48
1 Study for FHWA by AgileAssets with: o Ronald Hudson, Charles Dougan, Carl Monismith and Pim Visser o FHWA participation by Steve Gaj, Sonya Hill, Kathy Petros, Leslie Myers & Gary Crawford DOT’s of MS, WA, KS, and FL have been visited in 1 st phase Great interest from States resulted in extension with visits to NC, PA, MN and NM Using PMS Data to Calibrate & Validate the New Guide (MEPDG)

Using PMS Data to Calibrate & Validate ... - Transportation

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Using PMS Data to Calibrate & Validate ... - Transportation

1

Study for FHWA by AgileAssets with:o Ronald Hudson, Charles Dougan, Carl

Monismith and Pim Vissero FHWA participation by Steve Gaj, Sonya

Hill, Kathy Petros, Leslie Myers & Gary Crawford

DOT’s of MS, WA, KS, and FL have been visited in 1st phaseGreat interest from States resulted in extension with visits to NC, PA, MN and NM

Using PMS Data to Calibrate & Validate the New Guide (MEPDG)

Page 2: Using PMS Data to Calibrate & Validate ... - Transportation

2

Is a coordinated systematic process forcarrying out all activitiesrelated to providing pavements

Pavement Management

Page 3: Using PMS Data to Calibrate & Validate ... - Transportation

3

Pavement Management System

Rational procedures that provide optimum pavement strategies based on predicted pavement performance incorporating feedback regarding the various attributes, criteria, and constraints involved.

Page 4: Using PMS Data to Calibrate & Validate ... - Transportation

4

Let’s Review Pavement Management

Formalization of pavement decision makingEntire process to provide quality pavementsStrong emphasis on economics Involves all associated groups

Planning, Design, Construction, Maintenance, Materials, Field Groups.

Uses advanced tools and analysis techniques

Page 5: Using PMS Data to Calibrate & Validate ... - Transportation

5

General Structure of Systematic Pavement Management :

Coordinated modules at several organizationallevels accessing acommon database

Page 6: Using PMS Data to Calibrate & Validate ... - Transportation

6

Components of PMS

Engineering ApplicationsResearch - Special Studies

PMS

DesignDATA

BASE

NETWORK LEVEL

Rehabilitation

ProgrammingPROJECT LEVEL

Planning

Budget

Construction

Maintenance

Broader Management Concerns

Page 7: Using PMS Data to Calibrate & Validate ... - Transportation

7

Purpose of PMS Engineering Analysis

The use of pavement management data to evaluate and improve structural designs, materials, mix designs, construction, preservation strategies, rehabilitation, and preventive maintenance of pavements.

Page 8: Using PMS Data to Calibrate & Validate ... - Transportation

8

INPUTS• Traffic• Materials• Thickness

Models

Behavior Distress Performance

Costs

Safety

Traffic Counts & Weights

Condition Surveys

RoughnessPSI

Update Models•Test Pits

•Lab Tests

•Count•Weigh•Classification

•Rainfall•Temperature

RECORD• Construction• Maintenance

LONG-TERMDATABASE

&ANALYSIS

Deflection

Page 9: Using PMS Data to Calibrate & Validate ... - Transportation

9

PMS Conceived as Framework to Design for Local EnvironmentObjectives of early studies in 1960’s:o Develop descriptions of material

propertieso Develop measuring properties for

pavement design and evaluationo Develop pavement design methods using

measured material properties, for all locations, environments & traffic loads.

Goal: formulate overall pavement problem in broad conceptual and theoretical terms

Page 10: Using PMS Data to Calibrate & Validate ... - Transportation

10

Project Level Pavement Design Method

- -Materials

Coefficients

PerformancePSI IRI

Decision Criteria

Implementation

Multiple Runs

Apply Life Cycle Cost

Select Design

Calibration

C1, C2, C3C3

PredictedTrafficLoads

DesignModels

(Equations)

