8/10/2019 U.T @ 15.680 ON L.CANAL.xls
http://slidepdf.com/reader/full/ut-15680-on-lcanalxls 1/5
S.No DescriptionLength
mtsBreadth mts
Depth
mts
Qty
cum/kg
Total Qty
cum/kg
FOUNDATION
1CC M10 for Barrel (levelling
coarse)1 x 1 20.280 2.900 0.100 5.88
2 CC M10 U/S wing & return walls
Barrel portion 1 x 2 1.500 2.300 0.450 3.11
Wing walls 1 x 2 5.430 2.000 0.450 9.77
Returns 1 x 2 4.100 2.300 0.450 8.49
3 CC M10 D/S wing & return walls
Barrel portion 1 x 2 2.180 2.350 0.450 4.61
Wing walls 1 x 2 5.150 2.350 0.450 10.89
Returns 1 x 2 2.350 2.350 0.450 4.97
47.72 47.72
4 CC M15 U/S Appron 1 x 1 5.000 (2.2+6.467)/2 0.800 17.34
Dr opwall 1 x 1 6.467 1.700 0.800 8.80
5 CC M15 D/S Appron 1 x 1 5.000 (2.2+4.7)/2 0.300 5.18
1 x 1 4.700 0.150 1.315 0.93
32.23 32.23
SUB STRUCTURE IN M15
6 U/S Wings 1 x 2 1.300 (1.7+0.5)/2 3.362 9.62
1 x 2 5.430 (1.7+0.5)/2 3.362 40.16
7 U/S Returns 1 x 2 3.800 (1.7+0.5)/2 3.362 28.11
8 U/S Drop wall 1 x 1 6.467 (1.7+1.3)/2 0.865 8.39
9 D/S Wings 1 x 2 1.888 (1.75+0.5)/2 3.440 14.61
1 x 2 5.150 (1.75+0.5)/2 3.440 39.86
10 D/S Returns 1 x 2 2.050 (1.75+0.5)/2 3.440 15.87
156.62 156.62
SUPER STRUCTURE
11 RCC M20 for Barrel raft 1 x 1 20.300 2.700 0.250 13.70
RCC M20 for Barrel Side walls 1 x 2 20.300 1.500 0.250 15.23
RCC M20 for Barrel Slab 1 x 1 20.300 2.700 0.250 13.70
12 RCC M20 for Haunches 1 x 4 20.300 0.075 0.150 0.91
43.54 43.54
CC M25 for Wearing Coat
13 Barrel 1 x 1 20.300 2.200 0.075 3.35
14 U/S 1 x 1 5.000 (6.467+2.2)/2 0.075 1.63
15 D/S 1 x 1 5.000 (2.2+4.7)/2 0.075 1.29
6.27 6.27
16 CC M15 for U/S Head wall 1 x 1 2.700 (1.2+0.5)/2 1.637 3.76
17 CC M15 for D/S Head wall 1 x 1 2.700 (0.65+0.5)/2 0.850 1.32
5.08
18 Weep holes 2 x 10 1.200 24.00
19Silt cleaning by labour on NMR
basis20.00 NMR
UT @ Km. 15.680 ON LEFT CANAL
No's
Page 1 of 5
8/10/2019 U.T @ 15.680 ON L.CANAL.xls
http://slidepdf.com/reader/full/ut-15680-on-lcanalxls 2/5
S.No DescriptionLength
mtsBreadth mts
Depth
mts
Qty
cum/kg
Total Qty
cum/kgNo's
1 Bottom slab Bottom mat
20mm dia @ 120mm c/c 1 x 170 3.000 2.470 1259.70
2 Bottom slab Top mat
16mm dia @ 125mm c/c 1 x 163 2.900 1.580 746.87
3 Top slab Top mat
20mm dia @ 140mm c/c 1 x 145 3.000 2.470 1074.454 Top slab Bottom mat
16mm dia @ 130mm c/c 1 x 156 2.900 1.580 714.79
5 Exterior side wall
16mm dia @ 150mm c/c 2 x 136 2.200 1.580 945.47
6 Interior side wall
L/S 12mm dia @ 150mm c/c 1 x 136 2.200 0.880 263.30
R/S 12mm dia @ 135mm c/c 1 x 151 2.200 0.880 292.34
7 Haunches
10mm dia @ 300mm c/c 1 x 136 2.100 0.620 177.07
8 Distribution Bars
10mm dia @ 300mm c/c
Top & Bottom slab & Top &
Bottom bars4 x 10 20.200 0.620 500.96
Both Sides 4 x 7 20.200 0.620 350.67
9 Chairs 12mm dia 2 x 36 1.400 0.880 88.70
10 Over laps 10mm dia 4 x 17 0.400 0.620 16.86
6431.18
STEEL
Page 2 of 5
8/10/2019 U.T @ 15.680 ON L.CANAL.xls
http://slidepdf.com/reader/full/ut-15680-on-lcanalxls 3/5
S.No DescriptionLength
mtsBreadth mts
Depth
mts
Qty
cum/kg
Total Qty
cum/kg
FOUNDATION
1CC M10 for Barrel (levelling
coarse)1 x 1 20.280 2.900 0.100 5.88
2 CC M10 U/S wing & return walls
Barrel portion 1 x 2 1.500 2.300 0.450 3.11
Wing walls 1 x 2 5.430 2.000 0.450 9.77
Returns 1 x 2 4.100 2.300 0.450 8.49
3 CC M10 D/S wing & return walls
