VARDHMAN SPECIAL STEELS

CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP

SUBMITTED BY:

ROHIT GOTHWAL

IIT DELHI

Page 2: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

About Company

• Started Steel business in the year 1972• Manufactures Special and Alloy Steel• Net Capacity 80,400 mtpa

Page 3: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Steelmaking Process Chain

Raw Material30 Top UHP electric arc

furnace

Ladle Refining Furnace

Vacuum degassing

Bloom CasterBloom ConditioningRolling mill

(Optional) heat

treatment

(Optional) Bright bars

Testing & inspection Dispatch

Page 4: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Raw Material

• Pig iron• DRI- dead reduced iron• HMS- heavy melting scrap• SI- sponge iron• End Cutting• Skull• Scrap• Slag iron• Forging flash

Page 5: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Electric Arc Furnace (EAF)

Page 6: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

LADLE REFINING FURNACE

• Ladle refining furnaces(LRFs) are used to desulfurize steels, remove other impurities and hold the molten steel for casting operations

Page 7: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

VACCUM DEGASSING

• To remove hydrogen • To improve cleanliness by removing part of the oxygen • To produce steel of low Carbon content ( < 0.03%) • To produce steels to close • Chemical composition ranges (including deoxidizers), and • To control pouring temperatures, especially for continuous casting operations.

Page 8: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Continuous Casting Process

• Continuous casting. 1: Ladle. 2: Stopper. 3: Tundish. 4: Shroud. 5: Mold. 6: Roll support. 7: Turning zone. 8: Shroud. 9: Bath level. 10: Meniscus. 11: Withdrawal unit. 12: Billet.

A: Liquid metal. B: Solidified metal. C: Slag. D: Water-cooled copper plates. E: Refractory material.

Page 9: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• The bloom caster machine is 9/16 meters, two strands continuous machines equipped with In Mould Electro Magnetic Stirrer (EMS) from Danieli Rotelec, France to make three sizes of bloom

• 125 mm x 125 mm• 160 mm x 160 mm• 200 mm x 200 mmIt has fully protected metal stream while casting from ladle to tundish followed by closed using submerged entry nozzle from tundish to mould. It is equipped with automatic mould level indicator and has fully automated- PLC controlled casting.

Page 10: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Steel Manufacturing Process

Page 11: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

BRIGHT BAR SHOP

• VSSL is having in house peeling facility of 15000 MT/month of bright bar material production per month. The peeled bars are used in critical applications and are being supplied to customers like sriram pistons.Sona okewgawa, India Piston and Federal mogul to name a few in various size range from 19.5 dia to 58mm diameter

• Facility includes at Bright Bar Shop• Straightening- Used for the straightening of black bar. Maximum

acceptable straightness is 1mm/mtr .More the straightness will give the peeling effective

Page 12: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• PEELING:-It is the process of removing of upper layer of black bar containing surface defects and thereby achieving required dimensional accuracy (lobbing)

Page 13: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• Reeling• This is the process i.e done after peeling to smoothen the surface

more. It further removes the excess metal over the finished surface

• Centerless grinding is a machining process that uses abrasive cutting to remove material from a workpiece

Page 14: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

BRIGHT BAR SHOP OEE CALCULATION FOR BAR PEELING MACHINE 1 TO MAXIMIZE PRODUCTIVITY

Page 15: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

OEE( Overall Equipment Effectiveness)• Hierarchy of metrics developed in the 1960s to evaluate how

effectively a manufacturing operation is utilized.

• Commonly used as a key performance indicator (KPI) in conjunction with lean manufacturing efforts to provide an indicator of success.

• Is best used to identify scope for process performance improvement, and how to get the improvement.

Page 16: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

SIX BIG LOSSES

• DowntimeDowntime refers to time when the machine should be running, but it stands still. • Equipment FailureSudden and unexpected equipment failures, or breakdowns.• Setup and adjustmentsThis downtime loss often includes substantial time spent making adjustments until the machine gives acceptable quality on the new part.

Page 17: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• Speed LossesA speed loss means that the equipment is running, but it is not running at its maximum designed speed.• Idling and minor stoppagesIdling and stoppages in this case are caused not by technical failures, but by small problems such as parts that block sensors. • Defects LossesA defect loss means that the equipment is producing products that do not fully meet the specified quality characteristics.

