JSE Colocation Services Communication
20 November 2013
These slides may not be
used in any manner
without prior written
permission from the JSE
Welcome to the
JSE Market Communication Broadcast
Session start: 11h00 SAST (GMT+2)
Teleconference number: +27 87 350 0288
Conference ID: 677002#
JSE moderator will dial in at 10h55 SAST
http://www.jse.co.za/Markets/Equity-
Market/Broadcast-Page.aspx
2
Copyright© JSE Limited 2011
www.jse.co.za
Agenda
Colocation Services Schedules
• Colocation Services Schedules
Colocation Services
• Update
• Summary
General
• Non-Display Data Usage
• 2014 Key Market Facing Dates
• High Level Timeline
Questions
4
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services Schedules
Thank you to all customers for the feedback on the draft JSE Colocation
Services Schedules
The JSE will provide written feedback to each customer on the their
comments raised by the end of the week
It should be noted that the current JSA is not being amended with the
introduction of the Colocation Service, all comments raised relating to the
JSA will be taken into consideration when a JSA review is conducted
Final Colocation Services Schedules 1F and 2F are now available and have
been issued to all customers who have signed the JSE Letter of Undertaking
Customers wishing to make use of the Colocation Services must sign a JSA
and the Colocation Services Schedules. If the customer has already signed a
JSA then they only need to sign the Colocation Services Schedules
Please send an email request for a copy of the new schedules to your
Account Manager or [email protected]
5
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA) – Schedule 1F
This schedule must be signed prior to any take-on activity for the customer
Key Terms and Conditions in addition to JSA
• Initial contract period is 12 months from the effective date
• Thereafter, an annual automatic 12 month renewal unless notice provided
• For primary services, 2 months written notice period required – termination to be
effective at end of the initial or renewal period
• For additional services (associated and secondary services), termination at any
time with 30 days written notice
• Provision of Services linked to lease of JSE premises
• If the JSE has no HUs available and the Customer’s HU remains “dormant” for 60
consecutive days, the service can be terminated by the JSE
• JSE can relocate Customer Equipment to a different HU subject to reasonable
notice and at JSE’s cost
• No Colocation Services at JSE remote disaster recovery site
6
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA) – Schedule 1F
This schedule must be signed prior to any take-on activity for the customer
Key Terms and Conditions in addition to JSA contd.
• Network Round Trip Latency is a contracted service level and is the average daily
round trip network latency of 100µs over a calendar month and is measured
between the Colocation Network and the Equity Market Gateways
• Services Fees as per current JSA can only be revised annually excluding the
electricity consumption component
» if increased by more than CPI (60 days notice), Customer can terminate by giving JSE 30
days notice as long as notice is given within the 60 days
» if methodology change (90 days notice), Customer can terminate by giving JSE 30 days
notice as long as notice is given within the 90 days
• Electricity consumption is charged for separately and is subject to any revised
charges or rates as notified by the Municipality of the City of Johannesburg or
Energy Regulator of South Africa or other authorised body
» Fees related to power consumption come into effect from the day the equipment is
installed into the Colocation environment and starts to consume power
7
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA) – Schedule 1F
Customer Obligations
• Ensure Customer Services Order Form (CSOF) is up-to-date and accurate at all
times – CSOF will be issued shortly
• Access will only be authorised if all correct agreements and authorisations are in
place e.g. Membership, JSE Data Agreements, JSE SIP agreement, Sub-Lessee
approval etc.
• Ensure electricity consumption remains within the defined power usage thresholds
in the Services Documentation. In the event of a continuous breach of the
thresholds, customers will need to ensure adequate remedial actions are taken
• Customers must insure their own equipment - JSE will not be liable for loss
• Ensure compliance with all laws and regulations applicable as well as the JSE
policies and Services Documentation
8
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA) – Schedule 1F
Colocation Services Order Form (CSOF) details all Colocation Primary,
Associated and Secondary Services elected by the customer
• Colocation Primary Services
» The number of Hosting Units (HU)
» Power Consumption required per HU e.g. 3.3kVA = 3kW or 5.5kVA = 5kW
» Required Trading and/or Market Data Connectivity per market
» Remote management connectivity from the Access Network
» Network latency monitoring
• Colocation Associated Services
» HU initial setup
» Remote hands support
» Remote management connectivity through the JSE London PoP and bandwidth
9
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA) – Schedule 1F
Colocation Services Order Form (CSOF) details all Colocation Primary,
Associated and Secondary Services elected by the customer contd.
