Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
i
Updated Environmental Management Plan
Stage of the document: Updated
Project number: 49026-003
March 2020
VIE: Basic Infrastructure for Inclusive Growth in the North
Central Provinces Sector Project
Constructing and Upgrading Gio Linh – Cam Lo
Inter-District Road of Quang Tri Province
Prepared by Project Management Unit - Planning and Investment Department of Quang Tri province
for the Asian Development Bank.
ii
CURRENCY EQUIVALENTS
(as of 15 Feb 2020)
Currency unit – Viet Nam Dong (D)
D1.00 = $0.000044
$1.00 = Ð 23,215
ACRONYMS AND ABBREVIATIONS
ADB Asian Development Bank
CPC Commune People’s Committee
CSC Construction Supervision Consultant
DARD Department of Agriculture and Rural Development
DONRE Department of Natural Resources and Environment
DOT Department of Transportation
DPC District People’s Committee
DPI
ECT
Department of Planning and Investment
Emergency Control Team
EIAR Environmental Impact Assessment Report
EMP Environmental Management Plan
EPP Environmental Protection Plan
ESO Environmental Safeguards Staff
ESS Environmental Safeguard Specialist
GMS Greater Mekong Sub-region
IEE Initial Environmental Examination
IPM Integrated Pest Management
LEP Law on Environmental Protection
MPI Ministry of Planning and Investment
MPN Most Probable Number of viable cells of a pathogen - a measure of
water quality
PPC Provincial People’s Committee
PPE Personal Protective Equipment
PPMU Provincial Project Management Unit
PPTA Project Preparatory Technical Assistant
ROW Right of Way
iii
SPS Safeguard Policy Statement
SST Subproject Support Teams
The PPTA The Project Preparatory Technical Assistant Consultants
The Project Basic Infrastructure for Inclusive Growth in the North Central
Provinces Sector Project
The
Subproject
Constructing and Upgrading Gio Linh - Cam Lo Inter-district Road
of Quang Tri Province
UXO Unexploded ordnance
iv
WEIGHTS AND MEASURES
Km2 (square kilometer) – unit of length
m3 (cubic meter) – A measure of volume
Note:
(i) In this report, "$" refers to US dollars.
The environmental management plan is a document of the borrower. The views expressed herein do
not necessarily represent those of ADB’s Board of Directors, Management, or staff.
In preparing any country program or strategy, financing any project, or by making any designation of
or reference to a particular territory or geographic area in this document, the Asian Development Bank
does not intend to make any judgments as to the legal or other status of any territory or area.
v
CONTENTS
Page
I. INTRODUCTION ...................................................................................................................... 1
II. DESCRIPTION OF THE SUBPROJECT ................................................................................. 4
1. Location and scope of the subproject 4 2. Adjustment of Detail Engineering Design 11 3. Description of the environment 17
III. ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES ........... 25
1. Potential Impacts Summary 26 2. Environmental Mitigation Plan 29
IV. monitoring plan ........................................................................................................................ 38
A. Environmental Policy and Standard 38 B. Performance Monitoring 39
1. Compliance Monitoring .............................................................................................. 39 2. Environmental Effects Monitoring ............................................................................. 43
V. INSTITUTIONAL ARRANGEMENT .................................................................................... 45
VI. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION .................. 47
VII. CAPACITY BUILDING .......................................................................................................... 49
VIII. GRIEVANCE REDRESS MECHANISM ............................................................................... 50
IX. REPORTING ........................................................................................................................... 55
X. ESTIMATED COST OF EMP ................................................................................................. 56
XI. CONCLUSIONS AND RECOMMENDATIONS................................................................... 58
XII. Appendix .................................................................................................................................. 59
Appendix 1: Photos of the subproject road and the vicinity 59 Appendix 2: Minute of Consultation on DED 61 Appendix 3: Agreement on quarry source, soil borrow pit and dumpsites 66 Appendix 4: National Technical Regulations of Vietnam 76 Appendix 5: Decision on rock quarry, sand sources, borrow pit that potential for the subproject 87 Annex 6: UXO Clearance 109 Annex 7: Consultation on forest land in 3 communes of the subproject 114 Annex 8: Decision of Quang Tri People’s Counsil on aggreement of land use change for projects in Quang Tri
Province 120
vi
LIST OF FIGURES
Figure 1 – General Map of Cam Lo, Gio Linh Districts and Subproject Area ..............................................................3 Figure 2: Map of the subproject road ................................................................................................................................4 Figure 3 – Typical Straight Line Section ...........................................................................................................................6 Figure 4 – Bridge over Hieu River .................................................................................................................................... 10 Figure 5. Design of culvert at Km4+467.72 ...................................................................................................................... 10 Figure 6. Location and routes of construction material sources and disposal sites...................................................... 16 Figure 7: Grievance Redress Mechanism ........................................................................................................................ 54
LIST OF TABLES
Table 1: Location of bridges on the road ...............................................................................................................................7 Table 2: Design of the Gio Linh – Cam Lo inter-district road ............................................................................................. 11 Table 3: Descriptions of material transportation routes ....................................................................................................... 13 Table 4: Location of samples surface water on the Hieu River............................................................................................ 17 Table 5: Location of samples ambient air quality ................................................................................................................ 18 Table 6: Result of monitoring ambient air quality in 2019 .................................................................................................. 19 Table 7: Environmental Receptors ....................................................................................................................................... 20 Table 8. Summary of Potential Environmental Impacts ...................................................................................................... 26 Table 9 - Environmental Impact Mitigation Plan ................................................................................................................. 30 Table 10 - Environmental Monitoring Compliance ............................................................................................................. 40 Table 12 – Responsibilities for EMP implementation ........................................................................................................ 45 Table 13 – Main issues and information from local authorities ........................................................................................... 48 Table 14 – Main environmental concerns from public consultation .................................... Error! Bookmark not defined. Table 15 – Main environmental concerns from public consultation in DED ....................................................................... 49 Table 16 – Detail capacity building program ....................................................................................................................... 50 Table 17 – Reporting procedures ......................................................................................................................................... 55 Table 18 – Estimated cost for EMP Implementation (2-year construction/ 4-year in total) ................................................. 56
1
I. INTRODUCTION
1. The proposed Basic Infrastructure for Inclusive Growth in the North Central Provinces
Sector Project will invest in implementation of the north central coastal provinces sub-region socio-
economic development plans. The Project responds to the Government of Vietnam's strategy of
targeting the use of concessional ODA investment into poorer provinces using economic sub-
regions as a means of identifying interconnectivity and synergies between provinces to accelerate
economic growth in provinces that have previously lagged in terms of economic growth.
2. The project has three outputs being (i) Improved connectivity within value chains and their
supporting infrastructure; (ii) Improved business development infrastructure; and (iii) Strengthened
Sub-regional infrastructure planning and management.
3. The Project has been categorized as B on environmental issues during the Project Concept
note as it has few potential significantly adverse impacts and none of them are irreversible. During
the PPTA phase, IEE report was carried out and approved in July 2017 by ADB. Anyhow, in Detail
Engineering Design (DED), scope of the subproject has changed as follow:
✓ Upgrading category V mountainous road to category IV with width from 6.5m to 7.5m;
✓ Road alignment has not been changed, only adjust some short sections to ensure safety therefore
length of the road has been changed from 23.3km to 22.81km;
✓ Construct 6 bridges instead of 4 bridges as proposed in FS.
✓ There are two new sensitive receptors arising at two new bridge
✓ The section from Trang Rong village, Hai Thai commune Gio Linh district to Ban Chua village,
Cam Tuyen commune Cam Lo district is exactly 3.0km instead of 3.5km as in FS. This section is
a trail, currently not open to traffic;
4. According to requirement in Environmental Assessment and Review Framework (EARF),
with not only extension of width and length of the road but also addition two new bridges at
Km6+450,17 and Km8+524,35 as detailed design, an updated EMP report needs to be updated and
approved by ADB.
5. The purpose of updated EMP is to reflect the changes in detailed design and relevant all
adverse impacts as well as risks on environment in order to propose adequate and effective
mitigation measures. The updated EMP takes into consideration environmental impacts and
appropriate mitigation measures base on change in approved the detailed design.
