Vivek Project Summary 20141073

Embed Size (px)

DESCRIPTION

pm project summary

Citation preview

Page 1: Vivek Project Summary 20141073

Vivek_earned value_20141073

as of Sun 04-10-15

DatesStart: Mon 05-10-15 Finish: Mon 09-11-15Baseline Start: Mon 05-10-15 Baseline Finish: Mon 09-11-15Actual Start: Mon 05-10-15 Actual Finish: NAStart Variance: 0 days Finish Variance: 0 days

DurationScheduled: 26 days Remaining: 17.76 daysBaseline: 26 days Actual: 8.24 daysVariance: 0 days Percent Complete: 32%

WorkScheduled: 88 hrs Remaining: 68 hrsBaseline: 88 hrs Actual: 20 hrsVariance: 0 hrs Percent Complete: 23%

CostsScheduled: ₹ 9,125.00 Remaining: ₹ 6,800.00Baseline: ₹ 9,125.00 Actual: ₹ 2,325.00Variance: ₹ 0.00

Task Status Resource StatusTasks not yet started: 0 Work Resources: 0Tasks in progress: 10 Overallocated Work Resources: 1Tasks completed: 0 Material Resources: 2Total Tasks: 10 Total Resources: 3