Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Upgrades to the CAPS PHIL Facility - Selected Experiments with the new
5 MW MVDC Lab
Michael “Mischa” Steurer Center for Advanced Power Systems
Florida State University Tallahassee, FL, USA
November 5th, 2015
15 Years of CHIL & PHIL at CAPS
2
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
11/5/2015 3rd Grid Sim Workshop
CAPS in NHMFL
15 Years of CHIL & PHIL at CAPS
2
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
CAPS in NHMFL
11/5/2015 3rd Grid Sim Workshop
Braking Ground for new CAPS Facility
15 Years of CHIL & PHIL at CAPS
2
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
2
First 4 RTDS Racks at CAPS
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
2
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
2
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curre
nt (k
A)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
2
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
2
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Complete 14 RTDS Installation at CAPS
Complete 14 RTDS Installation at CAPS
First Geographically Distributed SACADA to RTDS Testing (SNL & CAPS)
15 Years of CHIL & PHIL at CAPS
2
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
First Geographically Distributed SACADA to RTDS Testing (SNL & CAPS)
Complete 14 RTDS Installation at CAPS
15 Years of CHIL & PHIL at CAPS
2
Time [s]
Hydrodynamic load torque
Torque measured at the motor shaft
Motor speed
Utility4.16 kVbus
=
~
=
~
~
=
~
=
M2
=
~
=
~
~
=
~
=
M1
2.5MW
Dynos: 5 MW @ 225 rpm
Simulate Electric System Response
Simulate DynamicTorque Loads
FeedbackMeasured Data
Real TimeSimulator
7.5MVA
12.47 kV
50 MVA 115 kV systemCity of Tallahassee
First MW scale PHIL of Ship “Crashback” Maneuver
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
Time [s]
Hydrodynamic load torque
Torque measured at the motor shaft
Motor speed
Utility4.16 kVbus
=
~
=
~
~
=
~
=
M2
=
~
=
~
~
=
~
=
M1
2.5MW
Dynos: 5 MW @ 225 rpm
Simulate Electric System Response
Simulate DynamicTorque Loads
FeedbackMeasured Data
Real TimeSimulator
7.5MVA
12.47 kV
50 MVA 115 kV systemCity of Tallahassee
First MW scale PHIL of Ship “Crashback” ManeuverFirst 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
First Geographically Distributed SACADA to RTDS Testing (SNL & CAPS)
Complete 14 RTDS Installation at CAPS
15 Years of CHIL & PHIL at CAPS
2
M3 Spee
d fe
edba
ck
Torq
ue
refe
renc
e
Speed reference
Torq
ue fe
edba
ck
4.16kV/60Hz utility feed
VSD
2
VSD
1
VSD
3
M1M2
Gaseous He refrigeration
Exciter
Fiel
d cu
rren
t mea
sure
men
t
Real TimeSimulator
First PHIL with 5 MW HTS Ship Propulsion Motor
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
Time [s]
Hydrodynamic load torque
Torque measured at the motor shaft
Motor speed
Utility4.16 kVbus
=
~
=
~
~
=
~
=
M2
=
~
=
~
~
=
~
=
M1
2.5MW
Dynos: 5 MW @ 225 rpm
Simulate Electric System Response
Simulate DynamicTorque Loads
FeedbackMeasured Data
Real TimeSimulator
7.5MVA
12.47 kV
50 MVA 115 kV systemCity of Tallahassee
First MW scale PHIL of Ship “Crashback” Maneuver
M3 Spee
d fe
edba
ck
Torq
ue
refe
renc
e
Speed reference
Torq
ue fe
edba
ck
4.16kV/60Hz utility feed
VSD
2
VSD
1
VSD
3
M1M2
Gaseous He refrigeration
Exciter
Fiel
d cu
rren
t mea
sure
men
t
Real TimeSimulator
First PHIL with 5 MW HTS Ship Propulsion Motor
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
First Geographically Distributed SACADA to RTDS Testing (SNL & CAPS)
