19
Uwe Riechert 10/04/2012 IEEE PES Switchgear Committee, 2012 Fall Meeting 1 © ABB Group September 28, 2012 | Slide 1 Very Fast Transient Overvoltages (VFTO) in Gas-Insulated EHV & UHV Substations Tutorial of CIGRÉ Working Group A3.22 / A3.28 Technical Requirements for UHV and EHV Substation Equipment Uwe Riechert, ABB Switzerland Ltd, High Voltage Products, 2012-10-04 IEEE PES Switchgear Committee, 2012 Fall Meeting September 30 – October 4, 2012 Catamaran Resort Hotel, San Diego, CA, USA © ABB Group September 28, 2012 | Slide 2 Contents VFTO Rise time Amplitude Simulation Simulation methods Verification Insulation Co-ordination Approach Trapped charge voltages Damping measures Summary Conclusions

Uwe Riechert, ABB Switzerland Ltd, High Voltage Products ... · PDF fileEntire process Detailed Calculation of GIS Insulation coordination Amplitude Rise Time Accuracy > 95% Considaration

  • Upload
    doantu

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 1

© ABB Group September 28, 2012 | Slide 1

Very Fast Transient Overvoltages (VFTO) inGas-Insulated EHV & UHV SubstationsTutorial of CIGRÉ Working Group A3.22 / A3.28Technical Requirements for UHV and EHV Substation Equipment

Uwe Riechert, ABB Switzerland Ltd, High Voltage Products, 2012-10-04

IEEE PES Switchgear Committee, 2012 Fall Meeting September 30 – October 4, 2012 Catamaran Resort Hotel, San Diego, CA, USA

© ABB Group September 28, 2012 | Slide 2

Contents

VFTO

Rise time

Amplitude

Simulation

Simulation methods

Verification

Insulation Co-ordination Approach

Trapped charge voltages

Damping measures

Summary

Conclusions

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 2

© ABB Group September 28, 2012 | Slide 3

Very Fast Transient Overvoltages (VFTO) Switching of Small Capacitive Currents with Gas-insulated Metal-Enclosed Disconnector Switches

0,4 0,5 0,6 0,7 0,8 0,9 1,0[s]-400

-250

-100

50

200

350

500

[kV]

0,0 0,1 0,2 0,3-400

-200

0

200

400

600

[kV]

[s]

Fixed ContactMoving Contact

Ope

ning

Clo

sing

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Very Fast Transient Overvoltages (VFTO) Rise Time

Air

SF6

Measured values

Field Utilization Factor1

10

100

1000

10000

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

Gas Pressure [MPa]

Ris

e T

ime

[ns]

Measured values

Time duration tb of spark ignition in gas such as SF6 is given by TOEPLER equation:

© ABB Group September 28, 2012 | Slide 4

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 3

VFTO - Amplitude Principle – Case A

5 mU

R = 0 Ω

UTC = -1 pu

Characteristic Impedance Z

Wave Travel Time τ

© ABB Group September 28, 2012 | Slide 5

Case AContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO - AmplitudePrinciple – Case B

5 mU

5 m

U

10 m

20 m

Case A Case B

R = 0 Ω

UTC = -1 pu

© ABB Group September 28, 2012 | Slide 6

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 4

VFTO - AmplitudePrinciple – Damping Effect

5 mU

R = 10 Ω

UTC = -1 pu

5 m

U

10 m

20 m

© ABB Group September 28, 2012 | Slide 7

Case A Case BContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO - Amplitude Principle – Real Trapped Charge

5 mU

R = 10 Ω

UTC = -0.45 pu

5 m

U

10 m

20 m

© ABB Group September 28, 2012 | Slide 8

Case A Case BContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 5

VFTO - Amplitude Traveling wave reflection – open end

© ABB Group September 28, 2012 | Slide 9

Open end reflection 2D model Coaxial line Vs= +1 V, ZS= Z0

ZL= ∞, (VL= 0 V) Simulation time: 100 ns

Coaxial line 2D model

Conductor

xuS=u(x2)uL=u(x1)

uL=u(t,x=x1)

uS=u(t,x=x2)

u(t,x)

Open endZL= ∞

ImpedancematchingZS=Z0

© ABB Group September 28, 2012 | Slide 10

VFTOVFTO versus Rated Voltages

Dependency of rated withstand voltages and calculated VFTO on rated voltage as per IEC 62271-203

Source: CIGRE TB 456, WG A3.22

0

1

4

5

300 500 700 900 1100Rated voltage Ur [kV]

