24
Use of FIDIC Red Book on International Road Projects Ellis Baker Partner & Global Head, Construction & Engineering 29 Sept 2015 Email: [email protected] Phone: +44 (0) 207 532 1601

Use of FIDIC Red Book on International Road Projects Ellis Baker

  • Upload
    lamhanh

  • View
    226

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Use of FIDIC Red Book on International Road Projects Ellis Baker

Use of FIDIC Red Book on

International Road Projects

Ellis Baker

Partner & Global Head, Construction & Engineering

29 Sept 2015

Email: [email protected]

Phone: +44 (0) 207 532 1601

Page 2: Use of FIDIC Red Book on International Road Projects Ellis Baker

Key features of the Red Book

Page 3: Use of FIDIC Red Book on International Road Projects Ellis Baker

Key features of the Red Book

Used for building or engineering works

designed by the Employer

– Employer, through the Engineer, is responsible

for design

Contractor is responsible for construction

– The works may include some elements of

Contractor-designed civil, mechanical, electrical

and/or construction works

Contract includes drawings, specifications,

bill of quantities

3

Page 4: Use of FIDIC Red Book on International Road Projects Ellis Baker

Key features of the Red Book

4

Employer

Architect Engineer

Contractor

Construction Contract

(Red Book)

Sub-

Contractor Sub-

Contractor

Sub-

Contractor

Sub-Contracts

Consultancy

Agreements

Page 5: Use of FIDIC Red Book on International Road Projects Ellis Baker

Key features of the Red Book

Payment based on measurements:

– Bill of quantities, certification by the Engineer, and final re-

measurement

– If want fixed price contract can use alternate wording

– Changes it from a measurement contract to a lump sum contract

5

Page 6: Use of FIDIC Red Book on International Road Projects Ellis Baker

Key features of the Red Book

‘Engineer’, typically a consulting engineer, is appointed

by the Employer to carry out the design (usually) and

supervise the construction of the project

– Engineer acts for the Employer

– Certifies payment

– Makes determinations (e.g. EOTs)

– Keeps Employer informed

6

Page 7: Use of FIDIC Red Book on International Road Projects Ellis Baker

Key features of the Red Book

7

Commonly used in conjunction

with:

– White Book (Client/Consultant Model

Services Agreement)

– Conditions of Subcontract for

Construction for Building and

Engineering Works

Page 8: Use of FIDIC Red Book on International Road Projects Ellis Baker

Usage of the Red Book

Page 9: Use of FIDIC Red Book on International Road Projects Ellis Baker

Usage of the Red Book

9

Procurement model widely used around the world,

including CEE

Used on many road projects funded by international

development banks, most recently:

• Bulgaria – Multiple contracts as part of Plodiv Roads Rehab Project

(2016)

• Bosnia and Herzegovina – Multiple contracts as part of the Pan

European Corridor Motorway (Pocitelj to Zvironvici) (2015)

• Macedonia – Motorway between Kumanovo – Miladinovci (2015)

• Georgia – Georgia East West Highway (2015)

Page 10: Use of FIDIC Red Book on International Road Projects Ellis Baker

Usage of the Red Book

10

Examples continued:

– Romania – Multiple

contracts as part of Galati

Urban Infrastructure Rehab

Project (2015)

– Sri Lanka – Extension of

Southern Expressway

(2014)

– Vietnam – Noi Bai–Lao Cai Expressway (8 sections,

5 contractors, >$1 billion)

Page 11: Use of FIDIC Red Book on International Road Projects Ellis Baker

Common Issues on Road Projects

Page 12: Use of FIDIC Red Book on International Road Projects Ellis Baker

Common Issues on Road Projects

12

Design changes

– Under the Red Book, Employer provides the design

– Gives Employer control over the design

BUT

– Employer responsible for risk of any

errors

– Contractor entitled to Variation if any

design changes required

• E.g. due to changes in road alignment

Page 13: Use of FIDIC Red Book on International Road Projects Ellis Baker

Common Issues on Road Projects

13

Geotechnical conditions

– Under the Red Book, Employer takes risk of “Unforeseen” physical

conditions

– High risk for road projects

• e.g. rock encountered (difficult

to excavate)

