Voltage Control Scheme Using Fuzzy Logic

Embed Size (px)

Citation preview

  • 7/25/2019 Voltage Control Scheme Using Fuzzy Logic

    1/6

    Abstract--One of the most important operational requirements

    for any electrical power network for both distribution and

    transmission level is voltage control. Many studies have been

    carried out to improve or develop new voltage control techniques

    to facilitate safe connection of distributed generation. In Saudi

    Arabia, due to environmental, economical and development

    perspectives a wide integration of photovoltaic (PV) generation in

    distribution network is expected in the near future. This

    development in the network may cause voltage regulation

    problems due to the interface with the existing conventional

    control system. Therefore, a new control system with PVs should

    be developed. This paper introduces a new voltage control

    scheme for residential area networks in Saudi Arabia based on

    Fuzzy Logic concept (FL). The structure of two implementations

    of FL controller to regulate the voltage by setting the on-load tap

    changing transformer is proposed. In order to confirm the

    validity of the proposed methods, simulations are carried out for

    a realistic distribution network with real data for load and solar

    radiation. Results showing the performance of each

    implementation are presented and discussed.

    Index Terms-- Distribution System, ETAP, Fuzzy logic

    controller, Grid Connected, MATLAB, Photovoltaic Systems,

    Saudi Arabia, Solar radiation, Voltage control

    I. INTRODUCTION

    raditionally, the distribution network of the power system

    is a passive network with a radial configuration.

    Electricity flows one way from a substation to a largedistribution network. During normal operation or planning

    period, a steady-state analysis of voltage regulation, system

    losses, protection coordination, power quality, and system

    reliability must be performed to ensure proper operation

    within appropriate operating voltage range. Each utility has its

    own operation and planning criteria depending on distribution

    system characteristics and design criteria.

    Currently, in Saudi Arabia, the exploitation of solar energy

    as an alternative source of electric power is being considered

    because of the abundant amount of irradiation and long hours

    of sunshine. One way to achieve this is by using Grid-

    Connected

    Photovoltaic systems (GCPV) on domestic dwellings directlyconnected to the distribution network. This means that in the

    This work was supported by the Ministry of High Education In Saudi

    Arabia under Grant U208. The support of the Saudi Cultural Bureau in

    London for sponsoring the fact-finding trip to Saudi Arabia to obtain the

    required data is gratefully acknowledged.R. A. Shalwala is with the Department of Engineering, University of

    Leicester, Leicester, UK (e-mail: [email protected]).

    J. A. M. Bleijs is with the Department of Engineering, University ofLeicester, Leicester, UK (e-mail:[email protected])

    2010 IEEE

    future the system performance will be affected by PV

    generators. According to [1-3] distributed generation has both

    advantages and disadvantages for the system.

    In this paper two implementations of fuzzy logic technique

    have been used to maintain the voltage in a residential area

    network with high penetration of PV generators in Saudi

    Arabia. The ETAP simulation package has been used for

    power flow calculation and the MATLAB software package

    has been used to design the fuzzy logic controller.

    II. POWER FLOW CALCULATIONS

    Generally, distribution utilities deliver electric energy to

    their customers within an appropriate voltage range to meet

    customer requirements. For a radial configuration the bus

    voltage, voltage drop, power flow, and power loss can be

    calculated by using a simplified model such as the two-bus

    system as shown in Fig. 1 [4].

    Fig. 1. Model of a two-bus distribution system.

    The model consists of a short distance line represented by a

    series connection of resistance (R) and inductive reactance

    (X). In this case, real and reactive power ( transferbetween bus #1 and bus #2 is described by (1) and (2). cos cos (1)

    sin sin (2)Where:is the voltage angle at bus #1 is the voltage angle at bus #2is the admittance anglePower loss between bus #1 and bus #2 is given by eq.(3):

    ||

    (3)In addition, the voltage at bus #2 and the voltage drop

    between theses buses can be calculated in terms of the voltage

    at bus #1 by using (4) and (5), respectively. (4) (5)

    In a typical distribution system there are many scenarios to

    be considered, and to handle calculation in a large system,

    power system simulation software is required. In this paper,

    the power systems simulation package ETAP is used for

    evaluating of steady-state performance under different load

    and PV generation conditions.