Page 18: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

ELEMENTS OF OEE

Page 19: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• AvailabilityIs the equipment portion up time i.e. when equipment is up and available for use.• Operating EfficiencyReflect idle time portion of uptime• Rate efficiency Ratio of unit's actual output to theoretical output. Losses in rate efficiency result form equipment running slow.• Rate of qualityPortion of output that is good.

• OEE= Availability* operating efficiency* rate efficiency* rate of quality

Page 20: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• Availability

Up time / (Up time + Down time)

=(Operating time + Idle time) / (Operating time + Idle time + Down time)

• Operating efficiency

= Operating time / Up time

• Rate Efficiency

= (Actual Production) / (Max Possible Production)

• Rate of Quality

= Good pieces / Total pieces processed

= Good pieces / (Good + bad pieces )

Page 21: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Calculation of OEE for month of May and JuneBreakdown for Peeling 1 for month of May

Total hours

No material

Size Change

Size setting

Cutter head Setting

Bush Change

Tool change

Tool point change

Polishing roll change

Electrical Mechanical Other

Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs.

720:00 6:20 26:12 21:10 14:25 2:40 5:50 21:50 8:20 3:55 21:10 12:5

0.87% 3.6% 2.9% 2% 0.37% 0.8% 3.03% 1.11% 0.54 2.93% 1.67%

Page 22: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Break down Peeling machine 1 for month of June

Total hours

No material

Size Change

Size setting

Cutter head Setting

Bush Change

Tool change

Tool point change

Polishing roll change

Electrical Mechanical

Other

Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs. Hrs.

720:00 3:45 22:45 16:55 10:25 4:40 3:45 6:50 2:15 8:50 15:25 19:30

0.50% 3.15% 2.34% 1.45% 0.64% 0.52% 1.78/% 2:15% 1.22% 2.141% 2.70%

Page 23: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• Availability= 40970/ 43200 = 0.948

• Operating efficiency = 0.844

• Rate efficiency = 0.831

• Rate of quality = 0.975

• OEE = 0.948* 0.844* 0.831* 0.975= 0.648

Page 24: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

What to expect??

Based on results by Total Productive Maintenance (TPM) Prize winning companies.

• Availability > 90%

• Performance > 95%

• Quality > 99%

• OEE = A X P X Q = 90% X 95% X 99% = 85%

Page 25: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• An OEE of 85% is considered to be World Class Manufacturing (WCM) for the TPM prize winners.

• The table below shows top-level OEE and Total OEE values from different types of industries

Industry OEE Top Level OEE Total

Manufacturing 85% 60%

Process >90% >68%

Metallurgy 75% 55%

Page 26: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Compare with Prize Winning Companies

VSSL Prize winning Companies

Availability 94% >90%

Performance ~84% >95%

Quality 97.5% >99%

Page 27: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Scope Of Improvement

• Tool Setting• Tool Change• Size Change• Avoid mechanical breakdown.

Lot of time is lost in doing above practises.

Page 28: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

How to Reduce time loss??

• Modern tool and powered tool

New modern and powered hand tools are available in market, easy to use, portable and intense flexible.

To achieve World class manufacturing we need to upgrade to new powered tools and train workers to how to use them effectively

Page 29: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

F1 Pit Crew change tyres in just 2.05s

• Impact wrench• Hydraulic jacks• Extension poles

Strategy used:

Get everything ready and use best tools

Page 30: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

What we are using??

• Allen keys• Spanners• Long extensions• Screw drivers

Page 31: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Upgrade to these tools

• Ratchet key sets • Powered screw driver Power Allen key

Page 32: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Bar Peeling Insert

• Tool breakage and tool wear is the major factor in down time of the machine.

Carbide Turning Insert, 7 Degrees,Round, Style RCMX, Insert Size 25 07 00, Grade 4225, Application Medium,Work piece Material Steel, Inscribed Circle 0.984 In, Insert Thickness 0.313 In, Nose Radius 0.492 In, Coating MTCVD, Cutting Direction Neutral, Mounting Style Top and Hole Clamping, Rake Positive, No. of Edges 4, ISO Number RCMX 25 07 00 4225, ANSI Number RCMX 25 07 00 4225.

