Upload
christopher-christie
View
216
Download
0
Embed Size (px)
Citation preview
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
1/45
EquipmentSelection,DesignEngineering,and
FinancialPlanningServicesfortheBakerCityUVTreatmentFacilit
KickOffMeeting&
BakerCity,OR
Januar 12 2012
WaterQuality,Treatment,andRegulatoryComplianceProject
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
2/45
Welcome,Introductions
Pro ectOb ectivesandU datesfromCit
ReviewAgenda
ReviewPro ect
Guide
Sco e
&
Schedule
DataExchange
OtherItems,Discussion
2. TechnologyWorkshop
&
Lunch
(10:30
2)
3. SiteVisit 23:30
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
3/45
Task1:
Project
Management
&
QC
Tas 2:UVEqu pmentSe ect on
Task3:
Project
Definition
Development
Task4:FinancialPlanningandRate
Evaluation
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
4/45
HDR PM:Anna
ZaklikowskiHDR Principal:
, David Keil
QA/QC Leads:Ron Brown (Treatment)Shawn Koorn (Finance)
BC Staff Contacts:Gary Van Patten (Asst PW Director/Surveyor)Larry McBroom (PW Construction Supervisor)
Jake Jones (Water Treatment Specialist)Jeanie Dexter (Finance Director)
~nna Zaklikowski (Project/Process Engineer)Bryan Black (Sr. Technical Advisor)Rich Stratton (Sr. Technical Advisor)Joseph Healy (Finance Task Lead)
Don Best (Electrical/I&C)Mike Zeltner (Civil)
Jerry Spencer (Structural)Karl Sutton (Building Mechanical)
Donn Hogan (Architect)Eric Sjoberg (CAD/BIM Lead)Mike Wallace (Permitting)
Rich Glassen (Cost Estimating)Paul Wasser (Geotech/Geoengineers)
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
5/45
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
6/45
?
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
7/45
Project
Milestone DateNoticetoProceed 11/9/11
UVEquipmentProcurementProposalDeadline 5/11/2012
Submitrecommendation
of
UV
System
Supplier
to
City 6/8/2012
NoticeofAwardtoUVEquipmentSupplier* 6/22/2012
*ConditionalNoticeofAwardpendingUVValidationReportapprovalbyOHA
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
8/45
Task Meeting Date
Project Concept& CriteriaReviewMtg (InternalQA/QC) 1/6/12
anagemen
(Task
1)UV System
Procurement
(Task2)
ProjectKickOffMeetingandTechnologyReviewWorkshop 1/12/12
ReviewofUVProcurementDocuments(conferencecall) 3/21/12
LampBreakageResponsePlanWorkshop 8/17/12
Project
Definition
Development
ProjectDefinitionTaskReviewMeeting(conferencecall) 9/26/12
as
Financial
Planningand
RateDesign
(Task4)
FinancialPlanningTaskInitiationConference(conferencecall) 1/17/12
FinancialPlanningWorkshop(conferencecall) 2/14/12
FinancialPlanDraftReportReviewMtg (conferencecall) 4/3/12
+Biweeklystanding30minuteprogress/coordinationcalls
RateDesign
Workshop
(conference
call) 5/15/12
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
9/45
Task Deliverables Date
DraftUVSolicitationPacka e 2 29 2012
UVEquipmentProcurement(Task 2)
FinalRFPpackage 4/13/2012
DraftLampBreakageResponsePlantoCITY 8/3/2012
DraftLampBreakageResponsePlantoOHA 8/24/2012
FinalLampBreakageResponsePlantoCITYand
OHA 9/14/2012
Pro ect
Geotech InvestigationWorkplan 7/13/2012
DraftGeotechReport 8/31/2012
Definition(Task 3)
FinalGeotech Report 9/28/2012
DraftDrawingPackagetoCITY 9/5/2012
DraftOPCCtoCITY 9/19/2012
FinancialPlanningand RateDesign
DraftFinancial
Plan
Report
3/13/2012
FinalFinancialPlanReport 4/17/2012
DraftRateDesignAnalysisReport 5/29/2012
na a e es gn na ys s epor
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
10/45
1. InfoReceived: 3. PreviousReportsandDocumentsforSite:
Sourcewaterqua ityData
4.5MG
reservoir
as
builts
ASR/siteCADfile
2000WaterFacilitiesPlan
RecentMasterP anUp ate i app ica e,
HDR
has
the
2000
Master
Plan) Geotechnicalreport(s)forsite,ifavailable
4. Historicaloperationsdata(previous3yrs)
2. SiteRecordDrawingsforthefollowing
facilities:
Storagetanks
Otheron
site
facilities,
including
yard
piping
Operations ata orsite owrate,tan levels)
Monthlyoperationsreports(e.g.,chlorine
usage/doses,CT
reports)
an metering va vevau ts,c orine ui ing,
generatorbuildingandtelemetrybuildings
Verifyexistingfacilitiesversusplans/reports;Identifyanymodificationsatthesitethat
.
