Various Drawings for Practice

Embed Size (px)

Citation preview

  • 8/17/2019 Various Drawings for Practice

    1/13

     

    Figure 1 Plan view of mine Expanding along longer axis

    Figure 2 Plan view of mine Expanding along shorter axis

    Figure 3 Plan view of pit developed by shovel and dumper operations

  • 8/17/2019 Various Drawings for Practice

    2/13

     

    Figure 4 Plan view of a bench developed by panel with Two blocks with longitudinal cuts

    Figure 5 Plan view of a pit being mined with Transverse blocks, wide panel

    Figure 6 Plan view of a pit being mined by shovel dumper showing blocks blasted, drilled and preparing

    for drilling

  • 8/17/2019 Various Drawings for Practice

    3/13

     

    Figure 7 Schemes of Mining Line Advancement and pit development

  • 8/17/2019 Various Drawings for Practice

    4/13

     

    Figure 8 Schematic diagram of Mining of horizontal and inclined seam

    Figure 8 Schematic diagram of a trench face

    Rcr: Digging radius at the level of

    crwalers

    Rre: Rear end clearing radius

    Rdg: Digging radius

    m: clearance between rear end of

    shovel and muck pile

  • 8/17/2019 Various Drawings for Practice

    5/13

     

    Figure 9 face parameters of a BWE face.

    CL – Distance between leading edge of

    crawler and the center of rotation of the

    BWE. 

    CW – Distance between the outside edge ofa crawler and the BWE centre line of

    advance. 

    D – Digging wheel diameter measured at

    cutting lips

    D1 – Digging wheel diameter without

    buckets, at wheel rim 

    DB – Discharge boom length

    DD – Lowest elevation of the discharge

    chute

    DM – Highest elevation of the discharge

    chute

    E – Distance between the load boom pivot

    point and the center of rotation of the

    BWE

    HD – Maximum depth of cut below crawler

    level

    HM – Maximum elevation the digging

    wheel center 

    LB – Length of the load boom 

    LBW – Width of the load boom

    Y – Elevation of the load boom pivot point 

    kh & k

    d – Lowest and highest load boom

    inclination angles

    I &

    r – Horizontal wheel free angles

     

    I&

    r – Vertical wheel free angles 

    I &

    r – Maximum discharge boom slew angles

    k – Minimum angle permitted between load and

    discharge booms 

  • 8/17/2019 Various Drawings for Practice

    6/13

     

    Figure 10 BWE excavator face

    Figure 11 Configuration of one BWE excavation block

  • 8/17/2019 Various Drawings for Practice

    7/13

     

    Figure 12 Application of BWE with Conveyor bridge

    Extended Bench Method of Dragline operation 

      This method of face development is applied when effective reach of the dragline is to beextended.

      This is associated with certain degree of rehandling  This method is useful when the overburden depths can not be handled by normal casting  It may be necessary when overburden depths are gradually increasing or there is a temporary

    change in relief. 

    Figure 13a Extended bench method of dragline

    At the completion of the previous block, the dragline is located at the end of the bridge. From this

    position the last of the block of OB can be spoiled directly . To start excavation of the new block, the

    dragline is walked off the bridge and placed in line with the new high wall at ‘A’. This is now ready for

    providing key cut for the block to be excavated

  • 8/17/2019 Various Drawings for Practice

    8/13

     

    Figure 13b Extended bench method of dragline

  • 8/17/2019 Various Drawings for Practice

    9/13

     

    Figure 13c Extended bench method of dragline

  • 8/17/2019 Various Drawings for Practice

    10/13

     

    Figure 13c Extended bench method of dragline

  • 8/17/2019 Various Drawings for Practice

    11/13

     

    Figure 14 Dragline and Bucket wheel excavator combined mining

    Figure 15 Dragline and Bucket wheel excavator combined mining

  • 8/17/2019 Various Drawings for Practice

    12/13

     

    Figure 16 Block mining by BWE

  • 8/17/2019 Various Drawings for Practice

    13/13

     

    Figure 17 different possible slope failure of OB dump