6. The subproject is entitled "Constructing and Upgrading Gio Linh - Cam Lo Inter-district
Road of Quang Tri Province" and is a representative subproject for Output 1 of the Project:
Improved connectivity within value chains and their supporting infrastructure.
7. The Gio Linh – Cam Lo inter-district road passes 2 districts, Gio Linh and Cam Lo, and
connects to provincial road 575B, and on to the Ho Chi Minh highway and to the National road 9.
The road plays an important role in socio-economic development because it provides access to the
special economic zones and commercial area at Lao Bao, to seaports such as Cua Viet and My
Thuy. Currently, vehicles transporting raw materials from Hai Thai commune, Gio Linh district to
the factories in Cam Lo commune, have to divert onto the Ho Chi Minh road and then to National
2
Road 9. The proposed subproject will reduce the transport distances and costs of transport to local
producers and improve economic efficiency for the production area.
8. The road will benefit traffic for 9,000 people of Hai Thai commune, Gio Linh district (about
4,000 people) and Cam Tuyen commune, Cam Lo district (about 5,000 people) through connecting
these people to the district centre areas. Direct beneficiaries are estimated to be over 3,400 who
will be directly involved in commerce, services, industry and agriculture in Hai Thai commune,
Gio Linh district (over 2,160 people) and Cam Tuyen commune of Cam Lo district (over 1,480
people). The road will also serve a total of 8,839ha of industrial and plantation forestry (including
rubber, coffee etc.) spread between Hai Thai commune (839ha) and Cam Tuyen commune
(8,000ha).
3
Figure 1 – General Map of Cam Lo, Gio Linh Districts and Subproject Area
4
II. DESCRIPTION OF THE SUBPROJECT
1. Location and scope of the subproject
9. The road passes Hai Thai commune, Gio Linh and Cam Tuyen and Cam Thanh communes, Cam Lo district, Quang Tri province. The start point (Km0+000) connects to provincial road 575B
and crosses the Ho Chi Minh trail in the area of Xuan Hoa village, Hai Thai commune, Gio Linh district.
The end point (Km22+810.93) is the T-junction with National Road No.9 at Km31+120 (which is
Km17+380 before) in the area of Quat Xa village, Cam Thanh commune, Cam Lo district.
10. The subproject is basically located on the existing alignment, except for a 3.0 km section from Trang Rong village, Hai Thai commune Gio Linh district to Ban Chua village, Cam Tuyen
commune Cam Lo district. This section is currently not open to traffic and the proposed subproject
will upgrade an existing pathway used by local people and the alignment has been approved by the
PPC.
Figure 2: Map of the subproject road
11. The Gio Linh – Cam Lo inter-districts road is formed on the basis of two existing roads (the access road to Ban Chua village, Cam Lo district and Xuan Hoa – Trang Rong road of Gio Linh
district constructed between 2001 and 2006) and lengthened to Quat Xa village Cam Thanh
Commune Cam Lo district by new bridge over the Hieu River, which will be constructed in the
subproject.
12. The existing road Xuan Hoa – Trang Rong of Gio Linh district has length 11,5km with different width of each section, from 3m to 7m. The road surface is mostly natural gravel or rugged
5
dirt with many deep and wide trenches. There are only approximate 800m with surface of cement
concrete still in good condition.
13. The existing road to Ban Chua village, Cam Tuyen commune has length 9,1km with width
of road from 2 m to 5m, of which around 1km has surface of cement concrete in good condition,
the remaining has surface of natural gravel or rugged dirt with many deep and wide trenches. This
road goes through the villages of Tan Hoa, Tan Lap, and Ban Chua in Cam Tuyen commune. At
the end of this road is section that currently not open to traffic, it is a trail with length 3.0km formed
by traveling of local people from Ban Chua village to Trang Rong village.
14. The lengthened section by new bridge over the Hieu River to Quat Xa village Cam Thanh
Commune is around 2,2km, of which, 2km with surface of cement concrete in good condition,
width 5,5m; the rest of the section has surface of rugged natural gravel.
15. Along of the existing road to Xuan Hoa – Trang Rong of Gio Linh district, on the two sides,
most area is rubber and melaleuca farms, interspersed a number of houses. Particularly section
from Km8 + 600 to Km11 + 500 has complex terrain, hill with height from medium to high,
melalueca forest on both sides. The route has 4 crossing points of streams. The population along
this route is quite sparse, there are only some small shops in the residential area of Trang Rong
village and the starting point of the road in Xuan Hoa village.
16. For the road to Ban Chua village, on both sides of the route are crops, rice fields and houses
of the people of Tan Hoa, Tan Lap, and Ban Chua village. The population along the road is more
crowded than the road to Trang Rong village but there are only some small shops. Along the road,
there are two crossing points of streams, the terrain of this route is relatively flat except 3.0km from
Ban Chua village to Trang Rong village has complex terrain, hill with height from medium to high,
melalueca forest around.
17. The lengthened section to Quat Xa village over the Hieu River, on both sides of the road
are crop and some houses as well as a primary school and health centre of Quat Xa village. This is
end point of the proposed road.
18. The proposed road of the subproject is basically located on the existing alignment of the
two existing roads and lengthened to Quat Xa village over the Hieu River therefore, environmental
and social aspect of two roads as well as lengthened section are also conditions of new road of the
subproject.
19. In DED period, there are two more points are determined that it is necessary to build bridges
instead of culvert at Km6+450,17 and spillway at Km8+524,35. At Km6+450,17, it is currently a
culvert over a small, narrow ditch with vegetable on its sides and melaleuca farm around. In dry
season, it is a negligible current of water on the ditch, however, in the rainy season, because of
narrow terrain, water way can be increased quicker and higher that leading to flood. The
construction of a new bridge will widen the drainage area compared to the present therefore the
water way will flow faster in the rainy season but will not affect the water way direction.
Construction new bridge is hardly affected to water way in dry season.
20. At Km8+524,35, it is currently a small stream with slow current of water and low water
level in dry season and existing a spillway with lower terrain compared with around area. This area
6
is also hills planted melaleuca. In the rainy season, water way increases over spillway and leading
to flood of this point. The construction of a new bridge over the stream will increase the flow rate
due to the expansion of the river bed at the point while direction of water way will not be changed.
Furthermore, during the construction time, excavation on the sides can result to obstruct the flow
and pile driving on the stream can lead to distribution of sediments into the water.
21. The road is proposed to be upgraded to category IV mountainous road in compliance with
Vietnamese Standard TCVN 4054-2005, with a roadway width of 7.5 m comprising a 5.5m wide
carriageway and shoulders of 2x1.0 = 2m. The total right-of-way (ROW) including side drainage
will generally be 14.5m. The proposed road is 22,810 km long.
- Design velocity: 40km/h
- Width of subgrade: 7.5m
- Width of pavement (carriage-way): 5.5m
- Width of shoulder: 2 x 1.0m
- Normal crossfall (%): 2%
- Max. Super elevation (%): 8%
- Pavement structure: Bitumen Surface Treatment
Figure 3 – Typical Straight Line Section
12. Bridges on the road: On the route, 6 new bridges will be designed for construction including
(i) a slab beam bridge at Km6+450,17; (ii) a slab beam bridge at Km8+524,35; (iii) a slab
7
beam bridge at Km11+521,78; (iv) a slab beam bridge at Km16+668.19 (v) a slab beam
bridge at Km17+811,98; (vi) a slab beam bridge at Km20+662,61; These bridges will be
designed with design flood frequency P = 4% for small bridges and P = 1% for medium
and large bridges, as following table.
Table 1: Location of bridges on the road
No Name +
Chainage
Beam / L
bridge
(m)
Width
(m) Note
Descriptions of affected water ways
1
Slab beam
bridge at
Km6+450,17
(added
during DED)
3I7 / 21.70
8.5
(7.5 +
2x0.5)
The new
bridge is
added in
DED, P = 4%
The construction of a new bridge will widen
the drainage area compared to the present
therefore the water way will flow faster in the
rainy season but the water way direction will
not be affected. It is hardly affected to water
way in dry season.
This is a natural flow with main water source
from rain and it is not to be used for living
activities or irrigation. Around the flow is
natural vegetable, bambo and melaleuca
farm, there is not special flora and fauna
species in this area.
