UV Kick‐Off Meeting & Technology Workshop, Baker City, OR, January 12, 2012

Embed Size (px)

Citation preview

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    1/45

    EquipmentSelection,DesignEngineering,and

    FinancialPlanningServicesfortheBakerCityUVTreatmentFacilit

    KickOffMeeting&

    BakerCity,OR

    Januar 12 2012

    WaterQuality,Treatment,andRegulatoryComplianceProject

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    2/45

    Welcome,Introductions

    Pro ectOb ectivesandU datesfromCit

    ReviewAgenda

    ReviewPro ect

    Guide

    Sco e

    &

    Schedule

    DataExchange

    OtherItems,Discussion

    2. TechnologyWorkshop

    &

    Lunch

    (10:30

    2)

    3. SiteVisit 23:30

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    3/45

    Task1:

    Project

    Management

    &

    QC

    Tas 2:UVEqu pmentSe ect on

    Task3:

    Project

    Definition

    Development

    Task4:FinancialPlanningandRate

    Evaluation

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    4/45

    HDR PM:Anna

    ZaklikowskiHDR Principal:

    , David Keil

    QA/QC Leads:Ron Brown (Treatment)Shawn Koorn (Finance)

    BC Staff Contacts:Gary Van Patten (Asst PW Director/Surveyor)Larry McBroom (PW Construction Supervisor)

    Jake Jones (Water Treatment Specialist)Jeanie Dexter (Finance Director)

    ~nna Zaklikowski (Project/Process Engineer)Bryan Black (Sr. Technical Advisor)Rich Stratton (Sr. Technical Advisor)Joseph Healy (Finance Task Lead)

    Don Best (Electrical/I&C)Mike Zeltner (Civil)

    Jerry Spencer (Structural)Karl Sutton (Building Mechanical)

    Donn Hogan (Architect)Eric Sjoberg (CAD/BIM Lead)Mike Wallace (Permitting)

    Rich Glassen (Cost Estimating)Paul Wasser (Geotech/Geoengineers)

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    5/45

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    6/45

    ?

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    7/45

    Project

    Milestone DateNoticetoProceed 11/9/11

    UVEquipmentProcurementProposalDeadline 5/11/2012

    Submitrecommendation

    of

    UV

    System

    Supplier

    to

    City 6/8/2012

    NoticeofAwardtoUVEquipmentSupplier* 6/22/2012

    *ConditionalNoticeofAwardpendingUVValidationReportapprovalbyOHA

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    8/45

    Task Meeting Date

    Project Concept& CriteriaReviewMtg (InternalQA/QC) 1/6/12

    anagemen

    (Task

    1)UV System

    Procurement

    (Task2)

    ProjectKickOffMeetingandTechnologyReviewWorkshop 1/12/12

    ReviewofUVProcurementDocuments(conferencecall) 3/21/12

    LampBreakageResponsePlanWorkshop 8/17/12

    Project

    Definition

    Development

    ProjectDefinitionTaskReviewMeeting(conferencecall) 9/26/12

    as

    Financial

    Planningand

    RateDesign

    (Task4)

    FinancialPlanningTaskInitiationConference(conferencecall) 1/17/12

    FinancialPlanningWorkshop(conferencecall) 2/14/12

    FinancialPlanDraftReportReviewMtg (conferencecall) 4/3/12

    +Biweeklystanding30minuteprogress/coordinationcalls

    RateDesign

    Workshop

    (conference

    call) 5/15/12

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    9/45

    Task Deliverables Date

    DraftUVSolicitationPacka e 2 29 2012

    UVEquipmentProcurement(Task 2)

    FinalRFPpackage 4/13/2012

    DraftLampBreakageResponsePlantoCITY 8/3/2012

    DraftLampBreakageResponsePlantoOHA 8/24/2012

    FinalLampBreakageResponsePlantoCITYand

    OHA 9/14/2012

    Pro ect

    Geotech InvestigationWorkplan 7/13/2012

    DraftGeotechReport 8/31/2012

    Definition(Task 3)