Barrel portion 1 x 2 2.180 2.350 0.450 4.61
Wing walls 1 x 2 5.150 2.350 0.450 10.89
Returns 1 x 2 2.350 2.350 0.450 4.97
47.72 47.72
4 CC M15 U/S Appron 1 x 1 5.000 (2.2+6.467)/2 0.800 17.34
1 x 1 6.467 1.700 0.800 8.80
5 CC M15 D/S Appron 1 x 1 5.000 (2.2+4.7)/2 0.300 5.18
1 x 1 4.700 0.150 1.315 0.93
32.23 32.23
SUB STRUCTURE IN M15
6 U/S Wings 1 x 2 1.300 (1.7+0.5)/2 3.362 9.62
1 x 2 5.430 (1.7+0.5)/2 3.362 40.16
7 U/S Returns 1 x 2 3.800 (1.7+0.5)/2 3.362 28.11
8 U/S Drop wall 1 x 1 6.467 (1.7+1.3)/2 0.865 8.39
9 D/S Wings 1 x 2 1.888 (1.75+0.5)/2 3.440 14.61
1 x 2 5.150 (1.75+0.5)/2 3.440 39.86
10 D/S Returns 1 x 2 2.050 (1.75+0.5)/2 3.440 15.87
156.62 156.62
11 RCC M20 for Barrel raft 1 x 1 20.300 2.700 0.250 13.70
RCC M20 for Barrel Side walls 1 x 2 20.300 1.500 0.250 15.23
RCC M20 for Barrel Slab 1 x 1 20.300 2.700 0.250 13.70
12 RCC M20 for Haunches 1 x 4 20.300 0.075 0.150 0.91
43.54 43.54
CC M25 for Wearing Coat
13 Barrel 1 x 1 20.300 2.200 0.075 3.35
14 U/S 1 x 1 5.000 (6.467+2.2)/2 0.075 1.63
15 D/S 1 x 1 5.000 (2.2+4.7)/2 0.075 1.29
6.27
16 CC M15 for U/S Head wall 1 x 1 2.700 (1.2+0.5)/2 1.637 3.76
17 CC M15 for D/S Head wall 1 x 1 2.700 (0.65+0.5)/2 0.850 1.32
5.08 5.08
18 Weep holes 2 x 12 1.200 28.80 28.80
UT @ Km. 15.680 ON LEFT CANAL
No's
STEEL
SUPER STRUCTURE
Page 3 of 5
8/10/2019 U.T @ 15.680 ON L.CANAL.xls
http://slidepdf.com/reader/full/ut-15680-on-lcanalxls 4/5
S.No DescriptionLength
mtsBreadth mts
Depth
mts
Qty
cum/kg
Total Qty
cum/kgNo's
1 Bottom slab Bottom mat
20mm dia @ 120mm c/c 1 x 170 3.000 2.470 1259.70
2 Bottom slab Top mat
16mm dia @ 125mm c/c 1 x 163 2.900 1.580 746.87
3 Top slab Top mat
20mm dia @ 140mm c/c 1 x 145 3.000 2.470 1074.45
4 Top slab Bottom mat16mm dia @ 130mm c/c 1 x 156 2.900 1.580 714.79
5 Exterior side wall
16mm dia @ 150mm c/c 2 x 136 2.200 1.580 945.47
6 Interior side wall
L/S 12mm dia @ 150mm c/c 1 x 136 2.200 0.880 263.30
R/S 12mm dia @ 135mm c/c 1 x 151 2.200 0.880 292.34
7 Haunches
10mm dia @ 300mm c/c 1 x 272 2.100 0.620 354.14
8 Distribution Bars
10mm dia @ 300mm c/c
Top & Bottom slab & Top &
Bottom bars4 x 10 20.200 0.620 500.96
Both Sides 4 x 7 20.200 0.620 350.67
9 Chairs 12mm dia 2 x 36 1.400 0.880 88.70
10 Over laps 10mm dia 4 x 17 0.400 0.620 16.86
6608.26
Page 4 of 5
8/10/2019 U.T @ 15.680 ON L.CANAL.xls
http://slidepdf.com/reader/full/ut-15680-on-lcanalxls 5/5
S.No DescriptionLength
mtsBreadth mts
Depth
mts
Qty
cum/kg
EARTH WORK EXCAVATION
1 Barrel Bed 1 x 1 20.280 4.100 3.200 266.07
2 U/S wing & return walls
Barrel 1 x 2 1.500 3.500 2.250 23.63
Slant 1 x 2 5.430 3.200 2.250 78.19
Returns 1 x 2 4.100 3.500 2.250 64.58
3 U/S Appron 1 x 1 5.000 (2.2+6.467)/2 2.250 48.76
1 x 1 6.467 2.300 2.250 33.47
4 D/S wing & return walls
1 x 2 2.180 3.550 2.700 41.79
1 x 2 5.150 3.550 2.700 98.73
1 x 2 2.350 3.550 2.700 45.05
5 D/S Appron 1 x 1 5.000 (2.2+4.7)/2 2.700 46.58
1 x 1 4.700 1.350 2.700 17.13
6Diversion for Vagu
1 x 1 30.000 2.500 2.000 150.00
7U/S & D/S Bund formation for
vagu portion1 x 2 40.000 4.000 2.200 704.00
1617.96
UT @ Km. 15.680 ON LEFT CANAL
No's
TOTAL QTY = 1617.96cum
UP TO Aug = 529.50cum
Balance Qty = 1617.96 - 529.50 = 1088.46cum
Page 5 of 5