2
Slab beam
bridge at
Km8+524,35
(added
during DED)
6l7 / 42.70
8.5
(7.5 +
2x0.5)
The new
bridge is
added in
DED, P = 1%
The construction of a new bridge instead of
existing spillway over the stream will
increase the flow rate due to the expansion of
space for drainage at the point while
direction of water way will not be changed.
Furthermore, during the construction time,
excavation on the sides can result to obstruct
the flow and pile driving on the stream can
lead to distribution of sediments into the
water.
This is a natural flow with small shrubs and
grass on the sides, surrounded by melaleuca
forest interspersed with some species of
bamboo and eucalyptus that grow naturally.
The water from the flow is not to be used for
living activities or irrigation. Furthermore,
8
No Name +
Chainage
Beam / L
bridge
(m)
Width
(m) Note
Descriptions of affected water ways
there is not special flora and fauna species in
this area
3
Slab beam
bridge at
Km11+521,7
8
21/32.10
8.5
(7.5 +
2x0.5)
Design new
bridge P =
4%
The construction of a new bridge instead of
existing spillway over the stream will
increase the flow rate due to the expansion
space for drainage at the point while
direction of water way will not be changed.
Furthermore, during the construction time,
excavation on the sides can result to obstruct
the flow and pile driving on the stream can
lead to distribution of sediments into the
water.
This is a natural flow with small shrubs and
grass on the sides, surrounded by melaleuca
forest interspersed with some species of
bamboo that grow naturally. The water from
the flow is not to be used for living activities
or irrigation. There is not special flora and
fauna species in this area
4 Slab beam
bridge at
Km16+668,19
21 / 31.10
7.5
(6.5 +
2x0.5)
Bridge over
La La stream,
P = 4%
The construction of a new bridge instead of
existing spillway over the stream will
increase the flow rate due to the expansion of
space for drainage at the point while
direction of water way will not be changed.
Furthermore, during the construction time,
excavation on the sides can result to obstruct
the flow and pile driving on the stream can
lead to distribution of sediments into the
water.
This is a natural flow with small shrubs and
grass on the sides, surrounded by melaleuca
forest interspersed with some species of
bamboo that grow naturally. The water from
the flow is not to be used for living activities
or irrigation. There is not special flora and
fauna species in this area.
9
No Name +
Chainage
Beam / L
bridge
(m)
Width
(m) Note
Descriptions of affected water ways
5 Slab beam
bridge at
Km17+811,98
2l15 /
42.15
7.5
(6.5 +
2x0.5)
Bridge over
La La stream,
P = 4%
The construction of a new bridge over the
stream will not affect to direction of water
way as well as flow rate compared with the
present because new bridge will not widen
the river bed. Anyhow it can be flowed
quickly in flooding time in comparison the
existing bridge. Furthermore, during the
construction time, excavation on the sides
can result to obstruct the flow and pile
driving on the stream can lead to distribution
of sediments into the water.
This is a natural flow with small shrubs and
grass mixed with some naturally growing
bamboo species and melaleuca forest on the
sides. There are some sections intermingled
with arable land of local people on its sides.
Anyhow water from the stream is not to be
used for living activities and irrigation. There
is not special flora and fauna species in this
area.
6 Slab beam
bridge at
Km20+662,61
4I33 /
150.35
7.5
(6.5 +
2x0.5)
Design new
bridge over
Hieu River, P
= 1%
The construction of a new bridge over the
stream will not affect to direction of water
way as well as flow rate compared with the
present because new bridge will not widen
the river bed. Anyhow, during the
construction time, excavation on the sides
and poor handling of materials as well as pile
driving on the river can cause blockages and
release of silt into the river. Runoff water
during rain could also bring waste and soil
into the Hieu River, leading to a temporary
reduction in water quality and impact
downstream user of Hieu River including
Cam Lo town and Dong Ha city.
At this section of the Hieu River, water from
the stream is not to be used for living
10
No Name +
Chainage
Beam / L
bridge
(m)
Width
(m) Note
Descriptions of affected water ways
activities and irrigation. There is not special
flora and fauna species in this area. On the
sides, small shrubs and grass mixed with
some bamboo species and eucalyptus
naturally grow.
Figure 4 – Bridge over Hieu River
13. Culverts on the route: consist of 118 culverts across the road, pipe culvert (52 items), box
culvert (18 items) and reinforced concrete culverts (48 items). They are built at locations
where drainage is required on roads and at cross-section of irrigation canals and ditches.
14. Others works along the road includes trenches with size 40x40x120(cm); reinforcing taluy
roofs with paving slabs in frequently flooded sections and embankment sections over hilly
terrain; retaining walls designed at steep slopes (> 50%) that cannot be covered with
conventional embankments; guardrail wall with reinforced concrete foundation.
Figure 5. Design of culvert at Km4+467.72
11
2. Adjustment of Detail Engineering Design
15. In PPTA phase, the Gio Linh – Cam Lo inter-district road is proposed to be upgraded to category
V mountainous road in compliance with Vietnamese Standard TCVN 4054-2005, with an
embankment width of 6.5 m pavement of 3.5m and shoulders of 2x1.5=3m. In DED, the road was
adjusted to category IV mountainous road as Vietnamese Standard. Table below summarizes
changes of subproject activities from the FS and the detailed design in 2019.
Table 2: Design of the Gio Linh – Cam Lo inter-district road
Items Basic design (FS report) Detailed design
1. 1. Route length 23,300 km 22,810 km
2. Technical index
Design velocity: 30km/h
Width of subgrade: 6.5m
Width of pavement (carriage-
way): 3.5m
Width of shoulder: 2 x 1.5m
Normal cross fall (%): 2%
Max. Super elevation (%): 6%
Pavement structure: BST
Design velocity: 40km/h
Width of subgrade: 7.5m
Width of pavement (carriage-way): 5.5m
Width of shoulder: 2 x 1.0m
Normal cross fall (%): 2%
Max. Super elevation (%): 8%
Pavement structure: BST
3. Other construction items
4 bridges
6 bridges
There are two more points are determined
that it is necessary to build a bridge instead
12
of culverts, these are bridges at
Km6+450,17 and Km8+524,35.
a. Construction Material Sources
16. During the period of PPTA, the technical consultant, after consulting with the local authorities,
came up with some suitable quarries including 1 rock/stone quarry, 6 sand / soil sources which
meet the required capacity for the construction project and acceptable transport distance. In the
detailed design phase, the DED consultant conducted a survey and worked with local
authorities on the soil borrow pits as well as disposal sites which are suitable for construction
of sections on the road. The minutes of working on soil borrow pits are shown in Annex 4.
Specific information about the material sources is as follows:
Quarry source: All quarries potentially used for the subproject are checked legal status by DED
consultant and PMU. All related legal documents on these source are enclosed in Annexes.
17. The estimated volume of rock to be used for the subproject construction is 54,000 m3. Tan Lam
quarry: situated on the side of 9 Road at Km28+00 along road to Lao Bao, Cam Thanh
Commune, Cam Lo district with an area 8.3ha and a capacity of 3,000,000m3. It is about
10.6km from the quarry to the start point of the construction site and is served by an asphalt
road. This quarry are exploited by two companies: Joint venture of Thien Tan JSC and Tan
Hung JSC with license No 1190/QD-UBND dated 6/7/2012 (valid for 10 years); Joint Venture
Quang Tri Construction – Transportation JSC and Minh Huong Company Ltd with license No
1191/QD-UBND dated 6/7/2012 (valid for 10 years)
18. Soil borrow pit and gravel source: The estimated soil volume to be used for the subproject
construction is 190,000 m3. The volume of excavated soil that can be reused as fill soil is 81,000
m3. The rest will be purchased from the following borrow pits:
(i) Hill gravel quarry in Gio An 2: situated to the left of the provincial road 575B at Km6
+ 000, 6km from the start point in Gio An Commune, Gio Linh district. The quarry is
within the Quang Tri planning area and approved as a quarry by Decision No.
