35
VISION PLAN UPDATE 31 January 2017

VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. [email protected]. parkmercedvision.com

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

VISION PLAN UPDATE31 January 2017

Page 2: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

TODAY’S TOPICS

1. Vision Plan

2. Subphases 1A and 1B

3. Q&A

Page 3: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

VISION PLAN

Page 4: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

SPRING 2015 Development Phase 1 Application Approved

SUMMER 2015 Informational Planning Commission Hearing

FALL 2015 Tentative Subdivision Maps Approved

Design Review Applications Buildings Approved

WINTER 2015/16 Building Permits Submitted

Privately Owned/Maintained Tree Removal

SUMMER 2016 Outdoor Resident Amenity Center Opens

Project Website Relaunch

FALL 2016 Ongoing Coordination of Implementing Approvals with City

QUARTERLY Resident Newsletter and Resident Meetings

History, Outreach, and Communication

Page 5: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

SPRING 2017 Resident Shuttle and Bike Share Launch

SUMMER 2017 Playground Closure (Meadow, 310/350 Arballo, 55 Chumasero)

Construction Start for Subphases 1A and 1B Street Improvements

Construction Start for Blocks 1, and 20

Existing Tenant Notices to first 56 Apartments

FALL 2017 Construction Start Block 6

WINTER 2017 Construction Start Block 22

QUARTERLY Resident Newsletter and Resident Meetings

Look Ahead

Page 6: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Parkmerced Today

152 Acres

3,221 Apartments

Single Ownership

Page 7: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Parkmerced (20-25 years)

Page 8: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Existing Homes to Remain 1,683 Tower Apartments

Existing Homes to be Replaced 1,538 Garden Apartments

New Homes 5,679 Net New Homes

TOTAL HOMES 8,900

Neighborhood Retail 230,00 square feet

Office 80,000 square feet

School 25,000 square feet

Community Center 64,000 square feet

Open Space & Parks 68 acres

Residential

Commercial, School, Recreation, and Open Space

By the Numbers

Page 9: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

SUBPHASES 1A & 1B

Page 10: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Subphases 1A and 1B By the Numbers

56 + 957 = 1013Replacement

HomesNew

HomesTotal for

Subphases

Page 11: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Subphases 1A & 1B

LAKE MERCED BLVD

BROTHERHOOD WAY

VIDAL DR

ACEVEDO AVE

HIGUERA AVE Juan BautistaCircle

ARB

ALLO D

R

Leasing

SFSU Community Amenities

Landscape and Hardscape

Children’s Play Areas

Flexible Open Space

Community Gardens

Car Share

Bike Share

Resident Shuttle

Wayfinding Signage

1

2

3

3

44

51

2

3 4

5

199 VIDAL

300 ARBALLO

455 SERRANO850 GONZALEZ

1208-1218 J. SERRA

95-99 CHUMASERO

310 Arballo

350 Arballo

405 Serrano

810 Gonzalez

125 Cambon

150 Font

100 Font

50 Chumasero

55 Chumasero

355Serrano

750Gonzalez

PINTO AVE

All Existing High Rises to Remain

Page 12: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

199 Vidal 64 Homes (40 Replacement Homes)

Page 13: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

300 Arballo 89 Homes (16 Replacement Homes)

Page 14: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

455 Serrano/850 Gonzalez 248 Homes // ~445 Parking Spaces

Page 15: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

1208-1218 Junipero Serra 299 Homes // 324 Parking Spaces

Page 16: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

95-99 Chumasero Drive 313 Homes // 266 Parking Spaces

Page 17: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

CONSTRUCTION

Page 18: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

199 Vidal

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

300 Arballo

455 Serrano and 850 Gonzalez

1208-1218 Junipero Serra

95-99 Chumasero

2017 2018

Phase 1A Street Improvements

Subphase 1A Construction Schedule

2019

Phase 1B Street Improvements

Page 19: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

SFSU

FONT BLVD

SUBPHASE 1A

B1

B6

B2O

B22

SUBPHASE 1B

Construction Mitigations

Noise Air Quality Resources

Construction HoursEquipment Selection

Dedicated Truck RoutesNoise Coordinator

Dust MonitoringReduce Idling

EPA Standard Vehicles

Bird SurveysTree Protection

Tree RemovalTree Replacement

Page 20: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

SFSU

FONT BLVD

B1

B6

B2O

B22

Communication

Project Websitee-mail

Information BoardsJob Site Entry

[email protected]

parkmercedvision.com

Page 21: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

STREET IMPROVEMENTS

Page 22: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Subphase 1A Street Improvements

LAKE MERCED BLVD

BROTHERHOOD WAY

VIDAL DR

ACEVEDO AVE

HIGUERA AVE Juan BautistaCircle

ARB

ALLO D

R

PINTO AVE

Leasing

SFSU Street Improvements

Enhanced Quality of Life

“Better Streets Plan” Elements

Promote Public Safety

Wider Sidewalks and Bulb Outs

Increased Accessibility for All

Improved Transit Access

Bicycle Infrastructure

New and Upgraded Utilities

Street Improvements: Reconstruction of portions of the publicright-of-way including sidewalk, curb, gutter, parking strip, parkway, driveway, etc.

310 Arballo

350 Arballo

405 Serrano

810 Gonzalez

355Serrano

750Gonzalez

Subphase 1B

Page 23: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Subphase 1B Street Improvements

LAKE MERCED BLVD

BROTHERHOOD WAY

Juan BautistaCircle

ARB

ALLO D

R

PINTO AVE

Leasing

SFSU Street Improvements

Enhanced Quality of Life

“Better Streets Plan” Elements

Promote Public Safety

Wider Sidewalks and Bulb Outs

Increased Accessibility for All

Improved Transit Access

Bicycle Infrastructure

New and Upgraded Utilities

Street Improvements: Reconstruction of portions of the publicright-of-way including sidewalk, curb, gutter, parking strip, parkway, driveway, etc.

125 Cambon

150 Font

100 Font

50 Chumasero

55 Chumasero

Subphase 1A

Page 24: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Subphase 1A and 1B Phased Street Construction

SFSU

FONT BLVD

SUBPHASE 1B

SUBPHASE 1A

B1

B6

B2O

B22

Page 25: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero (Existing)

Page 26: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero – Existing Crossings

Page 27: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Pedestrian Bridge

Page 28: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Constructed in 1960 by SFDPW after and as a separate project from Parkmerced

Not a historic resource as determined by Page & Turnbull (Historians)

Not ADA Compliant; Construction by City predates ADA

Ongoing Maintenance of Bridge is in Question

Brotherhood Way Bridge

Page 29: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero– Crossing During Construction

Page 30: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero– Crossing During Construction

Page 31: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero Post Construction

Page 32: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero Final Condition

Page 33: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Brotherhood Way at Chumasero Final Condition

Page 34: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Q&A

Page 35: VISION PLAN UPDATE · 1/31/2017  · e-mail. Information Boards. Job Site Entry. 415.405.4666. info@parkmercedvision.com. parkmercedvision.com

Contact Us!

415.405.4666

[email protected]

parkmercedvision.com

THANK YOU!