Page 33: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• The insert is carbide coated and it has got eight cutting points, each cutting point is used till it is completely worn out, this led to increase of temperature between insert tip and bar which led to insert break and failure sometime, this led to complete loss of tool.

Page 34: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

New Inserts

• Wiper Inserts• Sandvik TNMX insert• S-WNGX Inserts• PVD Coated inserts• TD/TRD Coated inserts

Page 35: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Wiper Technology Benefits

• Improve production performance where the key is to being able to raise the feed rate

• Better Surface finish- 15 Ra• Faster and more cost effectiveness• Eliminate centerless grinding • Elimination of time requirement to centerless grinding• Material handling associated with straightening and CG operation.• Elimination of possibility of having alpha case on bar surface because

of excessive heat generated during CG.

Page 36: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Company benefited by wiper technology

Precision Rolled Product Inc. (PRP), a company of Krupp VDM Gmbh.Company realized a 70% improvement in surface finish quality for bars peeled with wiper inserts.

This change has enabled PRP to eliminate centerless grinding for significant portion of company’s bar production, saving time, Labour and materials.

According to Brian Sego, Production manager, with wiper technology we have significantly increased production of peeled bars.

Page 37: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

PVD Coated Inserts

• More wear resistant.• Withstand high temperature and high forces.• Deposit a thin hard, dense protective layer at about half temperature

of conventional hot TD and CVD coating process.• Improved tool life.• Increase in dimensional accuracy

Page 38: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Company benefited by PVD coating processOmni Mfg. Inc. St. Marys, OH, Omni relies on coating to improve performance of certain inserts.

CVD Tic coating 139,000 hitsPVD coating 199,000 hits

Outperformed CVD coating by 43%

Page 39: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

WEAR CONTROL

Page 40: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

What else we can do?

It is necessary to change the tool point at the right time to avoid tool breakage and complete wear.• If an insert breaks entire cartridge is ruined.• Even all eight points on cartridge are of no use then• High forces which occur after the insert breaks cause peeling head to

start turning the bar instead of peeling.• Before inserts break the pressure rises and machine require more

power.• It can also damage the current bar

Page 41: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Tool Wear vs. Time

Page 42: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Tool Life

• Tool wear is a time dependent process. As cutting proceeds, the amount of tool wear increases gradually.

• Tool wear must not be allowed to go beyond a certain limit in order to avoid tool failure.

• Tool life is defined as the time interval for which tool works satisfactorily between two successive grinding or resharpening of the tool.

Page 43: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Taylor Tool Life Equation

VT^n = C

• where v = cutting speed, m/min; T = tool life, min; and • n and C are parameters that depend on feed, depth of cut, work

material, and tooling material, but mostly on material (work and tool).

Page 44: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Typical Values of n and C Tool material n C (m/min) High speed steel: Non-steel work 0.125 120 Steel work 0.125 70 Carbide Non-steel work 0.25 900 Steel work 0.25 500 Ceramic Steel work 0.6 3000

Page 45: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Cutting Fluids

What we are using:Tectyl Cool 1181

New coolants:Tectyl cool 1273

We are using most commonly used industrial coolant.

Page 46: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Industries in 1980’s

During 1980’s quality improvement became important with improved sales and profit performance.

Page 47: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Current Situation

• Now a days industries have been showing great commitment to customers.

• Manufacturing skills are no longer key asset, customer service level has been recognized as strategic value.

• Keep customer happy.

Page 48: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Key area of Service level improvementPerformance of supply chain is measured through two key performance indicators when it comes to customer deliveries.• FFCOFR(First fully confirmed order fulfilment rate): Related to delivery

ability. It measure whether industry can promise customer that his order will be fulfilled given his requirement.

• OTIF( On time in full): Measures how reliable industry is in delivering the customer the given quantity on time.

Page 49: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

What is OTIF?

 

"Getting the right stuff to the right place at the right time, in the right location on the jobsite, in the right condition with the right invoice–all day, every day."

