JEANSTATION(PROJECT TITLE)
Date : March 20, 2015
LOCATION: VICTORY PARK & SHOP, ANTIPOLO CITY
OWNER: TRENDS CHANNEL INC.
We are pleased to submit our quotation for the following items below. (Based on plan) Total Floor Area : 99 sqms.
DESCRIPTION UNIT COST(LABOR & MAT'LS) TOTAL COST
1. General Requirements 1 LOT P 35, 000.00
1.1. Mobilization / Demobilization
1.2. Site Clearing and Hauling of Debris
1.3. Housekeeping
SUB-TOTAL P 35, 000.00
2. Architectural
2.1. Floor Finishes
2.1.1. Supply and Installation of Floor Vinyl Tiles 1 LOT P 11, 115.00
(300mm x300mm) at Cashier and Baggage
Counter Platform
SUB-TOTAL P 11, 115.00
2.2. Wall Finishes
2.2.1. Supply and Installation of 6mm THK Ficem 1 LOT P 17, 900.00
Board on Metal Studs for Drywall Partitions,
Painted Finish for Changing Room
2.2.2. Supply and Installation of 6mm THK Ficem 1 LOT P 150, 280.00
Board on Metal Studs for Drywall Partitions,
Painted Finish for Selected Interior Perimeter
walls only
2.2.3. Supply and Installation of 6mm THK Ficem 1 LOT P 17, 830.00
Board on Metal Studs for Drywall Partitions,
Painted Finish for Office/Pantry Partition Wall
2.2.4. Supply and Application of Semi-gloss Paint 1 LOT P 63, 180.00
at Wall Finish
2.2.5. Supply and Installation of 6mm THK Ficem 1 LOT P 36, 340.00
Board on Metal Studs (Double Wall), Painted Finish for
display window
SUB-TOTAL P 285, 530.00
2.3. Counter and Cabinets
2.3.1. Supply and Fabrication of Cashier Counter 1 LOT P 90, 240.00
in Ducco Paint Finished
2.3.2. Supply and Fabrication of Baggage counter with 1 LOT P 67, 000.00
hanging cabinet and pigeonhole shelves
in Ducco Paint Finished
2.3.3. Supply and Fabrication of Storage Cabinets 1 LOT P 238, 500.00
in Ducco Paint Finished
2.3.4. Supply and Fabrication of Platform 1 LOT P 122, 300.00
SUB-TOTAL P 518, 040.00
2.4. Ceiling Works 1 LOT P 47, 385.00
2.4.1. Supply and Application of Davies Flat Latex
Paint for Ceiling Soffit
SUB-TOTAL P 47, 385.00
2.5. Carpentry Works 1 LOT P 20, 000.00
2.5.1. Supply and Installation of Two (2) 800mm x 2100mm
Flush Wooden Door
SUB-TOTAL P 20, 000.00
2.6. Glass Works
2.6.1. Supply and Installation of Mirror Glass (8 sets) 1 LOT P 29, 790.00
at Changing Room and Walls
SUB-TOTAL P 29, 790.00
GRAND TOTAL AMOUNT P 946, 860.00
12 % VAT INCLUSIVE
MR. GILBERT KUA
GENERAL MANAGER
KYNAR PANEL PHILIPPINES CORPORATION
NOTE : THE FOLLOWING ITEMS AND SCOPE OF WORKS ARE NOT INCLUDED
1. DISPLAY RACKS
2. DISPLAY BOXES
3. DISPLAY SHELVES
4. SIGNAGES
5. MODULES
6. LAMINATED FLOORING
7. HANGING RODS
8. PHOTO STICKER
9. FIXED WINDOW FOR WINDOW DISPLAY
10. ELECTRICAL WORKS AND FINISHES
11. PLUMBING WORKS AND FINISHES
12. MECHANICAL WORKS AND FINISHES
13. PERMITS AND OTHER FEES