Upload
others
View
7
Download
2
Embed Size (px)
Citation preview
A CM/GC Approach for the Design of a Two-Girder Horizontally Curved Pedestrian Bridge
Irvin J. Lopez, P.E., Senior Bridge Engineer
Ken D. Price, PE, SE, PEng, Manager Complex Bridge Group
2
Project Overview
— Purpose and Challenges
— Concept Development and Acceptance
— CM/GC Procurement
— Design and Analysis
— Global stability and redundancy
— Lessons learned
3
Project Location
UVU is located approx. 39 miles south of Salt Lake City.
North
4
— Destination of choice for many students in Utah
— Current enrollment is over 37,000
— Largest university in Utah
— Campus growth and expansion
Purpose and Challenges
5
Challenging Site Conditions and Constraints
MSE Walls
UPRR & UTA Private Property I-15 Interstate College Dr.
6
Concept Development and Acceptance
How did we get here?
Original DesignInverted Fink Truss
Re-design Concept
Three Plate GirdersConstant Depth
I I I OptimizeTwo Plate Girders
Constant Depth
I I
NTP
Final ConceptTwo Plate Girders
Haunched
Cost Reduction
Notice to Proceed
D-B-B CM/GC
80
% D
esig
n
7
Original (Complex) Fink Truss Concept
Original Design - Inverted Fink Truss Superstructure
Overall Length: 1022.5 ft.S-Curve Alignment
Pylon
Tower Bents = 4
Rods
Steel Box Chord
Anchor Bents = 2
8
Final Accepted Concept
Re-designed Bridge – Two Plate Girder Superstructure
Overall Length: 965 ft.Single Radial Curve Alignment
Roof Post
Steel Girder Outriggers & Floorbeams
Concrete Bents = 5
57.5 ft. Reduction (~6%)
9
CM/GC Project Team
UDOT
Client
WSP USA
Lead Designer
Design Sub Consultants
Architects, Environmental, Survey, Geotechnical
Kraemer North America
Lead Contractor
Stanton Construction Services
Cost Estimator
Innovating Contracting Consultant
CM/GC Lead for UDOT
Utah Valley University
(UVU)Stakeholder
Utah Transit Authority (UTA)
Stakeholder
10
CM/GC Project Schedule
Aw
arde
d to
Kra
emer
Feb.
201
9
Concept DevelopmentSteel Plate Girder
Bridge
Preliminary Design
30% Design Plans
Early Steel Package
Plans, Specs, & Estimate
Full Package Final DesignPlans, Specs, &
Estimate
Construction 12 month for substantial completion
Com
plet
e Co
nstr
ucti
onby
Nov
. 202
0
Aw
arde
d to
Kra
emer
Aug
. 201
9
Sept 1 8 Nov 1 9
S&L Plans
Nov 1 8
Jan 1 9
Feb 1 9
VE Efforts
11
Bridge Aesthetics
Aesthetic Elements— Roof Profile— Haunched Girders— Perforated Metal Enclosure— Materials— Lighting
12
Span Configuration
Site constraints resulted in unbalanced span arrangement
Sp. 1 / Sp. 2 = 1.15Sp. 4 / Sp. 3 = 0.56 (Uplift at Bent 5?)
226’Span 2
Ideal Ratio = 0.70
13
Bridge Elevation
UPRR & UTA Private Property I-15 Interstate College Dr.
14
Typical Sections
Section at End Bents
Typical Section
Section at Interior Bents
15
Design Loads
Project Design Criteria
UDOT SDDM
ASCE 7
AASHTO
Bridge Loads (AASHTO, UDOT SSDM)— Pedestrian Live Load & H5 Truck— Temperature— Wind— Earthquake— Fatigue (Wind AASHTO LTS)
Roof Loads (ASCE 7)— Snow = 30.5 psf.— Maintenance Live Load = 20 psf.— Wind
16
Pedestrian Live Load
Similar to AW3 “Crush” Load
Project Design Criteria → PL = 90 psf (no dynamic load allowance) → Load Factor (Strength) = 1.75→ 90 psf. x 1.75 = 157.5 psf.
AASHTO LRFD Guide Specification for the Design of Pedestrian Bridges
17
3D Analysis Model
SuperstructureDesign
Global Effects
Substructure Design
Foundation Design
Seismic Design
• Thermal• Wind• Stability
Lateral Bracing Other Analyses:• Staging• Dynamic• Redundancy
Roof Structure
18
Support Conditions
— Due to Seismic Demands, interior bent bearings were fixed.
Exp.(Guided)
Fix Fix Fix Exp.(Guided)
Theoretical point of “zero” movement
L/3L
19
Load Patterns for Maximum Demands
— “Patch” load cases were defined for PL, SN, and LLr.
M+ M+ M+ M+
M- M-
M-
Max. TotalLoad
20
Wind Load and Vibration Analysis
— RDWI conducted wind and pedestrian-vibration study
21
Wind Tunnel Testing
22
Fracture Critical and Redundancy Analysis
Reference Documents and Specifications
What about Pedestrian Bridges?
23
Pedestrian Bridges?
— Pedestrian bridges are not governed by fatigue
— Minimal guidance FCM requirements
— All referenced studies are based on vehicle loads
— Pedestrian loads and factors are calibrated differently than vehicular loads and factors
24
Damage Criteria
Complete failure of one girder at a critical location on the bridge with concurrent live load overload
Lateral bracing, floorbeams, deck, and composite action all contributed to load path redundancy (system redundancy).
Collapse Limit State
The bridge does not collapse under the above condition, and remains functional (deflection criteria)
How?
A Common Sense Approach
25
-25000
-20000
-15000
-10000
-5000
0
5000
10000
15000
20000
0 200 400 600 800 1000
M3
(k-
ft)
DC-Girder 1 Combined
Unfractured
Fracture
Dynamic
-20000
-15000
-10000
-5000
0
5000
10000
15000
20000
0 200 400 600 800 1000
M3
(k-
ft)
DC-Girder 2 Combined
Unfractured
Fracture
Dynamic
Redundancy AnalysisTwo Girder System is redundant – will not collapseAn event scaling approach was adopted to prove redundancy of bridge superstructure.
26
Fabrication and Weight Efficiency
Weight efficiency does not always result in most economical design.
Fabrication costs must also be considered when detailing bridges.
Field Splices 1 2 3 4 5 6 7
I-15 Interstate
27
Fabrication and Construction
— Large Field Sections (driven by site)
— Max. girder segment length (over RR) = 183 feet
— Max. weight = 70 tons.
28
— CM/GC worked well for this project.
— Two-girder bridges can be redundant
— Refined analysis was utilized to identify system redundancy
Lessons Learned
Thank you!
wsp.com
Marshall Railway Consulting