    R. A. Shalwala, Student Member, IEEE,and J. A. M. Bleijs,Member, IEEE

    Voltage Control Scheme Using Fuzzy Logic

    for Residential Area Networks with PV

    Generators in Saudi Arabia

    T

    Bus#1 Bus#2

    || || 1/ ||12

  • 7/25/2019 Voltage Control Scheme Using Fuzzy Logic

    2/6

    III. SYSTEM MODELING

    The following model of a real distribution network in a

    residential area will be used as a base case in this paper

    (Fig.2). The distribution network starts from the Station bus at

    110 kV, through a step-down 110/11 kV power transformer at

    each primary substation (ISK11, RSF04, and ISK10)

    connecting to 3 branches. Each branch includes a number of

    secondary substations (labeled as I1, I2,I9, R1,....R7,S1....and

    S9), connecting to a customer feeder through another step-

    down11/0.38 kV transformer (see detail in Fig. 2).

    Fig. 2. Test residential network with 3 branches

    There are 6 load nodes tapped off from each feeder. Each

    branch is equipped with on-load tap changing transformer

    (LTCT) that has the ability of changing the voltage level of

    the branch at the main substation bus in small steps (0.5% of

    nominal voltages), adjusted by the automatic voltage

    controller (AVC). The main branches can be interconnected

    through normally-open circuit breakers in the case of outage

    of one of the 110/11 kV transformers.

    Since this study is concentrating on the effect of GCPV on

    the voltage regulation in the network under normal operation

    (no faults), the longest branch which is ISK11 will be the most

    sensitive because it will have the largest variations for thedifferent load and irradiation scenarios. The line parameters of

    this branch are shown in Table I.

    A. Load Conditions

    Real load data for the selected residential area has been

    collected from the Saudi Electricity Company in the Western

    Region (SEC-WR) who has also provided details of the

    transformers and lines of the network. Based on this

    information a detailed model of the distribution network has

    been created in ETAP.

    TABLEI

    LINE PARAMETERS OF ISK11

    From Bus To Bus Lenghth (m) Impedance (/km)

    ISK11 I1 1875 0.128+j0.1344

    I1 I2 15 0.128+j0.1344

    I2 I3 327 0.128+j0.1344

    I3 I4 153 0.128+j0.1344

    I4 I5 513 0.128+j0.1344

    I5 I6 396 0.128+j0.1344

    I6 I7 132 0.128+j0.1344

    I7 I8 648 0.128+j0.1344

    I8 I9 255 0.128+j0.1344

    Fig. 3 shows the average daily load profile for this area

    during each month. This area includes 5000 residential

    properties.

    Fig. 3. Average daily load of a residential area.

    A considerable part of the load is due to air conditioning

    (A/C) systems and in general the load reaches its maximum

    between noon and 16:00 h in summer. This type of load can

    reach 65 per cent of the total load during summer and since

    the AC systems are motor-driven, this reduces the power

    factor (PF) of the total load to approximately 0.85. The

    minimum load is equal to about 30% of summer peak load.

    The following conditions of each consumer load in the

    network will be considered in this research:

    1-

    Extreme load (based on the maximum capacity of

    customer circuit breaker)

    2-

    Peak load (Maximum Summer load)

    3-

    Normal load (Annual Average load)4- Light load (30% of peak load)

    B. PV Generators

    PV generators are connected to the grid through power-

    electronic inverters. The current generation of PV inverters

    operate at unity power factor. So, their behavior during steady

    state is similar to that of a Synchronous Generator (SG) with

    unity power factor. Therefore, a SG with unity power factor is

    used in ETAP to represent the PV generator.

    Since in this research Building Integrating photovoltaic

    (BIPV) system will be used to address the effect of such

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    70.080.0

    90.0

    100.0

    0 2 4 6 8 10 12 14 16 18 20 22 24

    Laod(MW)

    Time (hour)

    Average Daily load for a residential AreaJan

    Feb

    Mar

    Apr

    May

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    Average

    Peak Load

    Light Load

    Average Load

  • 7/25/2019 Voltage Control Scheme Using Fuzzy Logic

    3/6

    system on voltage regulation, the available

    selected buildings must be known. The aver

    area for PV installation on houses in a reside

    100m. This figure comes from about 29 diresidential houses in Saudi Arabia.

