Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Vipin GuptaS/o Sh. G.P Gupta,House No. 329,Galli No. 10 Burari, Delhi.
To, Date: 12.03.2015
The Director (IA-II),Ministry of Environment, Forest & Climate Change,Indira Paryavaran Bhawan,Lodhi Road, Jor Bagh,New Delhi-110003
Sub: Regarding Environmental Clearance for Karnal Unit-I Sand Mining
Project (Area: 941.0 ha), District Karnal, Haryana.
Ref: Query letter received from MoEF & CC dated 5th March, 2015.
Dear Sir,
This is for your kind information that as the above mentioned reference, I
am here by submitting the reply of the short-comings in hard copy as well
as in soft copy for your immediate reference.
I humbly request you to kindly consider the same and take up our case for
the 31st Meeting of REAC scheduled on 16-18 March, 2015 and issue the
Environmental Clearance.
I will be grateful to you for this act of kindness.
Thanking you.
Yours truly,
Vipin Gupta
Encl:
1. A copy of MoEF&CC Letter dated 05.03.2015
2. Short comings reply along with necessary Annexures.
SHORT-COMING REPLY
1. Detailed report regarding likely increase in productivity of
Agricultural land after mining (as informed by the PP on the
basis of Reports of some Institutes); The Expert may also send
a Report in this regard.
Attached as Annexure-I.
2. Onsite disaster management plan with complete mitigation
measures for disaster management.
The project is for sand mining from the riverbed of river Yamuna & its
paleochnnels which posses some hazardous situations. The
identification of harzard, risk and preventive on site mitigation
measures for the proposed project is given below:
(A) Hazard Identification
The purpose of hazard identification is to identify and develop a list of
hazards that are reasonably likely to expose people to injury, illness or
disease if not effectively controlled. Workers can then be informed of
these hazards and controls put in place to protect workers prior to
them being exposed to the actual hazard.
1. Nearness of River (Flooding)
2. Collapsing of Banks of River & banks of pit
3. Quick Sand Condition
4. Accidents due to Vehicular Movements and loading &
unloading of mineral
5. Earth Quake
6. Presence of poisonous insects & snakes
(B) RISK ANALYSIS
Risk analysis is done for:
Forecasting any unwanted situation
Estimating damage potential of such situation
Decision making to control such situation
Evaluating effectiveness of control measures
1. Nearness of River (Flooding)
As the project is mine sand from the riverbed & its paleochannels
there is risk of flash floods in the riverbed area due to which the
workers at the site may get seriously injured or drowned.
2. Collapse of Banks of River & banks of pit
There is a risk of collapse of banks of riverbed & pits which will be
formed due to mineral excavation. Collapse of banks may injure the
workers/miners.
3. Quick Sand Condition
There are two things which may create the conditions to form
quicksand:
i. Underground water may seep-up and saturate the
sand, thereby reducing the friction between the
sand grains and giving the sand a liquid nature.
ii. Sand or another soil may be sifted by the force of an
earthquake so that friction is lessened and the
earth becomes unsteady.
This creates danger condition to the trucks plying near the river bed
and banks for transportation of minerals and also there will be a
chance of fall of human beings & animals in it.
4. Accidents due to Vehicular Movements and loading &
unloading of mineral
The possibilities of road accidents are due to reckless or untrained
driver or overloading of trucks or in case pathway is not compacted
suitably, etc. Also during loading and unloading of minerals
workers/miners may get injured due to river bank collapse, over
thrown boulders/pebbles or due to carelessness use of hand tools, etc.
5. Earth Quake
As the area lies in seismic zone III which indicates moderate damage risk
zone but still there is a chance of it and due to which workers/miners
may get affected.
6. Presence of poisonous insects & snakes
Snakes & other poisonous insects might be present inside the sand
which is going to be excavated and there is risk that they might bite
the workers/miners working at the site, which can be dangerous.
(C) PREVENTIVE/MITIGATIVE MEASURES
Mitigation measures plays a vital role as these are proposed so that
any hazard having its potential impact on an individual or structures
can be prevented or to combat with the disaster.
1. Nearness of River (Flooding)
During monsoon months and heavy rains the mining operations
will be ceased.
There is a mechanism/warning system of heavy rains and
discharges from the upstream dams. (A letter has been obtained
from Executive Engineer, Indri W/S Division, Karnal dated
10.02.2015 in this regard is attached as Annexure-II)
Prior information will be given to workers as per the advance
intimation received from concerned authority.