Page 50: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

ON TIME:

• On-time is defined as delivering the order to the customer when you promised.

• The measurement is the commitment the organization made, not necessarily the time the customer requested

Page 51: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

IN FULL:

• In-full measures order accuracy. It counts as in-full when everything ordered is delivered with no errors, backorders, or substitutions.

Page 52: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Calculation of OTIF:

Requirements for the OTIF measurement are:

• Have a delivery date (even hour for some organizations) on the customer order.

• Measure the date or the hour of delivery and archive it in the system• Maintain record of the reasons why an order was not OTIF.

Page 53: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

March OTIF:Late cases NO.s %

More than 60 days 80 12

31-60 119 18

16-30 138 21

8-15 70 11

1-7 91 14

On time 147 23

Page 54: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Reasons of failure:

• Wrong TDD.• Revised TDD updating in ERP not being done. • Over booking than plant capacity.• Dispatch against wrong COPS.• Sales budget should be in line with the booking if needed should be

revised and informed to PPC.

Page 55: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Root Causes:

• URGENCY and URGENCYLast moment addition of order disturbs the whole cycle.Moreover addition of smaller diameter order as urgency results in much delay of other order.• More time to roll small diameter bars.• Setup time: time lost in changing of rollers

Page 56: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Other reasons:

Internal• Overbooking: customers are committed for the orders which can

never be made.• No proper communication between marketing department and PPC

department.• Revised dates are not entered into ERP.

Page 57: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Hidden cause:

Steel Stacking: A problem in inventory management in the steel industry A key logistics problem between the continuous casting stage and the hot rolling mill in the steel industry.

Continuous

Caster (CC)

Slab

Slab Yard

Reheat

Furnace

Hot Rolling Area

Hot Rolling

Hot Strip

Mill

Page 58: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

• Commonly, the problem of such storage areas is that the next billet needed for the next production step is often not the one on the top of the respective stack.

• Therefore, a resorting has to be performed in order to access the desired billet.

Page 59: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

OK - let's look at the common mistakes

Page 60: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Mistake #1 - Overloading the BusinessThe best way to improve your on-time delivery performance is to stop setting yourself up for failure in the first place. Simply put, don't take on more than you can actually do.

The Solution Manage your capacity more adeptly when you are considering accepting new orders.

Page 61: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Mistake #2 – Not Using a ‘Contract ReviewThe Problem If we get the wrong decisions made at the start of the order then completing the delivery / project / service can become difficult, and expensive, near the end.

The Solution Ensure that your planning is done at the start of an order entering your business and not at the end just before despatch.

Page 62: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Mistake #3 – Poor Handovers Mid-ProcessThe Problem When we don’t consider how each part of our process passes its product (information or physical) to the next stage of the process problems can occur.

Actions Map your process and identify the transitions (the handovers).

Page 63: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Mistake #4 – Inadequate Performance MeasuresThe Problem If a business is using Key Performance Indicators (KPIs) there is a good chance that they will be using ‘output’ KPIs.

The Solution Similar to the dashboard of a car, you can create a small suite of KPIs that tell you how your process is doing, alongside keeping an eye on the outputs. Like OTIF, OEE etc

Page 64: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Mistake #5 – The Perils of ‘Dirty Data’ I visit businesses that have a main system that they use to manage their business (such as an ERP or MRP II systems). The data that is left in the main system is often incomplete and inaccurate, often referred to as ‘dirty data’. The Problem This leads to poor information that cannot be relied upon.ActionsPeriodically audit the system to make sure it is being adhered to.

Page 65: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Mistake #6 – Poor Inter-Team Communication“Get your team together, re-focus, and get the day started off right. The weeks and months will follow suit!”

Even in small teams it is easy to become silos of one person.

Page 66: VARDHMAN SPECIAL STEELS CUSTOMER SERVICE LEVEL IMPROVEMENT & MANUFACTURING PROCESS IMPROVEMENT IN BBS SHOP SUBMITTED BY: ROHIT GOTHWAL IIT DELHI

Now it’s Your Turn...

I hope that these six mistakes can be avoided by your business, and by implementing some of these ideas you will see an improvement in your on time delivery performance.