    FinalGeotech Report 9/28/2012

    DraftDrawingPackagetoCITY 9/5/2012

    DraftOPCCtoCITY 9/19/2012

    FinancialPlanningand RateDesign

    DraftFinancial

    Plan

    Report

    3/13/2012

    FinalFinancialPlanReport 4/17/2012

    DraftRateDesignAnalysisReport 5/29/2012

    na a e es gn na ys s epor

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    10/45

    1. InfoReceived: 3. PreviousReportsandDocumentsforSite:

    Sourcewaterqua ityData

    4.5MG

    reservoir

    as

    builts

    ASR/siteCADfile

    2000WaterFacilitiesPlan

    RecentMasterP anUp ate i app ica e,

    HDR

    has

    the

    2000

    Master

    Plan) Geotechnicalreport(s)forsite,ifavailable

    4. Historicaloperationsdata(previous3yrs)

    2. SiteRecordDrawingsforthefollowing

    facilities:

    Storagetanks

    Otheron

    site

    facilities,

    including

    yard

    piping

    Operations ata orsite owrate,tan levels)

    Monthlyoperationsreports(e.g.,chlorine

    usage/doses,CT

    reports)

    an metering va vevau ts,c orine ui ing,

    generatorbuildingandtelemetrybuildings

    Verifyexistingfacilitiesversusplans/reports;Identifyanymodificationsatthesitethat

    .

    Updatesindemand/flowprojections

    Powersupplyinformationforsite

    Historyofelectricalpoweroutagesatsite

    ofrecord

    drawings

    (identify

    on

    record

    drawingsifpossible) O M

    manua s

    or

    ma e mo e

    an

    contro

    strategiesforsitecontrolvalves

    ASRLicenseDocumentation

    FinancialData(requestedbyJoeHealy)

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    11/45

    UV

    D s n ect on

    Technolo

    Workshop

    January12,2012

    WaterQuality,Treatment,andRegulatoryComplianceProject

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    12/45

    1. Background(10:3011:15) Regulatory/TreatmentRequirements(ExistingandUnderLT2)

    Introductionand

    Review:

    Why

    UV?

    UVBasicsandRegulatoryRequirements

    2. UVTreatmentSystems(11:1512) ec no ogy verv ew SystemOperation&Maintenance GeneralUVSystemDesignCriteria WaterQualityReview&ImpactstoUV UV

    Process

    Schematic

    &

    Possible

    Layouts

    re m nary os n o

    3. Lunch(1212:45)

    4. UVSystemProcurement(12:451:15)

    5. OtherProjectConsiderations(1:151:30) ChlorinationMethod

    SCADA/CommunicationsUpgrades

    ProvisionsforFutureFacilities Hydraulics

    6. Closing(1:302)

    ReviewKeyDecisionsandNextSteps

    Adjourn

    to

    Site

    Visit

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    13/45

    UVT,future

    expansion)

    2. LimitUVTechnolo O tions?

    3. SelectUVEquipmentProcurementMethod:

    Ca italcost

    or

    life

    c cle

    cost

    Earlyprocurementw/equipmentstoragevs.assigncontracttoContractor

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    14/45

    1. Notreatmentfor

    Cryptosporidium2. DisinfectionRequirements:

    og . nact vat onoGiardia w/chlorine

    4log

    (99.99%)

    inactivation

    of

    (Giardia)

    virusesw/chlorine

    3. UnfilteredSystems:

    prior

    to

    disinfection);

    Excludingeventspermitted

    (Cryptosporidium)

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    15/45

    1. RequirementsforUnfilteredSystems:

    Complywithturbidityrequirements UnfilteredwatersystemsmustuseacombinationofTWOdisinfectantsto

    inactivateCryptosporidium,

    Giardia,

    and

    viruses

    Cryptosporidium controlunderWatershedControlProgram MeetRequirementsforsystemsutilizingsurfacewaterorGWUDIsources

    withoutfiltration)(OAR3330610032(2)&(3))

    2. DisinfectionRequirements:

    3log

    inactivation

    of

    Cryptosporidium (w/UV)

    4loginactivationofviruses(w/chlorine)

    3. ComplianceSchedule: ComplianceDeadline:October2016(Systems

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    16/45

    1. Costeffectivetreatmentfor

    LT2

    2. Targetswiderangeof

    microbialpathogens

    3. ReducesCTrequirements

    4. Chemicalfree

    5. Nowastestream

    6. Nodisinfection

    byproduct

    formation

    7. Doesnotaffecttasteof

    water

    CostOpinionforLT2ComplianceOptions (From2009HDRTM)