• e.g. Poor soil suitability

(additional piles required)

Page 14: Use of FIDIC Red Book on International Road Projects Ellis Baker

Common Issues on Road Projects

Site access

– Under the Red Book, Employer required to provide access to Site

– Contractor entitled to relief if Site access delayed

– On road projects, access often delayed due to:

• Delays in land acquisitions

• Requirement to phase access to keep the road operational during construction

• Disruptions caused by third parties (e.g. disgruntled landowners)

14

Page 15: Use of FIDIC Red Book on International Road Projects Ellis Baker

Common Issues on Road Projects

15

Social and environmental issues

– Red Book requires Contractor to take steps

to protect environment and limit nuisance to

people

– Is a particular risk for road projects

• High potential to damage environment

• Construction generates a lot of noise and dust

• Contracts often amended to include additional

environment and community engagement

requirements

Page 16: Use of FIDIC Red Book on International Road Projects Ellis Baker

Amendments to the Red Book

Page 17: Use of FIDIC Red Book on International Road Projects Ellis Baker

Amendments to the Red Book

In practice, the Red Book is frequently amended

– Countries often have standard form contracts based on an

amended version of the Red Book

– RSD is preparing draft contract for highway projects in the

Czech Republic

17

Page 18: Use of FIDIC Red Book on International Road Projects Ellis Baker

RSD amendments to the Red Book

Contractor to provide a Warranty Bond

– Will be provided in lieu of (not in addition to) Retention Money

– Is a common amendment to the Red Book

– International contractors will be please to see this - improves

their cash flow

18

Page 19: Use of FIDIC Red Book on International Road Projects Ellis Baker

RSD amendments to the Red Book

Employer may claim contractual penalties in parallel with

general damages

– Contractual penalties no longer Employer’s sole remedy for delay

(other than termination)

– Will be of concern to international contractors

• They will expect that if an amount is stipulated in the Contract – the Employer

cannot claim that amount AND general damages

• May cause them to qualify their tenders

19

Page 20: Use of FIDIC Red Book on International Road Projects Ellis Baker

RSD amendments to the Red Book

Dispute resolution limited to Czech civil courts

– Common practice to adopt a tiered dispute resolution process

• E.g. some combination of amicable settlement/mediation/DAB/arbitration/court

– International contractors will prefer arbitration to Czech courts

– Many different arbitration options

• ICC Arbitration

• London Court International Arbitration

20

Page 21: Use of FIDIC Red Book on International Road Projects Ellis Baker

Conclusions

Page 22: Use of FIDIC Red Book on International Road Projects Ellis Baker

Conclusions

Many good reasons for using the Red Book

– Balanced risk allocation – but still protects the Employer’s interests

– Well accepted – will be familiar to international contractors

– Well supported – is recommended/required by many development banks

– Is effective – clear and complete conditions; time limits; dispute resolution

22

Page 23: Use of FIDIC Red Book on International Road Projects Ellis Baker

Conclusions

Particular Conditions allow flexibility to amend the Red Book

for specific projects

Used by RSD on draft contract for highways

– Some of RSD amendments are commonly made and will be familiar to

international contractors (e.g. warranty bond)

– Other RSD amendments may be resisted by international contractors

23

Page 24: Use of FIDIC Red Book on International Road Projects Ellis Baker

Worldwide. For Our Clients.

In this presentation, White & Case means the international legal practice comprising White & Case LLP, a New York State registered limited liability partnership, White & Case LLP,

a limited liability partnership incorporated under English law and all other affiliated partnerships, companies and entities.

www.whitecase.com

White & Case LLP

5 Old Broad Street

London, EC2N 1DW

United Kingdom

Tel: + 44 20 7532 1000

Fax: + 44 20 7532 1001