Project –Vacation House - 3 stories Build and Design 2008-2009

Vacation House_Polythea

Embed Size (px)

Citation preview

Project –Vacation House - 3 stories Build and Design

2008-2009

Consultants and Supervisor Engineers

Design and construction Management

Angelos Papavasileiou

Civil-Structural-Architectural Engineer

Angelos Papavasileiou Surveying and Geoinformatics Engineer

Georgios Iliopoulos Geologist Engineer

Euaggelos Mermigas Mechanical Engineer

Orestis Basileios Electrical Engineer

Vlachavas Dimitrios

Project InformationLocation: Greece, Thessaly, Trikala, Pirra

Building Information3 Stories –Vacation House

0 Floor Level Flat 1 1 Upper Floor Flat 2 2 Upper Floor Semi Detached Flat 3 Roof Level Semi Detached Flat

138,70 m2 per Floor

476,10 m2 all levels

Budget 1.045.000 Euros

Technical Challenges

High falling gradient field

No access road

Unstable climate/weather conditions

Headwaters control

Rain water control

Rock falls in Construction site

Slow moving underground clay layers

Low Tension of ground σ=0,11MPa and Soil elastic modulus K=400 KPa/cm

Long distance of concrete construction site more than 60 Kilometres

Construction Management challenges

Long distance of Supplies contractors of the construction materials .

High material transfer cost.

4 months stop in the winder period.

Health and Safety challenges

Long distance from Hospital in the accident conditions .

High falling gradient field.

Quick daily change of the weather conditions.

Phase 0 - Before

Phase 1 - Excavation

Retaining Walls

Gravity Retaining Walls

Access Road

Phase 2 – Foundations

Phase 2 – Foundations

Phase 3 – Frame

Phase - Final stage

Design