Complete 14 RTDS Installation at CAPS
15 Years of CHIL & PHIL at CAPS
2
Measurement with 2.5 MW converter under load
1 pu = 1.15 kV
t [s]
CHIL for Optimizing VVS Controller
Simulator Model Builder GUI Front End RT Simulator
Hardware
Simulator Run-Time GUI Front End
RT Simulator Terminal
Universal Controller Hardware
D/A , D/D Conv
A/D, D/D Conv
Universal Controller Terminal
Batch Mode Scripting
Optimization Algorithm
Controller Settings
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
Time [s]
Hydrodynamic load torque
Torque measured at the motor shaft
Motor speed
Utility4.16 kVbus
=
~
=
~
~
=
~
=
M2
=
~
=
~
~
=
~
=
M1
2.5MW
Dynos: 5 MW @ 225 rpm
Simulate Electric System Response
Simulate DynamicTorque Loads
FeedbackMeasured Data
Real TimeSimulator
7.5MVA
12.47 kV
50 MVA 115 kV systemCity of Tallahassee
First MW scale PHIL of Ship “Crashback” Maneuver
M3 Spee
d fe
edba
ck
Torq
ue
refe
renc
e
Speed reference
Torq
ue fe
edba
ck
4.16kV/60Hz utility feed
VSD
2
VSD
1
VSD
3
M1M2
Gaseous He refrigeration
Exciter
Fiel
d cu
rren
t mea
sure
men
t
Real TimeSimulator
First PHIL with 5 MW HTS Ship Propulsion Motor
Measurement with 2.5 MW converter under load
1 pu = 1.15 kV
t [s]
CHIL for Optimizing VVS Controller
Simulator Model Builder GUI Front End RT Simulator
Hardware
Simulator Run-Time GUI Front End
RT Simulator Terminal
Universal Controller Hardware
D/A , D/D Conv
A/D, D/D Conv
Universal Controller Terminal
Batch Mode Scripting
Optimization Algorithm
Controller Settings
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
First Geographically Distributed SACADA to RTDS Testing (SNL & CAPS)
Complete 14 RTDS Installation at CAPS
15 Years of CHIL & PHIL at CAPS
2
Commissioning 5 MW Variable Voltage Source “VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
IEEE 39 bus system
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
0 10 20 30 40 50 60-2
0
2
4
6
8
10
12
Shaft torque TS [Nm/10] Requested Measured
Time [s]Shaft power PS [kW]
Tip speed ratio λ
Wind velocity [ms-1]Provided vW-P Estimated vE
PHIL of Wind-Turbine Generator, RTDS + dSpace
AC
T1PT
SCFCLT2
G
Relay
D/AD/D D/D
RTDSSimulation
Hardware
puRL 1.11=
puX L 1.0=1S
B1 B2 B3
CT
T-Line + Sequence Impedance (pu/km)
T1
T2
0.206e-3 + j*0.00419
Line Length (km)
100
1000.206e-3 + j*0.00419
Source + Sequence Impedance (pu)
S1
G
0.0478 + j*0.125
0.0021 + j*0.402
L-L RMS Voltage (kV)
230
230
Sbase
Vbase
590 MVA
230 kV
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
0.14 0.15 0.16 0.17 0.18 0.19 0.2-3
-2
-1
0
1
2
3
t (s )
Fault With FCL Be hind Re lay (50% Line Le ngth)
TotalS upe rconductorS hunttrip
Current (kA) Relay
State
Normal
Trip
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current Limiter
ROS
za
HUT
zb
V1(k)
V1(k-1)
I(k)
I(k)
AMPINT
Simulated System
V2(k)
+_
Z*=f(V, I)
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5-0.2
0
0.2
time (s)
curr
ent (
kA)
Generator current during shedding the base load (DIM)
Newly adapted “damping impedance method” (DIM) interface maintains stability even during transients
Experimental results from 50 kW PEBB system
+_
zfilt
Testing PHIL Interface Algorithms
Time [s]
Hydrodynamic load torque
Torque measured at the motor shaft
Motor speed
Utility4.16 kVbus
=
~
=
~
~
=
~
=
M2
=
~
=
~
~
=
~
=
M1
2.5MW
Dynos: 5 MW @ 225 rpm
Simulate Electric System Response
Simulate DynamicTorque Loads
FeedbackMeasured Data
Real TimeSimulator
7.5MVA
12.47 kV
50 MVA 115 kV systemCity of Tallahassee