• Colocation Secondary Services
» Inter-connects
» Cross connects
» Sub-letting
» Additional network latency monitoring
» Time sync service
» Additional ports
» HU cable troughs and shelves
10
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA) – Schedule 2F
Colocation Services - Schedule 2F
• Outlines Service Level Guidelines:
» Network latency monitoring and reporting
» Power consumption reporting
» Access to Hosting Units
» Production implementation
» Cross connect requests
» General customer support items and contact details
11
Copyright© JSE Limited 2011
www.jse.co.za
JSE Services Agreement (JSA)
To form part of the initial take-on for go live - signed JSA and Colocation
Services Schedules must be signed by the end of January 2014
Completed Colocation Services Schedules can be sent to
[email protected] (as per current JSA process)
A request has been received for a fee calculator for the Colocation Services –
JSE will look into the possibility of providing this to customers in the future
13
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services
Colocation Services updates made recently
• Power
» Due to Customer demand for additional power in HUs, the JSE investigated options to
offer additional power to customers who require it
» JSE will now offer either 3kW and/or 5kW HUs
» In the original build out of 35 HUs there will be 18 x 3kW HUs and 17 x 5kW HUs
» Additional costs are required to accommodate the 5kW HUs (PDUs, cooling, etc.) as well
as to standardise on the HU size resulting in a reduction of the total number of HUs being
available
• Time Sync Service with PTP
» Due to Customer demand for more accurate time syncing to microseconds
14
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Summary
Colocation Services Documentation
• Document is available on the JSE Colocation Page of the website
Customer Eligibility
• Members
• Member Clients
• Information Subscribers
• Shared Infrastructure Providers (SIPs)
Colocation available for all JSE markets
Fees and Billing
• Prorated billing is applicable where relevant
• Relevant agreements and authorisations must be in place prior to go live in
production
15
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Summary
Limited Capacity
• HUs will be provided on a first come first served basis
• HUs can only be secured once all signed agreements are in place
• Once the full capacity has been reached there will no further opportunity to make
additional HUs available
JSE will ensure fairness and service equality to all Customers subscribing to
the same services
Test services will only be facilitated through the Access Network – no access
from Colocation can be facilitated
16
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Primary Service Summary
Hosting Units
• Included as part of the monthly Primary Services fee
• Will be locked, access will be granted to authorised persons only
• Only full HUs will be allowed
• Size - width x depth = 600mm x 1070mm
• HU fee includes the Power Distribution Consumption Unit i.e. PDU but not the
electricity consumption usage fees
Access to JSE Markets
• 8 access ports available as part of the monthly Primary Services fee:
» 4 x Equity Market ports via fibre connectivity for Trading and Market Data access
» 2 x Derivative Market ports via fibre connectivity for Trading and Market Data access
» 2 x Remote Management connectivity ports
17
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Primary Service Summary
Network Latency Monitoring
• Performed during Trading Hours (06h00 to 19h00)
• Reporting will be provided to customers
Power
• Consumption is monitored daily and is excluded from the monthly Primary
Services fee and will be separately charged for
• Fully redundant power feeds to HUs
• 32 Amp single phase Raritan PDUs – only the PDU fee is included in the monthly
Primary Services fee
• PDU specification details – 20 x C13 and 4 x C19 plug types per PDU
• Power correction equipment implemented and therefore correction factor of 0.9 is
applied
18
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Primary Service Summary
Power contd.
• Original monthly power consumption calculation based on
» 3.3 kVA X 8 hours X 5 days
» 3.3 kVA X 50% X 16 hours X 5 days
» 3.3 kVA X 50% X 24 hours X 2 days
• Usage for a 3 kW HU
» R1.53 for consumption <= 1344 kWh
» R3.70 for consumption > 1344 kWh to the maximum cap of 2160 kWh
• Usage for a 5 kW HU
» R1.53 for consumption <= 2240 kWh
» R3.70 for consumption > 2240 kWh to the maximum cap of 3600 kWh
Note: kilovolt-amps (kVA) = kilowatts (kW) / PowerFactor (PF) therefore 3kW / 0.9 = 3.3kVA
19
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Associated Services Summary
Hosting Unit Initial setup
• Once off fee applicable for setup in Colocation
• Includes requirements gathering and design advice
• Caters for a maximum of 12 hours setup (set up may not be staggered)
Remote Hands Support
• Available on business days on a first come first served basis:
» Business days during Trading Hours
» Emergency changes only, visual inspection, power cycling and cable diagnostics
» Business days during non-Trading Hours
» Planned changes and emergency changes
» Including but not limited to visual inspection, power cycling, cross connect
installation, initial setup, maintenance to the hosting unit and basic testing of devices
and cables
• Not available on non business days unless it is an emergency
20
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Associated Services Summary
Remote Management Connectivity via JSE London PoP
• Enables connectivity via the JSE London PoP to remotely manage equipment
residing in Colocation
• Requires 5 additional production ports unless already connected to JSE London
PoP
» Production port fees - 1 x SA and 1 x UK
» Secondary port fees - 1 x SA and 1 x UK
» Remote disaster recovery port fees - 1 x SA
• Additional fees applicable
» Fees for international bandwidth as required for remote management to Colocation
• JSE London PoP being upgraded to cater for remote management connectivity and
