UWA Update October 2013.pptx

Embed Size (px)

Citation preview

  • 7/27/2019 UWA Update October 2013.pptx

    1/41

    THE CONSERVATION CHALLENGE: OIL ANDWILDLIFE IN THE ALBERTINE.

    PAPER PRESENTED TO EDITORS ON UGANDAS

    OIL AND GAS SECTOR TUESDAY OCTOBER 29,

    2013 AT SOYA

    BUNGA.

    AGGREY RWETSIBA

    SENIOR MONITORING & RESEARCH

    COORDINATOR, UGANDA WILDLIFE AUTHORITY

    Email: [email protected]

    Tel: 0414 355000

    mailto:[email protected]:[email protected]
  • 7/27/2019 UWA Update October 2013.pptx

    2/41

    Outline of presentation

    Brief about UWA

    Brief on oil exploration Vs PAs

    Impacts of oil on the PAs

    Challenges of managing the impacts

    What is UWA doing to minimizeimpacts

    Conclusion

  • 7/27/2019 UWA Update October 2013.pptx

    3/41

    Uganda Wildlife Authority

    UWA is an institution mandated to managewildlife in Uganda within and outside PAs

    Established in 1996 as merger of Uganda

    National Parks and Game Dept. It is in charge of 10 National Parks and 12

    Wildlife Reserves, and provides guidance for

    the management of 5 Community WildlifeAreas and 13 Wildlife Sanctuaries.

    PAs cover approx. 11% of Ugandas land area

  • 7/27/2019 UWA Update October 2013.pptx

    4/41

    Brief on exploration Uganda started exploring for oil way back in 1926

    Extensive exploration work started in 2001 with the

    first discovery made in 2006

    Since then more discoveries have been made with

    the total estimates of 3 billion barrels

    In 2008, the National Oil & Gas Policy was

    formulated

    The country is now at the stage of developing the

    oil fields

    - field developments, refinery, pipelines

  • 7/27/2019 UWA Update October 2013.pptx

    5/41

    Overlap of oil blocks with high biodiversity areas

    (national parks, wildlife reserves, forest

    reserves etc)

    over 70% of protected areas lie within the

    Albertine Graben

    About 50% of wells so far drilled are within

    protected areas

  • 7/27/2019 UWA Update October 2013.pptx

    6/41

    Exploration areas showing thestatus of licensing

    3N

    1N

    EA4B LAKES EDWARD-GEORGE BASIN

    Size 2,021sq.km

    Licensed to Dominion Petroleum Ltd on 27th

    July 2007

    EA4A LAKES EDWARD-GEORGE BASIN

    Size 3,812sq.km

    Not Licensed

    EA3A SEMLIKI BASIN

    Size 1,991sq.km

    First licensed to Heritage Oil and Gas Ltd as

    part of EA3 on 15th January 1997

    Re-licensed to Heritage Oil and Gas Ltd and

    Energy Africa (now Tullow Oil) on 8 th Sept 2004.

    EA2 LAKE ALBERT BASIN

    Size 4,675 sq.km

    Licensed to Hardman Resources Ltd and

    Enegy Africa Ltd (now Tullow Oil) on 8 th

    October 2001.

    EA1 PAKWACH BASIN

    Size 4,285 sq.kmLicensed to Heritage Oil and Gas Ltd and

    Energy Africa (now Tullow Oil) 0n 1st July 2004

    EA5 RHINO CAMP BASIN

    Size 6,040sq.km

    Licensed to Neptune Petroleum (U) Ltd ( Now

    Tower Resources) on 27th Sept 2005

    EA3B SEMLIKI BASIN

    Size 1,786 sq.km

    Includes Turaco Prospect Area

    Not licensed

    Lomunga Community Wildlife

    area

    East Madi Wildlife ReserveAjai Wildlife Reserve

    Karuma Wildlife Reserve

    Bugungu Wildlife Reserve

    Also numerous Forest Reserves

    Kaiso-Tonya Community WA

    Kabwoya Wildlife Reserve (EPS)

