Update on the Comprehensive Wastewater Management Plan
David Young, P.E.
Michaela Bogosh, P.E.
June 29, 2021
Select Board Meeting
Agenda
▪ Overview of the problem and sources
▪ Dennis’s Comprehensive Wastewater Management Plan▪ Non-infrastructure components
▪ Effluent Recharge
▪ Costs
▪ Next Steps
Controllable Nitrogen Sources –Swan Pond River Watershed
Overall Load
72%
3%
6%
12%
5%
2%
Wastewater
Landfill/Solid Waste
Fertilizers
Impervious Surfaces
Water Body Surface Area
"Natural" Surfaces
Stormwater
Watershed SepticLoad Reductions
▪ Figure shows required septic load reduction to meet Total Maximum Daily Load
6
CWMP and Program Status
▪ Draft CWMP submitted to Commonwealth of Massachusetts Environmental Policy Act (MEPA) Office and the Cape Cod Commission (CCC) (Summer 2017)
▪ Bass River Railroad/Cape Cod Rail Trail Bridge Abutment Widening (2016-2018)
▪ Economic Study conducted
▪ Aquaculture Pilot Project in Swan Pond (Summers 2018-2019)
▪ Initial Archeological Surveys of
future pumping stations completed
▪ Effluent recharge field
investigations (Aug. & Oct. 2020)
▪ Final CWMP to be submitted 20219
Watershed Septic Load Reduction Required
Bass River 60%
Herring River 58%
Swan Pond 100%
Chase Garden Creek
+24%
Sesuit Harbor Awaiting MEP Report
CWMP Alternatives
▪ Seven collection and treatment scenarios (1A to 7D) were initially evaluated based on:▪ Current and future community development
▪ TMDLs for embayments
▪ Seven screened down to five
▪ Scenario 6A was selected by WIC
▪ Highlights of Scenario 6A:▪ Meets MEP and TMDL nitrogen reduction thresholds;
▪ Allows for effluent recharge sites in multiple watersheds (Bass River and Swan Pond);
▪ Provides a phasing plan that provides for implementation flexibility;
▪ Allows for a potential regional solution between Dennis, Harwich, and Yarmouth; and
▪ Supports desired smart economic development.
10
Phasing Plan
11
1. Buildout Average Daily Flow with Planning District and I/I (GPD)
Phase Estimated Flow (gpd) 1
1 305,000
2 671,000
3 205,000
4 67,000
5 347,000
6 99,000
7 120,000
8 146,000
Total 1,960,000
Non-Infrastructure Components
▪ Public Outreach
▪ Fertilizer Education▪ Brochure
▪ Presentation
▪ Stormwater Best Management Practices
12
Swan Pond Aquaculture Demonstration Project
Route 6 Bass River Bridge(s) - Proposed Widening
14
▪ Potential solutions evaluated to help improve the Bass River water quality ▪ Removal of the flow restrictions from the former railroad bridge south
of Route 6 (completed) and the Route 6 east and west bound bridges
▪ Removing both restrictions would result in a 25 percent reduction in total time required to exchange water in that area
▪ Removing both restrictions will decrease concentrations by approximately 6-percent
▪ Removing restriction of railroad
bridge results in a 2-percent
reduction in concentration
Route 6 Bass River Bridge(s)- Proposed Widening cont.
15
▪ Larger restriction is from the Route 6 east and west bound bridge▪ Currently no plan to widen to pre-bridge conditions
▪ Reached out to MassDOT several times
▪ Dennis and Yarmouth in 2016
▪ Dennis, Harwich and Yarmouth in 2018
▪ MassDOT stated that bridge is neither functionally obsolete or structurally deficient and therefore will not be considered for widening at this time
Effluent Recharge and Recharge Sites
▪ Concentration of 35 mg/L-N in septic systems
▪ Wastewater Treatment Plant reduces concentration to 3 mg/L-N
▪ Treated effluent is sent to the subsurface
16
Effluent Recharge
DISCHARGE
Effluent Recharge Site Overview
17
DHY Shared Facilities Comparison
18
WWTF and
Effluent
Recharge Cost
Comparison
Capital Costs O&M Costs Equivalent Annual
Costs1
Annual Savings
Town Regional Town Regional Town Regional $ / year %
Dennis $109 M $72 M $5.0 M $2.8 M $9.9 M $6.0 M $3.8 M 39%
Harwich $82 M $44 M $2.8 M $1.7 M $6.5 M $3.6 M $2.9 M 44%
Yarmouth $152 M $136 M $9.6 M $5.0 M $16.4 M $11.1 M $5.3 M 32%
Total $343 M $252 M $17.4 M $9.5 M $32.8 M $20.7 M $12.0 M 37%
1. Equivalent annual costs based on 30-year loans at 2% interest.2. 2024 Costs with projected ENR of 13,060.
Dennis Recommended Program Comparison
19
Dennis Capital Costs O&M Costs
Equivalent Annual
Costs1
Annual
Savings
Town Regional Town Regional Town Regional $ / year %
Collection System $225 M $225 M $2.8 M $2.6 M $12.8 M $12.7 M $0.2 M 1.2%
WWTF $71 M $49 M $4.7 M $2.5 M $7.9 M $4.7 M $3.2 M 41%
Effluent Recharge
with PRB$39 M $24 M $0.3 M $0.3 M $2.0 M $1.3 M $0.7 M 34%
Non-Traditional
Technologies$10.4 M $10.4 M $0.1 M $0.1 M $552,000 $552,000 $0 0%
Total $345 M $308 M $7.9 M $5.5 M $23.3 M $19.3 M $4.1 M 17%1. Equivalent annual costs based on 30-year loans at 2% interest.2. 2024 Costs with projected ENR of 13,060.
Dennis Recommended Program - Phase 1
20
DennisCapital Costs O&M Costs
Town Regional Town Regional
Collection System $49.0 M $49.0 M $ 0.70 M $ 0.61 M
WWTF2$53.5 M $39.1 M $ 0.74 M $ 0.39 M
Effluent Recharge with PRB $20.7 M $12.7 M $ 0.16 M $ 0.10 M
Non-Traditional Technologies $1.3 M $1.3 M $ 86,400 $ 86,400
Total $124.5 M $102.1 M $1.69 M $1.18 M 1. 2024 Costs with projected ENR of 13,060.2. Estimated design flow of 1.3 MGD
Next Steps
21
Next Steps
▪ WIC endorsed Town-only solution in March 2021 Meeting
▪ Need confirmation from Select Board
▪ Finalize CWMP
▪ Begin following next WIC Meeting, July 12th
▪ 2 months
▪ MEPA begins review upon submission of CWMP
▪ 30-40 days to issue certificate
▪ CCC begins review following MEPA Certificate
▪ 208 Consistency Plan Review completed to become eligible for 0% interest State Revolving Fund (SRF) loans
▪ 30-40 days to review
▪ ~5 months to finalize CWMP process and receive final approval
▪ Mid November 2021