17
ODOT OFFICE OF PRODUCTION Matthew Blythe, PE Teddy Antonios, PE USE OF GEOWALLS UNDER APPROACH SLABS

USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

ODOT OFFICE OF PRODUCTIONMatthew Blythe, PE

Teddy Antonios, PE

USE OF GEOWALLS UNDER APPROACH SLABS

Page 2: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

DAR-722-0635

Page 3: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

DAR-722-0635 DISCUSSION• 3-span slab bridge replacement.

• Designed in 2006.

• Constructed in 2008.

• 102’ long bridge.

• District Concerns

• Abutment Keyway Failure

• Approach Slab Settlement

• Semi-Integral Staining

• Semi-Integral Cracking

• MSE Wall “Interface Shearing” & Material Loss

Page 4: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

ADVANTAGE OF JOINTLESS BRIDGES

Page 5: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

CAPPED PILE ABUTMENT – CPA-5-94

Page 6: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

CRACKED KEYWAY

Page 7: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

SEMI-INTEGRAL STAINING• History of appearance “disappointments”.

• Potential Staining Causes

• Backfill not draining fast enough.

• Back of joint saturated.

• Tacking of waterproofing causing puckering.

• Waterproofing damaged during backfilling.

Page 8: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

SEMI-INTEGRAL APPROACH SLAB CRACKS

Page 9: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

LA DOTD PROTOTYPEBRIDGES• Researched improvements to integral & semi-

integral designs.

• 2005 - LTRC Research Project #01-3ST

• Evaluated performance of several LA DOTD prototype semi-integral bridges.

• Details differed from ODOT’s standard.

• Project concluded that design performed very well.

• LA DOTD’s design incorporated a geo-synthetic wall underneath the approach slabs.

• A 6” gap was installed behind the backwall.

Page 10: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

DAR-722-0635 DETAILS

Page 11: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

DAR-722-0635 DETAILS

Page 12: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

GEOWALL CONSTRUCTION

Page 13: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

GEOWALL CONSTRUCTION

Page 14: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

FINISHED PRODUCT

Approach Slab

6” Void

Bridge Deck

Page 15: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

INISHED PRODUCT

Page 16: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

ONCLUSIONDesign successfully addressed all structural issues / District concerns.

Total bridge cost was $457,500.

The geowall total cost was $26,700.

Construction did not significantly affect schedule.

After almost 3 years of service, bridge and geowalls are performing well.

There is currently no significant bumps affecting smoothness of the drive.

Due to geowalls, approach slabs should not settle.

• No anticipated loss of material due to approach slab “pumping”.

• No anticipated long-term ride ability performance issues.

Page 17: USE OF GEOWALLS UNDER APPROACH SLABS · Microsoft PowerPoint - 5 MATTHEW BLYTHE 11.30 OP Geowall Presentation 3-17-11.ppsx Author: vbeale Created Date: 3/18/2011 1:44:05 PM

Matthew Blythe, PE

(614) 752-9848

[email protected]

Teddy Antonios, PE

(614) 644-6626

[email protected]

QUESTIONS?