    Toro Semuliki Wildlife Reserve

    Kyambura Wildlife Reserve

    Kigezi Wildlife Reserve

    Murchison Falls National Park

    Semuliki National Park

    Rwenzori Mountains National ParkKibale National Park

    Queen Elisabeth National Park

    Some conservation areas inAlbertine Graben

    Ramsar site (2006): Murchison

    Falls - Albert Delta Wetland

    System

    UN Biosphere Reserve (1979):

    Queen Elisabeth

    Murchison Falls NP: Ugandas

    largest protected area. Univers-

    ally recognised as one of East

    Africa / Africas best parks in 60s.

    Impressive growth in wildlife last

    10-15 years after lawlessness in

    70s and 80s. Tourism growing.

    Kabwoya WR: New protected

    area in Uganda (2002) with rapid

    growth in wildlife and

    reintroductions of locally extinct

    species. Area famous in 60s forlarge migrations between

    Murchison and Semuliki.

    Queen Elisabeth NP: Ugandas

    most popular and accessible

    park. Wildlife and tourism

    growing (ref. Murchison).

    Some indications of current

    status re. petroleum

    exploration and exploitation.

    EA5: Was licenced to

    Neptune. 3 Wells were

    drilled , but were all dry.

    Murchison FNP: Licenced to

    TOTAL

    over 30 wells drilled in prime

    tourism area., described as

    world class oil province

    Kabwoya WR: Licensed toTullow. over 8 wells drilled.

    More will be drilled for

    production

    Kingfisher area: 3 wells

    drilled. Field ready for

    production

    Semuliki . Licensed to CNOOC

    Seismics and test drilling done

    some sites. Findings not interest-

    ing enough.

    Queen Elisabeth NP &

    Kigezi WR: Was licenced

    to Dominion. one welldrilled and was dry.