2242/QD-Committee dated 10.15.2015. The licensed area for quarrying is 19ha in
extent and the estimated reserves are 2,500,000m3. The site has a mixture of soil and
gravel which is of suitable quality for road surfacing. The distance from the quarry to
the start point is about 6 km along provincial road 575B which has an asphalt concrete
pavement
(ii) Cam Chinh soil borrow pit : situated of the provincial road 585 at Km4+800, in Cam
Chinh commune, Cam Lo district. The quarry is within the Quang Tri planning area
and approved as a quarry by Decision No. 2242/QD-Committee dated 10.15.2015. The
licensed area for quarrying is 19ha in extent and the estimated reserves are 500.000m3
Visual inspection shows that material at the site is clay and gravel, sections of
13
weathered siltstone clay, golden brown stone and pale yellow, semi-hard state. Soil
quality at the mine is satisfactory for use in roadbed embankment works. The distance
from the quarry to the middle of section 2 (Km12+367,99 - Km20+576,81) is 14,9km
and to the middle of section 3 (Km20+576,81 - Km22+810,93) is 8,7km.
19. Sand Source: On the route, there are 02 sand suppliers: a sand yard at Hieu River at Dong
Ha city and another at Thach Han River in Quang Tri commune. These sand sources are
approved by Decision No 3330/QD-UBND dated 28/12/2016 (see Annex 4). Details are as
follows:
(i) The yard at the Hieu River is on the left bank, on the side of Dong Ha Bridge at
Km756+800 on route 1A. The material includes small grain sand, gravel, medium
grain sand of high quality and has substantial reserves, sufficient to meet the technical
requirements and volume of construction works for bridge and drain construction for
the project. The distance from Hieu River yard to the work site is approximately 18km,
involving travel for 10km along the Dong Ha city bypass, 1km on the Ho Chi Minh
Road to the East and 7km on the Cau Duoi road to Tan Hoa. All these routes have
good quality asphalt surfaces.
(ii) The yard at Thach Han River is on the right bank, near the Thach Han Bridge in Quang
Tri commune at Km770 + 100 on road 1A. The material includes small grain sand,
gravel, medium grain sand of high quality and sufficient reserves to meet the technical
requirements and volume for bridge and drain construction for the subproject. The
distance from the yard to the end point of construction is approximately 28.8km along
good quality asphalt surfaced roads.
20. Asphalt concrete: taken from the asphalt concrete plant at Km27 - QL9 in Thuong Lam
village, Cam Thanh commune, Cam Lo district. This concrete plant belongs to Viet Ren
Joint Stock Company with head office is located in QL9, Dong Ha City. This plant provides
asphalt concrete for construction sites in nearly districts and it operates legally with
permission of the local government. The distance from the mixing plant to the Km0+0 of
the road is 36km and to the end point of the road is 10,7km.
21. Total of volume of excavation (including rock and soil) is 244,000 m3, total volume of spoil
is 170,000 m3 , an amount of excavation soil is reused.
22. Material transportation routes include sensitive receptors are listed in the below table
Table 3: Descriptions of material transportation routes
Material Sources Transportation Routes Sensitive Receptors
4. 1. Tan Lam quarry
A distance of 10km from the No 9
National Road to the construction
site on direction to Cam Lo Town
Residence area of Cam Thanh
commune along the No 9
National Road
5. 2. Gio An 2 borrow pit 6 km from Road 575B to Km 0+0 of
the subproject at Tan Hoa village Maleleuca farm and crop land
14
6. 3. Cam Chinh borrow pit
A distance of 8,7 km from
provincial road 585 to Km22+810
on direction to Cam Lo Town, and
the No 9 National Road to Lao Bao
Residence area of Cam Chinh
commune along 585 Road and
the No 9 National Road
7. 4. Sand sources from Hieu River and Thach Han river
The distance from Hieu River yard to
the work site is approximately 18km,
involving travel for 10km along the
Dong Ha city bypass, 1km on the Ho
Chi Minh Road to the East and 7km
on the Cau Duoi road to starting point
of Tan Hoa village.
For section in Cam Lo district, this
sand source will be transported from
Dong Ha City to Cam Thanh
Commune by the No 9 National
Road.
Sand sources from Thach Han river
will be transported via a NR No1 and
NR No 9 to end point of the road in
Cam Thanh Commune – Cam Lo
district with distance approximate
29km.
Residence area in Dong Ha
city along the transportation
route ; Cau Duoi Bridge;
Residence area of Tan Lap, An
Khe Village along the Ho Chi
Minh Trail road to the East;
Residence area in Cam Lo
Town and Cam Thanh
Commune.
5. Asphalt concrete plant
Transportation road is NR No9 from
Thuong Lam village to Km22+810 in
Quat Xa Village, Cam Thanh
commune with distance of 10,7km
Residence area of Thuong Lam
and Quat Xa village along the
NR No9
b. Disposal sites
22. The subproject will use disposal sites in Hai Thai commune, Gio Linh district and in Cam
Tuyen commune, Cam Lo district. Volume of sites in Hai Thai commune is expected to
54.000 m3 on 4ha area. Besides, Cam Tuyen disposal sites have volume of 224.000 m3 on
12,2ha. Total area of disposal sites is 16,2ha with volume of 278,000 m3. The dumpsites
are located along the subproject road, in vacant lands at Km3+288 and gardens of
households at Km8+253 of Hai Thai Commune; in vacant lands at Km 11+608 of Cam
Tuyen village, Km14+744 of Ban Chua Village, Km 17+153 at Tan Quang Village,
Km19+379 and Km20+700 of Quat Xa village. Distance from the subproject road to
dumpsites is approximate 500m to 1,5km. Therefore, the transportation route to disposal
sites is current road of the subproject and trails to vacant lands or garden. As result in,
sensitive receptors of transportation route are the same with the subproject road at
corresponding section.
15
23. The minute of agreement on the location of disposal site has been established among Hai
Thai and Cam Lo CPC, detailed design Consultant, and land owner, see more in Annex 4.
24. Location and routes of construction material sources and disposal site in the Figure 6
16
Figure 6. Location and routes of construction material sources and disposal sites
17
3. Description of the environment
a. Surface water
Surface water resources and quality
23. The main water bodies in the subproject area are the Hieu River, and the Da Mai and Tan
Kim Reservoirs in Cam Lo district. As stated in the State of the Environment (SOE) 1 report
for Quang Tri, 2019, the surface water quality in the Hieu River was monitored but these
reservoirs was not and water quality of La La stream and other ravines was not also taken
sampling in the monitoring report in 2019 of Quang Tri province.
24. Monitoring program of Quang Tri province was taken place during whole the year and
sampling surface water and air quality every month. Locations for monitoring surface water
are 32 points in whole province, of which there are two points nearly the project area in Cam
Lo district. Ambient air quality are taken sampling at 25 points in the province and there are
two points in Cam Lo district nearly the subproject area.
25. Parameters were monitored: pH, F-, TSS, DO, BOD5, COD, NO3-N, NH4-N, PO4-P, Fe,
Total grease and oil, E.coli, Coliform.
26. Location of samples surface water on the Hieu River was presented in below table:
Table 4: Location of samples surface water on the Hieu River
No Location Label Coordinates Distance to subproject
location X Y
1 Dau Mau
Hydrological station,
in Cam Thanh
commune
SH1QG1
571301 1857216
Distance to point will be
constructed bridge over the
Hieu River is nearly 1km to
upstream
2
Cau Duoi Bridge –
Cam Lo district SH2 581077 1860470
Distance to point will be
constructed bridge over the
Hieu River is nearly 7km to
downstream.
27. As stated in State of Environment Report of Quang Tri 2019, the situation of parameters as
below:
28. pH: At all monitoring locations, the pH of river water is within the limit of column B1 of
QCVN 08, but there is a large variation according to space (locations) and time (months /
times of monitoring). The pH value at monitoring point of the hydrological stations Dau
Mau and Cau Duoi bridge is higher than the limit of column A2 in 2029 but is still under
the limit of Column A1.
29. NH4-N: NH4-N parameters at all monitoring locations are within the allowed limits of
column B1 of QCVN08-MT:2015/BNTMT. The location at Dau Mau hydrological station
has monitoring results of this parameter lower than that at Cau Duoi Bridge.
1 Quang Tri SOE 2019
18
30. BOD5, COD, DO: Monitoring results of DO, BOD5, COD parameters in 2019 at all river
water locations are within the allowable limit of column A2 of QCVN08-
MT:2015/BNTMT. DO parameters range from 5.5-6, 8 mg / l, BOD5 ranges from 1.1 to
4.7 mg / l, COD ranges from 3 mg / l to 13 mg / l.
