126
i Updated Environmental Management Plan Stage of the document: Updated Project number: 49026-003 March 2020 VIE: Basic Infrastructure for Inclusive Growth in the North Central Provinces Sector Project Constructing and Upgrading Gio Linh Cam Lo Inter-District Road of Quang Tri Province Prepared by Project Management Unit - Planning and Investment Department of Quang Tri province for the Asian Development Bank.

Updated Environmental Management Plan · 2020. 4. 2. · 1. Location and scope of the subproject 9. The road passes Hai Thai commune, Gio Linh and Cam Tuyen and Cam Thanh communes,

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • i

    Updated Environmental Management Plan

    Stage of the document: Updated

    Project number: 49026-003

    March 2020

    VIE: Basic Infrastructure for Inclusive Growth in the North

    Central Provinces Sector Project

    Constructing and Upgrading Gio Linh – Cam Lo

    Inter-District Road of Quang Tri Province

    Prepared by Project Management Unit - Planning and Investment Department of Quang Tri province

    for the Asian Development Bank.

  • ii

    CURRENCY EQUIVALENTS

    (as of 15 Feb 2020)

    Currency unit – Viet Nam Dong (D)

    D1.00 = $0.000044

    $1.00 = Ð 23,215

    ACRONYMS AND ABBREVIATIONS

    ADB Asian Development Bank

    CPC Commune People’s Committee

    CSC Construction Supervision Consultant

    DARD Department of Agriculture and Rural Development

    DONRE Department of Natural Resources and Environment

    DOT Department of Transportation

    DPC District People’s Committee

    DPI

    ECT

    Department of Planning and Investment

    Emergency Control Team

    EIAR Environmental Impact Assessment Report

    EMP Environmental Management Plan

    EPP Environmental Protection Plan

    ESO Environmental Safeguards Staff

    ESS Environmental Safeguard Specialist

    GMS Greater Mekong Sub-region

    IEE Initial Environmental Examination

    IPM Integrated Pest Management

    LEP Law on Environmental Protection

    MPI Ministry of Planning and Investment

    MPN Most Probable Number of viable cells of a pathogen - a measure of

    water quality

    PPC Provincial People’s Committee

    PPE Personal Protective Equipment

    PPMU Provincial Project Management Unit

    PPTA Project Preparatory Technical Assistant

    ROW Right of Way

  • iii

    SPS Safeguard Policy Statement

    SST Subproject Support Teams

    The PPTA The Project Preparatory Technical Assistant Consultants

    The Project Basic Infrastructure for Inclusive Growth in the North Central

    Provinces Sector Project

    The

    Subproject

    Constructing and Upgrading Gio Linh - Cam Lo Inter-district Road

    of Quang Tri Province

    UXO Unexploded ordnance

  • iv

    WEIGHTS AND MEASURES

    Km2 (square kilometer) – unit of length

    m3 (cubic meter) – A measure of volume

    Note:

    (i) In this report, "$" refers to US dollars.

    The environmental management plan is a document of the borrower. The views expressed herein do

    not necessarily represent those of ADB’s Board of Directors, Management, or staff.

    In preparing any country program or strategy, financing any project, or by making any designation of

    or reference to a particular territory or geographic area in this document, the Asian Development Bank

    does not intend to make any judgments as to the legal or other status of any territory or area.

  • v

    CONTENTS

    Page

    I. INTRODUCTION ...................................................................................................................... 1

    II. DESCRIPTION OF THE SUBPROJECT ................................................................................. 4

    1. Location and scope of the subproject 4 2. Adjustment of Detail Engineering Design 11 3. Description of the environment 17

    III. ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES ........... 25

    1. Potential Impacts Summary 26 2. Environmental Mitigation Plan 29

    IV. monitoring plan ........................................................................................................................ 38

    A. Environmental Policy and Standard 38 B. Performance Monitoring 39

    1. Compliance Monitoring .............................................................................................. 39 2. Environmental Effects Monitoring ............................................................................. 43

    V. INSTITUTIONAL ARRANGEMENT .................................................................................... 45

    VI. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION .................. 47

    VII. CAPACITY BUILDING .......................................................................................................... 49

    VIII. GRIEVANCE REDRESS MECHANISM ............................................................................... 50

    IX. REPORTING ........................................................................................................................... 55

    X. ESTIMATED COST OF EMP ................................................................................................. 56

    XI. CONCLUSIONS AND RECOMMENDATIONS................................................................... 58

    XII. Appendix .................................................................................................................................. 59

    Appendix 1: Photos of the subproject road and the vicinity 59 Appendix 2: Minute of Consultation on DED 61 Appendix 3: Agreement on quarry source, soil borrow pit and dumpsites 66 Appendix 4: National Technical Regulations of Vietnam 76 Appendix 5: Decision on rock quarry, sand sources, borrow pit that potential for the subproject 87 Annex 6: UXO Clearance 109 Annex 7: Consultation on forest land in 3 communes of the subproject 114 Annex 8: Decision of Quang Tri People’s Counsil on aggreement of land use change for projects in Quang Tri

    Province 120

  • vi

    LIST OF FIGURES

    Figure 1 – General Map of Cam Lo, Gio Linh Districts and Subproject Area ..............................................................3 Figure 2: Map of the subproject road ................................................................................................................................4 Figure 3 – Typical Straight Line Section ...........................................................................................................................6 Figure 4 – Bridge over Hieu River .................................................................................................................................... 10 Figure 5. Design of culvert at Km4+467.72 ...................................................................................................................... 10 Figure 6. Location and routes of construction material sources and disposal sites...................................................... 16 Figure 7: Grievance Redress Mechanism ........................................................................................................................ 54

    LIST OF TABLES

    Table 1: Location of bridges on the road ...............................................................................................................................7 Table 2: Design of the Gio Linh – Cam Lo inter-district road ............................................................................................. 11 Table 3: Descriptions of material transportation routes ....................................................................................................... 13 Table 4: Location of samples surface water on the Hieu River............................................................................................ 17 Table 5: Location of samples ambient air quality ................................................................................................................ 18 Table 6: Result of monitoring ambient air quality in 2019 .................................................................................................. 19 Table 7: Environmental Receptors ....................................................................................................................................... 20 Table 8. Summary of Potential Environmental Impacts ...................................................................................................... 26 Table 9 - Environmental Impact Mitigation Plan ................................................................................................................. 30 Table 10 - Environmental Monitoring Compliance ............................................................................................................. 40 Table 12 – Responsibilities for EMP implementation ........................................................................................................ 45 Table 13 – Main issues and information from local authorities ........................................................................................... 48 Table 14 – Main environmental concerns from public consultation .................................... Error! Bookmark not defined. Table 15 – Main environmental concerns from public consultation in DED ....................................................................... 49 Table 16 – Detail capacity building program ....................................................................................................................... 50 Table 17 – Reporting procedures ......................................................................................................................................... 55 Table 18 – Estimated cost for EMP Implementation (2-year construction/ 4-year in total) ................................................. 56

  • 1

    I. INTRODUCTION

    1. The proposed Basic Infrastructure for Inclusive Growth in the North Central Provinces

    Sector Project will invest in implementation of the north central coastal provinces sub-region socio-

    economic development plans. The Project responds to the Government of Vietnam's strategy of

    targeting the use of concessional ODA investment into poorer provinces using economic sub-

    regions as a means of identifying interconnectivity and synergies between provinces to accelerate

    economic growth in provinces that have previously lagged in terms of economic growth.

    2. The project has three outputs being (i) Improved connectivity within value chains and their

    supporting infrastructure; (ii) Improved business development infrastructure; and (iii) Strengthened

    Sub-regional infrastructure planning and management.

    3. The Project has been categorized as B on environmental issues during the Project Concept

    note as it has few potential significantly adverse impacts and none of them are irreversible. During

    the PPTA phase, IEE report was carried out and approved in July 2017 by ADB. Anyhow, in Detail

    Engineering Design (DED), scope of the subproject has changed as follow:

    ✓ Upgrading category V mountainous road to category IV with width from 6.5m to 7.5m;

    ✓ Road alignment has not been changed, only adjust some short sections to ensure safety therefore

    length of the road has been changed from 23.3km to 22.81km;

    ✓ Construct 6 bridges instead of 4 bridges as proposed in FS.

    ✓ There are two new sensitive receptors arising at two new bridge

    ✓ The section from Trang Rong village, Hai Thai commune Gio Linh district to Ban Chua village,

    Cam Tuyen commune Cam Lo district is exactly 3.0km instead of 3.5km as in FS. This section is

    a trail, currently not open to traffic;

    4. According to requirement in Environmental Assessment and Review Framework (EARF),

    with not only extension of width and length of the road but also addition two new bridges at

    Km6+450,17 and Km8+524,35 as detailed design, an updated EMP report needs to be updated and

    approved by ADB.