  • 7/27/2019 UWA Update October 2013.pptx

    7/41

    IMPACTS OF OIL ACTIVITIES

  • 7/27/2019 UWA Update October 2013.pptx

    8/41

    Impacts on biodiversity

    Movement of large numbers of exploration

    crews and heavy logistical equipment

    opens up virgin areas as well as destroys the habitat

    result in non-target killing of wildlife, disruption,

    disturbance and scare of wildlife, blockage and

    interference with animal migration routes and

    patterns interfere with animal breeding patterns like kob

    lekking grounds

    Some animals are very sensitive to earth vibrations

    e.g Elephants

  • 7/27/2019 UWA Update October 2013.pptx

    9/41

    Giraffe close to a drill site

  • 7/27/2019 UWA Update October 2013.pptx

    10/41

    Seismic surveys laying of Geo-phones along cut

    lines

  • 7/27/2019 UWA Update October 2013.pptx

    11/41

    Increased traffic

  • 7/27/2019 UWA Update October 2013.pptx

    12/41

    Noise and vibrations

  • 7/27/2019 UWA Update October 2013.pptx

    13/41

    Waste managementdrill cuttings

    Generation of

    sewage, waste

    water and

    garbage andtheir associated

    pressures on

    the environment

  • 7/27/2019 UWA Update October 2013.pptx

    14/41

    Drill waste Consolidation pits

  • 7/27/2019 UWA Update October 2013.pptx

    15/41

    Waste management

  • 7/27/2019 UWA Update October 2013.pptx

    16/41

    Road kills

  • 7/27/2019 UWA Update October 2013.pptx

    17/41

    Excess land take during road

    construction

    Bear area in the wild

  • 7/27/2019 UWA Update October 2013.pptx

    18/41

    Visual intrusion and negative impact of

    infrastructure on tourism e.g In MFNP

    one of the most popular circuits had to

    be closed to tourists for about 3 months

    during the initial drilling

    Negative publicity reduced number of

    visitors and therefore reduced revenue

    in the long term Oil drilling sites are areas of intensive

    human presence (bee-hive like) with up

    to 100 people during operations

    Impacts of oil activities on tourism

  • 7/27/2019 UWA Update October 2013.pptx

    19/41

    Chemicals used during drilling could find their

    way into surface and ground which may cause

    death of animals

  • 7/27/2019 UWA Update October 2013.pptx

    20/41

    Un restored well site with porous

    fence at Karuka 2 in Bugungu WR

  • 7/27/2019 UWA Update October 2013.pptx

    21/41

    Dead lioness at Jobi East 2

  • 7/27/2019 UWA Update October 2013.pptx

    22/41

    Challenges of managing the impacts

    Co-existence of tourism and oil activities

    Tourism is the main source of income for wildlifemanagement

    Anything that interferes with tourism thereforeinterferes with wildlife management

    So far Tourist arrivals in the parks has been increasingsteadily

    Tourists are interested in pristine nature of the PAsThe challenge is for UWA to ensure that these

    activities are done with minimal impacts to tourism

  • 7/27/2019 UWA Update October 2013.pptx

    23/41

    Challenges (2)

    Impacts that cannot be mitigated Habitat destruction

    Interference with animal behavior

    Interference with breeding patterns The challenge has been to have oil companies

    offset these impacts

  • 7/27/2019 UWA Update October 2013.pptx

    24/41

    Challenges (2)

    Inadequate capacity

    Institutional capacity

    Government concentrated training on energy sector

    specifically Petroleum Exploration & ProductionDepartment and environmental sector left behind

    Experts in environmental assessment still lacking

    staff have limited training in oil related activities yet are

    expected to monitor the activity in regulatory agencies

    Staff numbers- high demand on the staff to monitor

    Equipments to monitor oil activities

  • 7/27/2019 UWA Update October 2013.pptx

    25/41

    UWA Staff attempting to put off fire manually near

    an oil well head

  • 7/27/2019 UWA Update October 2013.pptx

    26/41

    Pipes burnt in QENP

  • 7/27/2019 UWA Update October 2013.pptx

    27/41

    Challenges (3)

    Limited financial resources (activities imposed

    on us because of oil exploration)

    monitoring compliance,

    Additional ecosystem monitoring,

    re-planning and re-zoning the park

    New infrastructure e.g. new tourism trails,

    accommodation facilities as alternatives

  • 7/27/2019 UWA Update October 2013.pptx

    28/41

    WHAT IS UWA DOING

  • 7/27/2019 UWA Update October 2013.pptx

    29/41

    Compliance monitoring

    Review all EIAs of oil developments in the PAsand ensure activities have minimal impacts onthe PAs

    Carry out compliance monitoring on a daily basis.The headquarter staff give backstopping to fieldstaff on a quarterly basis

    Have designated dedicated staff to undertakecompliance monitoring

    Recruited 100 rangers to work with oil companies Have a warden based in the field in charge of oil

    monitoring

  • 7/27/2019 UWA Update October 2013.pptx

    30/41

    Capacity building

    Undertaking building of capacity through staff

    training and study visits

    Over 50 rangers and wardens trained on

    basic facts regarding oil impacts

    Planning another round of similar training

    Senior staff of the organization have under

    taken study tours to outside countries e.gCanada and Gabon to get experience

  • 7/27/2019 UWA Update October 2013.pptx

    31/41

    Capacity building for UWA staff

  • 7/27/2019 UWA Update October 2013.pptx

    32/41

    Planning to establish and fully equip Field

    monitoring Units for Petroleum activities in

    Murchison NP, Toro Semliki WR and Queen

    Elizabeth National Park Recruiting staff

    Building accommodation and office

    Basic lab and lab equipment

    Other equipment vehicles, computers, cameras,

    GPS, PPE

    Create a unit at headquarter in charge of oil and gas

  • 7/27/2019 UWA Update October 2013.pptx

    33/41

    Developing monitoring tools

    Developed operational guidelines for oil companies operating in

    PAs (draft) To minimize long and short - term negative impacts of oil and

    gas developments on the integrity of protected areas andassociated ecological processes.