BehaviorStress Strain

Deflection

DistressesCrack RutDeformation

Rate ofDistress

Progression

InputsClimate

As-builtsTraffic Loads

C1 C2

TrafficDivisionModels

ForDesign

Page 11: Using PMS Data to Calibrate & Validate ... - Transportation

11

How Does PMS Relate To Your Engineering Activities

Pavement (overlay) design analysisMaterials & construction methodsPreventive maintenancePavement preservation strategies Pavement maintenance management

Page 12: Using PMS Data to Calibrate & Validate ... - Transportation

12

Concept for Linking Databases

Pavement Design

ElectronicMaterials &

ConstructionData Base

ElectronicPMS

Data BaseElectronic

Performance Analysis Data

Base

PERFORMANCEANALYSIS FOR

VARIOUSCONDITIONS

Climate & Environment

Traffic Information

Page 13: Using PMS Data to Calibrate & Validate ... - Transportation

13

• Common referencing is needed with Project Number, exact Location and Date

• Location with mile post or GPS, Lane and Direction

• Climate and Traffic (ESAL and ADT) Data• Age of original pavement and last rehab date• Type of wearing course• Performance Data for various distresses,

should be linked to exact location

Electronic PMS Database

Page 14: Using PMS Data to Calibrate & Validate ... - Transportation

14

Electronic Materials and Construction Database

• Common referencing is needed with Project Number, exact Location and Date

• Batch numbers should be linked to location• Mix data, as designed and in-place• Layer thicknesses, designed and as-built• Subgrade information• Drainage details• Other materials information and construction

details• Effects of maintenance activities

Page 15: Using PMS Data to Calibrate & Validate ... - Transportation

15

Electronic Performance Analysis Database Created by Linking

• Common referencing is needed with Project Number, exact Location and Date

• Essential materials and construction data linked to performance data through common referencing

• Possible to study effects of materials, construction techniques, traffic loads, climate, thickness design, etc.

Page 16: Using PMS Data to Calibrate & Validate ... - Transportation

16

Sources of Engineering Data other than from PMS database

• Research data files• Construction records• Material test records• Additional field evaluations• Project plans• Additional structural evaluation

and/or materials testing • Expert opinion• Maintenance Management Systems

Page 17: Using PMS Data to Calibrate & Validate ... - Transportation

17

Current Limitations (1of 2)• In most cases the materials,

construction, and maintenance data are not now tied to PMS activities.

• Many agencies store materials and construction data in flat files, so transfer and analysis of data is hard to do.

• Not all relevant data are recorded (e.g. in-place thickness is often missing).

• Linking materials and construction data to an exact location is often difficult.

Page 18: Using PMS Data to Calibrate & Validate ... - Transportation

18

• Performance data are often averaged over a mile. Distress is often sampled over short distances, e.g. milepost only. Normally only one lane is measured.

• Therefore difficult to link performance data to materials and construction data.

• Maintenance activities could distort the analysis if not properly recorded and referenced.

Current Limitations (2 of 2)

Page 19: Using PMS Data to Calibrate & Validate ... - Transportation

19

• Good meetings with eight States• Excellent coordination with NCHRP projects:

• 1-40b Local Calibration Guidance for the Recommended Guide for M/E Design of New and Rehabilitated Pavements and its PI, Harold Von Quintus

• 9-30 Experimental Plan for Calibration and Validation of HMA Performance Models for Mix & Structural Design

• Drafting of Final Report• Monitoring of FHWA “Community of Practice”

website, a forum for users to discuss the MEPDG

Main Activities So Far

Page 20: Using PMS Data to Calibrate & Validate ... - Transportation

20

• Many States have capability for long termcalibration using PMS data, not for short term

• Two States are awaiting “Release 1.0”, the corrected version of the software for the MEPDG in March-April 2006

• Several States are making extensive runs with the software to gain knowledge, particularly for engineering analysis and forensic studies

• Most States plan Level 2 input data for most of their variables, based on correlation and/or laboratory studies of their most typical materials

Preliminary Findings - 1

Page 21: Using PMS Data to Calibrate & Validate ... - Transportation

21

• Required traffic data are generally available, but usually in a different Section or Division which requires coordination. Generally expect Level 3 or Level 2 data pieced together from existing data

• Many States reported problems keeping WIM sites operational. Piezo-quartz are preferred, but accuracy ranges from 10 – 15%

• Most States find it hard to assemble all required materials data, particularly those obtained from sophisticated laboratory equipment. In many cases States plan to use facilities at Universities.

