Upload
phungdieu
View
229
Download
4
Embed Size (px)
Citation preview
1
Upgrade to 2.3.0.d
CCRCC 2013 Lille, 12 Novembre 2013
Silvia Domínguez
2
Index
1. Objective
2. ETCS deployment situation
3. Version management and migration plan
4. Compatibility analysis and B3 impact
5. Conclusions
3
1. Objective
2. ETCS deployment situation
3. Version management and migration plan
4. Compatibility analysis and B3 impact
5. Conclusions
The objective of the upgrade from our current ETCS
implementations 2.2.2 to version 2.3.0d is to
achieve:
• a fully interoperable system, no ETCS borders
• according to the European Reference Version
2.3.0d
Why to upgrade to 2.3.0.d?
4
European Version 2.3.0d is the reference version as stated:
• in the MoU clause 16:
SRS 2.3.0, as adopted by the European Commission on 23 April 2008, and
known as ‘2.3.0d’ currently constitutes the unique and interoperable
technical reference which will ensure the interoperability of all ETCS
equipment deployed in Europe.
• It is technically defined in Commission Decision 2012/88 and
amended in 2012/696
• ETCS version 2.3.0.d covers all the Spanish functional and
operational needs for the network
Why to upgrade to 2.3.0.d?
5
6
Index
1. Objective
2. ETCS deployment situation
3. Version management and migration plan
4. Compatibility analysis and B3 impact
5. Conclusions
Line Supplier ETCS Level Version Length
In service
Madrid - Lérida Ansaldo (CSEE) 1+2 2.2.2+ 490 km
Lérida - Barcelona Thales 1+2 2.2.2+ 190 km
Madrid - Valladolid Thales 1+2 2.2.2+ 180 km
Córdoba - Málaga Invensys (Dim.) 1+2 2.2.2+ 155 km
Madrid - Valencia Invensys (Dim.) 1+2 2.3.0.d 470 km
Zaragoza - Huesca Alstom 1 2.2.2+ 80 km
La Sagra – Toledo Thales 1+2 2.2.2+ 21 km
Barcelona – Figueras Thales 1+2 2.3.0d 131 km
Orense – Santiago Thales 1+2 2.3.0d 90 km
Commuter line Madrid Thales + Invensys 1+2 2.3.0d 50 km
Under construction
Albacete – Alicante Alstom 2 2.3.0d 165 km
Total 2.022 km
ETCS deployment Infrastructure
7
8 DIRECTION GÉNÉRALE DE DÉVELOPPEMENT DE L’INFRASTRUCTURE
Direction d’Innovation Technologique
Lleida-Barcelona ERTMS-N1-2 Thales
(2.2.2.+)
Madrid-Valladolid ERTMS-N1-2 Thales
(2.2.2.+)
La Sagra-Toledo ERTMS-N1-2 Thales
(2.2.2.+)
Córdoba-Malaga ERTMS-N1-2 (2.2.2.+)
Madrid-Lleida ERTMS-N1-2 Ansaldo
(2.2.2.+)
Zaragoza-Huesca N1- Alstom (2.2.2.+)
Madrid-Sevilla LZB ERTMS NSTM LZB
Madrid-Valencia-Albacete N1-2 Dimetronic (2.3.0.d)
Madrid Commuter lines ERTMS-N1-2 Thales and
Dimetronic (2.3.0.d)
Figueras-Perpignan ERTMS-N1-2 Ansaldo
(2.3.0)
Albacete-Alicante ASFA y N2 (2.3.0.d.)
Orense –Santiago (2.3.0.d.)
ETCS deployment Infrastructure (II)
8
ERTMS equipped trains
9
TRAIN ERTMS
SUPPLIER ERTMS LEVEL
No.
Units
S-100 ALSTOM L1 / L2 24
S-104 ALSTOM L1 / L2 20
S-114 ALSTOM L1 / L2 13
S-102/112 SIEMENS L1 / L2/ STM LZB 16/30
S-103 SIEMENS L1 / L2/ STM LZB 26
S-120/121 ANSALDO L1 / L2 57
S-130 BOMBARDIER
L1 / L2 / STM LZB /
STM EBICAB 44
Alaris INVENSYS L1 / L2/ STM EBICAB 10
v2.2.2.+ HS Total 240
TRAIN ERTMS
SUPPLIER
ERTMS
LEVEL
No.
units
S-446/447/450 INVENSYS L1 / L2 94
Civias ALSTOM L1 / L2 123
v.2.3.0.d LOCAL Total
217 LOCO
ERTMS
SUPPLIER
ERTMS
LEVEL
No.
units
252 SIEMENS L1 / L2 4
v.2.2.2.+ LOCOS 4
Total 244 vehicles to migrate
10
Index
1. Objective
2. ETCS deployment situation
3. Version management and migration plan
4. Compatibility analysis and B3 impact
5. Conclusions
Version management and migration plan
The work is coordinated by the Spanish ETCS versions working
group through the following tasks:
11
• Analyse the technical aspects related to compatibility between ETCS
versions 2.2.2 and 2.3.0.d, focusing on the Spanish implementations
• Follow up any incidence during APS or open point raised within the
projects and related to ERTMS specifications
• Define the migration technical conditions
It is formed by experts from Ministry of Fomento, Adif, Renfe,
Ineco and CEDEX.