Rated power frequency withstand voltage (peak)

Rated lightning impulse withstand voltage Rated switching impulse withstand voltage

Hybrid-IS

Hybrid-IS

Japan

GIS

GISGIS

South Africa China

300 500 700 900 1100

Japan

GIS

GISGIS

South Africa China

Vo

ltag

e [p

u]

2

3

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 6

VFTOClassification in High Voltage GIS Substation

© ABB Group September 28, 2012 | Slide 11

Origin

Propagation Internal transient voltages

Travelling wavesbetween inner conductor and

enclosure

Effect Stresses in insulation

Transientenclosure

voltageTEV

Transientelectromagnetic

fieldsEMF

Travellingwaves on

overhead lines

Stresses insecondary equipment

Stresses in air-insulated

operating equipment

switching operation in gas-insulated HV substations

Very fast transients in gas-insulated substationsVFTO

External transient voltages

design, free moving particles,DC stress

control circuits, EMC,personnel safety

Transformer, bushingsLeader branching

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

IEC 62271-102 Annex FRequirements for switching of bus-charging currents by disconnectors for rated voltages 72.5 kV and above

Test Duty TD 1: Switching of a very short section of busbar duct

Normal type test and mandatory for DS

The circuits for DS testing were chosen in such a way, that maximum pu (per unit) values for VFT peak were generated and it was assumed that they would also be the highest possible in the GIS.

The test circuit has to be arranged in such a way, that the measured peak voltage to ground without a trapped charge voltage at the load side and 1 pu at the source side is higher than 1.4 pu. The time to first peak should be less than 500 ns.

© ABB Group September 28, 2012 | Slide 12

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 7

VFTO Measurement Test Set-up TD 1

© ABB Group September 28, 2012 | Slide 13

10.7m

1.5m

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

© ABB Group September 28, 2012 | Slide 14

VFTO SimulationCalculation and Measurement of VFTO

Conventional single spark approach

EMTP- electromagnetic transient program

The accuracy of the simulation model must be verified

VFTO calculation and measurement when switching busbars with a GIS DS as per IEC 62271-102

without pre-charging

with pre-charging

The measured voltage progressions coincide very well with the simulation.

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 8

VFTO SimulationExtended Disconnector Model

ATP/EMTPMODEL

uL

r = r(t,uS,uL,i)

DC Trapped Charge

uS

i

Simulation of the entire process

Consideration of the dielectric behavior of the DS

Simulation of all pre-strikes and re-strikes

Calculation

Trapped Charge (DC)

Pre- and Re-strike duration

Number of strikes

As basis for the insulation coordination

© ABB Group September 28, 2012 | Slide 15

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO – Full DS Operation Comparison of Calculation and Measurement (Tests)

A comparison between simulation and measurement can verify the accuracy of the simulation.

(f ile disconnector_03_v erif ication_test_duty .pl4; x-v ar t) v :U2 0,0 0,1 0,2 0,3 0,4 0,5

-400

-300

-200

-100

0

100

200

300

400

*103

(f ile disconnector_03_v erif ication_test_duty .pl4; x-v ar t) factors:offsets:

10,00E+00

v :U2 -10,00E+00

0,0 0,2 0,4 0,6 0,8 1,0 1,2 1,4 1,6-400

-300

-200

-100

0

100

200

300

400

*103

© ABB Group September 28, 2012 | Slide 16

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 9

VFTO Simulation – Extended Model Calculation of Number of pre-strikes during one Closing

0.0

0.5

1.0

1.5

2.0

0.5 0.75 1 1.25 1.5Time [s]

VF

TO

(P

eak

Val

ue,

ab

s.)

[pu

]

TCV -1 pu

TCV -0.3 pu

© ABB Group September 28, 2012 | Slide 17

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

© ABB Group September 28, 2012 | Slide 18

VFTO Simulation – Extended ModelTrapped Charge Voltage TCV

Use of real trapped charge behavior of the disconnector, if known.

Otherwise the worst case assumption of a trapped charge voltage of -1 pu should be used for the simulation.

0%

5%

10%

15%

20%

0.0 0.2 0.4 0.6 0.8 1.0

Trapped charge voltage (abs.) [pu]

Pro

ba

bil

ity

Simulated

Measured

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 10

© ABB Group September 28, 2012 | Slide 19

VFTO Simulation – Extended ModelTCV Distribution

The TCV distribution depends strongly on the contact speed.

The TCV is specific for each design and could be analyzed during type testing or simulated with high accuracy.

