Upload
dinhkhanh
View
223
Download
0
Embed Size (px)
Citation preview
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Vacuum design of the
Double-Double Bend Achromat (DDBA) modification to the Diamond Storage
Ring
Matthew Cox Head of Vacuum Group
Diamond Light Source, UK
[email protected] www.diamond.ac.uk
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Motivation
Diamond DDBA Vacuum / Matthew Cox 2
Need for additional insertion devices ® Double Double Bend Achromat (DDBA) concept: Replace one or two “DBA” cells with a new “DDBA cell” creating a new mid-cell straight section for an Insertion Device, thus converting a BM beamline into an ID beamline.
Insertion device
BM beamline
ID beamline
+ Development of technology needed for a possible future major upgrade, Diamond-II
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Timescales
Diamond DDBA Vacuum / Matthew Cox 3
The plan:
Install one cell of DDBA in late Summer 2016 in an 8-week shutdown Plus a possible second cell in 2018 which implies:
Completing reference designs and issuing Vacuum Vessel Calls for Tender in June 2014. We believe this is challenging but achievable
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Vacuum requirements
Diamond DDBA Vacuum / Matthew Cox
• CO equivalent p ≤ 10-9 mbar with stored beam
• Beam compatible: Impedance, Beam stay clear, RF heating, DC/AC magnets, SR heat loads ...
• No pressure bursts or particles to trip beam
• Installation in a working machine + beam conditioning £ 8 weeks downtime
4
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Decisions taken
Diamond DDBA Vacuum / Matthew Cox
• Narrow bore vacuum vessels (typically 18 x 27 ellipse) and dense magnetic lattice – Combination of distributed and lumped photon absorbers – Pumping by discrete ion pumps and NEG cartridge pumps – No NEG-coated vessels
• Initially planning full NEG coating approach (best vacuum performance) • Redesign without NEG coating (cost, timescales, R&D effort , risk ... )
• Vacuum vessels – WORK IN PROGRESS DESIGNS – Copper alloy - high power densities – Stainless steel – lower power densities, corrector magnets, bellows, BPM
units – Prototype elliptical tubes in SS-316L and Cu-OFS already delivered
• Complete replacement girders built up and baked outside the storage ring and installed without venting
• Possibility of in-situ bakeout with magnet tops removed for recovery
5
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Existing (DBA) Arc Layout
Diamond DDBA Vacuum / Matthew Cox 6
Total length of arc 17.35 m (24 off) 16 ion pumps 2 TSP 2 NEG cartridge Mainly stainless steel 316LN 4 IMGs 2 RGAs
3 girders
2 RF intergirder bellows
2 RF sector gate valves
+ BPMs, absorbers etc
Beam direction
Straight section 18 x 5.3m 6 x 8.3m
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
New DDBA Arc Layout
Diamond DDBA Vacuum / Matthew Cox 7
2.486m between flanges for standard in-vac ID with ion pumps and NEG cartridge pumps 6.5m girder
carries half a cell
2 new RF gate valves
Existing RF gate valve
Crotch 3 and 4 ion pumps
Crotch 1 ion pump
Existing RF gate valve
Dipole/crotch 2
only NEG cartridge – lack of space + 7 NEG cartridge pumps
Pressure gauges and RGAs
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Calc pressure profile 100Ah no NEG coating
Diamond DDBA Vacuum / Matthew Cox 8
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Calc pressure profile 1000Ah no NEG coating
Diamond DDBA Vacuum / Matthew Cox 9
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Calc beam conditioning no NEG coating
Diamond DDBA Vacuum / Matthew Cox
Ibeam = 300mA 10
1000Ah
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Calc beam conditioning NEG coating
Diamond DDBA Vacuum / Matthew Cox
Ibeam = 300mA
5Ah
11
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Dipole vessels (WIP)
Diamond DDBA Vacuum / Matthew Cox 12
Dipole 2 – constant x-section - distributed SR - no crotch absorber – cooled copper vessel
Dipole 1,3,4 – widens to allow SR (ID + BM) to exit
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Crotch 1,3,4 area (WIP)
Diamond DDBA Vacuum / Matthew Cox 13
Work in progress: • SR ray tracing • FEA thermal and
stress • Photon
Stimulated Desorption
• Vacuum pumping (ion pump)
e-beam channel
x- rays (ID + BM)
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
NEG cartridge interface (WIP)
Diamond DDBA Vacuum / Matthew Cox 14
NEG cartridge pumping port Compromise between vacuum pumping and beam impedance 8 pumping slots 3 mm wide x 33.5 mm long
Cu-OFS elliptical tube 27 x 18 internal x 1 mm WT
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
RF Bellows (WIP)
Diamond DDBA Vacuum / Matthew Cox 15
Similar to existing designs at Diamond – LURE/SLS concept
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
BPM buttons (WIP)
Diamond DDBA Vacuum / Matthew Cox 16
Gap around button Gap between Case and hole
Gap between button and hole
Existing 10.7mm button 6mm button in discussion with ESRF
Improved design to reduce RF heating
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
RF Compatible Flanges (WIP)
Diamond DDBA Vacuum / Matthew Cox 17
Requirements Zero RF gap Accurate lateral alignment Reliable seal Tolerant to thermal cycling
Considered a number of designs Three being tested:
• CF flange with spigot • Helicoflex “Standard” • Helicoflex “Delta”
Difficult to get zero gap with DN63CF Good experience so far with the Helicoflex Standard seal and this is currently the most likely approach
Helicoflex DN63
DN63CF DN40CF
Test setup
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
In-situ bakeout in magnet bottoms
Diamond DDBA Vacuum / Matthew Cox 18
Requirements 200°C minimum Temperature uniformity ±20°C Compatible with small gap to magnet bottoms Temporary or permanently fitted
Permanent needs to be radiation resistant Temporary must be easy to fit and remove in confined space
Considering a number of approaches:
Commercial thin film Kapton heaters (clamped, wound or glued) CERN wrapping technology Coaxial sheath heaters Insulation / no insulation Low emissivity overlayer Radiation shield, e.g. Metallised Kapton
DDBA Review Meeting, Nov 25-26 2013 OLAV-4, Taiwan, Apr 2014
Build and installation strategy
Diamond DDBA Vacuum / Matthew Cox
• Fully tested and qualified vessels (250°C bakeout) delivered from supplier(s)
• Magnets aligned on girders and magnet tops removed
• Vessels assembled on to girders and magnet bottoms with vacuum equipment
• On-girder pump down, bakeout
• Installation in the storage ring tunnel under vacuum without venting
• Connect up to adjacent vacuum sections and front end (re-bake these if necessary)
• Open gate valves, inject beam and carry out beam vacuum conditioning
19