2. Collapse of Banks of River & Banks of Pit
Mining will be done in a systematic & scientific manner while making
proper benches.
In case of river bed: Mining will be leaving a safety zone of total of
1/4th of the width of the river from the banks for bank protection.
In case of paleochannels: Mining will be done leaving safety a barrier
zone of 7.5 m around the lease for off river bed blocks (paleochannels)
also it is proposed that banks of the mining area (paleochannels) will
be sloped to its angle of repose at 45o in a very gentle manner so that
there is no pit left which can pose any danger to collapse. Further, to
stabilize the slope plantation with shrubs, grasses & trees will be done
as mentioned in reference to Question no. 5.
3. Quick Sand Condition
The only way to avoid quick sand condition is by avoiding mineral
lifting below water table, which is not allowed in this case. Mining will
be done in layers rather than going for maximum depth at one time.
However, quick sand condition may occur due to natural reasons. The
following mitigation measures will be provided:
Area of “quick sand” conditions will be identified and warning
sign will be provided for the same, if observed.
Fencing will also be done around the quick sand areas, if
observed.
4. Accidents due to Vehicular Movements and loading &
unloading of mineral
All transportation within the main working shall be carried out
directly under the supervision and control of the management.
The Vehicles will be maintained/ repaired and checked
thoroughly by the competent person.
A statutory provision of constant education, training etc. will be
provided for reducing the incidents of such accidents.
Overloading will not be permitted and will be covered with
tarpaulin.
The maximum permissible speed limit will be ensured.
The truck drivers will have valid driving license.
The truck shall be brought to a lower level so that the loading
operation suits to the ergonomic condition of the workers.
The loading shall be done from one side of the truck only to
avoid over throw of materials.
The workers shall be provided with gloves and safety shoes
during loading.
5. Earth Quake
As the area lies in Seismic zone-III, following protective measure for
the same has been proposed:
Pit slopes will be stabilized by plantation as proposed in
reference to Question No. 5 which will prevent collapsing of
pit slopes during earthquake.
Evacuation plan for the workers at site including contract
labours will be developed.
“Emergency Helpline Number” will be displayed at all levels.
Mock drills regarding earthquake condition will be conducted
and arranged for the miners/workers by the concerned
department/authority, Karnal.
6. Presence of poisonous insects/snakes and other emergency
A regular tie-up with a nearby hospital (fully equipped with
doctors, medicines, anti-venoms, medical equipments etc)
will be ensured.
Ambulance will be made available at the site all the time
(during mining hours) for emergency purpose.
On Site Disaster Management Plan
In spite of the above mitigation measures disaster may happen. In
case a disaster happened, the proponent prepared an Onsite Disaster
Management Plan which is as follows:
This deals with action plan for high risk accidents like subsidence,
flood, and inundation in mines, seismic activities, etc. and emergency
plan proposed for quick evacuation, ameliorative measures to be taken
etc. The capability of lessee to meet such eventualities and the
assistance to be required from the local authorities is described.
The complete mining operation will be carried out under the
Management and control of experienced and qualified Mines
Manager having Certificate of Competency to manage the mines
granted by DGMS.
During heavy rainfall the mining activities will be closed and
workers will be evacuated.
All persons in supervisory capacity will be provided with proper
communication facilities to facilitate evacuation.
Injured person will be provided with FIRST AID facility which
will always be kept at nearby hospitals.
A person will be deputed to be in continuous touch with
District/local authority level office, for the timely dissemination
of message like releasing of water from dam (Hatnikund
Barrage), heavy rainfall etc. as received from IMD and take
precautionary action to prevent any consequential disaster.
“Disaster Warning System” as developed will be strictly
implemented in line with advance communication from
concerned authority as given in Annexure-II.
Identification of nearby hospitals with route & contact number
for emergency assistance.
Evacuation plan for the workers at site including contract
labours will be developed and they will be kept in nearby
shelters.
“Emergency Helpline Number” will be displayed at all levels.
3. Details of compensation proposed to be given to farmers as per
R&R Policy of the State Government along with pert chart
showing acquisition and returning land for cultivation after
mining activity.
The R&R plan prepared for the Project is inculcated from National
R&R Policy, 2007 as per the land holdings present in the area.
