County of Fairfax, Virginia Department of Transportation Update on Transportation Activities Transportation Round Table Dulles Area Transportation Association June 12, 2019 Eric M. Teitelman, P.E. F.ASCE Chief of Capital Projects and Traffic Engineering Division Fairfax County Department of Transportation

Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Department of Transportation

Update on Transportation Activities

Transportation Round TableDulles Area Transportation Association

June 12, 2019

Eric M. Teitelman, P.E. F.ASCEChief of Capital Projects and Traffic Engineering Division

Fairfax County Department of Transportation

Page 2: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Ongoing Project Implementation• Silver Line phase II and county garages:

– Herndon and Innovation Center Stations• Pedestrian and Bicycle Connections:

– Reston Metrorail Assess Group– Herndon Metrorail Station Access and Mobility Study

• Improvements to Route 28.• Route 28 and Dulles Toll Road.• Davis Drive Bridge.• Soapstone Connector.• Town Center Parkway underpass.• Silver Line phase 2 bus service planning.• Other Reston transportation projects.Department of Transportation

2

Page 3: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Silver Line StatusPhase 1• Old Meadow Road realignment – 100% design:

– Utility relocation underway– Construction completion scheduled for end of 2019

• VDOT punch list ongoing – MWAA to complete.

Phase 2• Overall phase 2 – 94%• Package A (rail line, system, and stations) – 94%• Package B (rail yard at Dulles) – 96%• Contractual substantial completion – August 2019.

– WMATA Board to establish revenue operations date– Dynamic testing ongoing for western portion of track

Department of Transportation 3 3

Old Meadow Road

Page 4: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Silver Line Phase II GaragesNew Herndon Metrorail Station Garage• Total project estimate: $44.5M

• Construction progress: 100% complete

Schedule• New garage occupancy permit: April 4, 2019

• New Garage opened to public: April 8, 2019.

• Existing garage refresh work initiated: November 2018.

• Complete work on existing garage: Summer 2019.

Department of Transportation 4 4

Presenter
Presentation Notes
1950 new spaces
Page 5: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Herndon Metrorail Station Garage

Department of Transportation 5 5

Page 6: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Herndon Metrorail Station Garage

Department of Transportation 6 6

Page 7: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Silver Line Phase II GaragesInnovation Metrorail Station Garage• Total project estimate: $52M

• Construction progress: 70% complete

Schedule• Construction award: March 2017

• Construction start: April 2017

• Precast erection start: April 5, 2018

• Projected completion: End of 2019

Department of Transportation 7 7

Presenter
Presentation Notes
About 2000 new spaces Precast Erection: Cranes putting up the concrete panels that make up the walls and structure of the garage concrete panels = precast concrete panels
Page 8: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Innovation Metrorail Station Garage

Department of Transportation 8 8

Page 9: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Pedestrian and Bicycle ConnectionsReston Metrorail Access Group Recommendations Phases I and II• More than 40 pedestrian and bicycle projects approved.• Implementation continues:

– 20 projects completed– 3 projects under construction– 5 projects in land acquisition – 12 projects under design– 2 projects in scoping

https://www.fairfaxcounty.gov/transportation/projects/silver-line/restonimp

Department of Transportation 9

Presenter
Presentation Notes
Complete: Intersection of Sunset Hills Rd and Wiehle Avenue - Construct a double left turn lane on westbound Sunset Hills Rd Intersection of Sunrise Valley Drive and Soapstone Drive - Upgrade crosswalks on all legs of the intersection Dec 2019: Sunrise Valley Drive Sidewalk - Sidewalk on south side of Sunrise Valley Drive between Glade Drive and Reston Parkway
Page 10: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Pedestrian and Bicycle ConnectionsHerndon Metrorail Station Access Management Study• Area around Herndon and Innovation Center Metrorail Stations.• Multimodal challenges and possibilities around stations identified.• Missing links and needed pedestrian and bicycle connections:

– 14 bicycle and pedestrian projects approved– 2 projects under construction– 2 projects in land acquisition – 6 projects in design– 2 projects being studied– 6 project in scoping

https://www.fairfaxcounty.gov/transportation/projects/silver-line/herndonimp

Department of Transportation 10

Presenter
Presentation Notes
Sunrise Valley Drive/Monroe Street - Improve signalized crosswalks - Design Van Buren Street/Worldgate Drive - Install signalized crosswalk – Bid Advertisement Dulles Toll Road/Centreville Road - Install signalized pedestrian crosswalk - Construction
Page 11: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Improvements to Route 28• Northern Virginia Transportation Authority allocated HB2313 funding

to multiple projects in the Route 28 corridor.• FY 2014 priorities included two construction projects on Route 28:

– Widen from 6 to 8 Lanes SB (Dulles Toll Road to Rt. 50) – completed– Widen from 6 to 8 Lanes NB (McLearen Road to Dulles Toll Road) –

completed• Funding strategy developed for remaining Fairfax segment (NB Rt.