Updatesindemand/flowprojections
Powersupplyinformationforsite
Historyofelectricalpoweroutagesatsite
ofrecord
drawings
(identify
on
record
drawingsifpossible) O M
manua s
or
ma e mo e
an
contro
strategiesforsitecontrolvalves
ASRLicenseDocumentation
FinancialData(requestedbyJoeHealy)
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
11/45
UV
D s n ect on
Technolo
Workshop
January12,2012
WaterQuality,Treatment,andRegulatoryComplianceProject
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
12/45
1. Background(10:3011:15) Regulatory/TreatmentRequirements(ExistingandUnderLT2)
Introductionand
Review:
Why
UV?
UVBasicsandRegulatoryRequirements
2. UVTreatmentSystems(11:1512) ec no ogy verv ew SystemOperation&Maintenance GeneralUVSystemDesignCriteria WaterQualityReview&ImpactstoUV UV
Process
Schematic
&
Possible
Layouts
re m nary os n o
3. Lunch(1212:45)
4. UVSystemProcurement(12:451:15)
5. OtherProjectConsiderations(1:151:30) ChlorinationMethod
SCADA/CommunicationsUpgrades
ProvisionsforFutureFacilities Hydraulics
6. Closing(1:302)
ReviewKeyDecisionsandNextSteps
Adjourn
to
Site
Visit
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
13/45
UVT,future
expansion)
2. LimitUVTechnolo O tions?
3. SelectUVEquipmentProcurementMethod:
Ca italcost
or
life
c cle
cost
Earlyprocurementw/equipmentstoragevs.assigncontracttoContractor
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
14/45
1. Notreatmentfor
Cryptosporidium2. DisinfectionRequirements:
og . nact vat onoGiardia w/chlorine
4log
(99.99%)
inactivation
of
(Giardia)
virusesw/chlorine
3. UnfilteredSystems:
prior
to
disinfection);
Excludingeventspermitted
(Cryptosporidium)
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
15/45
1. RequirementsforUnfilteredSystems:
Complywithturbidityrequirements UnfilteredwatersystemsmustuseacombinationofTWOdisinfectantsto
inactivateCryptosporidium,
Giardia,
and
viruses
Cryptosporidium controlunderWatershedControlProgram MeetRequirementsforsystemsutilizingsurfacewaterorGWUDIsources
withoutfiltration)(OAR3330610032(2)&(3))
2. DisinfectionRequirements:
3log
inactivation
of
Cryptosporidium (w/UV)
4loginactivationofviruses(w/chlorine)
3. ComplianceSchedule: ComplianceDeadline:October2016(Systems
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
16/45
1. Costeffectivetreatmentfor
LT2
2. Targetswiderangeof
microbialpathogens
3. ReducesCTrequirements
4. Chemicalfree
5. Nowastestream
6. Nodisinfection
byproduct
formation
7. Doesnotaffecttasteof
water
CostOpinionforLT2ComplianceOptions (From2009HDRTM)
.
