6
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. Using MsProject for Earned Value Calculations Advanced MsProject Course Dr. Leigh Geiger

Using MsProject for Earned Value Calculations

Embed Size (px)

DESCRIPTION

Using MsProject for Earned Value Calculations. Advanced MsProject Course Dr. Leigh Geiger. Set Up Process. Create Project Plan Baseline the Plan Track progress/actuals & update the plan Set the Status Date Select the Earned Value method Use MsProject EV Views & Reports. Set Up Process. - PowerPoint PPT Presentation

Citation preview

Page 1: Using MsProject for  Earned Value Calculations

© Copyright, 2009, S. Leigh Geiger & Associates, Inc.

Using MsProject for Earned Value Calculations

Advanced MsProject Course

Dr. Leigh Geiger

Page 2: Using MsProject for  Earned Value Calculations

© Copyright, 2009, S. Leigh Geiger & Associates, Inc.

Set Up Process

1. Create Project Plan

2. Baseline the Plan

3. Track progress/actuals & update the plan

4. Set the Status Date

5. Select the Earned Value method

6. Use MsProject EV Views & Reports

Page 3: Using MsProject for  Earned Value Calculations

© Copyright, 2009, S. Leigh Geiger & Associates, Inc.

Set Up Process

Create Project Plan Baseline the Plan Track progress/actuals & update the plan

4. Set the Status Date

5. Select the Earned Value method

6. Use MsProject EV Views & Reports

Page 4: Using MsProject for  Earned Value Calculations

© Copyright, 2009, S. Leigh Geiger & Associates, Inc.

Earned Value Methods

% Complete Calculated for each task: [Act Dur/Dur]*100 If you enter it directly -Project calculates Act. & Rem.

Duration Use if actual work is entered

Physical % Complete Not calculated, must be entered directly Use if Actuals aren’t accurate

Possible to use up 90% of total task duration and still be only 10% Physical Complete, e.g., when most work is planned for the last minute.

Page 5: Using MsProject for  Earned Value Calculations

© Copyright, 2009, S. Leigh Geiger & Associates, Inc.

EV Terms in Project

Old Term New Term

BCWS PV

BCWP EV

ACWP AC

Page 6: Using MsProject for  Earned Value Calculations

© Copyright, 2009, S. Leigh Geiger & Associates, Inc.

EV Views & Reports

Table Views Earned Value Earned Value Cost Indicators Earned Value Schedule Indicators

Cost Reports Earned Value

Visual Reports EV Over Time