to be followed, even if vacuum dewatering improves these properties

    further.

    Quality:The improved properties of vacuum concrete can be proved by taking specimensfrom cores or 15 cm cubes. The cubes are made in a TTREMIX laboratory apparatus calledTM 1.

    Work cycle according to the TREMIX Vacuum dewatering process.

    The TREMIX Vacuum dewatering process has been developed in order to rationalize the

    concrete work and to achieve high quality concrete floors.

    This system is advantageous to anyone involved in buildings projects, to the designer as itmeans high quality and new aspects on the practical work, to a contractor trouble-from

    application on sites, to estimating engineer noticeable cost savings and finally, to the end userdurability and maintenance costs.

    Concreting according to DIV 1045 and leveling according to DIN 18.202

  • 7/25/2019 Volume-i Part II Specification

    25/118

    25

    Concrete of consistency class K 2/K 3 (8-12 cm slump ) is placed either by pump crame skipor direct from concrete truck. Then follows poker vibration. The next step is leveling which is

    carried out with TREMIX surface vibrator.

    The surface vibrator, available in lengths of 3 to 12 m. consists of a light alloy double beam.The beam is provided with tensioning road to prevent deflection. The TREMIX surfacevibrator leaves a concrete surface within the tolerance region of DIN 18.202 line 6 or 7.

    Vacuum dewatering process

    The purpose of vacuum processing is the removal of surplus water forms the concrete toprovide quicker setting & earlier maximum strength properties. Vacuum dewatering takesplace immediately after the screeding operation.

    Upon the surface of the wet concrete is placed a filler pad consisting of two layers. Thebottom layer is contract with the concrete is the fine nylon cloth to act as filler. The upper

    layer consists of a special type of plastic net & acts as a water duct. Finally the top coverconsisting of a light plastic sheet is placed over the filler pad projecting slightly outside on allsides. The border of the top cover rests directly upon the wet concrete to produce an airtightseal.

    The suction met is connected with suction houses to a vacuum pump. the normal atmosphericpressure in the pump is reduced by 90% & 90% of the atmospheric pressure compresses the

    concrete.

    Concrete is submitted to a pressure of

    Air pressure .1N / mm2Depression .01N/mm2

    ________= Effective pressure .09 N/ mm2

    This pressure of about 9000 kp/m2 compresses the concrete & compacts the aggregates. Atthe same time the excess water which not necessary for the hydration process of the cement is

    extracted from the concrete & consciously discharged with the air.

    Apart from normal compaction through vibration, static compaction takes place duringvacuum dewatering with ensuring reduction w/c ratio. The initial w/c/ ratio is reduced by 10to 20%. This explains the noticeable improvement s of the concrete properties achieved

    through vacuum dewatering.

    Vacuuming time is about 1 to 2 min. per cm concrete thickness depending on the particleshape in the mix. M250

    One vacuum pump with two suction met can dewater 50 to 60 m2. A 20 cm thick concreteslab takes about 30 min. dewater. Accordingly a normal daily production rate is about 400

    m2.

    Mode of Measurement: The measurement shall be in Sq. Mt.

    Item No.30

    Construction of granular sub-base by providing close graded material, spreading in

    uniform layers with mortar grader on prepared surface, mixing by mix in place method

    with rotavator at OMC, and compacting with vibratory roller to achieve the desired

    density, complete.

    GRANULAR SUB-BASE

    Scope

  • 7/25/2019 Volume-i Part II Specification

    26/118

    26

    This work shall consist of laying and compacting well-graded material on prepared sub

    grade in accordance with the requirements of these Specifications. The material shall be

    laid in one or more layers as sub-base or lower sub-base and upper sub-base (termed as

    sub-base hereinafter) as necessary according to lines, grades and cross-sections shown

    on the drawings or as directed by the Engineer.

    Materials

    The material to be used for the work shall be natural sand, murrum, gravel, crushed

    stone, or combination thereof depending upon the grading required. Materials likecrushedslag crushed concrete, brick metal and kankar may be allowed only with thespecific approval of the Engineer. The material shall be free from organic or otherdeleterious constituents and conform to one of the three grading given in Table 7.4.

    While the gradings in Table 7.4 are in respect of close-graded granular sub base

    materials, one each for maximum particle size of 75 mm, 53 mm and 26.5 mm.