    Developed an MoU between UWA and TOTAL for operations inMFNP

    Developing a sensitivity atlas for MFNP

    Reviewing the GMPs of some key PAs to take into account oilimpacts

    - Looking at alternatives for tourism where applicable (newtourism trails and circuits)

  • 7/27/2019 UWA Update October 2013.pptx

    34/41

    Research

    Working with WCS to carry out research on impacts ofoil on animal movement e.g collaring of animals,

    Working with oil companies in carrying outbiodiversity surveys e.g ground surveys of birds,

    mammals, and fish

    Working with oil companies in generating informationon avoidance features

    Worked with WWF to carry out a survey on impact ofoil on tourism

    Working with companies in sensitizing and updatingthe tourism stakeholders on oil activities in the parks

  • 7/27/2019 UWA Update October 2013.pptx

    35/41

    National level

    Working with the environment technical

    monitoring committee (NEMA, Water, NFA,

    PEPD, Fisheries, Wetlands) to ensure

    compliance

    Participated in preparing the Strategic

    Environmental Assessment (SEA)

    Participated in developing the Sensitivity atlasfor the Albertine Graben

    Albertine Graben Monitoring Plan

  • 7/27/2019 UWA Update October 2013.pptx

    36/41

    Other interventions Provide information on park rules to oil

    workers Advocating for use of appropriate

    technologies to reduce impacts (directional

    drilling, smaller rigs) No waste in the park

    No flaring in the park

    All infrastructure should be out of the parkincluding workers camps

    Minimise number of workers on the drill site

  • 7/27/2019 UWA Update October 2013.pptx

    37/41

    Conclusions

    Having successfully explored, Government is nowentering into the development phase.

    This phase is inevitably going to increase the

    negative impacts on the protected areas andpossibly tourism.

    If the country has to benefit from both resources,

    the two have to sustainably coexist. UWAs duty therefore is working closely with all

    partners to ensure this co-existence more so

    given the fact that oil is a finite resource.

  • 7/27/2019 UWA Update October 2013.pptx

    38/41

    Concluding Remarks

    I thank the organizers, the Directors of Africa Centre

    for Media Excellence for according UWA an

    opportunity to interact and share with senior

    editors from the media who are the gate keepers

    who determine what the public consumes in the

    media.

    I appreciate the media organizations for the growing

    interest in conservation and eco-tourism issues byallocating dedicate pages and air space in the

    various outlets thereby creating more interest from

    other stake holders and consumers of our products.

  • 7/27/2019 UWA Update October 2013.pptx

    39/41

    Concluding Remarks

    I commend the media for helping UWA topromote new innovations like technologies

    including the new payment system using the

    Wildlife cards to access our parks

    I applaud the editors for always readily availing

    reporters to cover our functions and events evenon short notice.

  • 7/27/2019 UWA Update October 2013.pptx

    40/41

    Concluding Remarks

    As the channels of mass communication upon

    which the society looks for informative and

    educative information which most people take as

    divine truth, I urge you as key partners and stake

    holders to work to promote the cause ofconservation and the importance tourism plays as

    an engine of economic growth.

    UWA is always ready to provide timely and accurateinformation in regard to Wildlife conservation and

    tourism matters particularly to the media personnel

    as well as sharing with you our success stories.

  • 7/27/2019 UWA Update October 2013.pptx

    41/41

    Concluding Remarks

    Do not hesitate to cross check with us any

    information from the social media or other sourcessince we run an open door policy at UWA.

    Together we conserve for Generations

    Thank you very much for your

    kind attention