2 cut over dates for Customers available (5 Apr 2014 and 3 May 2014)
21
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Secondary Services Summary
Inter-Connect
• Cable connections between devices within a HU and between HUs of the same
Customer
• JSE approved cable troughs can be ordered and installed by the JSE
• Customers responsible for purchasing and installing inter-connect cables
• If a Customer rents multiple HUs which are not adjacent to each other in the same
row, then Cross Connects will be required with the applicable fees
Cross Connects
• Cable connections between HUs and/or the JSE meet me room
• Correct authorisation must be received prior to installation of Cross Connects
• JSE approved cross connect cables will be installed
• Initial setup and monthly cross connect fees are applicable as per the price list
• A Cross Connect is required to facilitate connectivity from the meet me room to the
HU for remote management connectivity
22
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Secondary Services Summary
Sub-letting
• Sub-letting is subject to the terms and conditions in the JSA and Services
Schedules
• Sub-letting allowed for:
» Member to Member Client
» Information Subscriber to Information Subscriber client i.e. member or member client if
accredited Shared Infrastructure Provider (SIP)
» Accredited SIP to Member
» Any changes to sub-letting must be approved by the JSE prior to changes being
implemented in production
Additional Network Latency Monitoring
• Latency monitoring from the HU to the Colocation network switch can be performed
for a limited period only on request and is subject to an additional fee
• Quotes will be provided as and when required (submit request to Customer
Support)
23
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Secondary Services Summary
Time Synchronisation Service
• Time synchronisation to Precision Time Protocol (PTP) or Network Time Protocol
(NTP)
• PTP option requires PTP server adapters to increase the accuracy from
milliseconds to microseconds or a PTP client installed by the customer
• The adapter will be used for normal network traffic
Additional Ports
• Additional ports can be requested and fees will be applicable
• Port requests will be subject to availability on the JSE and Customer infrastructure
to accommodate the additional ports
• If there are no available ports on the JSE Infrastructure, a lead time is required to
procure additional JSE infrastructure
24
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Summary
Customer Setup
• Customer setup or maintenance will involve 3 stages
» Data centre rack and stack activities to ensure HU setup
» Network connectivity tests to prove HU connectivity within the Colocation network
» Enablement of application connectivity to services of the JSE which will include a live
connectivity test to prove enablements and application connectivity to Gateways / Proxies
• Customer setup in Colocation follows a similar process to the current enablement
process i.e. order form submission, Customer Enablement Information Form (CEIF)
approval prior to Live Connectivity Test (LCON) etc.
• A detailed walkthrough will be provided to customers during a Technical Working
Group (TWG) session, once the CSOF template is available
25
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Summary
Change Management
• Emergency and Planned changes
• High level change process as per Services Documentation which includes best
practise standards for implementation of changes into a production environment
• No changes will be allowed without the correct documentation or approval in place
• Summary of change activities permitted / not permitted
» Trading hours
» No changes except critical approved emergency changes
» Equipment installation, setup and connectivity will not be permitted
» Non-trading hours
» Approved planned and emergency changes
» Equipment installation, setup and connectivity will be permitted
» Non Business days
» No changes except critical approved emergency changes
» Equipment installation, setup and connectivity will not be permitted
26
Copyright© JSE Limited 2011
www.jse.co.za
Colocation Services - Summary
Additional information included in Services Documentation
• Facility features and procedures for cabling, equipment, storage and
implementation
• Access control and security will be enforced and allowed for authorised persons
only
» Cell phone usage in the data centre is allowed and one landline is available (local calls
only)
» Valid identification will be required
» No photographs, food or drink permitted into the data centre
» Compliance to defined procedures is required
» Temporary access will only be permitted with the correct security forms in place
28
Copyright© JSE Limited 2011
www.jse.co.za
Market Data Non-Display Usage
Market Data Non-Display Usage:
• A party that uses select JSE data in a Non-Display way is obliged, before using the
JSE data, to have the usage covered under a JSE market data agreement and pay
Non-Display market data usage fees
• Market data usage fees are separate to Colocation fees
• Non-Display usage fees apply to all customers making use of JSE Services
including Colocation i.e. applicable to Colocation customers and clients of a
Colocation customer
• Colocation customers must therefore ensure their clients are informed of the JSE
market data usage implications. Customers must notify the Market Data division
(MDD) via email of clients requesting JSE data, the data type(s) requested as well
as contact details of the client – mailto: [email protected]
• MDD will verify the usage of Non-Display data, required contracts and
commercials, once all these are in place, customers can begin using data
• Any changes thereafter to the data usage will be the responsibility of the directly
contracted customer
29
Copyright© JSE Limited 2011
www.jse.co.za
2014 Key Market Facing Dates
Critical production changes scheduled for Jan 2014
# Date Description Participation
Equity Market Production Resources Upgrade i.e
memory, cpu etc.