50 to McLearen).• FY 2015-2023 priorities include design funds for widening Route 28

from Prince William line to New Braddock Road:– Design, environmental, and traffic work underway– RFQ responses received – RFP for design-build contract to be issued September

Department of Transportation 11

Page 12: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Route 28 and Dulles Toll Road• VDOT, MWAA, Fairfax County, Loudoun County, and the Dulles

Greenway have funded study of interchange at Route 28 and the Dulles Toll Road/Dulles Greenway.

• VDOT conducting the study.• Potential improvements:

– Ramp relocation, ramp widening, ramp reconfiguration, new ramp construction, eastbound Dulles Toll Road toll plaza relocation, elimination of eastbound Dulles Toll Road toll plaza cash payment option, roadway connectivity improvements, and/or collector-distributor lanes

• Expected study completion:– Late 2019 to early 2020

Department of Transportation 12

Page 13: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Davis Drive Bridge• New bridge connection across the Dulles Toll Road between

Sunrise Valley Drive in Fairfax County and Innovation Avenue in Loudoun County.

• Northern Virginia Transportation Authority has provided $20M for the project. Counties equally sharing $1M expense.

• Counties have contracted with VDOT to undertake the conceptual design work.

• VDOT is currently working on the feasibility study:– Draft report expected late 2019 to early 2020

Department of Transportation 13

Page 14: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Soapstone Connector• Phase I Reston Comprehensive Plan Amendment adopted by the

Board of Supervisors in 2014:– Includes three new connections across the Dulles Toll Road:

Soapstone Drive, Town Center Parkway, and South Lakes/Davis Drive

• Fairfax County complete an alternatives analysis for the Soapstone Connector.

• Currently working on the environmental assessment:– Additional work on heritage resources required

• Approximately $120M has been identified for the project.• Anticipate construction to begin 2024.• Estimated completion by 2027.Department of Transportation

14

Page 15: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Town Center Parkway Underpass• Town Center Parkway Underpass will connect Sunset Hills Road

and Sunrise Valley Drive beneath the Dulles Toll Road.• Fairfax County funding improvement to the Silver Line track in the

crossing area to allow future construction without disrupting rail traffic.

• Fairfax County requested VDOT to conduct feasibility study.• Estimated completion by 2032.

Department of Transportation 15

Presenter
Presentation Notes
Approximately 4 years for preliminary design and environmental Approximately 2 years for right of way and land acquisition Approximately 3 years in construction
Page 16: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Other Transportation Projects• As of February 2014:

– Network analysis/prioritization completed– Board adopted funding plan– Board adopted a comprehensive plan realignment of

Sunset Hills Road– Route 7 widening (Reston to Tysons) construction

bid awarded– Board approved $500,000 for Sunrise Valley/Fairfax

County Parkway intersection improvements – Board approved $500,000 for improvements at Baron

Cameron/Reston Parkway– W&OD Bridge over Wiehle advancing– Bike share Phase I implemented. Phase 2

implementation to begin soon.

Department of Transportation 16

Page 17: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Reston-Herndon Area Transit Service Overview

• Number of routes: 32• Route types:

– Commuter: 1– Circulator: 5– Local: 11 – Feeder: 15

• Peak-hour level of service:– 70 buses

Department of Transportation 17

Page 18: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Transit Services Planning inReston-Herndon for Silver Line Phase II

• Purpose is to enhance bus services in the Reston-Herndon area while capitalizing on Metrorail Silver Line Phase II.

• Process will encourage public input, examine past and existing transit conditions and future needs, and develop service change recommendations.

• Proposed service changes will include route efficiencies, new route designs, and improved access and mobility.

Department of Transportation 18

Presenter
Presentation Notes
Public Outreach ·  Consists of three phases, with each phase including an online survey and meetings with the public and stakeholders (Reston Association and Herndon Town Council) · Phase 1 was completed during January to February 2019. ·  Phase 2 is planned for September to October 2019. · Phase 3 is planned for November to December 2019. · Service Alternative Planning · The project team is currently working on quantitative and qualitative evaluations of the draft service alternatives. · These evaluations will result in three service alternatives. · The next step will include public and stakeholder review of and comment on the three service alternatives. · The best components from the three alternatives will be identified and incorporated into the preferred service plan. The initial planning process will be based on: 2016 Transit Development Plan (approved by County Board of Supervisors in March 2016) Public input on current service and future service needs Reassessment of existing service Impact of Metrorail Silver Line on travel patterns Level of funding available for service adjustments Assessment process will: Realign routes to increase connectivity and frequency Improve mobility within community Reduce congestion Improve community vitality Reallocate hours of operations
Page 19: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Planning Timeline July 2018 –January 2019

• Service review• Data

collection• Public

outreach

January 2018 –Sept 2019

• Identification of issues

• Development of route alternatives

• Obtain and review public input

Sept - November 2019

• Selection of preferred service adjustments

• Public review• Revise

adjustments per public input

December 2019 –February 2020

• Board approval• Marketing outreach

Silver Line Phase II (2020)

• Implementation of rail service

• Implementation of bus service

Department of Transportation 19

Page 20: Update on Transportation Activities · Other Transportation Projects • As of February 2014: – Network analysis/prioritization completed – Board adopted funding plan – Board

County of Fairfax, Virginia

Questions?

Department of Transportation 20