First MW scale PHIL of Ship “Crashback” Maneuver
M3 Spee
d fe
edba
ck
Torq
ue
refe
renc
e
Speed reference
Torq
ue fe
edba
ck
4.16kV/60Hz utility feed
VSD
2
VSD
1
VSD
3
M1M2
Gaseous He refrigeration
Exciter
Fiel
d cu
rren
t mea
sure
men
t
Real TimeSimulator
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
Measurement with 2.5 MW converter under load
1 pu = 1.15 kV
t [s]
CHIL for Optimizing VVS Controller
Simulator Model Builder GUI Front End RT Simulator
Hardware
Simulator Run-Time GUI Front End
RT Simulator Terminal
Universal Controller Hardware
D/A , D/D Conv
A/D, D/D Conv
Universal Controller Terminal
Batch Mode Scripting
Optimization Algorithm
Controller Settings
First 4 RTDS Racks at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
First Geographically Distributed SACADA to RTDS Testing (SNL & CAPS)
Complete 14 RTDS Installation at CAPS
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltage
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltage
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltage
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltage
First OPAL-RT at CAPS
First OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
Distributed Controls (DC) computing layer
Fast data links between DC and power components:
RT simulator specific
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Grand Opening NREL - ESIF
Grand Opening NREL - ESIF
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
10kW class “Virtual” Motor Demo
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Grand Opening NREL - ESIF
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
First full PHIL with 500 kW PV converter
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
First full PHIL with 500 kW PV converter
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Grand Opening NREL - ESIF
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
VVS
Rectifier
Gearbox DynoGenerator
+-
DAQ
~
RTDS
VoltageOpen/CloseTrigger/Synch
Voltage/Current/
Duty Cycle SpeedVoltage
Current
Speed/Torque
Measured Quantities
1.6 MW in400 ms
0…24,000 rpm
0…3,600 rpm
0…450 rpm
Dynamometers1st stage gear box2nd stage gear box
PHIL Testing High Speed Generator
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
First full PHIL with 500 kW PV converter
VVS
Rectifier
Gearbox DynoGenerator
+-
DAQ
~
RTDS
VoltageOpen/CloseTrigger/Synch
Voltage/Current/
Duty Cycle SpeedVoltage
Current
Speed/Torque
Measured Quantities
1.6 MW in400 ms
0…24,000 rpm
0…3,600 rpm
0…450 rpm
Dynamometers1st stage gear box2nd stage gear box
PHIL Testing High Speed Generator
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Grand Opening NREL - ESIF
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
First full PHIL with 500 kW PV converter
VVS
Rectifier
Gearbox DynoGenerator
+-
DAQ
~
RTDS
VoltageOpen/CloseTrigger/Synch
Voltage/Current/
Duty Cycle SpeedVoltage
Current
Speed/Torque
Measured Quantities
1.6 MW in400 ms
0…24,000 rpm
0…3,600 rpm
0…450 rpm
Dynamometers1st stage gear box2nd stage gear box
PHIL Testing High Speed Generator
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Grand Opening NREL - ESIF
Grand Opening Clemson - EGrid
Grand Opening Clemson - EGrid
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
First full PHIL with 500 kW PV converter
VVS
Rectifier
Gearbox DynoGenerator
+-
DAQ
~
RTDS
VoltageOpen/CloseTrigger/Synch
Voltage/Current/
Duty Cycle SpeedVoltage
Current
Speed/Torque
Measured Quantities
1.6 MW in400 ms