Migration plan should be able to update infrastructure
and fleet to 2.3.0d while maintaining the commercial
timetable
In addition, there are the following requirements:
• Extend the level 2 version 2.3.0.d commercial operation
• Keep the fleet freedom over the network
• Coordinate the migration of vehicles and infrastructure
• Coordinate the migration of 6 different ERTMS suppliers
Migration strategy. Challenges
12
• Network generic engineering rules:
Avoid the use of functions on the infrastructure that are not backwards
compatible and not essential for the operation.
• Specific migration guidelines:
Use of specific engineering rules (2.3.0d compatible) for the
implementation of some functions.
• Resolution of shortcomings in the reference specifications:
Consider mitigation measures possible with the already existing 2.3.0.d
functionality.
Migration is financed by the TEN-T Executive Agency through the
project "2011-ES-60001-P Upgrade of Spanish high-speed lines and
trains to ERTMS 2.3.0.d"
Migration strategy. Compatibility Key points
13
Train\ Track 2.2.2+
Level 1 Train 2.2.2+
Level 2 Train 2.2.2+
2.3.0d
Train 2.3.0d
Train 2.3.0d
Current
infrastructure
Migrated
infrastructure
• Current 2.2.2.+ Renfe fleet is able to run over all Adif infraestructure in L1.
However, this fleet needs to be migrated to run in all L2 2.3.0.d lines.
• Compatibility achieved in L1 allows the migration of the trains and the
infrastructure in L2 without disruption of the commercial service.
Migration strategy. Summary version compatibility
(+ CR 458)
(+CR 458)
Train 2.2.2+
(with engineering
rules)
14
1. Migration of Level 1 trackside to 2.3.0.d
APS of CCS trackside subsystem + impact analysis on existing vehicles
2. Migration of vehicles to 2.3.0.d
APS of the CCS onboard subsystem + integration with Level 1 network
3. Migration of Level 2 trackside to 2.3.0.d
APS of CCS trackside subsystem + integration of vehicles for the Level 2
operation
Migration strategy. Placing in service
It is required the use of the recommendation 2011/217 after adapting
the works performed in previous APS while better allocating
the responsibilities and strengthening the role of NoBos and
Assessment bodies
15
16
Index
1. Objective
2. ETCS deployment situation
3. Version management and migration plan
4. Compatibility analysis and B3 impact
5. Conclusions
The backwards compatibility analysis between Baseline 3 and Baseline 2
(2.3.0d) must be completed and agreed at the sector level with the
highest priority before the maintenance release
All Baseline 3 trains must be able to run over 2.3.0d infrastructure. All
modifications to Baseline 3 must include a explicit backwards
compatibility analysis.
Baseline 3 Baseline 2
Art 19 of 2012 MoU: As laid down in the 2008 MoU, trains equipped with ERTMS Baseline 3 will be able to run on lines equipped with Baseline 2 version 2.3.0d without any additional technical or operational restrictions created by ERTMS/ETCS. Baseline 3 specifications are based on this principle of backward compatibility. This principle has been the basis of the
work performed by the sector and ERA throughout the writing of the specifications and will be validated as a priority during the finalisation of the Baseline 3 specifications.
Art 17 of 2012 MoU. This MoU recognizes that this version (2.3.0.d) shall remain in force in the future. This will protect the investments made by the sector and interoperability in
countries that have chosen Baseline 2 as their reference.
17
18
Index
1. Objective
2. ETCS deployment situation
3. Version management and migration plan
4. Compatibility analysis and B3 impact
5. Conclusions
Lessons Learnt, what do we need? Stable set of specifications
• This has been achieved in the MoU for the SRS 2.3.0.d and there are active groups working on the rest of specifications
• Migration of the lines to a version compatible with v230d trains, 2.3.0.d covers all the functional and operational needs in the Spanish network
• Backwards compatibility for the new baseline 3 has to be guaranteed
Strengthen the role of the NoBo and assessment bodies
• Harmonised process and certificates
• The certificates contain all the relevant information (deviations)
Clear process for authorisation of placing in service
• Engineering & operational guidelines for critical points
• Separation of authorisation processes: trackside, train and integration.
• All the entities involved should have a clear role
19
Tren 2.3.0.d Tren ‘Baseline
3’
2000 2006 2005 2004 2001 2002 2003 2007 2008 2009 2010 2011 2012 2013
Primeras especificaciones
técnicas del
ERTMS
TSI CCS 2006/679/EG
TSI CCS 2004/446/EG
TSI CCS 2002/731/CE
Incluye
SRS 2.2.2
TSI CSS 201/73/EC
(HS Y CR)
TSI CCS 2007/153/CE
TSI CSS 2006/860/CE
Incluye
SRS 2.3.0
TSI CSS 2008/386/CE
Incluye
SRS 2.3.0.d
MADRID-LERIDA
LERIDA-TARRAGONA
SEGOVIA-VALLADOLID MADID SEGOVIA
CORDOBA-MALAGA LA SAGRA-TOLEDO
TARRAGONA-BARCELONA ZARAGOZA-HUESCA
CERCANIAS MADRID-VALENCIA
BARCELONA-FRONTERA FRANCESA
S121
S130 S103
S120
S102 S102
S104 S104
SRS Baseline 3
LÍNEA PILOTO ALBACETE-VILLAR DE
CHINCHILLA
2015
TSI CCS 2012/88
SRS Baseline
3.4.0
ALBACETE - ALICANTE
??
Modifications of the ETCS specifications
Backwards compatibility of any modification of
the Baselines
Conclusion
Trains equipped with the new ETCS version shall be
able to run in the lines designed with the reference
version baseline 2.3.0.d
20