    Physical requirements:The material shall have a 10 per cent fines value of 50 kN or

    more (for sample in soaked condition) when tested in compliance with BS: 812 (Part111). The water absorption value of the coarse aggregate shall be determined as per IS:

    2386 (Part 3); if this value is greater than 2 per cent, the soundness test shall be carriedout on the material delivered to site as per IS: 383. For Grading II and III materials, the

    CBR shall be determined at the density and moisture content likely to be developed inequilibrium conditions which shall be taken as being the density relating to a uniformair voids content of 5 per cent.

    TABLE: Grading for Close-Graded Granular Sub-Base Materials

    Per cent by weight passing the IS sieveIS Sieve

    DesignationGrading I Grading II Grading III

    75.0 mm 100 - -

    53.0 mm 80100 100 -

    26.5 mm 55-90 70-100 100

    9.50 mm 35-65 50-80 65-95

    4.75 mm 25-55 40-65 50-80

    2.36 mm 20-40 30-50 40-65

    0.425 mm 1025 1525 2035

    0.075 mm 3-10 3-10 3-10

    CBR value

    (Minimum)

    30 25 20

    Strength of sub-base

  • 7/25/2019 Volume-i Part II Specification

    27/118

    27

    It shall be ensured prior to actual execution that the material to be used in the sub base

    satisfies the requirements of CBR and other physical requirements when compacted and

    finished.

    When directed by the Engineer, this shall be verified by performing CBR tests in the

    laboratory as required on specimens remolded at field dry density and moisture content

    any other tests for the quality of materials, as may be necessary.

    Construction Operations

    Preparation of sub grade:Immediately prior to the laying of sub-base, the sub grade

    already finished to Clause 7.1 shall be prepared by removing all vegetation and other

    extraneous matter, lightly sprinkled with water if necessary and rolled with two passes

    of 80 100 kN smooth wheeled roller.

    Spreading and Compacting: The sub-base material of grading specified in theContract shall be spread on the prepared sub grade with the help of a motor grader ofadequate capacity, its blade having hydraulic controls suitable for initial adjustment and

    for maintaining the required slope and grade during the operation or other means asapproved by the Engineer.

    When the sub-base material consists of combination of materials mentioned in Clause

    7.3.2, mixing shall be done mechanically by the mix-in-place method.

    Manual mixing shall be permitted only where the width of laying is not adequate for

    mechanical operations, as in small-sized jobs. The equipment used for mix-in-place

    construction shall be

    a rotavator or similar approved equipment capable of mixing the material to the desired

    degree. If so desired by the Engineer, trial runs with the equipment shall be carried out

    to establish its suitability for the work.

    Moisture content of the loose material shall be checked in accordance with IS: 2720

    (Part 2) and suitably adjusted by sprinkling additional water from a truck mounted or

    trailer mounted water tank and suitable for applying water uniformly and at controlled

    quantities to variable widths of surface or other means approved by the Engineer so that,at the time of compaction, it is from 1 per cent above to 2 per cent below the optimum

    moisture content corresponding to IS: 2720 (Part 8). While adding water, due allowance

    shall be made for evaporation losses. After water has been added, the material shall be

    processed by mechanical or other approved means like disc harrows, rotavators until the

    layer is uniformly wet.

    Immediately thereafter, rolling shall start. If the thickness of the compacted layer does

    not exceed 100 mm, a smooth wheeled roller of 80 to 100 kN weight may be used. For a

    compacted single layer upto 225 mm the compaction shall be done with the help of a

    vibratory roller of minimum 80 to 100 kN static weight with plain drum or pad foot-

    drum or heavy pneumatic tyred roller of minimum 200 to 300 kN weight having a

    minimum tyre pressure of 0.7 MN/m2 or equivalent capacity roller capable of achieving

    the required compaction. Rolling shall commence at the lower edge and proceed

    towards the upper edge longitudinally for stretches of unidirectional cross falland super-

    elevation, and shall commence at the edges and progress towards the centre for stretches

    having cross fall on both sides.

    Each pass of the roller shall uniformly overlap not less than one-third of the track made

    in the preceding pass. During rolling, the grade and crossfall (camber) shall be checked

  • 7/25/2019 Volume-i Part II Specification

    28/118

    28

    and any high spots or depressions, which become apparent, corrected by removing or

    adding fresh material. The speed of the roller shall not exceed 5 km per hour.