    5. The purpose of updated EMP is to reflect the changes in detailed design and relevant all

    adverse impacts as well as risks on environment in order to propose adequate and effective

    mitigation measures. The updated EMP takes into consideration environmental impacts and

    appropriate mitigation measures base on change in approved the detailed design.

    6. The subproject is entitled "Constructing and Upgrading Gio Linh - Cam Lo Inter-district

    Road of Quang Tri Province" and is a representative subproject for Output 1 of the Project:

    Improved connectivity within value chains and their supporting infrastructure.

    7. The Gio Linh – Cam Lo inter-district road passes 2 districts, Gio Linh and Cam Lo, and

    connects to provincial road 575B, and on to the Ho Chi Minh highway and to the National road 9.

    The road plays an important role in socio-economic development because it provides access to the

    special economic zones and commercial area at Lao Bao, to seaports such as Cua Viet and My

    Thuy. Currently, vehicles transporting raw materials from Hai Thai commune, Gio Linh district to

    the factories in Cam Lo commune, have to divert onto the Ho Chi Minh road and then to National

  • 2

    Road 9. The proposed subproject will reduce the transport distances and costs of transport to local

    producers and improve economic efficiency for the production area.

    8. The road will benefit traffic for 9,000 people of Hai Thai commune, Gio Linh district (about

    4,000 people) and Cam Tuyen commune, Cam Lo district (about 5,000 people) through connecting

    these people to the district centre areas. Direct beneficiaries are estimated to be over 3,400 who

    will be directly involved in commerce, services, industry and agriculture in Hai Thai commune,

    Gio Linh district (over 2,160 people) and Cam Tuyen commune of Cam Lo district (over 1,480

    people). The road will also serve a total of 8,839ha of industrial and plantation forestry (including

    rubber, coffee etc.) spread between Hai Thai commune (839ha) and Cam Tuyen commune

    (8,000ha).

  • 3

    Figure 1 – General Map of Cam Lo, Gio Linh Districts and Subproject Area

  • 4

    II. DESCRIPTION OF THE SUBPROJECT

    1. Location and scope of the subproject

    9. The road passes Hai Thai commune, Gio Linh and Cam Tuyen and Cam Thanh communes, Cam Lo district, Quang Tri province. The start point (Km0+000) connects to provincial road 575B

    and crosses the Ho Chi Minh trail in the area of Xuan Hoa village, Hai Thai commune, Gio Linh district.

    The end point (Km22+810.93) is the T-junction with National Road No.9 at Km31+120 (which is

    Km17+380 before) in the area of Quat Xa village, Cam Thanh commune, Cam Lo district.

    10. The subproject is basically located on the existing alignment, except for a 3.0 km section from Trang Rong village, Hai Thai commune Gio Linh district to Ban Chua village, Cam Tuyen

    commune Cam Lo district. This section is currently not open to traffic and the proposed subproject

    will upgrade an existing pathway used by local people and the alignment has been approved by the

    PPC.

    Figure 2: Map of the subproject road

    11. The Gio Linh – Cam Lo inter-districts road is formed on the basis of two existing roads (the access road to Ban Chua village, Cam Lo district and Xuan Hoa – Trang Rong road of Gio Linh

    district constructed between 2001 and 2006) and lengthened to Quat Xa village Cam Thanh

    Commune Cam Lo district by new bridge over the Hieu River, which will be constructed in the

    subproject.

    12. The existing road Xuan Hoa – Trang Rong of Gio Linh district has length 11,5km with different width of each section, from 3m to 7m. The road surface is mostly natural gravel or rugged

  • 5

    dirt with many deep and wide trenches. There are only approximate 800m with surface of cement

    concrete still in good condition.

    13. The existing road to Ban Chua village, Cam Tuyen commune has length 9,1km with width

    of road from 2 m to 5m, of which around 1km has surface of cement concrete in good condition,

    the remaining has surface of natural gravel or rugged dirt with many deep and wide trenches. This

    road goes through the villages of Tan Hoa, Tan Lap, and Ban Chua in Cam Tuyen commune. At

    the end of this road is section that currently not open to traffic, it is a trail with length 3.0km formed

    by traveling of local people from Ban Chua village to Trang Rong village.

    14. The lengthened section by new bridge over the Hieu River to Quat Xa village Cam Thanh

    Commune is around 2,2km, of which, 2km with surface of cement concrete in good condition,

    width 5,5m; the rest of the section has surface of rugged natural gravel.

    15. Along of the existing road to Xuan Hoa – Trang Rong of Gio Linh district, on the two sides,

    most area is rubber and melaleuca farms, interspersed a number of houses. Particularly section

    from Km8 + 600 to Km11 + 500 has complex terrain, hill with height from medium to high,

    melalueca forest on both sides. The route has 4 crossing points of streams. The population along

    this route is quite sparse, there are only some small shops in the residential area of Trang Rong

    village and the starting point of the road in Xuan Hoa village.

    16. For the road to Ban Chua village, on both sides of the route are crops, rice fields and houses

    of the people of Tan Hoa, Tan Lap, and Ban Chua village. The population along the road is more

    crowded than the road to Trang Rong village but there are only some small shops. Along the road,

    there are two crossing points of streams, the terrain of this route is relatively flat except 3.0km from

    Ban Chua village to Trang Rong village has complex terrain, hill with height from medium to high,

    melalueca forest around.

    17. The lengthened section to Quat Xa village over the Hieu River, on both sides of the road

    are crop and some houses as well as a primary school and health centre of Quat Xa village. This is

    end point of the proposed road.

    18. The proposed road of the subproject is basically located on the existing alignment of the

    two existing roads and lengthened to Quat Xa village over the Hieu River therefore, environmental

    and social aspect of two roads as well as lengthened section are also conditions of new road of the

    subproject.

    19. In DED period, there are two more points are determined that it is necessary to build bridges

    instead of culvert at Km6+450,17 and spillway at Km8+524,35. At Km6+450,17, it is currently a

    culvert over a small, narrow ditch with vegetable on its sides and melaleuca farm around. In dry

    season, it is a negligible current of water on the ditch, however, in the rainy season, because of

    narrow terrain, water way can be increased quicker and higher that leading to flood. The

    construction of a new bridge will widen the drainage area compared to the present therefore the

    water way will flow faster in the rainy season but will not affect the water way direction.

    Construction new bridge is hardly affected to water way in dry season.

    20. At Km8+524,35, it is currently a small stream with slow current of water and low water

    level in dry season and existing a spillway with lower terrain compared with around area. This area

  • 6

    is also hills planted melaleuca. In the rainy season, water way increases over spillway and leading

    to flood of this point. The construction of a new bridge over the stream will increase the flow rate

    due to the expansion of the river bed at the point while direction of water way will not be changed.

    Furthermore, during the construction time, excavation on the sides can result to obstruct the flow

    and pile driving on the stream can lead to distribution of sediments into the water.

    21. The road is proposed to be upgraded to category IV mountainous road in compliance with

    Vietnamese Standard TCVN 4054-2005, with a roadway width of 7.5 m comprising a 5.5m wide

    carriageway and shoulders of 2x1.0 = 2m. The total right-of-way (ROW) including side drainage

    will generally be 14.5m. The proposed road is 22,810 km long.

    - Design velocity: 40km/h

    - Width of subgrade: 7.5m

    - Width of pavement (carriage-way): 5.5m

    - Width of shoulder: 2 x 1.0m

    - Normal crossfall (%): 2%

    - Max. Super elevation (%): 8%

    - Pavement structure: Bitumen Surface Treatment

    Figure 3 – Typical Straight Line Section

    12. Bridges on the road: On the route, 6 new bridges will be designed for construction including

    (i) a slab beam bridge at Km6+450,17; (ii) a slab beam bridge at Km8+524,35; (iii) a slab

  • 7

    beam bridge at Km11+521,78; (iv) a slab beam bridge at Km16+668.19 (v) a slab beam

    bridge at Km17+811,98; (vi) a slab beam bridge at Km20+662,61; These bridges will be

    designed with design flood frequency P = 4% for small bridges and P = 1% for medium

    and large bridges, as following table.

    Table 1: Location of bridges on the road

    No Name +

    Chainage

    Beam / L

    bridge

    (m)

    Width

    (m) Note

    Descriptions of affected water ways

    1

    Slab beam

    bridge at

    Km6+450,17

    (added

    during DED)

    3I7 / 21.70

    8.5

    (7.5 +

    2x0.5)

    The new

    bridge is

    added in

    DED, P = 4%

    The construction of a new bridge will widen

    the drainage area compared to the present

    therefore the water way will flow faster in the

    rainy season but the water way direction will

    not be affected. It is hardly affected to water

    way in dry season.

