v5 7746JAP Facade

Embed Size (px)

Citation preview

  • 8/14/2019 v5 7746JAP Facade

    1/4

    Winter 2004/2005

    Although topical in consequence of the Latham-inspired initiatives and

    increasingly recognised as being a merited solution to the challenge of providing

    optimum value, off-site prefabrication is not a new concept. Architecturalprecast concrete panels have been produced off-site for many decades and are

    increasingly being specified to clad a wide range of new buildings including commercial and

    civic office schemes, residential, retail and leisure developments as well as hospitals and

    schools. Despite this trend, there are many building projects that fail to benefit because

    the advantages of precast cladding construction are not fully considered early enough.

    Off-site prefabricationChairman of the ACA, Stephen Maddalena considers the

    advantages of precast cladding

    The direct and incidental advantages of

    precast cladding construction are many and

    varied. Importantly, they valuably contribute

    to enhancing quality and safety, to improving

    efficiency and productivity and to providing

    programme and price certainty.

    Designed by Chantrey Davis

    and Shepherd Design

    and built by Shepherd

    Construction, the Discovery

    Dock development in Canary Wharf, is

    predominantly clad in reconstructed stone

    panels supplied and erected by Techrete

    (UK) Ltd.

    The largely residential development,comprises three blocks; 14 storey, 16 storey

    and the 25 storey tower. The panels are in

    the main double-punched window units,

    and were delivered to the site, following

    the installation of the windows at Techretes

    factory by Parry Bowen, the curtain wall

    subcontractor. Typically 6m x 3m and

    weighing up to 9 tonnes the panels were

    produced with cut-outs to accommodate

    the cantilever support beams for the steel

    balconies.

    Although there was very good panelrepetition, it was necessary to manufacture

    several challenging shapes, which in some

    cases resulted in the adoption of a two-stage

    casting process.

    With such expansive areas of cladding

    it was important to minimise panel-

    to-panel colour variation and a new

    mix was developed by Techrete to

    provide as much colour stability as can

    be achieved, using natural materials

    The panels were fixed to the

    reinforced concrete frame, where

    the load was transmitted via integralcorbels on the rear of the panels

    adjacent to the columns.

    The restraint fixing was via channels

    typically cast into the underside of

    the post-tensioned floor slab, where

    accurate positioning of cast-in fixings

    has a substantial bearing on the

    economic and smooth running of

    the cladding system. Insulation and

    horizontal fire stopping was also

    included within the precast concrete

    cladding package.

    Rising high at Discovery Dock

    continued on page 2

    continued on page 3

    Design matters

    Innovation in production methods and

    significant investment in labour and plant

    resources enable architectural precast

    concrete panels to be provided in an

    increasing range of finishes and facings,

    shapes and sizes to suit the requirements of

    individual projects.

    Finishes and facings

    A comprehensive range of cladding finishes

    is available ranging from lightly textured

    reconstructed stone and polished concrete

    finishes to coarser washed exposed aggregate

    surfaces. Aggregates and cements can be

    selected to suit colour preferences. Precasting

  • 8/14/2019 v5 7746JAP Facade

    2/4

    effectively allows the pre-assembly of natural

    stone, granite, brick and terracotta tile facings

    with a reinforced concrete backing, a single

    panel perhaps incorporating 100+ facing

    stones or 1000+ bricks.

    Natural stones and granites are usedmore economically than with traditional

    construction methods as they can be

    produced in thinner sections. Panels may

    include a mix of finishes and facings that

    would otherwise demand separate trades.

    Shapes and sizes

    Fresh concrete is an extremely mouldable

    material allowing complex shapes to be

    formed. Panels can economically incorporate

    cill, coping, soffit, window reveal and special

    sections, especially where repetitive. Large

    panels avoid the need for secondary structurefor their vertical support and lateral restraint.

    Grid-width units can reduce mid-span

    loadings onto the structural slab edge.

    Panel sizes are usually limited by site craneage

    or transport constraints. Limitations may be

    overcome by using low-loader trailers that

    allow storey-height panels to be delivered

    vertically. Reduced wall thicknesses with

    precast cladding panels can increase net

    lettable floor area.

    Techrete, a leading manufacturer

    of architectural precast

    concrete in Ireland and the

    UK, has invested 5 million

    in an extension to its UK works at Brigg,

    making it one of the most modern factories

    in Europe. This reflects the companys

    increasing volume of business in the UK.

    Plant director John Stothard commented,

    This expansion will create more space for

    conventional production, as well as housing

    a new robotic plant to streamline the

    production of architectural concrete.

    A key feature will be a carousel system in which

    steel moulds will travel to the operative rather

    than visa versa. The aim is that all curing andfinishing will be contained within the building,

    thus creating a better working environment

    and a controlled curing regime for the panels.