basedon
water
quality
and
flowrate
9. Partofmultibarrier,reliable
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
17/45
1. Poorviralinactivation
2. Notaphysicaltreatmentbarrier:
Doesnot
remove
particulates
and
organics;
Doesnotprotectagainstfirethreatorexcursionsinwaterquality
. reqts,WatershedControlProgram,inspections,facilitymaintenance,etc)
4. Waterquality
may
limit
applicability
5. Lampbreakage;mercuryreleaseconcerns
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
18/45
RegulatoryReqts forUVFacilities:
OAR3330610036(5)(c)(D):SystemsmustvalidateandmonitorUV
reactorstodemonstratethattheyareachievingaparticularUV
dosevaluefortreatmentcredit.
(i)UV
dose
table.
The
treatment
credits
listed
in
this
table
are
for
UV
light
atawavelengthof254nmasproducedbyalowpressuremercuryvapor
. ,
demonstrateanequivalentgermicidaldosethroughreactorvalidation
testing
Doseneededfor3logcryptonearly2Xdosefor2logcrypto
3log
crypto
dose
meets
all
Giardia disinfection
reqts!
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
19/45
ValidationOptions
1. Off Site
equipment
only
(based
onstandardtestprotocol)
Acceptbidscontingentonsuccessful3rdpartyvalidationbeforepurchase
2. On
Site validationafterinstallation
3. ValidationMethods:
CalculatedDose
DoseSet
point
Method
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
20/45
Nolargecapacity(>2.5mgd)UVsystemsarelisted.
.
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
21/45
RegulatoryReqts forUVFacilities:
OAR3330610032(3)Disinfectionreqts forunfiltered
systems:
(A) Redundant
components,
including
an
auxiliarypowersupplywithautomatic
startu andalarmtoensurethatdisinfectantapplicationismaintainedcontinuouslywhilewater
isbeingdeliveredtothedistributionsystem;or
(B) Automaticshut
offofdeliveryofwatertothedistributionsystem.
inthewater,oriftheultravioletlightsystemfails.IftheDepartment
determinesthanautomaticshutoffwouldcauseunreasonablerisktohealth
orinterferewithfireprotection,thesystemmustcomplywithparagraph
.
OAR3330610032(18)Inactivationtoolboxcomponentsformeeting
CryptosporidiumtreatmentRequirements. ,
95percentofthewaterdeliveredtothepublicduringeachmonthby
UVreactors
operating
within
validated
conditions
for
the
required
UV
dose
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
22/45
RegulatoryReqts forUVFacilities:
OAR3330610036(5)(c)(D):
eac ormon or ng. ys emsmus mon or e r reac ors o
determineif
the
reactors
are
operating
within
validated
conditions...
This
monitoring mustincludeUVintensityasmeasuredbyaUVsensor,flow
rate,lampstatus,andotherparameterstheDepartmentdesignates
basedonUVreactoroperation.Watersystemsmustverifythe
calibrationofUVsensorsatleastmonthly,andmustrecalibratesensors
inaccordance
with
the
EPA
UV
Disinfection
Guidance
Manual
as
.
(iii)Watersystemsmustmonitorthepercentageofwaterdeliveredto
thepublicthatwastreatedwithinvalidatedconditionsfortherequired
UVdose.
If
less
than
95
percent
of
water
delivered
was
within
validated
conditions,aTier2publicnoticemustbeissued
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
23/45
RegulatoryReqts forUVFacilities:Reporting
OAR3330610040(1):
1. Su mitva i ationtestresu ts emonstratingoperating
conditionsthat
achieve
required
UV
doseno
later
than
applicablecompliancedeadline.
2. Monthlyreportsummarizingthepercentageofwater
enteringthedistributionsystemthatwasNOT treatedbyUV
requireddose...