    This is a natural flow with main water source

    from rain and it is not to be used for living

    activities or irrigation. Around the flow is

    natural vegetable, bambo and melaleuca

    farm, there is not special flora and fauna

    species in this area.

    2

    Slab beam

    bridge at

    Km8+524,35

    (added

    during DED)

    6l7 / 42.70

    8.5

    (7.5 +

    2x0.5)

    The new

    bridge is

    added in

    DED, P = 1%

    The construction of a new bridge instead of

    existing spillway over the stream will

    increase the flow rate due to the expansion of

    space for drainage at the point while

    direction of water way will not be changed.

    Furthermore, during the construction time,

    excavation on the sides can result to obstruct

    the flow and pile driving on the stream can

    lead to distribution of sediments into the

    water.

    This is a natural flow with small shrubs and

    grass on the sides, surrounded by melaleuca

    forest interspersed with some species of

    bamboo and eucalyptus that grow naturally.

    The water from the flow is not to be used for

    living activities or irrigation. Furthermore,

  • 8

    No Name +

    Chainage

    Beam / L

    bridge

    (m)

    Width

    (m) Note

    Descriptions of affected water ways

    there is not special flora and fauna species in

    this area

    3

    Slab beam

    bridge at

    Km11+521,7

    8

    21/32.10

    8.5

    (7.5 +

    2x0.5)

    Design new

    bridge P =

    4%

    The construction of a new bridge instead of

    existing spillway over the stream will

    increase the flow rate due to the expansion

    space for drainage at the point while

    direction of water way will not be changed.

    Furthermore, during the construction time,

    excavation on the sides can result to obstruct

    the flow and pile driving on the stream can

    lead to distribution of sediments into the

    water.

    This is a natural flow with small shrubs and

    grass on the sides, surrounded by melaleuca

    forest interspersed with some species of

    bamboo that grow naturally. The water from

    the flow is not to be used for living activities

    or irrigation. There is not special flora and

    fauna species in this area

    4 Slab beam

    bridge at

    Km16+668,19

    21 / 31.10

    7.5

    (6.5 +

    2x0.5)

    Bridge over

    La La stream,

    P = 4%

    The construction of a new bridge instead of

    existing spillway over the stream will

    increase the flow rate due to the expansion of

    space for drainage at the point while

    direction of water way will not be changed.

    Furthermore, during the construction time,

    excavation on the sides can result to obstruct

    the flow and pile driving on the stream can

    lead to distribution of sediments into the

    water.

    This is a natural flow with small shrubs and

    grass on the sides, surrounded by melaleuca

    forest interspersed with some species of

    bamboo that grow naturally. The water from

    the flow is not to be used for living activities

    or irrigation. There is not special flora and

    fauna species in this area.

  • 9

    No Name +

    Chainage

    Beam / L

    bridge

    (m)

    Width

    (m) Note

    Descriptions of affected water ways

    5 Slab beam

    bridge at

    Km17+811,98

    2l15 /

    42.15

    7.5

    (6.5 +

    2x0.5)

    Bridge over

    La La stream,

    P = 4%

    The construction of a new bridge over the

    stream will not affect to direction of water

    way as well as flow rate compared with the

    present because new bridge will not widen

    the river bed. Anyhow it can be flowed

    quickly in flooding time in comparison the

    existing bridge. Furthermore, during the

    construction time, excavation on the sides

    can result to obstruct the flow and pile

    driving on the stream can lead to distribution

    of sediments into the water.

    This is a natural flow with small shrubs and

    grass mixed with some naturally growing

    bamboo species and melaleuca forest on the

    sides. There are some sections intermingled

    with arable land of local people on its sides.

    Anyhow water from the stream is not to be

    used for living activities and irrigation. There

    is not special flora and fauna species in this

    area.

    6 Slab beam

    bridge at

    Km20+662,61

    4I33 /

    150.35

    7.5

    (6.5 +

    2x0.5)

    Design new

    bridge over

    Hieu River, P

    = 1%

    The construction of a new bridge over the

    stream will not affect to direction of water

    way as well as flow rate compared with the

    present because new bridge will not widen

    the river bed. Anyhow, during the

    construction time, excavation on the sides

    and poor handling of materials as well as pile

    driving on the river can cause blockages and

    release of silt into the river. Runoff water

    during rain could also bring waste and soil

    into the Hieu River, leading to a temporary

    reduction in water quality and impact

    downstream user of Hieu River including

    Cam Lo town and Dong Ha city.

    At this section of the Hieu River, water from

    the stream is not to be used for living

  • 10

    No Name +

    Chainage

    Beam / L

    bridge

    (m)

    Width

    (m) Note

    Descriptions of affected water ways

    activities and irrigation. There is not special

    flora and fauna species in this area. On the

    sides, small shrubs and grass mixed with

    some bamboo species and eucalyptus

    naturally grow.

    Figure 4 – Bridge over Hieu River

    13. Culverts on the route: consist of 118 culverts across the road, pipe culvert (52 items), box

    culvert (18 items) and reinforced concrete culverts (48 items). They are built at locations

    where drainage is required on roads and at cross-section of irrigation canals and ditches.

    14. Others works along the road includes trenches with size 40x40x120(cm); reinforcing taluy

    roofs with paving slabs in frequently flooded sections and embankment sections over hilly

    terrain; retaining walls designed at steep slopes (> 50%) that cannot be covered with

    conventional embankments; guardrail wall with reinforced concrete foundation.

    Figure 5. Design of culvert at Km4+467.72

  • 11

    2. Adjustment of Detail Engineering Design

    15. In PPTA phase, the Gio Linh – Cam Lo inter-district road is proposed to be upgraded to category

    V mountainous road in compliance with Vietnamese Standard TCVN 4054-2005, with an

    embankment width of 6.5 m pavement of 3.5m and shoulders of 2x1.5=3m. In DED, the road was

    adjusted to category IV mountainous road as Vietnamese Standard. Table below summarizes

    changes of subproject activities from the FS and the detailed design in 2019.

    Table 2: Design of the Gio Linh – Cam Lo inter-district road

    Items Basic design (FS report) Detailed design

    1. 1. Route length 23,300 km 22,810 km

    2. Technical index

    Design velocity: 30km/h

    Width of subgrade: 6.5m

    Width of pavement (carriage-

    way): 3.5m

    Width of shoulder: 2 x 1.5m

    Normal cross fall (%): 2%

    Max. Super elevation (%): 6%

    Pavement structure: BST

    Design velocity: 40km/h

    Width of subgrade: 7.5m

    Width of pavement (carriage-way): 5.5m

    Width of shoulder: 2 x 1.0m

    Normal cross fall (%): 2%

    Max. Super elevation (%): 8%

    Pavement structure: BST

    3. Other construction items

    4 bridges

    6 bridges

    There are two more points are determined

    that it is necessary to build a bridge instead

  • 12

    of culverts, these are bridges at

    Km6+450,17 and Km8+524,35.

    a. Construction Material Sources

    16. During the period of PPTA, the technical consultant, after consulting with the local authorities,

    came up with some suitable quarries including 1 rock/stone quarry, 6 sand / soil sources which

    meet the required capacity for the construction project and acceptable transport distance. In the

    detailed design phase, the DED consultant conducted a survey and worked with local

    authorities on the soil borrow pits as well as disposal sites which are suitable for construction

    of sections on the road. The minutes of working on soil borrow pits are shown in Annex 4.

    Specific information about the material sources is as follows:

    Quarry source: All quarries potentially used for the subproject are checked legal status by DED

    consultant and PMU. All related legal documents on these source are enclosed in Annexes.

    17. The estimated volume of rock to be used for the subproject construction is 54,000 m3. Tan Lam

    quarry: situated on the side of 9 Road at Km28+00 along road to Lao Bao, Cam Thanh

    Commune, Cam Lo district with an area 8.3ha and a capacity of 3,000,000m3. It is about

    10.6km from the quarry to the start point of the construction site and is served by an asphalt

    road. This quarry are exploited by two companies: Joint venture of Thien Tan JSC and Tan

    Hung JSC with license No 1190/QD-UBND dated 6/7/2012 (valid for 10 years); Joint Venture

    Quang Tri Construction – Transportation JSC and Minh Huong Company Ltd with license No

    1191/QD-UBND dated 6/7/2012 (valid for 10 years)

    18. Soil borrow pit and gravel source: The estimated soil volume to be used for the subproject

    construction is 190,000 m3. The volume of excavated soil that can be reused as fill soil is 81,000

    m3. The rest will be purchased from the following borrow pits:

    (i) Hill gravel quarry in Gio An 2: situated to the left of the provincial road 575B at Km6

    + 000, 6km from the start point in Gio An Commune, Gio Linh district. The quarry is

    within the Quang Tri planning area and approved as a quarry by Decision No.