    .

    basedon

    water

    quality

    and

    flowrate

    9. Partofmultibarrier,reliable

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    17/45

    1. Poorviralinactivation

    2. Notaphysicaltreatmentbarrier:

    Doesnot

    remove

    particulates

    and

    organics;

    Doesnotprotectagainstfirethreatorexcursionsinwaterquality

    . reqts,WatershedControlProgram,inspections,facilitymaintenance,etc)

    4. Waterquality

    may

    limit

    applicability

    5. Lampbreakage;mercuryreleaseconcerns

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    18/45

    RegulatoryReqts forUVFacilities:

    OAR3330610036(5)(c)(D):SystemsmustvalidateandmonitorUV

    reactorstodemonstratethattheyareachievingaparticularUV

    dosevaluefortreatmentcredit.

    (i)UV

    dose

    table.

    The

    treatment

    credits

    listed

    in

    this

    table

    are

    for

    UV

    light

    atawavelengthof254nmasproducedbyalowpressuremercuryvapor

    . ,

    demonstrateanequivalentgermicidaldosethroughreactorvalidation

    testing

    Doseneededfor3logcryptonearly2Xdosefor2logcrypto

    3log

    crypto

    dose

    meets

    all

    Giardia disinfection

    reqts!

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    19/45

    ValidationOptions

    1. Off Site

    equipment

    only

    (based

    onstandardtestprotocol)

    Acceptbidscontingentonsuccessful3rdpartyvalidationbeforepurchase

    2. On

    Site validationafterinstallation

    3. ValidationMethods:

    CalculatedDose

    DoseSet

    point

    Method

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    20/45

    Nolargecapacity(>2.5mgd)UVsystemsarelisted.

    .

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    21/45

    RegulatoryReqts forUVFacilities:

    OAR3330610032(3)Disinfectionreqts forunfiltered

    systems:

    (A) Redundant

    components,

    including

    an

    auxiliarypowersupplywithautomatic

    startu andalarmtoensurethatdisinfectantapplicationismaintainedcontinuouslywhilewater

    isbeingdeliveredtothedistributionsystem;or

    (B) Automaticshut

    offofdeliveryofwatertothedistributionsystem.

    inthewater,oriftheultravioletlightsystemfails.IftheDepartment

    determinesthanautomaticshutoffwouldcauseunreasonablerisktohealth

    orinterferewithfireprotection,thesystemmustcomplywithparagraph

    .

    OAR3330610032(18)Inactivationtoolboxcomponentsformeeting

    CryptosporidiumtreatmentRequirements. ,

    95percentofthewaterdeliveredtothepublicduringeachmonthby

    UVreactors

    operating

    within

    validated

    conditions

    for

    the

    required

    UV

    dose

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    22/45

    RegulatoryReqts forUVFacilities:

    OAR3330610036(5)(c)(D):

    eac ormon or ng. ys emsmus mon or e r reac ors o

    determineif

    the

    reactors

    are

    operating

    within

    validated

    conditions...

    This

    monitoring mustincludeUVintensityasmeasuredbyaUVsensor,flow

    rate,lampstatus,andotherparameterstheDepartmentdesignates

    basedonUVreactoroperation.Watersystemsmustverifythe

    calibrationofUVsensorsatleastmonthly,andmustrecalibratesensors

    inaccordance

    with

    the

    EPA

    UV

    Disinfection

    Guidance

    Manual

    as

    .

    (iii)Watersystemsmustmonitorthepercentageofwaterdeliveredto

    thepublicthatwastreatedwithinvalidatedconditionsfortherequired

    UVdose.

    If

    less

    than

    95

    percent

    of

    water

    delivered

    was

    within

    validated

    conditions,aTier2publicnoticemustbeissued

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    23/45

    RegulatoryReqts forUVFacilities:Reporting

    OAR3330610040(1):

    1. Su mitva i ationtestresu ts emonstratingoperating

    conditionsthat

    achieve

    required

    UV

    doseno

    later

    than

    applicablecompliancedeadline.

    2. Monthlyreportsummarizingthepercentageofwater

    enteringthedistributionsystemthatwasNOT treatedbyUV

    requireddose...

