VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 1
Introduction
VELO overview Overall planning A bit of (recent) history A look ahead
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 2
VELO overview
~1 m
module support
CO2 cooling
detector "hood"
kapton cables
Vacuum vessel repeater electronicsLHC collision point8
« RF box »
Home-made rectangular bellows
VELO exit window
Silicon modules
Wake field suppressor
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 3
VELO installation and commissioning: strategy
two parallel activities
Install detectors after bake-out (& sector test)
Global LHCb commissioning(starts nov 2006!)
Install vacuum/mechanics at IP8Vacuum continuity for LHC, bake out
Commission vacuum and positioning systems
"POINT8"
now
Assemble/commission detectors and electronics outside IP8
Test beam run, rec. s/w, alignment..."Alignment Challenge & Detector Commissioning"
"ACDC"
now
jan 2007
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 4
VELO installation and commissioning: schedule excerpt
v6.0
v6.0
install detector halves in vessel: january 2007
ACDC-1 ACDC-2a ACDC-2bVELO detector commissioning "ACDC"
all modules for detector half must be avai-lable 3 months before going to a test beam run
all modules for detector half must be avai-lable 3 months before going to a test beam run
test beam test beam 25ns
Considerable resources from other LHCb groups (such as Online and Infra-structure) is being diverted to ACDC support
Considerable resources from other LHCb groups (such as Online and Infra-structure) is being diverted to ACDC support
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 5
From EDR to PRR (1)
Module EDR report:
Answers from the VELO group:
in red boxes, text by the referees in blue boxes, text by VELO group
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 6
From EDR to PRR (2)
...
EDR referees' statements
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 7
From EDR to PRR (3)
since then, another 3 (to 4 ?) months slipping
VELO group's answer
EDR referees' statement
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 8
PRR prerequisites
VELO group's answer
EDR referees' statements
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 9
Most recent history
~dec'05 - jan'06
Because of further slipping of PRR target date, it was decided to
allow parallelizing the development of the module assembly
procedure:
– produce 4 mechanical modules up to specs (geometry)
– produce 3 electrical (two-sided) hybrids up to specs (eletrically)
– start PRR with these achievements and finish the review process with
full electrical module tests within a couple of weeks after the PRR
(follow-up meeting with referees).
This does not free us from making 3-5 full modules and having them
fully qualified (in vacuum, under bias, cooled) before starting
production.
involves some
components
wastage
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 10
Recent LHCC comprehensive review
Slides at http://indico.cern.ch/conferenceDisplay.py?confId=741
From LHCb Spokesperson's email summary:
“Concerns are expressed for the silicon detectors, i.e. IT, TT and VELO;
being late significantly. Since their module production is not reaching to the
state of real serial production yet, they find it difficult to assess whether the
claimed milestones can indeed be reached. […] They have noted the very
tight schedules for the production of VELO RF-box and Kapton cables […]. ”
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 11
Review goals of this review
Given that prerequisites for PRR are not met,
Aim at
– reviewing inventory of steps that are yet to be taken for achieving the
PRR prerequisites
– review estimates of time required for each step
– review resources allocated for these steps
– review inventory of components (with QA flags)
– agree on a plan toward PRR finalization and a framework for
continuous monitoring until PRR finalization paralell processing: discover all (yet unraveled) issues!
e.g.: finalize a complete module (even if not up to specs) and operate it in
vacuum system, with cooling and power + bias.
– in particular, agree on a list of measurements/graphs that ought to be
produced for demonstrating that PRR prerequisites are achieved
VELO Module PRR preparation meeting 28-feb-2006 Liverpool Massimiliano Ferro-Luzzi 12
Look ahead
Finalize PRR process by March 31
Achieve full production speed by week 17 (2 modules / week)– week of 24 to 28 of April
May 15: more than 5 modules mounted on Right detector half