0…24,000 rpm
0…3,600 rpm
0…450 rpm
Dynamometers1st stage gear box2nd stage gear box
PHIL Testing High Speed Generator
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Second OPAL-RT System at CAPS
Second OPAL-RT System at CAPS
Grand Opening NREL - ESIFGrand Opening Clemson - EGrid
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
Hardware
Simulated Surrounding System
DC Amp
AC AmpDUT
Voltage References
Current Reference
Voltage and Current Measurements
DRTS
PHIL Testing of MW scale Naval AC-DC Converter
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
First full PHIL with 500 kW PV converter
Hardware
Simulated Surrounding System
DC Amp
AC AmpDUT
Voltage References
Current Reference
Voltage and Current Measurements
DRTS
PHIL Testing of MW scale Naval AC-DC Converter
VVS
Rectifier
Gearbox DynoGenerator
+-
DAQ
~
RTDS
VoltageOpen/CloseTrigger/Synch
Voltage/Current/
Duty Cycle SpeedVoltage
Current
Speed/Torque
Measured Quantities
1.6 MW in400 ms
0…24,000 rpm
0…3,600 rpm
0…450 rpm
Dynamometers1st stage gear box2nd stage gear box
PHIL Testing High Speed Generator
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Second OPAL-RT System at CAPS
Grand Opening NREL - ESIFGrand Opening Clemson - EGrid
15 Years of CHIL & PHIL at CAPS
3
IEEE 39 bus system
PHIL of Wind-Turbine Generator, RTDS + dSpace
FCL in downstreamof PTs and CTs
=> Relay trips appropriately
Distance Relay and Fault Current LimiterTesting PHIL Interface Algorithms
First MW scale PHIL of Ship “Crashback” Maneuver
First PHIL with 5 MW HTS Ship Propulsion MotorCommissioning 5 MW Variable Voltage Source
“VVS” System: 4.16 (8.2) kVAC & 1.1 kVDC
CHIL for Optimizing VVS ControllerFirst 4 RTDS Racks at CAPS
Distributed Controls (DC) computing layer
RT simulation of electric power system
RT simulation of Controls Communications
Cyber-Physical RT Simulation Test Bed
Dynapower needed to test a 1 MW DC-AC inverter for standard compliance
European Certifying Agency“Technischer Uberwachungsverein” (TUV)
witnessed tests at CAPS and certified results
Italian standard requires 50 Hzand variations in symmetric and asymmetric voltage conditions
Norma Italiana CEI, CEI 0-16, Reference technical rules for the connection of active and passive consumers to the HV and MV electrical networks of distribution companies, December 2013.
LV Ride-Through Tests using the VVS
2000 2002 2004 2006 2008 2010 2012 2014
2001 2003 2005 2007 2009 2011 2013 2015
FCL voltage (inverted)
Ip,lim = 0.7 kAVp,lim = 1.8 kV
Vsource=1 kV, Ip=15 kA4.16 kV utility bus
4.16 kV experimental bus
AC current reference
from RTDS
AC Voltage feedback to
RTDS 5 MW Converter „Amplifier“
FCL element
Real Time Simulator RTDS
First MW scale PHIL experiments with FCLs at medium voltage
Real Time Digital Simulator
D/A
A/DHardware response
Simulated System response
External Hardware
STATCOM controller by NCSU
2 VLL, 3 IL
24 firing
pulses≈≈
69 kV
≈≈
C1 C2
C3
C4
C5
C6
C7
C8
FSIG1Turbine 1
ModelWind
speed 1
CaT
1
CbT
1
34.5 kV
SS1
Turbine N Model
Wind speed N
CaT
N
CbT
N
SSn
N units connected
through underground
cabling
0.6 kV
TT1
TTN
STATCOM
Utility system
CWDM FS MP
69 kV69 kV
TCW
WF
Turbine i Model
Wind speed i
CaT
i
CbT
i
SSiTTi
FSIGi
FSIGN
PCC
BPA System– 85 μs time-step size, 1 Rack
Wind Farm– Modeled with 36 individual turbines– 85 μs time-step size, 12 Racks
Statcom– Simulated with 2 μs time-step, 1 Rack
CHIL Testing of Windfarm STATCOM Controller
“INTERNET”
(LAMBDA RAIL-
U of A LAN