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    24/45

    UVDisinfection

    as cs

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    25/45

    UV

    Technolo

    O tions:

    LPHO

    and

    MPLowPressureHighOutput(LPHO) MediumPressure

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    26/45

    UVTechnologyOptions:

    1. General:

    Availableindifferentsizeranges Nearl all UV intensit at 254nm MFRs:Wedeco (ITT),Trojan

    2. Pros Smallerpowerreqt (smaller

    generator/UPS?)

    Wedeco Kseriesreactors:

    owerpowerconsump on Goodcleaningsystem Longerlamplife Lessreductionindoseiflampfails Reducedfoulingpotential potentially

    Largeflowsupto40mgdlowerDesignFoulingFactor

    Integralbaffleplateforflowdistribution;providesaddedprotection?

    3. Cons

    reactors Highheadloss throughreactor(upto52in) Morelamps,maintenance Potentiallylongerstarttimes

    Wedeco LBXReactors:

    Smallerflowsupto8.5mgd

    Generallyonly50%turndowninreactor

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    27/45

    UVTechnologyOptions:

    1. General: va a e n eren s zeranges UVintensityoverbroaderwavelength

    range;less

    efficient

    dose

    delivery

    MFRs:Trojan,Calgon,Ozonia

    TrojanSwift@Kennewick

    Compactdesign&systemfootprint Lowheadloss throughreactors(05in) LowercapitalcostthanLPHOathigher

    designUVTs

    (>85%)

    Fewertotallamps Betterreactorturndown

    3. Cons Higherpowersupplyreqt Hig erenergyusage Greater

    potential

    to

    be

    out

    of

    spec

    in

    the

    eventlampfails

    Subjecttospectraeffect uncertaintyindoseneeded

    Calgon SentinelReactors

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    28/45

    RecentDoseConcernsforMPSpectraEffect

    InrecentvalidationtestsforMPsystems:

    Dependingonthevalidationtesting

    approachand

    implementation

    at

    the

    water

    treatmentplant,thecontributionoflowwavelengthUVlightmaysuggestbetterCryptosporidiuminactivation(e.g.,whenMS2phageisusedforvalidationtesting)thanisactuallyoccurring.

    Questions:1. WhatdoesOHAsayaboutthis?

    2. HowcanwebalanceriskofallowingMPtobidwithcompetitiveness?

    .

    correctionfactor,

    but

    nothing

    confirmed.

    4. OHAhasverballyindicatedtheywouldbecomfortablewitha15%correctionfactor

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    29/45

    LPHO MP

    Footprint 2x 1x

    Number of Lamps 10x 1x

    Lamp Replacement Cost 3x 1x

    Ballast Replacement Cost 1x 2x

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    30/45

    UVSystemOperation&Maintenance

    1. UVSensorCalibration

    2. CleaningSystems: Optional

    automatic

    or

    manualsleevewiping

    Trojan

    SwiftSC LPHO

    Lamp

    Replacement

    systems(mech orcombinedmech/chemical)

    Offlinechemical

    cleaning

    . omponentrep acement: Lamps Sleeves

    Ballasts UVSensors Cleaningcomponents

    TrojanSleeve

    Wiping

    System

    forSwiftMPsystem

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    31/45

    UVSystemOperation&Maintenance:

    FromEPAUVDGM:

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    32/45

    UVSystemDesignCriteria

    UVS stemDesi nCriteria:

    Lamp

    technology CleaningSystem owrates UVT

    CombinedDeratin Factor

    for

    End

    of

    Lam

    Life

    (EOLL)andfouledcondition

    No.DutyandStandbyTrains Headloss WaterQualityCharacteristics

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    33/45

    WaterQualityParametersImpactingUVDesignand

    pera on

    arame er es gn mpac mpac

    UVT ReactorSizing;

    Dose

    Basis UV

    Dose/energy

    efficiency

    Iron&

    Manganese

    Treatmentreqd >0.3 mg/L

    Fe,200

    mg/L Lamp fouling;

    energy

    Organics DesignFoulingFactor Lamp fouling;energy

    efficiency;cleaning

    ar c es nergye c ency

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    34/45

    Water

    ualit :

    UVT

    Data120%4.5

    Turbidity UVT

    100%

    3.5

    4.0

    (%)

    )

    Count 76Min 65%

    Avera e 97%

    60%

    2.0

    2.5

    .