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
24/45
UVDisinfection
as cs
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
25/45
UV
Technolo
O tions:
LPHO
and
MPLowPressureHighOutput(LPHO) MediumPressure
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
26/45
UVTechnologyOptions:
1. General:
Availableindifferentsizeranges Nearl all UV intensit at 254nm MFRs:Wedeco (ITT),Trojan
2. Pros Smallerpowerreqt (smaller
generator/UPS?)
Wedeco Kseriesreactors:
owerpowerconsump on Goodcleaningsystem Longerlamplife Lessreductionindoseiflampfails Reducedfoulingpotential potentially
Largeflowsupto40mgdlowerDesignFoulingFactor
Integralbaffleplateforflowdistribution;providesaddedprotection?
3. Cons
reactors Highheadloss throughreactor(upto52in) Morelamps,maintenance Potentiallylongerstarttimes
Wedeco LBXReactors:
Smallerflowsupto8.5mgd
Generallyonly50%turndowninreactor
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
27/45
UVTechnologyOptions:
1. General: va a e n eren s zeranges UVintensityoverbroaderwavelength
range;less
efficient
dose
delivery
MFRs:Trojan,Calgon,Ozonia
TrojanSwift@Kennewick
Compactdesign&systemfootprint Lowheadloss throughreactors(05in) LowercapitalcostthanLPHOathigher
designUVTs
(>85%)
Fewertotallamps Betterreactorturndown
3. Cons Higherpowersupplyreqt Hig erenergyusage Greater
potential
to
be
out
of
spec
in
the
eventlampfails
Subjecttospectraeffect uncertaintyindoseneeded
Calgon SentinelReactors
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
28/45
RecentDoseConcernsforMPSpectraEffect
InrecentvalidationtestsforMPsystems:
Dependingonthevalidationtesting
approachand
implementation
at
the
water
treatmentplant,thecontributionoflowwavelengthUVlightmaysuggestbetterCryptosporidiuminactivation(e.g.,whenMS2phageisusedforvalidationtesting)thanisactuallyoccurring.
Questions:1. WhatdoesOHAsayaboutthis?
2. HowcanwebalanceriskofallowingMPtobidwithcompetitiveness?
.
correctionfactor,
but
nothing
confirmed.
4. OHAhasverballyindicatedtheywouldbecomfortablewitha15%correctionfactor
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
29/45
LPHO MP
Footprint 2x 1x
Number of Lamps 10x 1x
Lamp Replacement Cost 3x 1x
Ballast Replacement Cost 1x 2x
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
30/45
UVSystemOperation&Maintenance
1. UVSensorCalibration
2. CleaningSystems: Optional
automatic
or
manualsleevewiping
Trojan
SwiftSC LPHO
Lamp
Replacement
systems(mech orcombinedmech/chemical)
Offlinechemical
cleaning
. omponentrep acement: Lamps Sleeves
Ballasts UVSensors Cleaningcomponents
TrojanSleeve
Wiping
System
forSwiftMPsystem
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
31/45
UVSystemOperation&Maintenance:
FromEPAUVDGM:
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
32/45
UVSystemDesignCriteria
UVS stemDesi nCriteria:
Lamp
technology CleaningSystem owrates UVT
CombinedDeratin Factor
for
End
of
Lam
Life
(EOLL)andfouledcondition
No.DutyandStandbyTrains Headloss WaterQualityCharacteristics
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
33/45
WaterQualityParametersImpactingUVDesignand
pera on
arame er es gn mpac mpac
UVT ReactorSizing;
Dose
Basis UV
Dose/energy
efficiency
Iron&
Manganese
Treatmentreqd >0.3 mg/L
Fe,200
mg/L Lamp fouling;
energy
Organics DesignFoulingFactor Lamp fouling;energy
efficiency;cleaning
ar c es nergye c ency
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
34/45
Water
ualit :
UVT
Data120%4.5
Turbidity UVT
100%
3.5
4.0
(%)
)
Count 76Min 65%
Avera e 97%
60%
2.0
2.5
.