    According to Stothard, The advantages

    are that each product will be finished in a

    controlled environment regardless of the

    season and external areas will only be used

    for storage of completed units. Achieving this

    is quite a challenge as much of the equipment

    is bespoke and must be adapted for the

    special needs of architectural concrete.

    The new building and offices are constructed of

    Techretes precast concrete sandwich panels,

    which provide a complete wall solution.

    TECHRETE INVESTS IN UK PLANT

    Off-site prefabricationcontinued from page 1

    Quality matters

    Panels are produced by skilled

    craftsmen, motivated by long-

    term employment prospects, in a

    purpose-built factory environment

    using specialist equipment. Each

    stage of manufacture is subject

    to inspection in accordance with

    an independently certified quality

    system, and finish and dimensionalaccuracy are checked before

    delivery.

    Sustainability matters

    Precast panel construction produces negligible

    waste, just enough concrete being batched

    to fill available moulds. And at the end of the

    economic life of a building, the precast panels

    may be refurbished for re-use or crushed for

    recycling.

    Functional matters

    Precast concrete cladding produced inaccordance with BS 8297:2000 has a life

    expectancy of 60+ years and is generally

    maintenance-free. Dense concrete is air-

    and water-tight, giving superior weathering

    performance and corrosion resistance. Joints

    between panels are usually filled with sealant.

    The thermal mass of concrete serves to reduce

    peak heating and cooling loads. Insulation can

    readily be incorporated either as a lining to the

    internal face of a panel or as a core between

    two concrete layers, achieving U-

    value requirements of 0.35W/m2

    Kand better. In addition, concrete is

    an inherent sound insulator, non-

    combustible and fire-resistant.

    Construction matters

    Precast cladding panels are erected

    on site by specialist teams trained

    in safe handling and fixing, typically

    without the need for an external

    scaffold. Panels are delivered on

    a just-in-time basis, allowing large

    areas of the frame to be rapidly enclosed

    to give an early start to weather-sensitive

    following trades. Window apertures within

    the panels can be framed, glazed and sealed

    before delivery.

    In addition to issues of quality and practicality,

    each of the above points correspondingly

    contributes financial advantages. Off-

    site prefabrication and increased on-siteproductivity, especially using the largest units

    that are practical to deliver and handle at site,

    facilitate optimum value. Similarly, decreasing

    the dependence on site-based activities

    helps stabilise the total construction cost and

    shortens construction periods, at the same

    time reducing financing costs. However, it

    should be recognised that all these advantages

    can only be attained by early involvement of

    the specialist precaster.

  • 8/14/2019 v5 7746JAP Facade

    3/4

    Rising high at Discovery Dockcontinued from page 1

    Trent Concrete recently

    completed its 2.3m

    cladding contract at Belgrave

    House, a high-profile office

    development at the rear of Victoria Station

    on Buckingham Palace Road in London.

    The contract was awarded following a

    two-stage tender process, with Trents

    previous successful cladding work with

    contractors Sir Robert McAlpine (on the

    new Bull Ring development in Birmingham)

    proving influential.

    Trent designed, manufactured and erected

    350 units in total. In the main these were

    two-storey mullions, 7.5m high, with a facing

    of deeply profiled natural Portland stone, and

    8.5m long spandrels with projecting Portland

    stone sills. Trent was also responsible for

    600m2 of handset in-situ Portland stone

    cladding. In addition, 1000m2 of matching

    reconstructed stone cladding for the servicecore and plant room were produced.

    This combined natural and reconstructed

    stone approach provides a high-quality, cost-

    effective solution. Natural stone is used on

    the main elevations, whilst reconstructed

    stone is used elsewhere and provides an

    extremely good imitation of the natural stone

    in both colour and texture.

    Combined natural and reconstructed Portlandstone for Belgrave House facade

    Erection of the 880 or so panels was completed

    in approximately seven months, with a month

    or so overlap as the double mastic pointing was

    applied by a youthful but very professional team

    of abseilers. Serious consideration has to be

    given to wind conditions at Canary Wharf, when

    formulating a programme for this type of system;

    crane down-time of 40% is not uncommon.

    A further challenge to be addressed was

    negotiating the cantilever formwork at rooflevels, this was achieved by using a C hook

    which circumnavigated the obstruction and

    resulted in a smoother operation than had been

    envisaged.

    Award for TrentThe Experian Data Centre in Nottingham

    is the winner of the Building category

    in this years Concrete Society Awards

    held at the London Marriott Hotel on

    4 November. The judges commented

    Viewed from the front, the building is

    striking: indeed its innovation is in the

    appearance. Low rise, precast, pigmented

    concrete units have been differentially

    etched and are of various lengths to

    provide a bomb-resistant screen with

    unspectacular but effective windows. The

    building is unobtrusive and entirely in

    harmony with the surroundings.