    nsmittance

    bid

    ity(NTU Max 100%

    90% 100%

    95% 100%

    10% 95%

    20%

    40%

    1.0

    1.5

    UVTra

    Tur 5 90

    1% 68%

    0%0.0

    0.5

    J09 O09 J10 M10 A10 N10 F11 J11 S11 D11

    RareLowUVTeventscouldimpactdesignrequirements,increasingcost

    Averageenergyusagewillbesignificantlylowerthanduring

    UVT/turbidityevents

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    35/45

    Distribution

    of

    Sam le

    UVT

    6596% 100%

    2

    6

    86% 90%

    91%

    95%

    e

    0

    81% 85%

    %

    )Ran

    071% 75%

    UVT

    1

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    36/45

    Man anese

    Iron

    and

    Hardness

    arame er verage ange o.

    SamplesHardness(mg/LCaCO3) none 38 120 73 21

    Iron 0.3

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    37/45

    DesignCriteriaIdentification:UVSystemCriterion Value

    UVLampTechnology MediumPressure orLowPressureHigh

    Output

    Cleanin S stem Automatic

    DesignFlowrate

    MaximumDesign

    Flow 12

    mgd?

    MinimumDesign Flow 2mgd?

    UltimateDesignFlow 12mgd?

    AverageDesignFlow ?

    DesignUVT

    MinimumValidatedUVT 70%

    DesignUVT@12mgd 85%?

    DesignUVT&6 mgd 70%

    UVT(95th Percentile) 90%

    Com ne Derat ng Factor orEOLLan ou e con t on 0.72

    Minimum No.DutyTrains 2

    MaximumNo.DutyTrains 3

    No.StandbyTrains 1

    SystemOperatingPressure(PSIG)

    SystemDesignPressure(PSIG) 100

    MaximumHeadloss through UVReactor 54inches

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    38/45

    Desi nCriteriaIdentification:Water ualit

    Criterion Value

    Water QualityCharacteristics

    WaterTemperature

    UVTRange 70% 99%

    pH 69

    Iron

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    39/45

    UVDisinfectionSystemSchematic

    UV#1

    From4.5

    MG To3MG

    M

    FMeservo r Reservoir/

    Distribution

    UVT

    UV#2

    UV#3 Stan y

    UV Facility and Generator

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    40/45

    UVFacilityandGenerator

    PossibleLocations

    ro CITY- OISrRlOOT"IONSYSTEM

    14" OVERFLOWIE . 3647.68

    nr - t""" ' r -n \ / r ' \ I r "" ' l Mlntt. tr "

    CITY OFBAKER CITY, OREGONWATER FACILITIES PLAN

    Ill!fl

    ~\\\ll!fl'"T\\

    -12"OR- -

    3.0 MG RES.WS = 3647.68FF = 3620.68

    w - - j ~ : t /.92 MG RES.WS = 3647.68FF = 3634.78

    ORAIN ANDRISER VAULr

    'i 'IIIIIIIIII,IIIG""~ ~()-J-

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    41/45

    2011ProjectEstimate:$2.5M,assuming:

    2,000sf building

    2+1pipingconfiguration

    ,

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    42/45

    IdentifytaskstobeincludedinFY2012Predesign/FinalDesignTO:

    ChlorinationMethod: Improvements

    to

    existing

    chlorine

    gas

    system?

    Conversiontoliquidhypochlorite(onsitegeneratorordeliveredbulkhypo)

    Provisionsforfutureinstallationof

    SCADA/CommunicationsImprovements

    Im rovements in h draulic control

    integrationwith

    UV

    MCCs Communicationsofsystemalarms

    Localandoffsitecontrolpreferences

    ProvisionsforFutureFiltrationFacility

    UVSystemMCCs

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    43/45

    .

    2. UVTechnology

    Preferences

    3. Se ectUVEquipmentProcurement

    Method

    4. Othertasks/evaluationsneededduring

    design

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    44/45

    DataRequest

    EquipmentProcurement:

    ContinuediscussionswithOHA

    PrepareDesignCriteriaTMforOHA

    Investigatehydraulics

    Beginpreparationofprocurementspecs(frontendsandtechnical)

    FinancialPlanning

  • 8/22/2019 UV KickOff Meeting & Technology Workshop, Baker City, OR, January 12, 2012

    45/45