31. TSS parameters: Most of the river water quality monitoring times have TSS parameters
within the permissible limit of column A1 of QCVN08-MT:2015/BNTMT at Cau Duoi
Bridge and hydrological station Dau Mau. Particularly result of the location at the
hydrological station of Dau Mau (SH1QG1) exceeds the limit of column B1 1.4 times in
November.
32. NO3-N Parameter: Results of monitoring NO3-N parameters of river water environment at
all positions are within the permitted limits of column A2 of QCVN08-MT:2015/BNTMT
and fluctuate within
19
1 Sampling point is
opposite area of Thien
Tan Rock Quarry in
Cam Thanh commune,
Cam Lo district
K42 566201 1856713
Distance to end of point at
Km22+810 (T-junction with
NR9) in Quat Xa village is
nearly 1,5km
2
At NR9 near the Cam
Lo Post Office in Cam
Lo Town
K39 579019 1859059
Distance to end of point at
Km22+810 (T-junction with
NR9) in Quat Xa village is
nearly 3,5km
39. The result of monitoring ambient air quality in 2019 as below:
Table 6: Result of monitoring ambient air quality in 2019
Location TSP (µg/mᶟ) Noise (dB(A)) CO(µg/mᶟ) SO2(µg/mᶟ) NO2(µg/mᶟ)
min-max min-max min-max min-max min-max
K39 249 – 306 68,4 – 73,4 MDL – 2596 MDL – 32 14 – 25
K42 250 – 278 66,1 – 68,8 2119 – 2308 23 – 28 19 – 35
QCVN 05:
2013/BTNMT 300 30.000 350 200
QCVN 26:
2010/BTNMT 70
40. The dust in the air at most locations is within the permissible limits of QCVN 05. However,
the weather from March to September is hot and dry, the humidity in the air is low, so the
dust particles are weak adhesive, easily attracted to the air. So the dust is larger than other
times and exceeds the allowed limit of QCVN 05 in some locations. In particular, in
locations of main roads and large vehicle concentration areas such as the location of Cam
Lo town (K39), the dust concentration is approximately and over the permitted limit by 1.5
times in August.
41. Noise at most locations in 2019 is smaller than the permissible limit of QCVN 26 for normal
areas from 6am - 9pm. Particularly in some locations on the main roads such as Cam Lo
town (K39), Thien Tan rock Quarry area (K42), the noise regularly approximates and
exceeds the limit of QCVN 26 and fluctuates within about 60.3 - 76.3 dB (A)
42. Concentrations of toxic gases SO2, NO2, CO in 2019 at all monitoring locations are within
the permitted limits of QCVN 05, concentrations of NO2 fluctuate in the range of 8 - 74 µg
/ m³, SO2 fluctuates in the range < MDL (17 µg / m³) - 53 µg / m³, CO ranges from
20
land, the impact of road construction could cause forest fires or tree breakdown due to the
operation of machines and workers. In the operation phase, the new road will increase
accessibility to the forest as vehicles can flow easily.
Unexploded Ordnance
46. Along the subproject road, there is some possibility that UXO remains from
wartime, especially for Quang Tri, the province that suffered the most in the aftermath of the
war.
Therefore, PMU BIGG2 signed a contract with Enterprise 319.9 of 319 Corporation, Ministry
of Defense to detected and cleared UXO along the road. The clearing UXO was completed in
November 2019.
Sensitive receptors
47. Sensitive receptors of the road are identified in the below table
Table 7: Environmental Receptors
Environmental Receptors Description on receptors
Water Receptors – rivers, streams, canal
Canal at Km4+467.72
Natural ditch at Km6+450,17
There are some canals, streams and river
run crossing to the road in including:
• Canal at Km4+467.72 for irrigation in Xuan Hoa Village
• Natural ditch at Km6+450,17 in Trang Rong Village
• Stream at Km8+524,35 in Trang Rong Village
• Stream at Km11+521,78 in Trang Rong Village
• La La River at Km16+668,19 in Ban Chua vilalge
• La La River at Km17+811,98 Tan Hoa Village
• Hieu River at Km20+662,61 in Quat Xa Village
21
Environmental Receptors Description on receptors
Stream at Km8+524,35
Stream at Km11+521,78
La La River at Km16+668,19
La La River at Km17+811,98
22
Environmental Receptors Description on receptors
Hieu River at Km20+662,61
Ecological Receptors
Typical vegetation in section in Hai Thai ommune
Along the road, all most area in Hai Thai
Commune is Melaleuca and Rubber trees,
some area the vegetation is a mixture of
grass, shrub and melaleuca or rubber trees.
A mature trees that may need to be removed in Trang
Rong village
23
Environmental Receptors Description on receptors
Typical vegetation in section to Ban Chua village
Typical vegetation in section in Quat Xa village
In the section to Ban Chua village, the
vegetation is a mixture of crop field, of
grass, shrub and melaleuca or rubber trees.
In section of Quat Xa village – Cam Thanh
Commune including place will be
constructed new bridge over Hieu River,
the vegetation is a mixture of grass, shcrub
and some kind of tree such as bamboo,
banana and meliaceae.
Cultural Receptors
Cultural house of Trang Rong village
Graves at sides of the road in Quat Xa Village
A cultural house of Trang Rong village is
located at right side of the road.
Graves at sides of the road in Quat Xa
Village
Infrastructure
24
Environmental Receptors Description on receptors
Power lines along section from the beginning point to
Trang Rong village
Power lines on both sides of the road at Quat Xa
village Cam Thanh Commune
Along the road from the beginning point to
Trang Rong village has a power line are
outside of ROW therefore no electricity
poles need to be moved for this road.
Along the section to Quat Xa village Cam
Thanh Commune, there are power lines and
electricity poles are located on the both
sides of the road.
Health Receptors –
Hospital, Health Centre, Clinic
There is a health centre of Cam Thanh
Commune is located on the left of the road
at T-junction with NR 9
Educational Receptors -
Schools, University, Kindergarten
Cam Thanh Primary school in Cam Thanh commune
There are 3 primary schools one in Ban
Chua Village, one in Tan Kim village -
Cam Tuyen commune and one in Cam
Thanh commune
25
Environmental Receptors Description on receptors
Residential Receptors –and Businesses/Livelihoods
Residence are in Quat Xa village
Restaurant at the beginning point of the road inTan Hoa
Village
Residence are in Trang Rong village
Residential receptors are Trang Rong, Ban
Chua, Tan Lap, Quat Xa village and a
number of houses are located dispersed
along the road.
There are some small restaurants/shops
currently are located dispersed along the
road.
III. ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES
43. This section discusses the potential environmental impacts of the subproject and
identifies mitigation measures to minimize the impacts in all pre-construction, construction and
operation phases of the subproject.
44. The potential environmental impacts as well as the mitigation measures associated with
the pre-construction, construction and operational phases are assessed below. The criteria for
assessment are in line with ADB's Safeguard Policy Statement 2009 and the Government of
Viet Nam standards based on the Environmental Protection Law (2014). Where government
standards or guidelines have some kind of conflict with the ADB SPS, the ADB SPS will be
applied as the policy for the subproject implementation.
26
45. ADB safeguard policy statement (SPS) 2009 imposes safeguard requirements for all its
funded projects. The SPS 2009 clarifies the rationale, scope and contents of the environmental
assessment. It emphasizes environmental and social sustainability in progress of economic
growth and poverty reduction in Asia and the Pacific, with the following aims:
• Avoid adverse impacts of projects on the environment and affected people, where possible;
• Minimize/mitigate and/or compensate for adverse impacts on environment and affected people
when avoidance is not possible; and
• Help borrowers/clients to strengthen their safeguard systems and develop the capacity to
manage environmental and social risks
46. For environmental safeguards, the Subproject is initially categorized as ‘B’. A
subproject that is classified as category A on environmental safeguards would be ineligible as
a BIIG 2 subproject.