Preliminary Findings - 2

Page 22: Using PMS Data to Calibrate & Validate ... - Transportation

22

• Several States have ongoing contracts with consultants for implementing the MEPDG.

• Some States sponsor research on material properties, development of performance models & calibration/validation of the Guide at Universities.

• Most States are disappointed with the treatment of rehabilitation and overlay design in the MEPDG

• Prospects for calibration seems better when there is a close organizational tie within a DOT between pavement management and pavement design

Preliminary Findings - 3

Page 23: Using PMS Data to Calibrate & Validate ... - Transportation

23

Calibration/ValidationPMS calibration will require setting up new data fields for Sections designed and built using the MEPDG for all input parameters, including:• Design values for all relevant parameters• As-constructed values for the same

parameters• Annual measurements and records of traffic

load spectra• Annual weather data or tie to NOAA

Page 24: Using PMS Data to Calibrate & Validate ... - Transportation

24

Design Input Levels

• Level 1– Use of site specific materials, environment,

and traffic characteristics; material characteristics from laboratory tests

• Level 2– Use of less detailed information

• Level 3– Use of default values

Page 25: Using PMS Data to Calibrate & Validate ... - Transportation

25

Design Inputs

• Climate/Environment• Traffic• Materials• Reliability and Construction

Considerations

Page 26: Using PMS Data to Calibrate & Validate ... - Transportation

26

Input Parameters for MEPDG1. General Inputs: Project name, ID, Dates,

Design life, Limits & Reliability for Performance, Distress.

2. Traffic Inputs: Projected AADT, Growth, Volume adjustment, Axle load distribution, Etc

3. Predicted Climate Inputs from ICM4. Structural Inputs: PCC design features,

Drainage & surface properties, Layers, Material properties, Thermal cracking, Distress potential

A total of at least 150 parameters are required

Page 27: Using PMS Data to Calibrate & Validate ... - Transportation

27

Input Parameters for Calibration1. General Inputs: Project name, ID, Dates,

Design life, Annual Data on Performance, Distress, Deflection

2. Traffic Inputs: Annual data for AADT, Growth, Volume adjustment, Axle load distribution, etc

3. Actual Climate Inputs from ICM4. Structural Inputs: Actual surface & drainage

properties, Actual layer thicknesses, As-built & aged Material properties, Actual Thermal cracking

A total of several 100 parameters are required

Page 28: Using PMS Data to Calibrate & Validate ... - Transportation

28

Synthesis of Findings from Eight State DOTs

One of the main challenges in using the MEPDG and validating and calibrating the design method and its various prediction models, is to access / collect / find / measure / organize the many input parameters for the system

Page 29: Using PMS Data to Calibrate & Validate ... - Transportation

29

Analysis1. Assemble Database for adequate number of

sections,2. The more sections the better, large sample

statistics very powerful,3. Several States can combine Data with good

coordination at the national level,4. Effects of all variables present in the

Database can be evaluated and analyzed,5. Early start provides impetus to enter data

early – No “build-up” of backlog.

Page 30: Using PMS Data to Calibrate & Validate ... - Transportation

30

Final Report

Our Final Report synthesizes a viable plan to set up a long-term enhanced database for new Sections to be used for calibration. Prior data from existing Sections will only be useful if they can be used for enhancement of these new Calibration Sections.

Page 31: Using PMS Data to Calibrate & Validate ... - Transportation

31

• Hudson, W. R., P. Visser, C. Monismith, C. Dougan, “Using Pavement Management Data to Calibrate and Validate the New MEPDG, An Eight State Study,” Final Report, Volumes I and II, FHWA Contract DTFH 61-05-C-00011, September 30, 2006.

• Hudson W. R., P. Visser, C. L. Monismith, and C.E. Dougan,“Evaluating Superpave Using Performance, Materials, and Construction Data for Task Order 34,” Final Report, US Department of Transportation, FHWA, Contract DTFH61-98-C-00075, Battelle Subcontract 180686, November 30, 2004.