There are mainly three components in the said policy (a) Land
compensation (b) Economic rehabilitation of project affected
families and (c) Development of skills for the displaced persons.
Total area of lease is as per LoI is 941.00 ha out of which River bed
land considered for mining is 763.00 ha and Agriculture land
(Paleochannel) is 178.0 ha. To assess the losses of the project
affected people due to the mining, a survey was done and it was
found that there is no ST population as well as there are no
hutments in the lease area. Thus no compensation on account of
resettlement shall apply. Also employment to one person from each
land owner on priority basis will be given. In addition, annual
compensation Rs.1, 80, 000 per ha (for paleochannel/ agriculture
land) till the land is not returned to them and Rs.35, 000 per ha till
the end of lease period for barren land will be given to the land
owners to compensate for the loss of product. Also the top fertile
soil which has been stacked separately, will be spread on the
excavated land again to make it fertile and then will be returned to
the original land owners. Also in this regard manure will be
provided to the farmers for better agricultural practices. The
development of skills of the youth of the nearby villages will be
enhanced by providing vocational training to them through nearby
institutes. Towards this, an amount of Rs. 15 Lakh per annum has
been earmarked in the CSR including scholarship to the students
and vocational training.
4. A plan for providing potable drinking water in villages namely
Chandrown, Garhpur, Tapu, Nagal, Kamalpur, Garhi-Birbal and
other having high fluoride in water.
RO water system/ water purifiers will be installed and provided in
the villages for drinking water purpose. An affidavit regarding the
same has been attached as Annexure-III. Towards this, an amount
of Rs. 5 lakhs per annum has been allocated.
5. Proposed Plan with map for 7.5 m green belt as proposed by
the PP between mining land and adjacent Agricultural land.
A plan is proposed for green belt development in the 7.5 m barrier
zone between the mining land & adjacent agricultural land. It is
proposed that pits of the mining area will be sloped to its angle of
repose at 45o in a very gentle manner so that there is no chance of
slope collapse which can pose any danger to human being or
animals. The process of simultaneous reclamation will be
continued till the mining is over. Also plantation is proposed on the
slopes of the pit to stabilize them and which also makes the area
greener. List of species proposed to be planted is given below:
Sandy Clay Loam Binding Plants for Green Belt in Safety Zone of
Mine Lease
The green belt to be proposed on the earthen bund in 7.5 m safety
zone around the mine lease in Paleochannels of Yamuna River will be
composed of trees, shrubs and grasses. This green belt will bind the
sandy loam soil of earthen bund in safety zone and would not allow
the run off with eroded soil in mined areas. These plants are
recommended in research papers for soil conservation as well as
recommended by CPCB for the green belt. The selected plants as soil
binders over the bund in 7.5 m safety zone of mine lease is given
below:
A. Grasses
Bothriocloa intermedia
Cenchrus setigerus
Chrysopogon fulvus
Saccharum bengalense
B. Shrubs
Bouganvillea sp.
Ipomoea fistulosa
Nerium odorum
Sesbania sesban
Salix caprea
Ricinus communis
Poinciana pulcherrima
C. Trees
Acacia nilotica
Prosopis juliflora
Butea frondosa
Albizzia lebbek
Alstonia scholaris
Anthocephalus cadamba
Azadirachta indica
Cassia fistula
Cassia siamea
Lagerstroemia flosreginae
Leucaena macrophylla
Pithecolobium dulce
Also plan with a map for the same has been made and attached as
Annexure-IV.
6. Proposed Protective measures in respect of Project located in
seismic zone-III as part of Disaster management plan.
The proposed project lies in Seismic zone III which is classified as
Moderate Damage Risk Zone.
Hazard Identification: Earth Quake
Risk Analysis:
Earth Quake
As the area lies in seismic zone III which indicates moderate damage risk
zone but still there is a chance of it and due to which workers/miners
may get affected.
PREVENTIVE/MITIGATIVE MEASURES
As the area lies in Seismic zone-III, following protective measure for
the same has been proposed:
Pit slopes will be stabilized by plantation as proposed in
reference to Question No. 5 which will prevent collapsing of
pit slopes during earthquake.
Evacuation plan for the workers at site including contract
labours will be developed.
“Emergency Helpline Number” will be displayed at all levels.
Mock drills regarding earthquake condition will be conducted
and arranged for the miners/workers by the concerned
department/authority, Karnal.
************
ANNEXURES