1DISTRIBUTION A. See first page.
U.S. ARMY COMBAT CAPABILITIES DEVELOPMENT COMMAND –GROUND VEHICLE SYSTEMS CENTER
Tony McKheen
Associate Director
Sustainment Engineering - May 2020
DISTRIBUTION A. Approved for public release; distribution unlimited. OPSEC# 4117
2DISTRIBUTION A. See first page.
How Does GVSC Support Sustainment?
GVSC serves as the Engineering Support Activity (ESA) to DLA and Team Detroit Arsenal for ground systems in sustainment. Tasks include:
• Manage the technical data required to support the vehicle fleets and systems
• Provide technical support for the procurement of spare parts
• Support Depot and Arsenal production programs
• Engineering support to resolve field and safety issues
• Management and resolution of obsolescence issues
3DISTRIBUTION A. See first page.
• Maintain Systems Configuration In Our Product Data Management (PDM) System
• Collaborate With OEMs And Other Stakeholders On Tech Data Management
• Manage & Coordinate Engineering Change Management Workflow
• Drawing Conversion And Updates• CCDC GVSC Windchill PDM
Stores:– 2,431,966 Army Parts – 4,188,933 Drawings/Documents– 896,534 CAD Models– 162,738 Engineering Change
Records
Sustainment Engineering TasksTechnical Data Management
4DISTRIBUTION A. See first page.
• Manage The Tech-loop Process Workflow That Logs, Tracks And Assigns Tasks For The Development Of Data Required For Spare Part Procurement.
• Deliver Complete Technical Data Packages To DLA & ILSC For Procurement Of Spare Parts.
• Manage 339/355 Engineering Support Process Request.
• Over 6000 Validated TDPsProvided In FY2019.
• Approximately 3750Engineering Support Items Resolved In FY2019.
Sustainment Engineering TasksSpare Part Procurement Technical Support
Technician
Transportation
Packaging
Quality
Engineering
Materials
Requirement IdentifiedStart-LMP-DLA-AdHoc
zPASS ActionCD Image
Available or TDP posted to
Web
Buyer
DLA Coordinator
Assembly of the TDP may start additional Product Data Management workflows. Product Data is validated at this point.
Provide Complete Reviews for Secondary Part Procurement
Workflow starts when Technical Procurement Package (TPP) is created or enters the “In GVSC” State in PDMLink Buyer notified via email from PRON Control
IN GVSC
5DISTRIBUTION A. See first page.
• Depot Reclamation Procedures• Technical Support For
Development Of Procedure• Development Of Test Criteria
• Reverse Engineering• Technical Support For DMWRs,
NMWRs, & SOWs• Request For Variance
Approval/Review• Root Cause Analysis
Sustainment Engineering TasksDepot/Arsenal Support
6DISTRIBUTION A. See first page.
• Review And Resolution Of Safety Issues (Including Development Of Safety of Use Messages)
• Investigating Technical Inquiries From The Field
• PQDR Investigations And Resolution
• Post Production Software Support
Sustainment Engineering TasksField and Safety Issue Resolution
7DISTRIBUTION A. See first page.
Purpose: Provide total program proactive obsolescence management.
Products / Tools / Resources: Payoff:• Improved Readiness• Cost Savings & Cost
Avoidance• Informs POM Planning
DOD SD-22 DMSMS Guidebook: Utilize predictive methods to prepare an obsolescence plan, identify obsolescenceissues, assess cost, schedule & readiness impacts, analyze mitigation strategies & implement the optimum solution.
The challenge, especially for platforms in late stages of the life cycle, is funding, which drives the question:
“How do we operationalize the benefits of Predictive Obsolescence Management?”
There is no “one size fits all” solution for Obsolescence Management
Obsolescence Technical Authority at the intersection of Logistics, Engineering & Industrial Base.
Sustainment Engineering TasksObsolescence Management
8DISTRIBUTION A. See first page.
Sign-up for one-on-one meetings with Sustainment Engineering
by filling out the request form on the main page and submitting
ONE-ON-ONES