RTDS RACK ELECTRICAL MODEL
DIGITAL I/O µCONTROLLER
FSU/CAPS “Gateway
PC”
OPAL-RT SIMULATOR (THERMAL MODEL)
(See Fig. 4)
CAPS LAN
Geographically Distributed Electro-Thermal CoSim w/ OPAL-RT
0…24,000 rpm
0…3,600 rpm
0…450 rpm
High Speed Machinery Test Stand
10kW class “Virtual” Motor Demo
First full PHIL with 500 kW PV converter
Hardware
Simulated Surrounding System
DC Amp
AC AmpDUT
Voltage References
Current Reference
Voltage and Current Measurements
DRTS
PHIL Testing of MW scale Naval AC-DC Converter
VVS
Rectifier
Gearbox DynoGenerator
+-
DAQ
~
RTDS
VoltageOpen/CloseTrigger/Synch
Voltage/Current/
Duty Cycle SpeedVoltage
Current
Speed/Torque
Measured Quantities
1.6 MW in400 ms
0…24,000 rpm
0…3,600 rpm
0…450 rpm
Dynamometers1st stage gear box2nd stage gear box
PHIL Testing High Speed Generator
Dynapower needed to test a 1 MW DC-AC inverter for standard compliance
European Certifying Agency“Technischer Uberwachungsverein” (TUV)
witnessed tests at CAPS and certified results
Italian standard requires 50 Hzand variations in symmetric and asymmetric voltage conditions
Norma Italiana CEI, CEI 0-16, Reference technical rules for the connection of active and passive consumers to the HV and MV electrical networks of distribution companies, December 2013.
LV Ride-Through Tests using the VVS
VSD2 VSD1
VVS1
=
~
=
~
~
=
~
=
M1
=
~
=
~
~
=
~
=
M2
Dynamometers 2x2.5 MW @ 225 rpm
4.16 kV utility bus
VVS2T1
12.47 kV feeder
T0115 kV utility system
T0115 kV utility system
=
~
=
~
~
=
~
=
=
~
=
~
~
=
~
=
4.16 kV experimental AC bus
DC bus0-1.1 kV
Simulates Electric System Response
Real Time Simulator
T6
T2
Dynamic Torque Request
Dynamic Speed Request Bus voltage reference
Load current feedback
Customer supplied mechanical load
VREF IMEAS
T3
VMEAS
0 2 4 6 8-0.2
0
0.2
0.4
VVS
Pow
er (
MW
)
0 2 4 6 8-50
0
50
100
Mot
or S
peed
, RP
M
0 2 4 6 8-10
0
10
20
Time (s)
Torq
ue R
efer
ence
(kN
m)
First MW scale PHIL experiments with motor drive at medium voltageFirst OPAL-RT at CAPS
CAPS in NHMFL
Braking Ground for new CAPS Facility
11/5/2015 3rd Grid Sim Workshop
Second OPAL-RT System at CAPS
Grand Opening NREL - ESIFGrand Opening Clemson - EGrid
New CAPS MVDC Lab
4
T11 T12
MMC #3
MMC #2
MMC #1
MMC #4 Pre- Charge
Master Controls & RTDS Interfaces
4 individual Modular Multi-Cell (MMC) Converters
Each 0…+/-6 kVdc, 0…+/- 210 A
12 kHz effective switching frequency
Galvanically isolated
Any series & parallel configuration possible
11/5/2015 3rd Grid Sim Workshop
Full Bridge MMC
5
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
PU
U
V
W
DC+
DC-
GND
• Allows insertion of capacitor voltage in either polarity • Fewer cells per phase arm for MVDC applications • Superior voltage control • Capability to fully control DC currents, even if Vdc <<
S11
S12
C_c1 R_c1
S21
S22
C_c2 R_c2
S31
S32
C_c3 R_c3
S41
S42
C_c4 R_c4
11/5/2015 3rd Grid Sim Workshop
MMC Controller HIL (CHIL) Simulation
6
Voltages Currents
Firing pulses
Two full converters modeled in RTDS (dt = 2us) Two converter controls interfaced with RTDS
CHIL simulation of the PHIL amplifier is an essential tools to de-risking PHIL experiments
32
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
PU
U
V
W
DC+
DC-
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
FB cell
PU
U
V
W
DC+
DC-
S11
S12
C_c1 R_c1
S21
S22
C_c2 R_c2
S31
S32
C_c3 R_c3
S41
S42
C_c4 R_c4
11/5/2015 3rd Grid Sim Workshop
MVDC Lab Experimental Possibilities
7
12.47 kV
MVDC Lab
Utility
MMCController
MMCController