Trading Switch replacement (3K)
Prod firewall & NW routing changes
(VDC/Firewall)
Implementation of Network monitoring taps
1
18 Jan 2014
Contingency:
25 Jan 2014
All Markets
- All Clients for connectivity
tests
30
Copyright© JSE Limited 2011
www.jse.co.za
2014 Key Market Facing Dates
Critical production changes scheduled for Feb/Mar 2014
# Date Description Participation
2
8 Feb 2014
Contingency:
15 Feb 2014
Enable Colocation Network in production
All Markets
- Selected Clients for
connectivity tests
310 Feb 2014
(TBC)Equity Market CTS - New Gateways implemented
Equity Market
- CTS functional testing for
booked Clients
4
15 Feb 2014
Contingency:
22 Feb 2014
Derivatives Trading Systems migration to the
Trading Network
All Derivative Markets
- All Derivatives Clients for
connectivity tests
5
22 Feb 2014
(TBC)
Contingency:
1 Mar 2014
Equity Market Trading System Upgrade
for New Gateways
(software deployment only)
Equity Market
- All Equity Market Clients for
connectivity tests
31
Copyright© JSE Limited 2011
www.jse.co.za
2014 Key Market Facing Dates
Critical production changes scheduled for Mar/Apr/May 2014
# Date Description Participation
6
1 Mar 2014
Contingency:
8 Mar 2014
New CISCO 4500s implementation and Firewall
upgrade to Production Network
All Markets
- Selected Clients for
connectivity tests
7
15 Mar 2014
29 Mar 2014
5 Apr 2014
3 May 2014
Colocation Customer Take-on
All Markets
- Booked Colocation
Customers for connectivity
tests
8
21 Mar 2014
Contingency:
29 Mar 2014
JSE London PoP migration
Equity Market
- All JSE London PoP Clients
for connectivity tests
32
Copyright© JSE Limited 2011
www.jse.co.za
2014 Key Market Facing Dates
Critical production changes scheduled for April/May 2014
# Date Description Participation
9
5 Apr 2014
Contingency:
3 May 2014
Colocation Customers Take-on for Remote
Management via the JSE London PoP
All Markets
- Booked Colocation
Customers for connectivity
tests
10 10 May 2014Cut over and go-live weekend for Colocation
Customers
All Markets
- All Colocation Customers
33
Copyright© JSE Limited 2011
www.jse.co.za Agreements
JSE London PoP
Colocation Client Activities
Equity Market
Equity Market Participant Test Weekends (PTW)
Exchange Test Weekends (ETW) - Client Testing
Exchange Test Weekends (ETW) - Contingency - Client testing
Go live
High Level Colocation Timeline
2014
Colocation Services Build
Nov Dec Jan Feb Mar Apr May
12/05GO
LIVE
Customer Build, Rack, Stack & Enablement
10/02EQM
CTS
18/01EQM Res.
3K Trd Switch Firewall
NW Routes
& Taps25/01
User Readiness Activities
Data Centre Build
NW POC
Col
ocat
ion
25/01
15/03Live
Tst
25/01PTW
EQM
03/02
22/03PoP
[29/03]
31/01Signed
Agree-ments
Install HUs
25/01
JSE User Acceptance Testing
Procure, Prepare and Build Enhanced JSE London PoP
08/02Colo
NW to prod 15/02
15/02 DTR
Mkts move toTrd NW
22/02
22/02EQM
Upg.15/02
01/03NW
Mgmt & FW08/03
08/03
29/03PoP
Customer Site Visits
10/05PTW
EQM
29/03Live
Tst
05/04Live
Tst
03/05Live
Tst
15/02PTW
EQM
15/03PTW
EQM
12/04PTW
EQM
Equipment Freeze
31/07
Enablement / Emergency only
Specissue
10/05Live
Tst
05/04 & 03/05Remote Mgmt
via PoP
Final Integration
34
Copyright© JSE Limited 2011
www.jse.co.za
Copyright© JSE Limited 2011
Questions ?
Refer queries to:
+27 11 520 7384 or 7211