V.O.04(REV.01) - Data Centre & Card Room Variation

Embed Size (px)

Citation preview

  • 8/12/2019 V.O.04(REV.01) - Data Centre & Card Room Variation

    1/3

    1DEWA shop drawing / load schedule preparation / modifications/ site survey, online submissions, DEWA engineer visits, technical discussions, revisions etc 12,550

    2 Inspection application follow up with DEWA, enginner availability etc 4,500

    3 Supervision of other electrical contractors work and to check compliance with DEWA regualtions 4,500

    3 MBBs, Meter panel, related main cables, cable tray, works complete. 23,500

    4 Lighting works in data centre. 27 points 6,750

    5 Water and drain proviosnons at 2 locations with valve and necessary terminations 3,450

    7 Removal of duct work and making good 1,250

    8 Earth pits 2 nos with boring, copper earth rods, earth cover 16,500

    9 Integration of fire suppression with main panel with dedicated wiring 2,800

    10 Builders work inside data centre like coring, wall chasing, etc 4,900

    11Builders work for main cable laying, including interlock / external tile removal, excavation, slabcoring, wall openings, excavation for earth pits etc 12,300

    12 Fire rated Aluminium suspension panel ceiling 13,043

    Sub total 106,043

    Exclusions1 Power cabling works from MDB to related DBs.2 Any comment by DEWA on office area works and related modifications.3 Meter panel and MDB is assumed to be in external electrical room4 Any kind of modifiations / additions to existing DBs cables etc

    Variation or MEP works related to Data center - Mavarid

  • 8/12/2019 V.O.04(REV.01) - Data Centre & Card Room Variation

    2/3

    1DEWA shop drawing / load schedule preparation / modifications/ site survey,online submissions , DEWA engineer visits, technical discussions, revisions etc 14,433

    2 Inspection application follow up with DEWA, enginner availability etc 5,175

    3Supervision of other electrical contractors work and to check compliance withDEWA regualtions 5,175

    3 MBBs, Meter panel, related main cables, cable tray, works complete. 27,0254 Lighting works in data centre. 27 points 7,763

    5Water and drain proviosnons at 2 locations with valve and necessaryterminations 3,968

    7 Removal of duct work and making good 1,4388 Earth pits 2 nos with boring, copper earth rods, earth cover 18,975

    9 Integration of fire suppression with main panel with dedicated wiring 3,22010 Builders work inside data centre like coring, wall chasing, etc 5,635

    11Builders work for main cable laying, including interlock / external tile removal,excavation, slab coring, wall openings, excavation for earth pits etc 14,145

    12 Fire rated Aluminium suspension panel ceiling to Data room 15,000TOTAL AMOUNT OF VARIATION AED. 121,952

    Exclusions1 Power cabling works from MDB to related DBs.2 Any comment by DEWA on office area works and related modifications.3 Meter panel and MDB is assumed to be in external electrical room4 Any kind of modifiations / additions to existing DBs cables etc

    . ar at on or wor s re ate to ata center

  • 8/12/2019 V.O.04(REV.01) - Data Centre & Card Room Variation

    3/3

    Item Description Qty Unit Rate Amount

    1 Floor finish FF-03 - 600x600 tiles for the Card roomflooring

    24.00 m2 94.00 2,256.00

    2 Skirting finish- porcelain skirting 25.00 Rm 31.00 775.00

    3 Gypsum Fire rated dry wall to cver the window openings 18.00 m2 275.00 4,950.00

    3 Fire rated paint finish to the card room walls 71.00 m2 28.00 1,988.00

    4 Fire rated Aluminium suspension panel ceiling 24.00 m2 150.00 3,600.00

    5 All MEP related works- such as rerouting of AC ducting,lighting, power, cabling, etc

    1.00 LS 8,000.00

    TOTAL AMOUNT OF VARIATION AED. 21,569.00

    Exclusions1 Power cabling works from MDB to related DBs.2 Any comment by DEWA on office area works and related

    3Meter panel and MDB is assumed to be in externalelectrical room

    4Any kind of modifiations / additions to existing DBs cablesetc

    ar at on or ar room wor s