    Architect for the project was Sheppard

    Robson, main contractor Bowmer &

    Kirkland Ltd and the precaster Trent

    Concrete Ltd.

    The project also benefited from maximising

    the use of precast and specification of alarge-panel scheme. This enabled rapid

    construction and the early enclosure of a

    weatherproof envelope, allowing follow-on

    trades to start sooner.

    Client: Belgrave House Development Ltd &

    JER Victoria Ltd

    Contractor: Sir Robert McAlpine Ltd

    Architect: Squire and Partners

    Engineer: Whitby Bird and Partners

  • 8/14/2019 v5 7746JAP Facade

    4/4

    Arup Associates design of this

    new office block for British

    Land incorporates an innovative

    solution to the construction of

    its facade, albeit founded on the traditional

    principle of a load-bearing structure.

    The facade includes storey-height panels of

    Bavarian limestone and reconstructed stone

    finished precast concrete spandrel units, both

    acting as structural elements.

    The natural stone panels, which serve as

    the perimeter columns, were provided by

    Stone Cladding International. Each column

    was constructed as a set of five solid blocks of

    stone that were pre-tensioned with steel tie-

    bars to prevent their splaying under load.

    The precast concrete spandrel units at each floor level provide the connection between

    the stone panels and the steel beams that tie

    the facade back to the main structure. The

    precast spandrels were manufactured and

    delivered by The Marble Mosaic Co Ltd,

    typically as 6m-long units. The concrete

    mix and surface finish specifications for their

    manufacture were developed to match

    An Innovative Solution

    Architectural Cladding Association 60 Charles Street, Leicester LE1 1FB.

    Tel: 0116 253 6161 Fax: 0116 251 4568 Website: www.britishprecast.org/aca

    A product association of British Precast

    Member CompaniesDecomo UK Ltd, 180-186 Kings Cross Road, London, WC1X 9DE. Tel: 0207 689 8058. Contact: Paul Desmet.

    Redland Precast Concrete Products Ltd, 15/F Kai Seng Commercial Centre, 4-6 Han Kow Road, Tsimshatsui, Kowloon, Hong Kong.

    Tel: 00852 2590 0328. Contact: Trevor Gregory.

    Techrete (UK) Ltd, Warren Court, Feldspar Close, Warren Park Way, Enderby, Leics, LE4 5SD. Tel: 0116 275 0785. Contact: David Kennell.

    The Marble Mosaic Company Ltd, Winterstoke Road, Weston-super-Mare, BS23 3YE. Tel: 01934 419941. Contact: Stephen Maddalena.

    Trent Concrete Ltd, Colwick, Nottingham, NG4 2BG. Tel: 0115 987 9747. Contact: David Walker.

    the appearance of the natural stone. Each

    spandrel unit required a number of stainless

    steel boxes to be cast-in with exceptional

    accuracy to suit the irregular locations of the

    fixing positions on both the stone panel and

    steel beam.

    The stone panels and precast spandrels were

    erected by William Hare for Bovis Lend Lease.

    With over twenty years experience of providing

    architectural concrete solutions on the Continent,

    Belgium based Decomo, entered the UK market

    in 1998.

    With such prestigious projects as the European Parliament Building in

    Strasbourg and the Hilton Hotel in Paris to its credit, it was not long

    before the companys expertise and flair became recognised by many

    leading UK architects and contractors.

    An impressive portfolio of completed projects, this side of the Channel,

    built up over the last six years, is something Decomo UK Ltd is now

    rightly proud of. Amongst these are the Guinness Headquarters in

    London, the Fenwick Store in Canterbury and the Royal Academy of

    Music in London.

    Currently, three major projects are being undertaken, at Wembley

    Park Station, Chesham House and the University College, London.

    Offering complete design, supply and installation packages, the

    companys ethos is based on providing client satisfaction and it is

    always striving to give that little bit extra in order to enhance both its

    product and service.

    This is evident, not only in the extensive range of finishes and colours

    available, but also from the substantial investments made in production

    facilities, equipment and people.

    This year, alone, a new finishing building, covering an additional

    3500m2 has been opened in Mouscron, Belgium, where all productionis undertaken. A new office building and showroom is also planned for

    construction next year.

    In the UK, offices have recently been opened in London, where Paul

    Desmet has been joined by Andrew Tyrrell, formerly with Histon

    Concrete Products Ltd, to provide closer client support as the

    company realises its targets for continued growth in a market which it

    believes holds much potential.

    Welcome to new member