• “Method of Evaluating the Performance of Superpave using the Pavement Management Database,” FHWA Contract No. DTFH61-98-C-00075, November 2004.

• Hudson, W. R., P. Visser, C. L. Monismith, and C.E. Dougan, “Use of PMS Data for Performance Monitoring with Superpave as an Example,” Final Report, US Department of Transportation, Contract DTFH61-98-C-00075, B98C75-007, Battelle Subcontract 156421, March 20, 2002.

Page 32: Using PMS Data to Calibrate & Validate ... - Transportation

32

• Valid Sensitivity Analyses involving so many variables are very difficult due to complex interaction of variables.

• Many over-simplified Sensitivity Analyses are being done – waste of money.

Page 33: Using PMS Data to Calibrate & Validate ... - Transportation

33

Using up to 150 Default Values can completely mask the true effects

of many important variables.

Page 34: Using PMS Data to Calibrate & Validate ... - Transportation

34

Level 1 Measured Value

“True”

The Level 1 Mean Value is the “Best Available” Estimate..

Page 35: Using PMS Data to Calibrate & Validate ... - Transportation

35

The Level 2 Mean Value may be greatly in error as well as Greater Variability

?

Level 1 Measured Value

“True”

Level 2

Page 36: Using PMS Data to Calibrate & Validate ... - Transportation

36

Level 2Estimate

Level 3Default Value

?

Level 1 Measured Value

“True”

?

The Level 3 “Default” Mean Value has even greater potential errorIn the Mean and Variance

Page 37: Using PMS Data to Calibrate & Validate ... - Transportation

37

Once we start using “easy” Default Values, it is hard to move on to the

tough job of Real Measurements and Data

Collection.

Page 38: Using PMS Data to Calibrate & Validate ... - Transportation

38

For ExampleIn the very first AASHTO

Guide we provided default values for Materials Coef. for SN (Structural Number) with a

note, “You must test to determine your own.”

Page 39: Using PMS Data to Calibrate & Validate ... - Transportation

39

As late as 2002, I worked with designers all over

the world using the Guide. After 40 years,

many still use the Default Values.

Page 40: Using PMS Data to Calibrate & Validate ... - Transportation

40

Even in the important LTPP program, started 19 years ago, somewhere between

25 and 50% of the so-called research data is assumed,

estimated, or adjusted from raw observed data.

An Example

Page 41: Using PMS Data to Calibrate & Validate ... - Transportation

41

Men occasionally stumble over the truth, but most of them pick themselves up and hurry off as if nothing ever happened.

- Sir Winston Churchill

Page 42: Using PMS Data to Calibrate & Validate ... - Transportation

42

Perhaps the biggest benefit of the New MEPDG is that it can help bring Design and

Pavement Management back together as they were originally envisioned.

Page 43: Using PMS Data to Calibrate & Validate ... - Transportation

43

Page 44: Using PMS Data to Calibrate & Validate ... - Transportation

44

The New MEPDG is doomed to be a minor

analysis tool if we don’t take valid data collection

seriously and quickly.

Page 45: Using PMS Data to Calibrate & Validate ... - Transportation

45

The MEPDG will be most useful if Agencies can be convinced to centralize its use as a good theoretical

tool, the way Bridge Design has always been done.

Page 46: Using PMS Data to Calibrate & Validate ... - Transportation

46

Don’t start vast

projects with half vast

ideas

Page 47: Using PMS Data to Calibrate & Validate ... - Transportation

47

1. We have spent an estimated $7 or 8 million to define a complex, more “precise” analysis tool.

2. Only adequate calibration will make it “accurate.”

3. It is also essential that we spend the required effort and money to gather INPUT DATA that matches the precision and accuracy of the Guide.

Page 48: Using PMS Data to Calibrate & Validate ... - Transportation

48

Whatever you vividly Imagine, ardently Desire,

sincerely Believe, and enthusiastically Act upon…

must inevitably come to pass

- Paul J. Meyer