    2242/QD-Committee dated 10.15.2015. The licensed area for quarrying is 19ha in

    extent and the estimated reserves are 2,500,000m3. The site has a mixture of soil and

    gravel which is of suitable quality for road surfacing. The distance from the quarry to

    the start point is about 6 km along provincial road 575B which has an asphalt concrete

    pavement

    (ii) Cam Chinh soil borrow pit : situated of the provincial road 585 at Km4+800, in Cam

    Chinh commune, Cam Lo district. The quarry is within the Quang Tri planning area

    and approved as a quarry by Decision No. 2242/QD-Committee dated 10.15.2015. The

    licensed area for quarrying is 19ha in extent and the estimated reserves are 500.000m3

    Visual inspection shows that material at the site is clay and gravel, sections of

  • 13

    weathered siltstone clay, golden brown stone and pale yellow, semi-hard state. Soil

    quality at the mine is satisfactory for use in roadbed embankment works. The distance

    from the quarry to the middle of section 2 (Km12+367,99 - Km20+576,81) is 14,9km

    and to the middle of section 3 (Km20+576,81 - Km22+810,93) is 8,7km.

    19. Sand Source: On the route, there are 02 sand suppliers: a sand yard at Hieu River at Dong

    Ha city and another at Thach Han River in Quang Tri commune. These sand sources are

    approved by Decision No 3330/QD-UBND dated 28/12/2016 (see Annex 4). Details are as

    follows:

    (i) The yard at the Hieu River is on the left bank, on the side of Dong Ha Bridge at

    Km756+800 on route 1A. The material includes small grain sand, gravel, medium

    grain sand of high quality and has substantial reserves, sufficient to meet the technical

    requirements and volume of construction works for bridge and drain construction for

    the project. The distance from Hieu River yard to the work site is approximately 18km,

    involving travel for 10km along the Dong Ha city bypass, 1km on the Ho Chi Minh

    Road to the East and 7km on the Cau Duoi road to Tan Hoa. All these routes have

    good quality asphalt surfaces.

    (ii) The yard at Thach Han River is on the right bank, near the Thach Han Bridge in Quang

    Tri commune at Km770 + 100 on road 1A. The material includes small grain sand,

    gravel, medium grain sand of high quality and sufficient reserves to meet the technical

    requirements and volume for bridge and drain construction for the subproject. The

    distance from the yard to the end point of construction is approximately 28.8km along

    good quality asphalt surfaced roads.

    20. Asphalt concrete: taken from the asphalt concrete plant at Km27 - QL9 in Thuong Lam

    village, Cam Thanh commune, Cam Lo district. This concrete plant belongs to Viet Ren

    Joint Stock Company with head office is located in QL9, Dong Ha City. This plant provides

    asphalt concrete for construction sites in nearly districts and it operates legally with

    permission of the local government. The distance from the mixing plant to the Km0+0 of

    the road is 36km and to the end point of the road is 10,7km.

    21. Total of volume of excavation (including rock and soil) is 244,000 m3, total volume of spoil

    is 170,000 m3 , an amount of excavation soil is reused.

    22. Material transportation routes include sensitive receptors are listed in the below table

    Table 3: Descriptions of material transportation routes

    Material Sources Transportation Routes Sensitive Receptors

    4. 1. Tan Lam quarry

    A distance of 10km from the No 9

    National Road to the construction

    site on direction to Cam Lo Town

    Residence area of Cam Thanh

    commune along the No 9

    National Road

    5. 2. Gio An 2 borrow pit 6 km from Road 575B to Km 0+0 of

    the subproject at Tan Hoa village Maleleuca farm and crop land

  • 14

    6. 3. Cam Chinh borrow pit

    A distance of 8,7 km from

    provincial road 585 to Km22+810

    on direction to Cam Lo Town, and

    the No 9 National Road to Lao Bao

    Residence area of Cam Chinh

    commune along 585 Road and

    the No 9 National Road

    7. 4. Sand sources from Hieu River and Thach Han river

    The distance from Hieu River yard to

    the work site is approximately 18km,

    involving travel for 10km along the

    Dong Ha city bypass, 1km on the Ho

    Chi Minh Road to the East and 7km

    on the Cau Duoi road to starting point

    of Tan Hoa village.

    For section in Cam Lo district, this

    sand source will be transported from

    Dong Ha City to Cam Thanh

    Commune by the No 9 National

    Road.

    Sand sources from Thach Han river

    will be transported via a NR No1 and

    NR No 9 to end point of the road in

    Cam Thanh Commune – Cam Lo

    district with distance approximate

    29km.

    Residence area in Dong Ha

    city along the transportation

    route ; Cau Duoi Bridge;

    Residence area of Tan Lap, An

    Khe Village along the Ho Chi

    Minh Trail road to the East;

    Residence area in Cam Lo

    Town and Cam Thanh

    Commune.

    5. Asphalt concrete plant

    Transportation road is NR No9 from

    Thuong Lam village to Km22+810 in

    Quat Xa Village, Cam Thanh

    commune with distance of 10,7km

    Residence area of Thuong Lam

    and Quat Xa village along the

    NR No9

    b. Disposal sites

    22. The subproject will use disposal sites in Hai Thai commune, Gio Linh district and in Cam

    Tuyen commune, Cam Lo district. Volume of sites in Hai Thai commune is expected to

    54.000 m3 on 4ha area. Besides, Cam Tuyen disposal sites have volume of 224.000 m3 on

    12,2ha. Total area of disposal sites is 16,2ha with volume of 278,000 m3. The dumpsites

    are located along the subproject road, in vacant lands at Km3+288 and gardens of

    households at Km8+253 of Hai Thai Commune; in vacant lands at Km 11+608 of Cam

    Tuyen village, Km14+744 of Ban Chua Village, Km 17+153 at Tan Quang Village,

    Km19+379 and Km20+700 of Quat Xa village. Distance from the subproject road to

    dumpsites is approximate 500m to 1,5km. Therefore, the transportation route to disposal

    sites is current road of the subproject and trails to vacant lands or garden. As result in,

    sensitive receptors of transportation route are the same with the subproject road at

    corresponding section.

  • 15

    23. The minute of agreement on the location of disposal site has been established among Hai

    Thai and Cam Lo CPC, detailed design Consultant, and land owner, see more in Annex 4.

    24. Location and routes of construction material sources and disposal site in the Figure 6

  • 16

    Figure 6. Location and routes of construction material sources and disposal sites

  • 17

    3. Description of the environment

    a. Surface water

    Surface water resources and quality

    23. The main water bodies in the subproject area are the Hieu River, and the Da Mai and Tan

    Kim Reservoirs in Cam Lo district. As stated in the State of the Environment (SOE) 1 report

    for Quang Tri, 2019, the surface water quality in the Hieu River was monitored but these

    reservoirs was not and water quality of La La stream and other ravines was not also taken

    sampling in the monitoring report in 2019 of Quang Tri province.

    24. Monitoring program of Quang Tri province was taken place during whole the year and

    sampling surface water and air quality every month. Locations for monitoring surface water

    are 32 points in whole province, of which there are two points nearly the project area in Cam

    Lo district. Ambient air quality are taken sampling at 25 points in the province and there are

    two points in Cam Lo district nearly the subproject area.

    25. Parameters were monitored: pH, F-, TSS, DO, BOD5, COD, NO3-N, NH4-N, PO4-P, Fe,

    Total grease and oil, E.coli, Coliform.

    26. Location of samples surface water on the Hieu River was presented in below table:

    Table 4: Location of samples surface water on the Hieu River

    No Location Label Coordinates Distance to subproject

    location X Y

    1 Dau Mau

    Hydrological station,

    in Cam Thanh

    commune

    SH1QG1

    571301 1857216

    Distance to point will be

    constructed bridge over the

    Hieu River is nearly 1km to

    upstream

    2

    Cau Duoi Bridge –

    Cam Lo district SH2 581077 1860470

    Distance to point will be

    constructed bridge over the

    Hieu River is nearly 7km to

    downstream.

    27. As stated in State of Environment Report of Quang Tri 2019, the situation of parameters as

    below:

    28. pH: At all monitoring locations, the pH of river water is within the limit of column B1 of

    QCVN 08, but there is a large variation according to space (locations) and time (months /

    times of monitoring). The pH value at monitoring point of the hydrological stations Dau

    Mau and Cau Duoi bridge is higher than the limit of column A2 in 2029 but is still under

    the limit of Column A1.

    29. NH4-N: NH4-N parameters at all monitoring locations are within the allowed limits of

    column B1 of QCVN08-MT:2015/BNTMT. The location at Dau Mau hydrological station

    has monitoring results of this parameter lower than that at Cau Duoi Bridge.