    The solar radiation data for this study h

    from King Abdul-Aziz City for Science

    (KACST) which has 40 stations around the

    the solar radiation every 5 minutes. The mon

    radiation that was recorded at Jeddah meteo

    year 2002 is shown in Fig. 4.

    Fig 4. Monthly average solar radiation, Jed

    Fig. 4 shows clearly the large amount

    between 9:00 to 15:00 throughout the yea

    value of 400 W/m^2 and maximum valu

    W/m^2.

    In this study, concentrating PV modules

    efficiency has been assumed. Also, a 90%

    inverter is considered in designing the PV

    to increase the penetration level. The output

    generator which will be delivered to the

    network can be estimated as:

    Based on the previous information and

    range of power that can be generated using

    system between 9:00 to 15:00 for each

    between 14.4 kW to 36 kW. So, the followi

    PV will be considered in this research:

    1-

    Max PV = 36 kW

    2- Minimum midday PV = 14.4 kW

    3- No PV

    IV. IMPACT OF PVON PRESENT VOLTA

    At each branch of Fig. 2 the voltage lev

    the AVR, which estimates the voltage drop o

    measuring the branch current at the mai

    However, this method assumes that the powe

    from the main substation bus (where the

    flowing to the end of the branch. The prese

    feeders makes the power flow bi-directiona

    connected to feeders are carrying most or al

    then the voltage profile along the feeders d

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    1100

    0 2 4 6 8 10 12 14 16 18 20 22

    SolarRadiation(W/m^2)

    Time (hour)

    Average daily Solar Radiation

    Max Radiation

    Minimum Midday

    Radiation

    No Radiation

    roof area of the

    ge available roof

    tial area is about

    fferent designs of

    as been obtained

    and Technology

    ountry recording

    hly average solar

    rology station for

    ah 2002.

    f solar radiation

    r with minimum

    e of about 1000

    (CPV) with 40%

    efficiency of the

    enerator in order

    power of the PV

    customer or the

    (6)

    y using (6), the

    concentrating PV

    single house is

    ng conditions for

    E CONTROL

    l is regulated by

    ver the branch by

    substation end.

    r is unidirectional

    AVR is located)

    nce of GCPV on

    l, and if the PVs

    l the branch load,

    pends mainly on

    the PVs location, power generated,

    This creates an unpredictable and u

    the voltage level of all nodes mig

    acceptable limits. To illustrate such

    the worse scenarios at light load a

    case the PVs, connected to feeders

    carrying the most of the branch l

    from the LTCT will be very low.

    assume that the branch load is at th

    will adjust its voltage level to 1.

    shows the voltage profile of each fe

    Fig. 5.Voltage profile of all feeders co

    It can be concluded that the co

    technique cannot properly adjust th

    with various PVs connected to the

    on measuring the branch current at

    which is no longer a good indica

    Therefore, a new technique must be

    coordination between PVs and the

    larger penetration and better voltage

    V. SCENARIOSAND

    In order to proof that the adjust

    sufficient to keep the voltage level a

    permissible level, the system has

    possible scenarios of load con

    combinations. It has been assumed t

    to each node in the system with equ

    assumed to be same for all house

    scenarios more realistic a further 3

    load feeders are also considered.

    The standard deviation for all vo

    from the nominal is used to det

    position of LTC (-5.0% to +5.0% in

    order to reduce the number of tap chresults are rounded to the nearest

    5.0%,-2.5%,0%,+2.5%,+5%). This

    for the tap changer and reduce the

    due to changing the LTC setting.

    for all scenarios.

