Upload
jada-footman
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
Update on the Western Region Resource Plan
Presented to the Community Energy Advisory Council
November 14, 2008
2
Update on the Western Region Resource Plan
Agenda
• Latest load forecast for the Western Region and Dashboard update
• Review of resource planning principles and objectives
• Where do we stand today?
• What issues remain to be addressed and where do we go from here?
Update on the Western Region Resource Plan Latest load forecast for the Western Region
3
Recent forecasts show increasing trend
DSM/EE activities cut load growth in half
Update on the Western Region Resource Plan Latest load forecast for the Western Region
4
Future AdditionsOther MW above
CT Solar PV Wind DR EE Purchase Minimum2008 0.1 0.0 662009 0.8 0.0 442010 4.6 0.4 150 792011 11.2 1.4 722012 147 13.1 2.3 -150 662013 13.3 3.0 642014 8.4 3.3 582015 2.5 3.3 432016 1.9 3.3 292017 4.8 3.2 182018 3.7 3.1 62019 49 2.3 2.7 412020 1.1 2.1 252021 0.0 1.7 6
Select Year --> 2012
Dashboard
Update
5
Update on the Western Region Resource Plan Review of resource planning principles and objectives
System Resource
Planning
NCUC SCPSC SERC NERC FERC
Plus:
Federal, state and Local Environmental Regulations
6
Update on the Western Region Resource Plan Review of resource planning principles and objectives
Regulatory Body Areas of Regulation
North Carolina Utilities Commission Cost, reliability, adequacy
NERC/SERC Reliability, adequacy
FERC Cost, reliability
EPA, NCDENR Environmental performance, siting
Local Authorities Zoning/siting
This list is not intended to be all inclusive or a complete representation of the authority of any given regulatory body.
7
Update on the Western Region Resource Plan Review of resource planning principles and objectives
Some of the regulatory considerations in creating the plan:
• Adequacy of resources – Are there enough to meet the peak?
• Reliability of resources – Are there enough to deal with contingencies?
• Least Cost – Is the plan the lowest cost to customers?
• Environmental Performance – Does the plan meet environmental limits?
Clean Smokestacks
CAIR, CAMR, CAVR etc.
• Licensing/zoning requirements
The plan must consider planning and operating requirements.
8
Update on the Western Region Resource Plan Review of resource planning principles and objectives
The objective of the planning process is to provide an adequate, reliable supply of electricity at the lowest (least) cost to customers.
9
Update on the Western Region Resource Plan Where do we stand today?
West Region Supply Resources
Asheville 1 - Coal
Asheville 2 - Coal
Asheville 3 - Combustion Turbine
Asheville 4 - Combustion Turbine
SEPA - Purchase
Rockport - Purchase
Marshall & Walters - Hydro
0
200
400
600
800
1,000
1,200
Meg
aw
atts
2007 Winter Peak Demand2010 Winter Peak Demand
Marshall & Walters - Hydro
Remember where we started
10
Update on the Western Region Resource Plan Where do we stand today?
West Region Peak Day 2006 (December 8)
650
700
750
800
850
900
950
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour of Day
Meg
awat
ts
Morning
Peak
928 MW
(about 7-8 a.m.)
West Region Peak Day 2006 (December 8)
DSM and energy efficiency activities aim to reduce peak usage
11
Update on the Western Region Resource Plan Where do we stand today?
An adequate supply meets firm demand plus reserve requirements
8000
9000
10000
11000
12000
13000
14000
15000
16000
17000
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
New ResourcesRequired
Purchases
Existing Capacity
Reserves Plus FirmDemand
Firm Demand
8000
9000
10000
11000
12000
13000
14000
15000
16000
17000
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
New ResourcesRequired
Purchases
Existing Capacity
Reserves Plus FirmDemand
Firm Demand
Reduction of firm demand reduces supply requirements
Update on the Western Region Resource Plan Where do we stand today?
12
So how did we address the resource shortfall in 2010?
• Purchases of firm capacity (250 MW) for two years from multiple sources
• Extended purchases an additional year through 2012
13
Update on the Western Region Resource PlanWhat issues remain to be addressed and where do we go from
here?
West Region Hourly Load for 2006
0
100
200
300
400
500
600
700
800
900
1000
Meg
awat
ts
J F M A M J J A S O N D
Peak Demand
Daily
Load
Variation
~ 200 MW
West Region Hourly Load for 2006
We are in the process of addressing adequacy.
Now we need to consider reliability.
14
Update on the Western Region Resource PlanWhat issues remain to be addressed and where do we go from
here?
West Region Hourly Load for 2006
0
100
200
300
400
500
600
700
800
900
1000
Meg
awat
ts
J F M A M J J A S O N D
Amount of Resources
Must be Adequate to
Meet Peak Demand
and Provide ReservesReserves must be
Available to Meet
Contingencies
at any time
Reliability
West Region Hourly Load for 2006
Operating reserves are required to meet contingencies
Update on the Western Region Resource PlanWhat issues remain to be addressed and where do we go from
here?
15
What are operating reserves?
Operating reserves are resources that can quickly replace any generating resource that may be lost due to equipment failure or other cause. There are 3 sources of operating reserves:
• Spinning reserves
• Fast start reserves (available within 10 minutes)
• Demand reduction
These reserves must be available to replace the power that is provided instantaneously by neighboring utilities.
Update on the Western Region Resource PlanWhat issues remain to be addressed and where do we go from
here?
16
How do we provide operating reserves in the Western region today?
Unique AEP contract transmission arrangements
How will we provide operating reserves after the AEP contract expires?
Spinning reserves and reserved transmission capacity
Update on the Western Region Resource PlanWhat issues remain to be addressed and where do we go from
here?
17
Issues that need to be addressed :
• Spinning reserves and reserved transmission capacity burns additional fuel and increases cost (vs. fast start reserves in area)
• DSM capacity, which acts like fast start, varies hourly and seasonally (2 a.m. in April)
• New federal standards may require specific allocation of operating reserves
How should we provide needed operating reserves?