    1 Quang Tri SOE 2019

  • 18

    30. BOD5, COD, DO: Monitoring results of DO, BOD5, COD parameters in 2019 at all river

    water locations are within the allowable limit of column A2 of QCVN08-

    MT:2015/BNTMT. DO parameters range from 5.5-6, 8 mg / l, BOD5 ranges from 1.1 to

    4.7 mg / l, COD ranges from 3 mg / l to 13 mg / l.

    31. TSS parameters: Most of the river water quality monitoring times have TSS parameters

    within the permissible limit of column A1 of QCVN08-MT:2015/BNTMT at Cau Duoi

    Bridge and hydrological station Dau Mau. Particularly result of the location at the

    hydrological station of Dau Mau (SH1QG1) exceeds the limit of column B1 1.4 times in

    November.

    32. NO3-N Parameter: Results of monitoring NO3-N parameters of river water environment at

    all positions are within the permitted limits of column A2 of QCVN08-MT:2015/BNTMT

    and fluctuate within

  • 19

    1 Sampling point is

    opposite area of Thien

    Tan Rock Quarry in

    Cam Thanh commune,

    Cam Lo district

    K42 566201 1856713

    Distance to end of point at

    Km22+810 (T-junction with

    NR9) in Quat Xa village is

    nearly 1,5km

    2

    At NR9 near the Cam

    Lo Post Office in Cam

    Lo Town

    K39 579019 1859059

    Distance to end of point at

    Km22+810 (T-junction with

    NR9) in Quat Xa village is

    nearly 3,5km

    39. The result of monitoring ambient air quality in 2019 as below:

    Table 6: Result of monitoring ambient air quality in 2019

    Location TSP (µg/mᶟ) Noise (dB(A)) CO(µg/mᶟ) SO2(µg/mᶟ) NO2(µg/mᶟ)

    min-max min-max min-max min-max min-max

    K39 249 – 306 68,4 – 73,4 MDL – 2596 MDL – 32 14 – 25

    K42 250 – 278 66,1 – 68,8 2119 – 2308 23 – 28 19 – 35

    QCVN 05:

    2013/BTNMT 300 30.000 350 200

    QCVN 26:

    2010/BTNMT 70

    40. The dust in the air at most locations is within the permissible limits of QCVN 05. However,

    the weather from March to September is hot and dry, the humidity in the air is low, so the

    dust particles are weak adhesive, easily attracted to the air. So the dust is larger than other

    times and exceeds the allowed limit of QCVN 05 in some locations. In particular, in

    locations of main roads and large vehicle concentration areas such as the location of Cam

    Lo town (K39), the dust concentration is approximately and over the permitted limit by 1.5

    times in August.

    41. Noise at most locations in 2019 is smaller than the permissible limit of QCVN 26 for normal

    areas from 6am - 9pm. Particularly in some locations on the main roads such as Cam Lo

    town (K39), Thien Tan rock Quarry area (K42), the noise regularly approximates and

    exceeds the limit of QCVN 26 and fluctuates within about 60.3 - 76.3 dB (A)

    42. Concentrations of toxic gases SO2, NO2, CO in 2019 at all monitoring locations are within

    the permitted limits of QCVN 05, concentrations of NO2 fluctuate in the range of 8 - 74 µg

    / m³, SO2 fluctuates in the range < MDL (17 µg / m³) - 53 µg / m³, CO ranges from

  • 20

    land, the impact of road construction could cause forest fires or tree breakdown due to the

    operation of machines and workers. In the operation phase, the new road will increase

    accessibility to the forest as vehicles can flow easily.

    Unexploded Ordnance

    46. Along the subproject road, there is some possibility that UXO remains from

    wartime, especially for Quang Tri, the province that suffered the most in the aftermath of the

    war.

    Therefore, PMU BIGG2 signed a contract with Enterprise 319.9 of 319 Corporation, Ministry

    of Defense to detected and cleared UXO along the road. The clearing UXO was completed in

    November 2019.

    Sensitive receptors

    47. Sensitive receptors of the road are identified in the below table

    Table 7: Environmental Receptors

    Environmental Receptors Description on receptors

    Water Receptors – rivers, streams, canal

    Canal at Km4+467.72

    Natural ditch at Km6+450,17

    There are some canals, streams and river

    run crossing to the road in including:

    • Canal at Km4+467.72 for irrigation in Xuan Hoa Village

    • Natural ditch at Km6+450,17 in Trang Rong Village

    • Stream at Km8+524,35 in Trang Rong Village

    • Stream at Km11+521,78 in Trang Rong Village

    • La La River at Km16+668,19 in Ban Chua vilalge

    • La La River at Km17+811,98 Tan Hoa Village

    • Hieu River at Km20+662,61 in Quat Xa Village

  • 21

    Environmental Receptors Description on receptors

    Stream at Km8+524,35

    Stream at Km11+521,78

    La La River at Km16+668,19

    La La River at Km17+811,98

  • 22

    Environmental Receptors Description on receptors

    Hieu River at Km20+662,61

    Ecological Receptors

    Typical vegetation in section in Hai Thai ommune

    Along the road, all most area in Hai Thai

    Commune is Melaleuca and Rubber trees,

    some area the vegetation is a mixture of

    grass, shrub and melaleuca or rubber trees.

    A mature trees that may need to be removed in Trang

    Rong village

  • 23

    Environmental Receptors Description on receptors

    Typical vegetation in section to Ban Chua village

    Typical vegetation in section in Quat Xa village

    In the section to Ban Chua village, the

    vegetation is a mixture of crop field, of

    grass, shrub and melaleuca or rubber trees.

    In section of Quat Xa village – Cam Thanh

    Commune including place will be

    constructed new bridge over Hieu River,

    the vegetation is a mixture of grass, shcrub

    and some kind of tree such as bamboo,

    banana and meliaceae.

    Cultural Receptors

    Cultural house of Trang Rong village

    Graves at sides of the road in Quat Xa Village

    A cultural house of Trang Rong village is

    located at right side of the road.

    Graves at sides of the road in Quat Xa

    Village

    Infrastructure

  • 24

    Environmental Receptors Description on receptors

    Power lines along section from the beginning point to

    Trang Rong village

    Power lines on both sides of the road at Quat Xa

    village Cam Thanh Commune

    Along the road from the beginning point to

    Trang Rong village has a power line are

    outside of ROW therefore no electricity

    poles need to be moved for this road.

    Along the section to Quat Xa village Cam

    Thanh Commune, there are power lines and

    electricity poles are located on the both

    sides of the road.

    Health Receptors –

    Hospital, Health Centre, Clinic

    There is a health centre of Cam Thanh

    Commune is located on the left of the road

    at T-junction with NR 9

    Educational Receptors -

    Schools, University, Kindergarten

    Cam Thanh Primary school in Cam Thanh commune

    There are 3 primary schools one in Ban

    Chua Village, one in Tan Kim village -

    Cam Tuyen commune and one in Cam

    Thanh commune

  • 25

    Environmental Receptors Description on receptors

    Residential Receptors –and Businesses/Livelihoods

    Residence are in Quat Xa village

    Restaurant at the beginning point of the road inTan Hoa

    Village

    Residence are in Trang Rong village

    Residential receptors are Trang Rong, Ban

    Chua, Tan Lap, Quat Xa village and a

    number of houses are located dispersed

    along the road.

    There are some small restaurants/shops

    currently are located dispersed along the

    road.

    III. ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES

    43. This section discusses the potential environmental impacts of the subproject and

    identifies mitigation measures to minimize the impacts in all pre-construction, construction and

    operation phases of the subproject.

    44. The potential environmental impacts as well as the mitigation measures associated with

    the pre-construction, construction and operational phases are assessed below. The criteria for

    assessment are in line with ADB's Safeguard Policy Statement 2009 and the Government of

    Viet Nam standards based on the Environmental Protection Law (2014). Where government

    standards or guidelines have some kind of conflict with the ADB SPS, the ADB SPS will be

    applied as the policy for the subproject implementation.

  • 26

    45. ADB safeguard policy statement (SPS) 2009 imposes safeguard requirements for all its

    funded projects. The SPS 2009 clarifies the rationale, scope and contents of the environmental

    assessment. It emphasizes environmental and social sustainability in progress of economic

    growth and poverty reduction in Asia and the Pacific, with the following aims:

    • Avoid adverse impacts of projects on the environment and affected people, where possible;

    • Minimize/mitigate and/or compensate for adverse impacts on environment and affected people

    when avoidance is not possible; and

    • Help borrowers/clients to strengthen their safeguard systems and develop the capacity to

    manage environmental and social risks

    46. For environmental safeguards, the Subproject is initially categorized as ‘B’. A

    subproject that is classified as category A on environmental safeguards would be ineligible as

    a BIIG 2 subproject.