    Rolling shall be continued till the density achieved is at least 98 per cent of the

    maximum dry density for thematerial determined as per IS: 2720 (Part 8). The surface

    of any layer of material on completion of compaction shall be well closed, free from

    movement under compaction equipment and from compaction planes, ridges, cracks or

    loose material. All loose, segregated or otherwise defective areas shall be made good to

    the full thickness of layer and re-compacted.

    Surface Finish and Quality Control of Work

    The surface finish of construction shall conform to the requirements of Clause 7.15.

    Control on the quality of materials and works shall be exercised by the Engineer in

    accordance with Section 7.15.

    Arrangements for Traffic

    During the period of construction, arrangement of traffic diversions shall be maintained

    as per the direction of Engineer.

    Measurements for Payment

    Granular sub-base shall be measured as finished work in position in cubic meters.

    The protection of edges of granular sub-base extended over the full formation as shown

    in the drawing shall be considered incidental to the work of providing granular sub-base

    and as such no extra payment shall be made for the same.

    Rate

    The Contract unit rate for granular sub-base shall be payment in full for carrying out the

    required operations including full compensation for:

    (i) Making arrangements for traffic diversions. Except for initial treatment toverges, shoulders and construction of diversions;

    (ii) furnishing all materials to be incorporated in the work including all royalties,

    fees, rents where necessary and all leads and lifts;

    (iii) all labor, tools, equipment and incidentals to complete the work to theSpecifications;

    (iv) carrying out the work in part widths of road where directed;

    (v) carrying out the required tests for quality control and

    (vi) multiple handling of materials

    Item No.31Wet Mix Macadam Sub- Base/ Base Course: Providing , laying & Compacting clean, graded

    aggregates and granular materials, premixed with water or a dense mass or prepared sub grade /

    sub-base/base as required thickness / as per drawing including Spreading, Compacting with 10

    to 12 MT Power road roller, make cambering/ slope as directed by Clerk-Of -Work.Note: Compacted measurement shall be considered.

    WET MIX MACADAM

    BASEScope

    This work shall consist of laying and compacting clean, crushed, graded aggregate and

    granular material, premixed with water, to a dense mass on a prepared sub grade/sub-

    base/base or existing pavement as the case may be in accordance with the requirements

    of the these Specifications. The material shall be laid in one or more layers as necessary

  • 7/25/2019 Volume-i Part II Specification

    29/118

    29

    to lines, grades and cross-sections shown on the approved drawings or as directed by the

    Engineer.

    The thickness of a single compacted Wet Mix Macadam layer shall not be less than 75

    mm. When vibrating or other approved types of compacting equipment are used, the

    compacted depth of a single layer of the sub-base course may be increased to 200 mm

    upon approval of the Engineer.

    Materials

    Aggregates

    Physical requirements:

    Course aggregates shall be crushed stone. If crushed gravel/shingle is used, not less than

    90 percent by weight of the gravel/shingle pieces retained on 4.75 mm sieve shall haveat least two fractured faces. The aggregates shall conform to the physical requirements

    set forth in Table below.

    TABLE: Physical Requirements of Coarse Aggregates for Wet Mix

    Macadam for Base Courses

    *Aggregate may satisfy requirements of either of the two tests.

    ** To determine this combined proportion, the flaky stone from a representative sample

    should first be separated out. Flakiness index is weight of flaky stone metal divided by

    weight of stone sample. Only the elongated particles shall be separated out from the

    remaining (non-flaky) stone metal. Elongation

    index is weight of elongated particle divided by total non-flaky particles. The value of

    flakiness index and elongation index so found are added up.

    If the water absorption value of the coarse aggregate is greater than 2 per cent, thesoundness test shall be carried out on the material delivered to site as per IS: 2386 (Part-

    5).

    Grading requirements: The aggregates shall conform to the grading given in Tablebelow

    TABLE 7.6: Grading Requirements of Aggregates for Wet Mix Macadam

    Test Test Method Requirements

    . * Los Angeles Abrasion value or

    *Aggregate Impact valueIS: 2386 (Part-4)

    2386 (Part-4) or IS: 5640

    40 per cent (Max.)