    The worse cases are shown in F

    with the preferred position of tap ch

    The simulations show that both b

    for all scenarios improve the voltag

    the allowable limits for all customer

    24

    Jan

    Feb

    Mar

    Apr

    May

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    949596979899

    100101102103104105106

    1 2 3 4 5

    Voltage%ofNominal

    Customer Nodes

    Voltage profile ( Light load, Ma

    and the PV power factor.

    controlled situation where

    t or might not be within

    problem, consider one of

    nd maximum PV. In this

    long ISK11 in Fig. 2, are

    oad. The current flowing

    The AVR will therefore

    e minimum level; hence it

    0 p.u. (0% Tap). Fig. 5

    der in this case.

    nnected to ISK11 branch.

    ventional voltage control

    e voltage level of feeders

    , since it depends mainly

    the main substation end,

    tion of the feeder status.

    developed to facilitate the

    TCT for safe integration,

    control.

    SSUMPTION

    ment of the LTC only is

    long the branch within the

    been simulated for all

    ditions, PV status and

    hat the PVs are connected

    al power. Also, the load is

    s. However, to make the

    random conditions of the

    ltage nodes in the system

    ermine the best possible

    0.5% steps). However, in

    anging operations the bestpreferred position of (-

    ill increase the life time

    isturbances in the system

    able II shows the results

    g. 6, and Fig. 7, together

    nger.

    est and preferred position

    e level and keep it within

    s in the branch.

    6

    PV&0% tap)

    I1

    I2

    I3

    I4

    I5

    I6

    I7

    I8

    I9

    Upper limit

    Lower Limit

  • 7/25/2019 Voltage Control Scheme Using Fuzzy Logic

    4/6

    TABLE IIBEST &PREFERRED POSITION OF TAP CHANGER FO

    Scenario Load PVAverage

    V(p.u.)

    ALNPV Average No 98.19 +

    ALAPV Average Min 100.12 0

    ALMPV Average Max 102.71 -

    XLNPV Extreme No 94.39 +

    XLAPV Extreme Min 96.51 +

    XLMPV Extreme Max 99.33 +

    LLNPV Light No 99.56 +

    LLAPV Light Min 101.43 -

    LLMPV Light Max 103.94 -

    NLMPV No Max 104.35 -

    PLNPV Peak No 96.32 +

    PLAPV Peak Min 98.34 +

    PLMPV Peak Max 101.04 -

    R1LNPN Random1 No 97.48 +

    R1LAPV Random1 Min 99.44 +

    R1LMPV Random1 Max 102.07 -

    R2LNPV Random2 No 96.92 +

    R2LAPV Random2 Min 98.91 +

    R2LMPV Random2 Max 101.58 -

    R3LNPV Random3 No 97.33 +

    R3LAPV Random3 Min 99.31 +

    R3LMPV Random3 Max 101.95 -

    Fig. 6. Voltage profile of XLNPV scenario with pre

    Fig. 7. Voltage profile of LLMPVscenario with prefer

    949596979899

    100101102103104105106

    1 2 3 4 5Voltage%ofNominal

    Customer Nodes

    ( Extreme load, No PV & +5%

    949596979899

    100101102103104105106

    1 2 3 4 5 6Voltage%ofNominal

    Customer Nodes

    ( Light load, Max PV & -5%tap)

    ALL SCENARIOS

    est Preferred

    .0% +2.5%

    .0% 0.0%

    .5% -2.5%

    .0% +5.0%

    .5% +2.5%

    .5% 0.0%

    .5% 0.0%

    .5% -2.5%

    .0% -5.0%

    .5% -5.0%

    .5% +5.0%

    .0% +2.5%

    .0% 0.0%

    .5% +2.5%

    .5% 0.0%

    .0% -2.5%

    .0% +2.5%

    .0% 0.0%

    .5% -2.5%

    .5% +2.5%

    .5% 0.0%

    .0% -2.5%

    erred position of tap

    red position of tap

    VI. FUZZY LOGIC

    Fuzzy Logic Control (FLC)

    conventional controllers when ther

    model of the system to be controlle

    input-output linguistic variables and

    of desirable control outcomes ca

    features might include user-specifie

    analogous to a control range, clos

    conditions if desired, and the ability

    off between energy costs and intlogic controllers consist of a set

    based on fuzzy implications and t

    providing an algorithm, they con

    strategy based on expert knowledge

    strategy [5]. Just as fuzzy logic ca

    "computing with words rather tha

    can be described simply as "control

    equations". Therefore, in contrast t

    other expert systems, fuzzy log

    representation of imprecise huma

    way, with approximate terms and

    the use of precise statements and

    them more robust, more compact, a

    1stImplementation of FLC

    Fig. 8 shows the straight forward

    controller based on the numerical so

    changer position at each scenario

    simulated in MATLAB software.

    one input, the average customer vo

    preferred tap changer setting.