47. Due to the change in the detailed design compared to the FS such as widening the
roadbed by 1m, reducing the length of 500m, building 2 more bridges, the environmental
impacts are added at two points (Km6+450,17 and Km8+524,35) where two new bridges will be
built in comparison with the impact identified in the IEE report. Additional impacts take place
during the construction phase, and these impacts are flow rate of runoff and surface water
quality. They are assessed in moderate level and are the most significant change on impacts in
detailed design phase.
48. Potential impacts was identified in the original IEE report as well as additional impacts
are presented in the next section.
1. Potential Impacts Summary
Table 8. Summary of Potential Environmental Impacts
Issues Potential Impacts
Pre-construction Phase
Land acquisition and
resettlement The impact is mainly on the residential area along the road including
Hai Thai commune center in Gio Linh district; Tan Hiep and Tan
Hoa villages, Cam Tuyen commune and Quat Xa village in Cam
Thanh commune, Cam Lo district.
The subproject will affect approximate 160 households consist of
ethnic minority, poor and vulnerable households. The subproject
also affects perennial crop land, production forest land, annual crop
land and public land with total area is around 7,2ha.
Production forest land acquisition ( 5.4 ha) will reduce temporary
forest land areas of two districts but it does not have significant
impact to environment. Because, acquired forest area is scattered
along the existing road, almost of this forest land is planted
melaleuace which are periodically harvested by cutting down and
27
Issues Potential Impacts
replaced by a new plantation. Therefore, the forest land acquisition
will not affect significant to surrounding environment as well as
erosion of soil.
Site clearance The impact is mainly on the residential area along the road including
Hai Thai commune center in Gio Linh district; Tan Hiep and Tan
Hoa villages, Cam Tuyen commune and Quat Xa village in Cam
Thanh commune, Cam Lo district
The subproject also affects land, tree, crop and structures of some
households, organizations and enterprises.
Disturbance of
Unexploded Ordnance
(UXO)
In November 2019, UXO was cleared by a military unit according
to contract with PMU.
Construction Phase
Disfiguration of landscape/
Tree and vegetation
removal
Construction work will involve some removal of trees along the
route, mainly along the 3.0 km section of new road and other trees
cultivated by people who live along the road. Land clearance at the
3.0 km section will involve minor alteration of the landscape. The
impacts will take place over 24 months of construction time.
Impact on crossing
streams or bridge
construction locations
The construction of new bridges may increase the flow rate in rainy
season due to expansion of space for drainage at that points although
direction of water way will not be changed. During the construction
time, excavation on the sides can result to obstruct the flow and pile
driving on the stream can lead to distribution of sediments into the
water. Furthermore, careless construction and poor handling of
materials at bridge sites can cause blockages and release of silt into
streams and other waterways. Runoff water during rain could bring
waste and soil into streams and the Hieu River, leading to a
temporary reduction in water quality and impact downstream user
of Hieu River including Cam Lo town and Dong Ha city.
All streams are natural flows and it is not to be used for living
activities or irrigation as well as aquaculture production except
some section of the Hieu River at downstream. Anyhow, the
implementation of subproject except impacting from construction
activities that are mentioned above, it does not affect to water uses.
Surface water pollution
The surface water quality of the subproject area could be degraded
due to silt runoff, release of chemicals used in construction and of
sanitary wastes from workers camps: (i) surface and subsurface
water resources may be contaminated by fuel and chemicals used in
construction, or by solid waste and effluent generated by the
kitchens and toilets at construction campsites; (ii) streams and the
Hieu River may subject to release of silt from borrow materials
28
Issues Potential Impacts
piled near the construction area (iii) water in streams could be
temporary blocked during construction period at the crossing
positions.
The impacts will mainly on water bodies along the subproject road
and worker camps area, especially at crossing point with the Hieu
River as the main water source for Cam Lo Water Supply Factory
is Hieu River with the intake point located downstream of the
subproject area.
All streams are natural flows and it is not to be used for living
activities or irrigation as well as aquaculture production except
some section of the Hieu River at downstream so impact to water
use as mentioned above.
Impact related to material
transportation and Storage
Material transportation from Dong Ha city, communes of Cam Lo,
Gio Linh districts via NR No1, NR No9, Ho Chi Minh Trail and
some urban roads. This can affect to residence areas along these
roads by dust, noise, exhaust air from vehicles as well as risk of
traffic accidents. Besides, storage of construction material can cause
traffic jam, surface water dust pollution or community safety.
Impacts on dust and air
pollution
Earthworks and rock crushing activities will be the main sources of
dust.
Construction machines and vehicles will generate gaseous
emissions (NOx SOx, CO, CO2, etc.) when they are in operation.
Bitumen activity will also generate gas and odor.
These gaseous emissions, dust could cause respiratory problems for
residents who live along the subproject road likes Trang Rong, Ban
Chua, Quat Xa, Tan Hoa and Tan Lap villages.
Civil nuisance impact
including:
- noise, vibration,
- increased traffic,
- worker & public
accidents and safety
- Construction machines will also create noise during their
operation.
- Local people and people from other areas who travel on the
subproject road will be affected during the 24 month construction
period due to there is the only route for local people in several
villages of Hai Thai and Cam Tuyen to access the Ho Chi Minh road
and National Road No.9.
- Works and the public are at risk of accidents associated with
construction, particularly excavations, and operations involving
heavy machinery. Material transport and construction activities on
the existing road may create the risk of traffic safety and affect
houses and other structures on roadsides, particularly on the
residential areas along the road.
- The influx of construction workers can cause (i) a burden on local
public services like electricity and water supplies; (ii) risks of
transmission of diseases in the subproject area; (iii) conditions theat
29
Issues Potential Impacts
favour thte spread of diseases such as sore eyes, cholera, flu and
respiratory problems; (iv) risks of social problems such as those
associated with gambling, drug use, prostitution, and violence. The
impacts would be on both workers and on the communities near the
construction sites in residential.
Erosion
Erosion can happened at slopes such as in 3.0km connected Trang
Rong and Ban Chua, and at crossing streams or bridge construction
locations. Erosion can affect to surface water quality or taluy, suface
of the road as well as vegetation around.
Solid/liquid wastes
Solid/liquid wastes from construction and worker activities can
bring about land contamination, surface water quality and
surounding environment of construction sites, worker camps.
Borrow pits and Spoil
Management
Borrow pits can lead to erosion, loss vegetation around or dust of
vehicles transportation, so all borrow pits will be used for the
subproject need to get permission of DONRE with measures to
reduce those impact.
Spoil/excavated soil can obstruct flows at crossing streams,
conterminate surface water, affect to traffic at residence area on the
road.
Site clean up
When construction work has been completed, any un-collected
waste or abandoned borrow pits pose potential hazards to people
and land as well as being unsightly.
Operation Phase
Increased traffic
The upgrading of the road is likely to increase the vehicle speed on
the road, leading to increased traffic congestion, traffic accidents.
2. Environmental Mitigation Plan
49. The anticipated environmental impacts and mitigation measures discussed in the
previous section are presented in Table 4. The table also shows responsibilities and
timeframe/schedule for implementation of mitigation measures and monitoring.
50. To ensure implementation of mitigation measures during construction, the EMP shall
be included in the tender and contract documents for civil works. Contractors’ conformity with
environmental contract procedures and specifications shall be regularly monitored by PMU
with assistance from CSC and results shall be reported semi-annually to ADB.
30
Table 9 - Environmental Impact Mitigation Plan
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
Pre-construction Phase 1. Land
acquisition and
resettlement
Loss of trees and
disfiguration
landscape
1. Land Acquisition and Resettlement Report of the subproject is being
updated and the report will be submitted to PPC/ADB for approval.
2. PMU will also inform Cam Tuyen, Cam Thanh, Gio An, Hai Thai
CPCs, local people and affected households, companies all information
related to the road construction in advance.
3. With approximate 5,4 ha production forestland acquisition, besides the
implementing the compensation in accordance with regulations, Quang
Tri PMU will implement afforestation/reforestation as defined in article
21, the Law on forestry 2017:
- Quang Tri PMU shall develop the plan of afforestation and reforestation
to summit to the Quang Tri PPC for approval. If the approved plan is not
implemented, Quang Tri PMU shall pay an amount to the Quang Tri forest
protection and development fund.