    47. Due to the change in the detailed design compared to the FS such as widening the

    roadbed by 1m, reducing the length of 500m, building 2 more bridges, the environmental

    impacts are added at two points (Km6+450,17 and Km8+524,35) where two new bridges will be

    built in comparison with the impact identified in the IEE report. Additional impacts take place

    during the construction phase, and these impacts are flow rate of runoff and surface water

    quality. They are assessed in moderate level and are the most significant change on impacts in

    detailed design phase.

    48. Potential impacts was identified in the original IEE report as well as additional impacts

    are presented in the next section.

    1. Potential Impacts Summary

    Table 8. Summary of Potential Environmental Impacts

    Issues Potential Impacts

    Pre-construction Phase

    Land acquisition and

    resettlement The impact is mainly on the residential area along the road including

    Hai Thai commune center in Gio Linh district; Tan Hiep and Tan

    Hoa villages, Cam Tuyen commune and Quat Xa village in Cam

    Thanh commune, Cam Lo district.

    The subproject will affect approximate 160 households consist of

    ethnic minority, poor and vulnerable households. The subproject

    also affects perennial crop land, production forest land, annual crop

    land and public land with total area is around 7,2ha.

    Production forest land acquisition ( 5.4 ha) will reduce temporary

    forest land areas of two districts but it does not have significant

    impact to environment. Because, acquired forest area is scattered

    along the existing road, almost of this forest land is planted

    melaleuace which are periodically harvested by cutting down and

  • 27

    Issues Potential Impacts

    replaced by a new plantation. Therefore, the forest land acquisition

    will not affect significant to surrounding environment as well as

    erosion of soil.

    Site clearance The impact is mainly on the residential area along the road including

    Hai Thai commune center in Gio Linh district; Tan Hiep and Tan

    Hoa villages, Cam Tuyen commune and Quat Xa village in Cam

    Thanh commune, Cam Lo district

    The subproject also affects land, tree, crop and structures of some

    households, organizations and enterprises.

    Disturbance of

    Unexploded Ordnance

    (UXO)

    In November 2019, UXO was cleared by a military unit according

    to contract with PMU.

    Construction Phase

    Disfiguration of landscape/

    Tree and vegetation

    removal

    Construction work will involve some removal of trees along the

    route, mainly along the 3.0 km section of new road and other trees

    cultivated by people who live along the road. Land clearance at the

    3.0 km section will involve minor alteration of the landscape. The

    impacts will take place over 24 months of construction time.

    Impact on crossing

    streams or bridge

    construction locations

    The construction of new bridges may increase the flow rate in rainy

    season due to expansion of space for drainage at that points although

    direction of water way will not be changed. During the construction

    time, excavation on the sides can result to obstruct the flow and pile

    driving on the stream can lead to distribution of sediments into the

    water. Furthermore, careless construction and poor handling of

    materials at bridge sites can cause blockages and release of silt into

    streams and other waterways. Runoff water during rain could bring

    waste and soil into streams and the Hieu River, leading to a

    temporary reduction in water quality and impact downstream user

    of Hieu River including Cam Lo town and Dong Ha city.

    All streams are natural flows and it is not to be used for living

    activities or irrigation as well as aquaculture production except

    some section of the Hieu River at downstream. Anyhow, the

    implementation of subproject except impacting from construction

    activities that are mentioned above, it does not affect to water uses.

    Surface water pollution

    The surface water quality of the subproject area could be degraded

    due to silt runoff, release of chemicals used in construction and of

    sanitary wastes from workers camps: (i) surface and subsurface

    water resources may be contaminated by fuel and chemicals used in

    construction, or by solid waste and effluent generated by the

    kitchens and toilets at construction campsites; (ii) streams and the

    Hieu River may subject to release of silt from borrow materials

  • 28

    Issues Potential Impacts

    piled near the construction area (iii) water in streams could be

    temporary blocked during construction period at the crossing

    positions.

    The impacts will mainly on water bodies along the subproject road

    and worker camps area, especially at crossing point with the Hieu

    River as the main water source for Cam Lo Water Supply Factory

    is Hieu River with the intake point located downstream of the

    subproject area.

    All streams are natural flows and it is not to be used for living

    activities or irrigation as well as aquaculture production except

    some section of the Hieu River at downstream so impact to water

    use as mentioned above.

    Impact related to material

    transportation and Storage

    Material transportation from Dong Ha city, communes of Cam Lo,

    Gio Linh districts via NR No1, NR No9, Ho Chi Minh Trail and

    some urban roads. This can affect to residence areas along these

    roads by dust, noise, exhaust air from vehicles as well as risk of

    traffic accidents. Besides, storage of construction material can cause

    traffic jam, surface water dust pollution or community safety.

    Impacts on dust and air

    pollution

    Earthworks and rock crushing activities will be the main sources of

    dust.

    Construction machines and vehicles will generate gaseous

    emissions (NOx SOx, CO, CO2, etc.) when they are in operation.

    Bitumen activity will also generate gas and odor.

    These gaseous emissions, dust could cause respiratory problems for

    residents who live along the subproject road likes Trang Rong, Ban

    Chua, Quat Xa, Tan Hoa and Tan Lap villages.

    Civil nuisance impact

    including:

    - noise, vibration,

    - increased traffic,

    - worker & public

    accidents and safety

    - Construction machines will also create noise during their

    operation.

    - Local people and people from other areas who travel on the

    subproject road will be affected during the 24 month construction

    period due to there is the only route for local people in several

    villages of Hai Thai and Cam Tuyen to access the Ho Chi Minh road

    and National Road No.9.

    - Works and the public are at risk of accidents associated with

    construction, particularly excavations, and operations involving

    heavy machinery. Material transport and construction activities on

    the existing road may create the risk of traffic safety and affect

    houses and other structures on roadsides, particularly on the

    residential areas along the road.

    - The influx of construction workers can cause (i) a burden on local

    public services like electricity and water supplies; (ii) risks of

    transmission of diseases in the subproject area; (iii) conditions theat

  • 29

    Issues Potential Impacts

    favour thte spread of diseases such as sore eyes, cholera, flu and

    respiratory problems; (iv) risks of social problems such as those

    associated with gambling, drug use, prostitution, and violence. The

    impacts would be on both workers and on the communities near the

    construction sites in residential.

    Erosion

    Erosion can happened at slopes such as in 3.0km connected Trang

    Rong and Ban Chua, and at crossing streams or bridge construction

    locations. Erosion can affect to surface water quality or taluy, suface

    of the road as well as vegetation around.

    Solid/liquid wastes

    Solid/liquid wastes from construction and worker activities can

    bring about land contamination, surface water quality and

    surounding environment of construction sites, worker camps.

    Borrow pits and Spoil

    Management

    Borrow pits can lead to erosion, loss vegetation around or dust of

    vehicles transportation, so all borrow pits will be used for the

    subproject need to get permission of DONRE with measures to

    reduce those impact.

    Spoil/excavated soil can obstruct flows at crossing streams,

    conterminate surface water, affect to traffic at residence area on the

    road.

    Site clean up

    When construction work has been completed, any un-collected

    waste or abandoned borrow pits pose potential hazards to people

    and land as well as being unsightly.

    Operation Phase

    Increased traffic

    The upgrading of the road is likely to increase the vehicle speed on

    the road, leading to increased traffic congestion, traffic accidents.

    2. Environmental Mitigation Plan

    49. The anticipated environmental impacts and mitigation measures discussed in the

    previous section are presented in Table 4. The table also shows responsibilities and

    timeframe/schedule for implementation of mitigation measures and monitoring.

    50. To ensure implementation of mitigation measures during construction, the EMP shall

    be included in the tender and contract documents for civil works. Contractors’ conformity with

    environmental contract procedures and specifications shall be regularly monitored by PMU

    with assistance from CSC and results shall be reported semi-annually to ADB.

  • 30

    Table 9 - Environmental Impact Mitigation Plan

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    Pre-construction Phase 1. Land

    acquisition and

    resettlement

    Loss of trees and

    disfiguration

    landscape

    1. Land Acquisition and Resettlement Report of the subproject is being

    updated and the report will be submitted to PPC/ADB for approval.

    2. PMU will also inform Cam Tuyen, Cam Thanh, Gio An, Hai Thai

    CPCs, local people and affected households, companies all information

    related to the road construction in advance.

    3. With approximate 5,4 ha production forestland acquisition, besides the

    implementing the compensation in accordance with regulations, Quang

    Tri PMU will implement afforestation/reforestation as defined in article

    21, the Law on forestry 2017:

    - Quang Tri PMU shall develop the plan of afforestation and reforestation

    to summit to the Quang Tri PPC for approval. If the approved plan is not

    implemented, Quang Tri PMU shall pay an amount to the Quang Tri forest

    protection and development fund.

