Update on Module Mounting on Staves and Stavelets
25/8/11
1
2
Pipe clamps
Stavelet clamps two flavours for US and UK stavelets
lid
All items electrically connected
Stavelet test/shipping box.Two lengths, one for the stavelet with long pipes, 2 for standard length pipes
Construction based around ‘ideal’ aluminium extrusion
Frame for light curtain support and overhead cable gantry
3
Overhead gantry is being constructedAwaiting material for frame. Expected WB 22/8/11Simple bolt together system.
Fits standard current table and granite up to 2.5m x 1.2m
Prototype runners
4
Granite table (2.5m x 1.2m)
Main access door
infrastructure
5
Work to reduce distance from stages
Add rotating head for camera
Room Status
• New fire alarms installed. (but not yet in the electronic room) and not tested.• Extra mains sockets installed.• Lighting replaced.• Awaiting replacement ceiling tiles. (done 23/8/11)• Awaiting coupling for vacuum system and final connection into existing system.
(done 23/8/11)• Discussion about how to move the new granite into position has started with
RAL heavy gang.• Stages now on temporary table and being wired up.
6
Adhesive
Se 4445 delivered 23/8/11 (but note DOM was June 2011) and it’s out of date in December 2011. Second batch ordered (with usual 8 /10 week delivery) as this is only made to order.
On the question of Intertronics 2125 .. No manufactures value for the thermal conductivity.