    Fig. 8. 1stImplementati

    1) The membership of input and

    Input: Average voltage (AvgV) of al

    Very High (VH), High (H), Normal

    Low (VL) as shown in Fig.9.

    Fig. 9. Input membership function for

    Output: Tap changer setting (TC); V

    Normal (N), Low (L) and Very low

    6

    tap)

    I1

    I2

    I3

    I4

    I5

    I6

    I7

    I8

    I9

    Upper limit

    Lower Limit

    I1

    I2

    I3

    I4

    I5

    I6

    I7

    I8

    I9

    Upper limit

    Lower Limit

    Allcusto

    mersvoltages Centralized

    system

    Average Voltage

    Avr V Fuzzy Lo

    Controll

    Input variable Avg

    ONTROL

    offers an alternative to

    is no available accurate

    d. By suitable selection of

    a rule base, a broad range

    n be achieved. Possible

    overall control 'tightness'

    er adherence to set point

    to explicitly set the trade-

    rior environment. Fuzzyf linguistic control rules

    e rules of inference. By

    ert the linguistic control

    into an automatic control

    n be described simply as

    numbers" fuzzy control

    with sentences rather than

    mathematical models or

    c controllers allow the

    knowledge in a logical

    alues, rather than forcing

    xact values, thus making

    d simpler [6].

    application of fuzzy logic

    lution for the preferred tap

    . This control system is

    he controller consists of

    ltage, and one output, the

    on of FLC

    utput signals:

    l customers in the branch;

    (N), Low (L) and Very

    1stimplementation of FLC

    ery High (VH), High (H),

    (VL) as shown in Fig.10.

    Tap position

    +5.0%

    +5.0%

    +2.5%

    0.0%

    -2.5%

    gic

    er

    V

  • 7/25/2019 Voltage Control Scheme Using Fuzzy Logic

    5/6

    Fig. 10. Output membership function for 1

    st

    imple

    2) The control rules:TABLEIII

    RULE TABLE FOR 1ST IMPLEMENTATION O

    Input: AvgV VH H N L

    Output: TC VL L N H

    Fig. 11 shows the difference between

    calculated and proposed FLC setting for the t

    Fig. 11. Numerical and Fuzzy Logic setting

    The FLC gives almost the same results

    solutions. The small differences in Fig. 9 ar

    range of variation in average voltage is

    numerical calculation (scenarios only). The

    this way of control is that it is independent o

    parameters and can be applied to various tHowever, it needs the installation of a digital

    customer to send the voltage values to a cent

    a communication network. This make

    prohibitively expensive. Also, if all requi

    method are available, there are many techniq

    can be used based on look-up tables for th

    and then set the preferred tap changer pos

    does not give any advantages of using FLC.

    B. 2ndImplementation of FLC

    In order to find a better solution than prev

    for controlling the voltage in the branch

    communication network and take advant

    features, the correlation between the localthe system and the preferred setting have

    based on engineering sense. Table

    measurements of active power (P) and reac

    ISK11. It is quite clear that there is a po

    between the load of the branch and the react

    ISK11. So, as the load increases the reactiv

    and vice versa. On the other hand the

    correlation between the PV generation and

    flow at ISK11. According to the new relatio

    in Fig. 12 can be set up.