    - The amount remitted into the Quang Tri Forest Protection and

    Development Fund is equal to the afforestation/reforestation area

    multiplies by the unit price per ha decided by Quang Tri PPC; Quang Tri

    PPC shall decide to use the amount paid to such fund to carry out the

    afforestation/ reforestation in the Quang Tri province.

    - If the Quang Tri PPC fails to implement the afforestation/ reforestation

    program within 12 months from the day on which the Quang Tri PMU

    make full payment to the Quang Tri forest protection and development

    fund, the payment shall be transferred to the national forest protection and

    development fund in order to implement the afforestation/reforestation

    program in other provinces.

    4. The reforestation plan will monitored as regulation in Circular

    13/2019/TT-BNNPTNT dated October 25, 2019: Regulation on

    reforestation when changing the forest use purposes.

    - According to Article 4 “Project owners shall not carry out reforestation

    by themselves” at Clause 5: Project owner fulfill their obligation to

    reforestation when they are informed by the provincial Forest Protection

    and Development Fund about fulfilling the obligation of payment for

    reforestation. Therefore, DPI Quang Tri (Project Owner of BIGG2

    project) will submit confirmation of Forest Protection and Development

    Fund Quang Tri as evidence for reforestation.

    5. Monitor the compensation process to ensure it is suitable with the

    approved Land Acquisition and Resettlement Report.

    PMU Social

    Safeguard

    Specialist

    - LIC

    Included in

    project

    manageme

    nt cost of

    PMU and

    the contract

    with SSS

    (LIC)

    Before

    commencemen

    t

    As updated

    Land

    Acquisition

    and

    Resettlement

    Report

  • 31

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    6. Institutional implementation arrangements will be made for regular

    monitoring (detail in Land Acquisition and Resettlement Report) and to

    record and redress grievances (see more Part VIII. Grievance Redress

    Mechanism)

    2. UXO

    survey, &

    removal

    Injured worker or public

    1. PMU signed contract with an authorized UXO clearing contractor.

    2. The clearance UXO of the subproject has been done in November 2019.

    3. The UXO clearing firm has certified that the subproject areas are

    already cleared and safe for commencement work by the contractors

    PMU UXO

    clearing

    Contractor

    Included in

    contract

    with the

    contractor

    Before

    commencemen

    t

    Along the

    road

    3. Detailed

    design

    River Crossings Detail engineering designs have taken into account maximum flood levels.

    PMU Design

    consultant

    Included in

    design cost

    In approved

    DED

    River and

    stream

    crossings

    4. Detailed

    design

    Road safety All signage of transport safety are designed along the road in approved DED as regulation on transportation and road

    PMU Design

    consultant

    Included in

    design cost

    In approved

    DED

    Along the

    road

    5. All of

    construction

    activities

    All impacts

    according to sub-

    plans in Site-

    EMP

    1. Contractor need to develop site-EMP that includes individual management sub-plans for:

    a) Tree and vegetation removal b) Construction Drainage & Water Pollution Prevention c) Erosion Control; d) Noise and Dust control; e) Solid and Liquid Waste Disposal; f) Construction Traffic Management; g) Community, Occupational Health and Safety and Emergency

    Response

    h) Construction Materials Acquisition, Transport, Storage i) Borrow Site and Spoil Management j) Construction Workers Camp and Management k) Site cleanup sub-plan 2. The Site EMP will include a map of the construction site, showing

    as a minimum: Access routes, storage areas for waste, storage area

    for chemicals such as fuels, concrete mixing, stockpiles, first aid kit

    and equipment used in emergency response.

    ESS/PMU Contractor Included in

    bid price

    Before

    commencemen

    t

    N/A

    Construction Phase

  • 32

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    1. Implement

    Tree and

    vegetation

    removal sub-

    plan

    Tree and

    vegetable loss

    and landscape

    changing

    1. No unnecessary cutting of trees – all vegetation to be removed will be

    in accordance with the Tree and Vegetation Removal and Site

    Restoration management sub-plan which will be in accordance with the

    detailed engineering design

    2. All replanting works to utilize locally available non-invasive species.

    3. No construction camps, material storage sites are to be located in area

    where can damage vegetation.

    4. Contractors will take all precautions necessary to ensure that damage

    to vegetation is avoided due to fires resulting from execution of the

    works.

    5. No vegetation will be burned on site

    CSC

    ESS/PMU

    ; CPCs

    Contractor

    s

    Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Along the

    subproject

    road,

    especially

    3.0 km

    newly

    construction

    section;

    2. Implement

    Construction

    Drainage &

    Water Pollution

    Prevention

    subplan

    Loss of drainage

    & surface water

    pollution

    1. No construction waste, including excavated material, to be placed in

    rivers or streams.

    2. Work in streams at bridge construction sites will be scheduled during dry season and work duration shall be as short as possible. 3. Cofferdams, silt fences, sediment barriers or other devices will be used as appropriate based on the design to control release of silt during excavation and boring operations within or near streams. 4. Provision of adequate short-term drainage away from construction sites to prevent ponding and flooding. 5. The contractor will prevent borrow pits from filling with water. 6. Installation of temporary storm drains or ditches for construction sites to manage and control the flow and direction of surface water run off 7. Ensure connections among surface waters (canals, drainage ditches and streams draining into Hieu river) are maintained or enhanced to sustain existing storm water storage capacity throughout construction. 8. Protective silt curtains will be used within Hieu River during construction and earthworks on the river bank 9. Erosion channels will be built around aggregate stockpile areas to contain rain-induced erosion. 10. Stockpiles and materials, fuel will be stored at least 50m from surface waters with drainage directed away from the river or drainage channels leading to the river and other sensitive receptors 11. No washing or repair of machinery within 50m of surface waters. 12. Pit latrines for workers to be located at least 200m from surface

    waters, and in areas of suitable soil profiles and above the groundwater

    levels

    Contractor Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Throughout

    construction

    sites; Hieu

    River,

    streams and

    other water

    bodies,

    material

    storage sites,

    temporary

    waste

    disposal area

  • 33

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    3. Erosion

    Control

    Loss of soil

    through erosion

    1. Maintain a stockpile of topsoil for immediate site restoration

    following backfilling.

    2. Protect exposed or cut slopes, in accordance with a slope stabilization

    good practice.

    3. Speed up construction at slopes to minimize erosion

    4 Speed up construction at pile driving points on the streams/river to reduce sediments into the water

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractor

    Throughout

    construction

    phase

    Throughout

    construction

    sites; Hieu

    River,

    streams and

    other water

    bodies,

    material

    storage sites

    4. Noise, dust

    and vibration

    Air Pollution

    (dust)

    Civil nuisance

    (Noise and

    vibration)

    1. Cover or keep moist construction roads, all stockpiles of construction aggregates, and all truck loads of aggregates.

    2. Minimize time that excavations and exposed soil are left open/exposed

    3. All equipment will be properly and adequately maintained as well as regularly serviced in accordance with manufacturer

    recommendations

    4. Replace or repair unnecessarily noisy vehicles and machinery. 5. Vehicles and machinery will be turned off when not in use. 6. All mud on public roads resulting from construction traffic will be

    removed before the end of the working day on which it was deposited on

    the road.

    7. Powered mechanical equipment and vehicle emissions to meet national

    TCVN/QCVN standards. All construction equipment and vehicles shall

    have valid certifications indicating compliance to vehicle emission and

    noise creation standards.

    8. To protect buildings and structures from vibration, non-vibrating rollers

    shall be used in construction sites near buildings and structures.

    9. Structures, which are damaged due to

    vibration caused by the construction activities, shall be repaired

    immediately as directed by ESP/PMU.

    10. Pile driving to be schedule for daytime if construction site is near

    residential areas or approved by DONRE, CPCs and ESP/PMU.

    11. Impose speed limits on construction machines and transportation

    vehicles to minimize dust emission along areas where residential areas are

    located.

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractor

    Throughout

    construction

    phase

    Construction

    sites especial

    residential

    area Trang

    Rong, Ban

    Chua, Tan

    Hoa, Tan

    Lap, Quat

    Xa village

    5. Construction

    Traffic

    Management

    Traffic

    disruption,

    Community

    Health & Safety

    1. Communicate to the public through local officials regarding the scope

    and schedule of construction, as well as certain construction activities

    causing disruptions or access restrictions.

    2. Post speed limits, especial at Ban Chua, Quat Xa, Tan Hoa and Tan

    Quang villages, and create dedicated construction vehicle roads or lanes.

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Construction

    sites especial

    residential

    area Trang

    Rong, Ban

    Chua, Tan

  • 34

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    3. Inform community of location of construction traffic areas, and provide

    them with directions on how to best co-exist with construction vehicles

    on their roads

    4. The contractor will ensure road and walkway lighting is provided

    during construction and that all construction sites are lit to prevent

    accidental injury to the public.