+ -
MMC
Controller
MMC
Controller
+ -
+ -+ -
MVDC Lab
Distributed Energy Storage Management
System Stability Studies
Fault Management
Pulsed Power Management
PHIL Testing of MVDC
Equipment (i.e. DUT)
Disconnect individual converter chassis from earth
ground
11/5/2015 3rd Grid Sim Workshop
FSU-CAPS 3 x 5 MW Facilities
8 34 11/5/2015 3rd Grid Sim Workshop
PHIL based Rapid Power Transfer
9 DISTRIBUTION STATEMENT A: Approved for Public release, Distribution is unlimited
• Power transfer with different rates • 5 ms delay in action of second load • AC voltage and frequency fluctuation is minimal • Generator power reaches 1.5 pu for 15 ms
750 kW, 5 kV, 150 A 3.9 MW, 4.16 kV, 60 Hz
Energy Storage Control via MVDC Bus
10
Compensation of load fluctuations with ES locally controlled from
MVDC bus
11/5/2015 3rd Grid Sim Workshop
IMU Testing at FSU-CAPS
11
• Installed and commissioned on May 18th • Goal: Exercising the IMU on active loads & sources • Individual PEBB tests: OK • Discovered effects of HF common-mode currents • Improved EMI, learned valuable lessons for
PEBB-1000 and PEBB-6000 programs
11/5/2015 3rd Grid Sim Workshop
Fault Management in Breaker-less MVDC shipboard power systems
12
Fault clearance process of MVDC system
Detect and localize fault
Re-energize system
De-energize system
Isolate faulted segment
• Identify and isolate short-circuit faults via coordinated control of power converters and non-fault-breaking ultra-fast mechanical disconnects
• Challenges Looped system with multiple sources Fault current waveforms (transients during faults) Bi-directional power flow from power electronics Targeted system response (1) to (4): 8 ms
• Primary – Centralized Fault Management (CFM) Based on federated data aquistion Instantaneous percentage differential scheme
• Backup – Localized Fault Management (LFM) Based only on local measurements Distance protection principle
11/5/2015 3rd Grid Sim Workshop
Current Limiting with MMCs
13
-5 0 5 10 15
x 10-3
0
0.5
1
1.5
DC v
oltag
e (k
V)
Time (s)
Exp
CHIL
-5 0 5 10 15
x 10-3
-0.1
0
0.1
0.2
0.3
DC c
urre
nt (k
A)
Time (s)
ExpCHIL
• DC voltage reference set to 1 kV
• Prospective current: 597 A
• Contactor closes at t=0
• Max current 270 A • Steady state current
201 A @ 385 V • DC voltage
reference set to 0 kV at t = 0.3 s 11/5/2015 3rd Grid Sim Workshop
Arc Fault Testing
14
Photograph of the arc fault setup with 8” gap between DC rails and aluminum rod shorted between probes.
Setup: Two MMCs connected in parallel in CSM and to a set of copper bus bars. The bus bars are set with 8”
gap of separation and an aluminum rod provides a short between the two.
Snapshot of the arc during the test with correcting voltage and current waveforms
11/5/2015 3rd Grid Sim Workshop
Concluding Remarks
15
• Established MVDC facility with MMCs
• Ongoing experiments – Testing of VaTech’s Impedance
Measurement Unit – Rapid Power Transfer in shipboard
MVDC systems – Fault Management in fault current
limited shipboard MVDC systems – Common mode coupling of MW
scale converters
11/5/2015 3rd Grid Sim Workshop
Concluding Remarks
15
• Established MVDC facility with MMCs
• Ongoing experiments – Testing of VaTech’s Impedance
Measurement Unit – Rapid Power Transfer in shipboard
MVDC systems – Fault Management in fault current
limited shipboard MVDC systems – Common mode coupling of MW
scale converters
11/5/2015 3rd Grid Sim Workshop
15 years of CAPS Leadership in CHIL & PHIL to be continued…