    -5%

    -4%

    -3%

    -2%-1%

    0%

    1%

    2%

    3%

    4%

    5%

    94 95 96 97 98 99 100 101 102 103 104 105

    TapchangerSetting

    Average Costomer voltages

    entation of FLC

    F FLC

    VL

    VH

    the numerically

    ap changer.

    for LTC

    as the numerical

    because the full

    not used in the

    ain advantage of

    f branch and line

    pes of networks.voltmeter at each

    alized system via

    s this solution

    rements for this

    ues other than FL

    average voltage

    ition which may

    iously introduced

    without using a

    ge of the FLC

    measurements into be established

    IV shows the

    ive power (Q) at

    sitive correlation

    ve power flow at

    power increases

    e is a negative

    the active power

    ships, the system

    TABLEIVPOWER FLOW MEASUREMENTS @ISK11

    Scenario P@ISK11(kW) Q@ISK

    ALNPV 805 479

    ALAPV -915 486

    ALMPV -3382 638

    XLNPV 2444 1549

    XLAPV -670 1480

    XLMPV -1859 1540

    LLNPV 200 99

    LLAPV -1502 130

    LLMPV -3946 315

    NLMPV -4134 208

    PLNPV 1619 1004

    PLAPV -127 974

    PLMPV -2624 1082

    R1LNPN 1122 691

    R1LAPV -609 683

    R1LMPV -3088 818

    R2LNPV 1327 824

    R2LAPV -411 805

    R2LMPV -2899 927

    R3LNPV 1168 720

    R3LAPV -565 709

    R3LMPV -3046 841

    Fig. 12. Fuzzy Logic controlle

    where:

    1) The membership of input and

    Input1: Reactive power (Q) @ ISK1

    loadhigh Q (HL), average load

    light loadlight Q (LL) as shown i

    Fig. 13. Input membership function 1 for

    Input2: Active power (P) @ ISK11;

    Minimum PVmedium P (MinPV

    light P (MaxPV) as shown in Fig.14

    Numerical

    Fuzzy

    Q @ ISK11

    P @ ISK11 Fuzzy Logic

    Controller

    OR SCENARIOS USING ETAP

    1(kVar) Preferred tap

    +2.5%

    0.0%

    -2.5%

    +5.0%

    +2.5%

    0.0%

    0.0%

    -2.5%

    -5.0%

    -5.0%

    +5.0%

    +2.5%

    0.0%

    +2.5%

    0.0%

    -2.5%

    +2.5%

    0.0%

    -2.5%

    +2.5%

    0.0%

    -2.5%

    implementation 2

    utput signals:

    1; extreme and peak

    medium Q (ML) and

    Fig.13.

    2nd implementation of FLC

    no PVhigh P (NoPV),

    and maximum Power

    .

    Tap position

    +5.0%

    +5.0%

    +2.5%

    0.0%

    -2.5%

  • 7/25/2019 Voltage Control Scheme Using Fuzzy Logic

    6/6

    Fig. 14. Input membership function 2 for 2nd imple

    Output: Tap changer setting (TC); Very High

    Normal (N), Low (L), Very low (VL) as sho

    Fig. 15. Output membership function for 2nd imple

    2) The control rules:TABLEV

    RULE TABLE FOR 2NDIMPLEMENTATION O

    PPV

    QLoadNo PV Min PV

    HL VH H

    ML H N

    LL N L

    Fig. 16 shows the tap changer settings for p

    and Q using the proposed FLC.

    Fig. 16. Fuzzy Logic set for LTC ased on power

    The controller gives the preferred tap ch

    all scenarios when the values of P and

    scenario have been used as an input to the

    key benefit of this implementation is that all

    taken locally and there is no need for remot

    This makes this solution simple and cheaother control technique. In order to optimize

    membership for the input has to be tuned b

    preferred position numerically for the pow

    the transition region.

    VII. CONCLUSIONS

    Two methods of implementation the o

    controller for setting the tap changer positi

    network were investigated in this paper. It h

    both proposed FLCs have the ability to im

    profile of distribution network and kee

    permissible limits.