- The amount remitted into the Quang Tri Forest Protection and
Development Fund is equal to the afforestation/reforestation area
multiplies by the unit price per ha decided by Quang Tri PPC; Quang Tri
PPC shall decide to use the amount paid to such fund to carry out the
afforestation/ reforestation in the Quang Tri province.
- If the Quang Tri PPC fails to implement the afforestation/ reforestation
program within 12 months from the day on which the Quang Tri PMU
make full payment to the Quang Tri forest protection and development
fund, the payment shall be transferred to the national forest protection and
development fund in order to implement the afforestation/reforestation
program in other provinces.
4. The reforestation plan will monitored as regulation in Circular
13/2019/TT-BNNPTNT dated October 25, 2019: Regulation on
reforestation when changing the forest use purposes.
- According to Article 4 “Project owners shall not carry out reforestation
by themselves” at Clause 5: Project owner fulfill their obligation to
reforestation when they are informed by the provincial Forest Protection
and Development Fund about fulfilling the obligation of payment for
reforestation. Therefore, DPI Quang Tri (Project Owner of BIGG2
project) will submit confirmation of Forest Protection and Development
Fund Quang Tri as evidence for reforestation.
5. Monitor the compensation process to ensure it is suitable with the
approved Land Acquisition and Resettlement Report.
PMU Social
Safeguard
Specialist
- LIC
Included in
project
manageme
nt cost of
PMU and
the contract
with SSS
(LIC)
Before
commencemen
t
As updated
Land
Acquisition
and
Resettlement
Report
31
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
6. Institutional implementation arrangements will be made for regular
monitoring (detail in Land Acquisition and Resettlement Report) and to
record and redress grievances (see more Part VIII. Grievance Redress
Mechanism)
2. UXO
survey, &
removal
Injured worker or public
1. PMU signed contract with an authorized UXO clearing contractor.
2. The clearance UXO of the subproject has been done in November 2019.
3. The UXO clearing firm has certified that the subproject areas are
already cleared and safe for commencement work by the contractors
PMU UXO
clearing
Contractor
Included in
contract
with the
contractor
Before
commencemen
t
Along the
road
3. Detailed
design
River Crossings Detail engineering designs have taken into account maximum flood levels.
PMU Design
consultant
Included in
design cost
In approved
DED
River and
stream
crossings
4. Detailed
design
Road safety All signage of transport safety are designed along the road in approved DED as regulation on transportation and road
PMU Design
consultant
Included in
design cost
In approved
DED
Along the
road
5. All of
construction
activities
All impacts
according to sub-
plans in Site-
EMP
1. Contractor need to develop site-EMP that includes individual management sub-plans for:
a) Tree and vegetation removal b) Construction Drainage & Water Pollution Prevention c) Erosion Control; d) Noise and Dust control; e) Solid and Liquid Waste Disposal; f) Construction Traffic Management; g) Community, Occupational Health and Safety and Emergency
Response
h) Construction Materials Acquisition, Transport, Storage i) Borrow Site and Spoil Management j) Construction Workers Camp and Management k) Site cleanup sub-plan 2. The Site EMP will include a map of the construction site, showing
as a minimum: Access routes, storage areas for waste, storage area
for chemicals such as fuels, concrete mixing, stockpiles, first aid kit
and equipment used in emergency response.
ESS/PMU Contractor Included in
bid price
Before
commencemen
t
N/A
Construction Phase
32
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
1. Implement
Tree and
vegetation
removal sub-
plan
Tree and
vegetable loss
and landscape
changing
1. No unnecessary cutting of trees – all vegetation to be removed will be
in accordance with the Tree and Vegetation Removal and Site
Restoration management sub-plan which will be in accordance with the
detailed engineering design
2. All replanting works to utilize locally available non-invasive species.
3. No construction camps, material storage sites are to be located in area
where can damage vegetation.
4. Contractors will take all precautions necessary to ensure that damage
to vegetation is avoided due to fires resulting from execution of the
works.
5. No vegetation will be burned on site
CSC
ESS/PMU
; CPCs
Contractor
s
Included in
the contract
with
contractors
Throughout
construction
phase
Along the
subproject
road,
especially
3.0 km
newly
construction
section;
2. Implement
Construction
Drainage &
Water Pollution
Prevention
subplan
Loss of drainage
& surface water
pollution
1. No construction waste, including excavated material, to be placed in
rivers or streams.
2. Work in streams at bridge construction sites will be scheduled during dry season and work duration shall be as short as possible. 3. Cofferdams, silt fences, sediment barriers or other devices will be used as appropriate based on the design to control release of silt during excavation and boring operations within or near streams. 4. Provision of adequate short-term drainage away from construction sites to prevent ponding and flooding. 5. The contractor will prevent borrow pits from filling with water. 6. Installation of temporary storm drains or ditches for construction sites to manage and control the flow and direction of surface water run off 7. Ensure connections among surface waters (canals, drainage ditches and streams draining into Hieu river) are maintained or enhanced to sustain existing storm water storage capacity throughout construction. 8. Protective silt curtains will be used within Hieu River during construction and earthworks on the river bank 9. Erosion channels will be built around aggregate stockpile areas to contain rain-induced erosion. 10. Stockpiles and materials, fuel will be stored at least 50m from surface waters with drainage directed away from the river or drainage channels leading to the river and other sensitive receptors 11. No washing or repair of machinery within 50m of surface waters. 12. Pit latrines for workers to be located at least 200m from surface
waters, and in areas of suitable soil profiles and above the groundwater
levels
Contractor Included in
the contract
with
contractors
Throughout
construction
phase
Throughout
construction
sites; Hieu
River,
streams and
other water
bodies,
material
storage sites,
temporary
waste
disposal area
33
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
3. Erosion
Control
Loss of soil
through erosion
1. Maintain a stockpile of topsoil for immediate site restoration
following backfilling.
2. Protect exposed or cut slopes, in accordance with a slope stabilization
good practice.
3. Speed up construction at slopes to minimize erosion
4 Speed up construction at pile driving points on the streams/river to reduce sediments into the water
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractor
Throughout
construction
phase
Throughout
construction
sites; Hieu
River,
streams and
other water
bodies,
material
storage sites
4. Noise, dust
and vibration
Air Pollution
(dust)
Civil nuisance
(Noise and
vibration)
1. Cover or keep moist construction roads, all stockpiles of construction aggregates, and all truck loads of aggregates.
2. Minimize time that excavations and exposed soil are left open/exposed
3. All equipment will be properly and adequately maintained as well as regularly serviced in accordance with manufacturer
recommendations
4. Replace or repair unnecessarily noisy vehicles and machinery. 5. Vehicles and machinery will be turned off when not in use. 6. All mud on public roads resulting from construction traffic will be
removed before the end of the working day on which it was deposited on
the road.
7. Powered mechanical equipment and vehicle emissions to meet national
TCVN/QCVN standards. All construction equipment and vehicles shall
have valid certifications indicating compliance to vehicle emission and
noise creation standards.
8. To protect buildings and structures from vibration, non-vibrating rollers
shall be used in construction sites near buildings and structures.
9. Structures, which are damaged due to
vibration caused by the construction activities, shall be repaired
immediately as directed by ESP/PMU.
10. Pile driving to be schedule for daytime if construction site is near
residential areas or approved by DONRE, CPCs and ESP/PMU.
11. Impose speed limits on construction machines and transportation
vehicles to minimize dust emission along areas where residential areas are
located.
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractor
Throughout
construction
phase
Construction
sites especial
residential
area Trang
Rong, Ban
Chua, Tan
Hoa, Tan
Lap, Quat
Xa village
5. Construction
Traffic
Management
Traffic
disruption,
Community
Health & Safety
1. Communicate to the public through local officials regarding the scope
and schedule of construction, as well as certain construction activities
causing disruptions or access restrictions.
2. Post speed limits, especial at Ban Chua, Quat Xa, Tan Hoa and Tan
Quang villages, and create dedicated construction vehicle roads or lanes.
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractors
Throughout
construction
phase
Construction
sites especial
residential
area Trang
Rong, Ban
Chua, Tan
34
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
3. Inform community of location of construction traffic areas, and provide
them with directions on how to best co-exist with construction vehicles
on their roads
4. The contractor will ensure road and walkway lighting is provided
during construction and that all construction sites are lit to prevent
accidental injury to the public.