nsmittance
bid
ity(NTU Max 100%
90% 100%
95% 100%
10% 95%
20%
40%
1.0
1.5
UVTra
Tur 5 90
1% 68%
0%0.0
0.5
J09 O09 J10 M10 A10 N10 F11 J11 S11 D11
RareLowUVTeventscouldimpactdesignrequirements,increasingcost
Averageenergyusagewillbesignificantlylowerthanduring
UVT/turbidityevents
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
35/45
Distribution
of
Sam le
UVT
6596% 100%
2
6
86% 90%
91%
95%
e
0
81% 85%
%
)Ran
071% 75%
UVT
1
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
36/45
Man anese
Iron
and
Hardness
arame er verage ange o.
SamplesHardness(mg/LCaCO3) none 38 120 73 21
Iron 0.3
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
37/45
DesignCriteriaIdentification:UVSystemCriterion Value
UVLampTechnology MediumPressure orLowPressureHigh
Output
Cleanin S stem Automatic
DesignFlowrate
MaximumDesign
Flow 12
mgd?
MinimumDesign Flow 2mgd?
UltimateDesignFlow 12mgd?
AverageDesignFlow ?
DesignUVT
MinimumValidatedUVT 70%
DesignUVT@12mgd 85%?
DesignUVT&6 mgd 70%
UVT(95th Percentile) 90%
Com ne Derat ng Factor orEOLLan ou e con t on 0.72
Minimum No.DutyTrains 2
MaximumNo.DutyTrains 3
No.StandbyTrains 1
SystemOperatingPressure(PSIG)
SystemDesignPressure(PSIG) 100
MaximumHeadloss through UVReactor 54inches
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
38/45
Desi nCriteriaIdentification:Water ualit
Criterion Value
Water QualityCharacteristics
WaterTemperature
UVTRange 70% 99%
pH 69
Iron
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
39/45
UVDisinfectionSystemSchematic
UV#1
From4.5
MG To3MG
M
FMeservo r Reservoir/
Distribution
UVT
UV#2
UV#3 Stan y
UV Facility and Generator
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
40/45
UVFacilityandGenerator
PossibleLocations
ro CITY- OISrRlOOT"IONSYSTEM
14" OVERFLOWIE . 3647.68
nr - t""" ' r -n \ / r ' \ I r "" ' l Mlntt. tr "
CITY OFBAKER CITY, OREGONWATER FACILITIES PLAN
Ill!fl
~\\\ll!fl'"T\\
-12"OR- -
3.0 MG RES.WS = 3647.68FF = 3620.68
w - - j ~ : t /.92 MG RES.WS = 3647.68FF = 3634.78
ORAIN ANDRISER VAULr
'i 'IIIIIIIIII,IIIG""~ ~()-J-
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
41/45
2011ProjectEstimate:$2.5M,assuming:
2,000sf building
2+1pipingconfiguration
,
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
42/45
IdentifytaskstobeincludedinFY2012Predesign/FinalDesignTO:
ChlorinationMethod: Improvements
to
existing
chlorine
gas
system?
Conversiontoliquidhypochlorite(onsitegeneratorordeliveredbulkhypo)
Provisionsforfutureinstallationof
SCADA/CommunicationsImprovements
Im rovements in h draulic control
integrationwith
UV
MCCs Communicationsofsystemalarms
Localandoffsitecontrolpreferences
ProvisionsforFutureFiltrationFacility
UVSystemMCCs
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
43/45
.
2. UVTechnology
Preferences
3. Se ectUVEquipmentProcurement
Method
4. Othertasks/evaluationsneededduring
design
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
44/45
DataRequest
EquipmentProcurement:
ContinuediscussionswithOHA
PrepareDesignCriteriaTMforOHA
Investigatehydraulics
Beginpreparationofprocurementspecs(frontendsandtechnical)
FinancialPlanning
8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012
45/45