    5. In coordination with local traffic authorities, implement appropriate

    traffic diversion schemes to avoid inconvenience due to subproject

    operations to road users, ensure smooth traffic flow and avoid or minimize

    accidents, traffic hold ups and congestion

    6. Provide temporary safe vehicle and pedestrian access around

    construction areas.

    7. Install bold diversion signs that would be clearly visible even at night

    and provide flag persons to warn of dangerous conditions.

    Hoa, Tan

    Lap, Quat

    Xa village

    and the

    connecting

    points with

    NR9 and Ho

    Chi Minh

    Trail

    6. Community,

    Occupational

    Health and

    Safety and

    Emergency

    Response

    Community and

    Occupational

    Health and

    Safety.

    Emergency cases

    1. Sufficient signage giving health and safety warnings and information

    disclosure at all sites.

    Speed limits will be imposed on all construction vehicles

    2. The contractor will not cause standing water suitable for disease vector

    breeding on any construction site or worker camp area

    3. Worker education and awareness seminars for construction hazards will

    be given. A construction site safety program will be developed and

    distributed to workers

    4. Drinking water will be provided at all construction sites

    5. Fencing on all excavation, borrow pits and sides of temporary bridges.

    6. Ensure that all workers are equipped with, and use Personal Protective

    Equipment.

    7. Health and Safety qualified engineer and adequate first aid will be on

    site

    8. Where worker exposure to traffic cannot be completely eliminated,

    protective barriers shall be provided to shield workers from traffic

    vehicles.

    9. The Contractor will set out an Emergency Response Plan. The plan will

    contain:

    • Roles and Responsibilities for those working on behalf of the contractor who will be involved in an incident response;

    • Actions and Procedures which will be taken for each incident;

    • Measures to Prevent an Incident.

    • Contact details of emergency medical facilities; and

    • Corrective action procedures following in incident

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Construction

    sites especial

    residential

    area Trang

    Rong, Ban

    Chua, Tan

    Hoa, Tan

    Lap, Quat

    Xa village

    and the

    connecting

    points with

    NR9 and Ho

    Chi Minh

    Trail, worker

    camps

  • 35

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    • The location of a First Aid Kit to be kept on site and stocked at all times

    10. The Contractor will develop Incident Response procedures prior to

    construction. The procedures will cover actions to be taken in case of:

    • Worker injury (e.g. construction or traffic accident)

    • Spillage (e.g. fuel spillage)

    • Fire (e.g. fuel or chemicals storage area); and

    • Any other incidents anticipated by the contractor. 11. The Incident Response Plan will set out Preventative Measures for all

    types of incidents covered in the Incident Response Plan. This will

    include:

    • Prevention of Injury – to include Personal Protective Equipment requirements for construction workers, training requirements

    • Prevention of Spillage - All construction fluids such as oils, and fuels will be stored on hard standing with sealed drainage with

    a capacity of 110% of the largest fuel container, will include

    procedures on refueling and maintaining vehicles

    • Prevention of Fire – to include measures for Ignition Sources including prevention of smoking on construction site,

    management of flammable materials and liquid.

    • Other Incidents – prevention measures relevant to other issues considered relevant by the contractor

    7. Construction

    Workers Camp

    and

    Management

    Negative impact

    to local

    communities and

    surrounding

    environment

    (water bodies,

    hygienic

    sanitation)

    1. Construction and workers' camp location and facilities to be at least

    500m from settlements and agreed with local communities and facilities

    approved by ESS and managed to minimize impacts.

    2. Hire and train as many local workers as

    practicable.

    3. Provide adequate housing for all workers at the construction camps and

    establish clean canteen/eating and cooking areas.

    4. Workers camps shall be provided with toilets/sanitation facilities in

    accordance with local regulations to prevent any hazard to public health

    or contamination of land, surface or groundwater. These facilities shall be

    well maintained to allow effective operation.

    5. Provide separate hygienic sanitation

    facilities/toilets and bathing areas with sufficient water supplies for male

    and female workers.

    6. HIV Aids education will be given to workers.

    7. Camp areas must be restored to original condition after construction

    completed.

    8. Register temporary stay for workers with police.

    CSC

    ESS/PMU

    Contractor Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Worker

    camps

  • 36

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    8. Solid and

    Liquid Waste

    Disposal;

    Land

    contamination,

    surface water

    pollution,

    resource use

    1. Management of general solid and liquid waste of construction will

    follow National regulations, and will cover the collection, handling,

    transport, recycling, and disposal of waste created from construction

    activities and worker force.

    2. Appropriate sites for disposal of solid and liquid waste to be determined

    by DoNRE and adhered to by the contractor

    3. Construction sites will have appropriate sized garbage bins. All solid

    waste to be stored in containers with lids.

    4. Collection, storage, transport, and disposal of hazardous waste such as

    used oils, gasoline, paint, and other toxics will follow National

    regulations.

    5. Wastes will be stored above ground in closed, well labeled, ventilated

    plastic bins in good condition well away from all surface water, water

    supplies, and cultural and ecological sensitive receptors.

    6. All spills will be cleaned up completely with all contaminated soil

    removed and treated as waste.

    7. A schedule of solid and liquid waste pickup and disposal will be

    established and followed to ensure construction sites are as clean as

    possible.

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Construction

    sites, worker

    camps.

    9. Construction

    Materials

    Acquisition,

    Transport,

    Storage

    Water and air

    pollution, soil

    erosion,

    community health

    and safety

    1. Define and schedule how fabricated materials such as steel, concrete

    structures, and scaffolding will transported and handled in safe way.

    2. All aggregate loads on trucks will be covered.

    3. Bitumen need to be stored in in specialized tools and closed.

    4. Fabricated materials with big size need to be stored far from

    temporary accesses for vehicles

    5. Define & schedule how materials are extracted from borrow pits and

    rock quarries, transported, and handled & stored at sites.

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Construction

    sites,

    material

    storage

    10. Borrow Site

    and Spoil

    Management

    Land

    contamination,

    surface water

    pollution, ecology

    1. All borrow pits and quarries will be approved by DoNRE

    2. All borrow pits and quarries will have a fence perimeter with signage

    to keep public away.

    3. Uncontaminated spoil will be disposed of in designated sites, which

    must never be in or adjacent surface waters. Designated sites must be

    clearly marked and identified

    4. Spoil will not be disposed of on sloped land, near cultural property or

    values, ecologically important areas,, or on/near any other culturally or

    ecologically sensitive feature.

    5. Where possible spoil will be used at other construction sites, or

    disposed in spent quarries or borrow pits.

    6. A record of type, estimated volume, and source of disposed spoil will

    be retained.

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractors

    Throughout

    construction

    phase

    Construction

    sites,

    Borrow pits

  • 37

    Component

    Activity

    Potential

    Environmental

    Impacts

    Proposed Mitigation Measures Institutional

    Responsibilities

    Mitigation

    Cost

    Timing Location

    Supervisi

    on

    Impleme

    ntation

    7. Spoil from excavation on the bridge points should be transported out

    of water every day to avoid obstructing the flow.

    11. Site cleanup

    sub-plan

    Land use,

    nuisance,

    community health

    and safety

    On completion of construction works:

    1. The contractors must fill pits, land excavation areas and any landscaping and planting done on land that has been

    temporarily in the Contractor's possession during construction

    2. All sites to be cleaned of all litter, debris and any other materials or equipment associated with construction activities

    3. Any conditions placed on use if sites by local authorities or in agreements with landowners must be complied with.

    4. All sites to be handed over only after inspection completed by CSC/PMU

    CSC

    ESS/PMU

    Contractor

    s

    Included in

    the contract

    with

    contractors

    After

    completion

    works

    Whole the

    construction

    sites

    Operation Phase

    1. Traffic and

    road safety

    Community

    health and safety,

    Increased air

    pollution & noise,

    Water pollution

    and flooding

    1. Undertake road safety awareness campaigns for local residents and

    other road users of Gio Linh - Cam Lo Inter-district road.

    2. Install and maintain road warning signs and markings.

    3. Enforce well marked speed limits, provide guard rails along road, and

    educate public on new road safety

    4. Maintenance of all culverts by removing contaminated debris at

    regularly intervals

    5. Maintenance of all cross drains by removing debris or waste which

    may block water flow and cause flooding

    CPCs Quang Tri

    DOT/

    Included in

    operation

    and

    maintenanc

    e cost

    In operation

    phase

    Whole the

    road

  • 38

    IV. MONITORING PLAN

    A. Environmental Policy and Standard

    51. The subproject shall comply with requirements of ADB SPS 2009 and with the

    environmental legal framework of Vietnam, which is outlined in this section. Environmental

    quality standards and criteria for Viet Nam are listed in Appendix 5. The environ