    30 per cent (Max.)

    Combined Flakiness and

    Elongation indices

    (Total)

    IS: 2386 (Part I) 30 per cent (Max.)**

  • 7/25/2019 Volume-i Part II Specification

    30/118

    30

    IS Sieve Designation er cent by weight passing the IS sieve

    53.00 mm 100

    45.00 mm 95-100

    26.50 mm -

    22.40 mm 60-80

    11.20 mm 40-60

    4.75 mm 25-40

    2.36 mm 15-30

    600.00 micron 8-22

    75.00 micron 0-8

    Materials finer than 425 micron shall have Plastically Index (PI) not exceeding 6.

    The final gradation approved within these limits shall be well graded from coarse to fine

    and shall not vary from the low limit on one sieve to the high limit on the adjacent sieve

    or vice versa.

    Construction Operations

    Preparation of base:

    Prior to laying of the wet mix macadam base the granular sub-base already laid shouldbe prepared by removing of extraneous material, lightly sprinkled with water and rolledwith two passes of 80 100 kN smooth wheeled roller.

    Provision of lateral confinement of aggregates:

    While constructing wet mix macadam, arrangement shall be made for the lateralconfinement of wet mix. This shall be done by lying materials in adjoining shouldersalong with that of wet mix macadam layer and constructing the adjoining shoulder with

    approved material along with that of the wet Mix Macadam layer.

    Preparation of mix:

    Wet Mix Macadam shall be prepared in an approved mixing plant of suitable capacity

    having provision for controlled addition of water and forced/positive mixingarrangement like pugmill or pan type mixer of concrete batching plant. For smallquantity of wet mix work, the Engineer may permit the mixing to be done in concrete

    mixers.

    Optimum moisture for mixing shall be determined in accordance with IS:2720 (Part-8) after replacing the aggregate fraction retained on 22.4 mm sievewith material of 4.75 mm to 22.4 mm size. While adding water, dueAllowance should

    be made for evaporation losses. However, at the time of Compaction, water in the wetmix should not vary from the optimum value by more than agreed limits. The mixed

    material should be uniformly wet and no segregation should be permitted.

    Spreading of mix:

    Immediately after mixing, the aggregates shall be spread uniformly and evenly upon the

    prepared sub grade/sub-base/base in required quantities. In no case should these be

  • 7/25/2019 Volume-i Part II Specification

    31/118

    31

    dumped in heaps directly on the area where these are to be laid nor shall their haulingover a partly completed stretch be permitted.

    The mix may be spread either by a paver finisher or motor grader. For portions wheremechanical means cannot be used, manual means as approved by the Engineer shall beused. The motor grader shall be capable of spreading the material uniformly all over the

    surface. Its blade shall have hydraulic control suitable for initial adjustments andmaintaining the same so as to achieve the specified slope and grade.

    The paver finisher shall be self-propelled, having the following features:

    i) Loading hoppers and suitable distribution mechanism

    ii) The screed shall have tamping and vibrating arrangement for initial compactionto the layer as it is spread without rutting or otherwise marring the surface

    profile.

    iii) The paver shall be equipped with necessary control mechanism so as to ensurethat the finished surface is free from surface blemishes.

    The surface of the aggregate shall be carefully checked with templates and all

    high or low spots remedied by removing or adding aggregate as may be required. The

    layer may be tested by depth blocks during construction. Nosegregation of larger and fine particles should be allowed. The aggregates as Spread

    should be of uniform gradation with no pockets of fine materials.

    Compaction: After the mix has been laid to the required thickness, grade and cross

    fall/camber the same shall be uniformly compacted, to the full depth with suitable roller.

    If the thickness of single compacted layer does not exceed 100 mm, a smooth wheel

    roller of 80 to 100 kN weight may be used. For a compacted single layer upto200 mm,

    the compaction shall be done with the help of vibratory roller of minimum static weight

    of 80 to 100 kN or equivalent capacity roller. The speed of the roller shall not exceed 5

    km/h

    In portions having unidirectional cross fall/super elevation, rolling shall commence fromthe lower edge and progress gradually towards the upper edge. Thereafter, roller should

    progress parallel to the centre line of the road, uniformly over-lapping each preceding

    track by at least one third width until the entire surface has been rolled. Alternate trips

    of the roller shall be terminated in