    -5.0%

    -2.5%

    0.0%

    2.5%

    5.0%

    50

    200

    350

    500

    650

    800

    950

    1100

    1250

    1400

    1550

    Tapchan

    gersetting

    Reactive Power Q(kVar)

    entation of FLC

    (VH), High (H),

    n in Fig.15.

    entation of FLC

    F FLC

    Max PV

    N

    L

    VL

    ssible range of P

    flow @ ISK11

    nger position for

    value of each

    this system. The

    easurements are

    communication.

    compared withthis solution, the

    determining the

    r flow values in

    f a fuzzy logic

    on in distribution

    s been found that

    rove the voltage

    p it within the

    The first implementation is as

    costs due to hardware cost and

    communication infrastructure but i

    networks since it is independent on t

    The second implementation sho

    control the LTCT based on the po

    transformer itself. The main advant

    is that all measurements are taken l

    for remote communication with

    system. However, the main drawba

    depends on the network par

    characteristics. So, for each network

    based on analysis of the network

    results are encouraging and warrant

    the fuzzy logic concept in such prob

    VIII. REFERE[1]

    Davis, W. Murray, Distributed ResourSignificant Advantages Over Central

    Power Systems Part I, Proceedings

    Society Transmission and Distribution2002, pp. 54-61.

    [2]

    Davis, Murray W., Distributed Resour

    Significant Advantages Over CentralPower Systems Part II, Proceedings

    Society Transmission and Distribution

    2002, pp 62-69.[3]

    H.B. Puttgen, P.R. MacGregor, F.C. L

    Semantic Hype or the Dawn of a

    Magazine, IEEE Vol. 1, Issue 1, Jan-Fe

    [4]

    N. Jenkins, R. Allan, P. Crossley, D. Ki

    generation: The Institution of Electrical

    [5]

    C.C. Lee, "Fuzzy Logic in Control SParts I & II,"IEEE Transactions on Sys

    20, No. 2, March/April 1990, pp. 404-4

    [6]

    A.I. Dounis, M. Bruant, M. Santamo"Comparison of conventional and fuzz

    quality in buildings,", Journal of Intel

    pp.131-140

    IX. ACKNOWLE

    The authors would like to thanks

    solar irradiance data, and SEC-WR

    providing the utility grid data.

    X. BIOGRAP

    Raed A. Shalwala

    King AbdulAziz U

    in 2002 and theNottingham, Notti

    electrical engineeri

    Ph.D. degree at UU.K.

    His research interes

    and operation, re

    distribution network

    Johannes (Hans)

    Electrical andEindhoven Unive

    Netherlands, in 19

    College in Londonon integration o

    generators. He wa

    Imperial College inLecturer in Electric

    of Engineering at t

    he teaches Electrical Machines and Power

    covers a wide range of subjects in Renewabl

    Storage, from electrical generators and po

    and advanced controllers.

    -4150

    -2610

    -1070

    470

    2010

    sociated with significant

    the need to widespread

    can be applied to many

    he network parameters.

    ws a novel technique to

    er flow information at the

    ge of this implementation

    cally and there is no need

    other information in the

    k of this method is that it

    meters and the load

    the FLC need to be set up

    oad data. In general, the

    further investigation using

    lems.

    CESce Electric Power Systems Offer

    Station Generation and T&D

    f the IEEE Power Engineering

    Conference, Vol. 1, Jul 21-25

    ce Electric Power Systems Offer

    Station Generation and T&Df the IEEE Power Engineering

    Conference, Vol. 1, Jul 21-25

    mbert, Distributed Generation:

    ew Era?, Power and Energy

    b 2003, pp. 22 29.

    schen, and G. Strbac,Embedded

    Engineers, London , UK, 1995.

    stems: Fuzzy Logic Controller,tems, Man and Cybernetics, Vol.

    5.

    ris, G. Guaraccino, P. Michel,control of indoor of indoor air

    igent and Fuzzy Systems, 1996,

    GMENT

    KACST for providing the

    main office in Jeddah for

    IES

    received the B.S. degree from

    iversity, Jeddah, Saudi Arabia,

    .S. degree from University ofgham, U.K., in 2006, both in

    g. He is currently pursuing the

    iversity of Leicester, Leicester,

    ts are in power system planning

    ewable energy resources and

    .

    leijsreceived his MSc degree in

    lectronic Engineering fromrsity of Technology, The

    2. In 1983 he joined Imperial

    s a Research Associate workingwind turbines with diesel

    awarded a PhD degree from

    1990. Since 1991 he has been al Engineering in the Department

    e University of Leicester, where

    Systems. His field of research

    Energy Conversion and Energy

    er electronics to power systems