0

0.2

0.4

0.6

0.8

1

0 0.5 1 1.5 2 2.5 3 3.5Contact speed [m/s]

Tra

pp

ed

ch

arg

e v

olt

ag

e (

ab

s.)

[p

u] calculated

90% probability

95% probability

99% probability

measured

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO 3D Simulation Full-Maxwell Simulation Approach

Full-Maxwell simulation approach (vector FEM implemented in COMSOL)

Full-Maxwell time-domain simulation approach offers the following advantages:

Very fast transients can be visualized and its wave character can be better understood

Local field values are available over the 3D GIS geometry

Critical places of the GIS design can be reliably detected

Sensitivity study with small geometrical changes is possible

Design optimization is possible

© ABB Group September 28, 2012 | Slide 20

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 11

VFTO 3D Simulation Example

© ABB Group September 28, 2012 | Slide 21

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO 3D SimulationSimulation Results

© ABB Group September 28, 2012 | Slide 22

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 12

VFTO 3D Simulation Experimental Verification of the Results

© ABB Group September 28, 2012 | Slide 23

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO Simulation Comparison of Simulation Methods

Conventional Model

Extended EMTP Model

3D Model

Description

One Strike „Worst case“

Entire process Detailed Calculation of GIS

Insulation coordination

AmplitudeRise Time

Accuracy > 95%

Considaration ofTrapped Charge

Pre- and Re-strikingTimes

Design

VisualizationLocal Field StrengthInternal Mitigation

StudiesOptimization

© ABB Group September 28, 2012 | Slide 24

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 13

© ABB Group September 28, 2012 | Slide 25

Insulation Co-ordination ApproachOverview according to IEC 60071-1

Step 1 Calculation of VFTO (peak value and rise time)

Step 2 Comparison of calculated VFTO values with LIWV level for the different equipment by using:

Co-ordination factor Kc

Safety factor Ks

Test conversion factor Ktc

Step 3 Definition of measures according to the insulation co-ordination

System analysisVFTO calculation

(verified calculation method)

Selection of the insulation meeting the

performance criterion

Application of factors to account for the

differences between type test and actual service conditions

Maximumcalculated VFTO

Umax_VFTO

Trapped charge voltage (TCV) behavior

known

YES

YES: UTCV = - 0.3 … - 1.0 puNO: UTCV = - 1.0 pu

Co-ordination withstand voltage

Ucw_VFTO

Insulation characteristic

Statistical distribution

Inaccuracy of simulation

Co-ordination factor KC

KC = 1.05

Required withstandvoltageUrw_VFTO

Correction factors

Atmospheric correction factor Kt

Aging in service

Quality of installation

Safety factor KS

YES: KtExternal

insulation

Test conditions

Test conversion factor Ktc

Standard lightning impulse withstand voltage (LIWV)

Ktc ≤ 1Comparison with LIWV

LIWV ≥ Urw_VFTO

No damping measures necessary

YESDefinition of requireddamping measures

Trapped charge behavior Resistance value for

damping resistor Other mitigation methods

NO

NO

Evaluation of trapped

charge behavior

KS

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO Co-ordination: Step 2Comparison of calculated VFTO values with LIWV level

Calculation of the required VFTO withstand voltage UCW_VFTO for the different equipment by using:

Co-ordination factor Kc (statistical distribution, inaccuracy of simulation, frequency of occurrence) 1.05 ( 1.0 … 1.1)

Safety factor Ks (atmospheric correction, aging behavior in service, quality of installation) 1.15 (1.05 for air insulation)

Test conversion factor Ktc (for a given equipment or insulation configuration, describes the different withstand behavior under VFTO stress compared to the stress with standard LI voltages) 1.0 (0.95 for SF6)

Comparison of calculated required VFTO withstand voltage values with LIWV level

© ABB Group September 28, 2012 | Slide 26

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 14

© ABB Group September 28, 2012 | Slide 27

Insulation Co-ordination ApproachDefinition of Damping Measures

Definition of measures according to the insulation co-ordination

No damping measure required

Damping measure required

DS with low TCV

Damping resistor

Definition of required resistance value

Other mitigation methods

Magnetic damping or resonators

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO Mitigation – Damping Resistor Principles

Arc commutation

Series resistor (contact)

Parallel resistor (contact)

(2) (1)

(1)

(2)

© ABB Group September 28, 2012 | Slide 28

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 15

VFTO Mitigation – Damping Resistor Effect

Italy: 110 Ω

China, Japan, Korea: 500 Ω

© ABB Group September 28, 2012 | Slide 29

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

VFTO Mitigation – Damping Resistor Working Principle and Structure

© ABB Group September 28, 2012 | Slide 30

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 16

VFTO Mitigation – Damping Resistor Requirements for the Resistor

Voltage withstanding characteristic and energy absorption capability of the resistor in case of re-strikes and pre-strikes between the moving contact and the arcing electrode of the resistor.