5. In coordination with local traffic authorities, implement appropriate
traffic diversion schemes to avoid inconvenience due to subproject
operations to road users, ensure smooth traffic flow and avoid or minimize
accidents, traffic hold ups and congestion
6. Provide temporary safe vehicle and pedestrian access around
construction areas.
7. Install bold diversion signs that would be clearly visible even at night
and provide flag persons to warn of dangerous conditions.
Hoa, Tan
Lap, Quat
Xa village
and the
connecting
points with
NR9 and Ho
Chi Minh
Trail
6. Community,
Occupational
Health and
Safety and
Emergency
Response
Community and
Occupational
Health and
Safety.
Emergency cases
1. Sufficient signage giving health and safety warnings and information
disclosure at all sites.
Speed limits will be imposed on all construction vehicles
2. The contractor will not cause standing water suitable for disease vector
breeding on any construction site or worker camp area
3. Worker education and awareness seminars for construction hazards will
be given. A construction site safety program will be developed and
distributed to workers
4. Drinking water will be provided at all construction sites
5. Fencing on all excavation, borrow pits and sides of temporary bridges.
6. Ensure that all workers are equipped with, and use Personal Protective
Equipment.
7. Health and Safety qualified engineer and adequate first aid will be on
site
8. Where worker exposure to traffic cannot be completely eliminated,
protective barriers shall be provided to shield workers from traffic
vehicles.
9. The Contractor will set out an Emergency Response Plan. The plan will
contain:
• Roles and Responsibilities for those working on behalf of the contractor who will be involved in an incident response;
• Actions and Procedures which will be taken for each incident;
• Measures to Prevent an Incident.
• Contact details of emergency medical facilities; and
• Corrective action procedures following in incident
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractors
Throughout
construction
phase
Construction
sites especial
residential
area Trang
Rong, Ban
Chua, Tan
Hoa, Tan
Lap, Quat
Xa village
and the
connecting
points with
NR9 and Ho
Chi Minh
Trail, worker
camps
35
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
• The location of a First Aid Kit to be kept on site and stocked at all times
10. The Contractor will develop Incident Response procedures prior to
construction. The procedures will cover actions to be taken in case of:
• Worker injury (e.g. construction or traffic accident)
• Spillage (e.g. fuel spillage)
• Fire (e.g. fuel or chemicals storage area); and
• Any other incidents anticipated by the contractor. 11. The Incident Response Plan will set out Preventative Measures for all
types of incidents covered in the Incident Response Plan. This will
include:
• Prevention of Injury – to include Personal Protective Equipment requirements for construction workers, training requirements
• Prevention of Spillage - All construction fluids such as oils, and fuels will be stored on hard standing with sealed drainage with
a capacity of 110% of the largest fuel container, will include
procedures on refueling and maintaining vehicles
• Prevention of Fire – to include measures for Ignition Sources including prevention of smoking on construction site,
management of flammable materials and liquid.
• Other Incidents – prevention measures relevant to other issues considered relevant by the contractor
7. Construction
Workers Camp
and
Management
Negative impact
to local
communities and
surrounding
environment
(water bodies,
hygienic
sanitation)
1. Construction and workers' camp location and facilities to be at least
500m from settlements and agreed with local communities and facilities
approved by ESS and managed to minimize impacts.
2. Hire and train as many local workers as
practicable.
3. Provide adequate housing for all workers at the construction camps and
establish clean canteen/eating and cooking areas.
4. Workers camps shall be provided with toilets/sanitation facilities in
accordance with local regulations to prevent any hazard to public health
or contamination of land, surface or groundwater. These facilities shall be
well maintained to allow effective operation.
5. Provide separate hygienic sanitation
facilities/toilets and bathing areas with sufficient water supplies for male
and female workers.
6. HIV Aids education will be given to workers.
7. Camp areas must be restored to original condition after construction
completed.
8. Register temporary stay for workers with police.
CSC
ESS/PMU
Contractor Included in
the contract
with
contractors
Throughout
construction
phase
Worker
camps
36
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
8. Solid and
Liquid Waste
Disposal;
Land
contamination,
surface water
pollution,
resource use
1. Management of general solid and liquid waste of construction will
follow National regulations, and will cover the collection, handling,
transport, recycling, and disposal of waste created from construction
activities and worker force.
2. Appropriate sites for disposal of solid and liquid waste to be determined
by DoNRE and adhered to by the contractor
3. Construction sites will have appropriate sized garbage bins. All solid
waste to be stored in containers with lids.
4. Collection, storage, transport, and disposal of hazardous waste such as
used oils, gasoline, paint, and other toxics will follow National
regulations.
5. Wastes will be stored above ground in closed, well labeled, ventilated
plastic bins in good condition well away from all surface water, water
supplies, and cultural and ecological sensitive receptors.
6. All spills will be cleaned up completely with all contaminated soil
removed and treated as waste.
7. A schedule of solid and liquid waste pickup and disposal will be
established and followed to ensure construction sites are as clean as
possible.
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractors
Throughout
construction
phase
Construction
sites, worker
camps.
9. Construction
Materials
Acquisition,
Transport,
Storage
Water and air
pollution, soil
erosion,
community health
and safety
1. Define and schedule how fabricated materials such as steel, concrete
structures, and scaffolding will transported and handled in safe way.
2. All aggregate loads on trucks will be covered.
3. Bitumen need to be stored in in specialized tools and closed.
4. Fabricated materials with big size need to be stored far from
temporary accesses for vehicles
5. Define & schedule how materials are extracted from borrow pits and
rock quarries, transported, and handled & stored at sites.
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractors
Throughout
construction
phase
Construction
sites,
material
storage
10. Borrow Site
and Spoil
Management
Land
contamination,
surface water
pollution, ecology
1. All borrow pits and quarries will be approved by DoNRE
2. All borrow pits and quarries will have a fence perimeter with signage
to keep public away.
3. Uncontaminated spoil will be disposed of in designated sites, which
must never be in or adjacent surface waters. Designated sites must be
clearly marked and identified
4. Spoil will not be disposed of on sloped land, near cultural property or
values, ecologically important areas,, or on/near any other culturally or
ecologically sensitive feature.
5. Where possible spoil will be used at other construction sites, or
disposed in spent quarries or borrow pits.
6. A record of type, estimated volume, and source of disposed spoil will
be retained.
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractors
Throughout
construction
phase
Construction
sites,
Borrow pits
37
Component
Activity
Potential
Environmental
Impacts
Proposed Mitigation Measures Institutional
Responsibilities
Mitigation
Cost
Timing Location
Supervisi
on
Impleme
ntation
7. Spoil from excavation on the bridge points should be transported out
of water every day to avoid obstructing the flow.
11. Site cleanup
sub-plan
Land use,
nuisance,
community health
and safety
On completion of construction works:
1. The contractors must fill pits, land excavation areas and any landscaping and planting done on land that has been
temporarily in the Contractor's possession during construction
2. All sites to be cleaned of all litter, debris and any other materials or equipment associated with construction activities
3. Any conditions placed on use if sites by local authorities or in agreements with landowners must be complied with.
4. All sites to be handed over only after inspection completed by CSC/PMU
CSC
ESS/PMU
Contractor
s
Included in
the contract
with
contractors
After
completion
works
Whole the
construction
sites
Operation Phase
1. Traffic and
road safety
Community
health and safety,
Increased air
pollution & noise,
Water pollution
and flooding
1. Undertake road safety awareness campaigns for local residents and
other road users of Gio Linh - Cam Lo Inter-district road.
2. Install and maintain road warning signs and markings.
3. Enforce well marked speed limits, provide guard rails along road, and
educate public on new road safety
4. Maintenance of all culverts by removing contaminated debris at
regularly intervals
5. Maintenance of all cross drains by removing debris or waste which
may block water flow and cause flooding
CPCs Quang Tri
DOT/
Included in
operation
and
maintenanc
e cost
In operation
phase
Whole the
road
38
IV. MONITORING PLAN
A. Environmental Policy and Standard
51. The subproject shall comply with requirements of ADB SPS 2009 and with the
environmental legal framework of Vietnam, which is outlined in this section. Environmental
quality standards and criteria for Viet Nam are listed in Appendix 5. The environ