A flashover across the resistor may lead to high VFTO and has to be avoided. A higher resistance value leads to a higher voltage stress across the switching resistor. The rate of rise of the voltage across the resistor could be very high and depends on the set-up and the capacitances on the load and source side.

The thermal absorption capability of damping resistor is defined to withstand the thermal stress of one close-open operation. During the switching a lot of re-strikes or pre-strikes occur. The absorption energy of each strike must be added to get the whole absorption energy for one operation.

© ABB Group September 28, 2012 | Slide 31

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

© ABB Group September 28, 2012 | Slide 32

Insulation Co-ordination ApproachNew Mitigation Methods

High frequency RF resonator

Low quality factor designed to cover a wider frequency range

Tuned to the dominant harmonic component

20 % damping

Nano-crystalline material

Placed around the conductor

Depending on number, material and size of the rings

20 % damping

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 17

© ABB Group September 28, 2012 | Slide 33

Summary

Summarizing the different experiences an insulation co-ordination procedure with three steps is proposed, following the general insulation co-ordination approach.

The trapped charge voltage is specific for each design and could be analyzed during type testing or simulated with high accuracy and has to be used for the insulation coordination.

Required damping measures could be defined for the specific project.

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

© ABB Group September 28, 2012 | Slide 34

Conclusions

Everything should be as simple as it is-

but not simpler.

Albert Einstein

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 18

© ABB Group September 28, 2012 | Slide 35

CIGRÉUHV Working Groups

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

(1) CIGRÉ WG A3.22: Technical Requirements for Substation Equipment Exceeding 800 kV – TB 362 & TB 456

(2) CIGRÉ WG B3.22: Technical Requirement for Substations Exceeding 800 kV –TB 400

(3) CIGRÉ Ad Hoc TF of SC D1: VFTO in UHV GIS Systems

(4) CIGRÉ WG D1.36: Special Requirements for Dielectric Testing of Ultra High Voltage (UHV) Equipment

(5) CIGRÉ WG C4.306: Insulation Coordination for UHV AC Systems

(6) CIGRÉ WG A3.28: Switching phenomena and testing requirements for UHV & EHV equipment

(7) CIGRÉ WG B3.27: Field tests technology on UHV substation during construction and operation

© ABB Group September 28, 2012 | Slide 36

SummaryOutlook – EHV & UHV AC World Map

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

RussiaCanada

USA

Venezuela

Brazil

South Africa

Italy ChinaJapan

South KoreaIndia

Source: CIGRÉ WG C4.306 / highest voltages

1050 kV – 1100 kV

735 kV – 800 kV

735 kV – 800 kV and 1100 kV – 1200 kV

Uwe Riechert 10/04/2012

IEEE PES Switchgear Committee, 2012 Fall Meeting 19

© ABB Group September 28, 2012 | Slide 37

AuthorCV Dr.-Ing. Uwe Riechert

ContentIntroductionVFTOSimulationInsulation Co-ordinationDampingSummaryConclusion

Studies in electrical engineering at the Dresden Technical University

Research assistant at the Dresden Technical University

Diagnostics and dielectric properties of polymeric insulated cables for ac and dc applications

PhD on the topic of polymeric insulated HVDC cables in 2001

Since 1999 ABB Switzerland Ltd

Up to 2001: test engineer in the high voltage laboratory

Since 2001: switchgear development, responsible for partial discharge diagnostic and monitoring, solid insulating materials, dielectric design, patents, testing, product certification and cooperation with research centers and universities

Since 2004: development project manager (e.g. 1100 kV circuit-breaker)

2008: senior manager

2009-2011: high current systems (generator circuit breaker) development

Since 2011: gas insulated switchgear development

Membership

DKE (German Commission for Electrical, Electronic & Information Technologies of DIN and VDE)

Swiss Electrotechnical Committee (CES) TK42 (convener) and TK115 (convener)

CIGRÉ working groups (AG D1.03, WG A3.28, WG D1.25, WG D1.28, WG C4.306).

Convener of CIGRÉ working group D1.36: Special requirements for dielectric testing of Ultra High Voltage (UHV) equipment

IEC TC42/WG19

email: [email protected]

© ABB Group September 28, 2012 | Slide 38