Upload
jamal-bowman
View
34
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Update on FCPS Construction/Renovation Projects. June 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date:$0 - PowerPoint PPT Presentation
Citation preview
Update on FCPS Construction/Renovation Projects
June 2009
June 2009
Cassidy Elementary – Renovation
Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010 Contract Sum: $9,061,000
Change Orders to Date: $0
Current Phase: 1 (On Schedule)
Estimated Completion: 14%
June 2009
Cassidy Elementary – RenovationRendering of Final Façade
June 2009
Cassidy Elementary – RenovationWork Completed in Last 30 Days:Primary electric conduit at new Cassidy parking lot.Foundations for 2-Story Admin/Classroom and Music Rm./Mech. Rm. Additions.Masonry mockup complete and block work begun on additions.Under slab plumbing and electrical rough-ins installed and inspected in 2-Story Admin/Classroom Addition.Under slab plumbing and electrical rough-ins begun in Music Rm./Mech. Rm. Addition.
Current Work Effort (June):Primary electric conduits to new transformer pad location.Site storm and sanitary sewer work will begin at front of building.Gas, water and fire protection utilities will begin into building.All Phase 1 foundation and ground floor slab concrete will be complete.Block masonry bearing wall installation to continue.
June 2009
Cassidy Elementary – Renovation Current Work Effort (June - continued): Steel columns and beams in front 2-Story Addition to be complete. Underground primary plumbing rough-ins complete. Secondary
rough-ins to continue. Underground electrical work to be complete. Secondary rough-ins
to continue.
June 2009
Cassidy Elementary – RenovationNew 2-Story Admin Addition Masonry Mockup
June 2009
Interior Corridor Barrier
Music Room Addition
Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker
Construction
Substantial Completion Date: August, 2010
Contract Sum: $5,001,150
Change Orders to Date: $0
Current Phase: 1 (On Schedule)
Estimated Completion: 6%
June 2009
Russell Cave Elementary – RenovationRendering of Final Façade
June 2009
Russell Cave Elementary – RenovationWork Completed in Last 30 Days:Footing and foundation walls continue: 40 feet of footings poured and 38 feet of foundation wall have been pouredInterior wall footings: 200 feet have been poured.Footings at new mechanical enclosures have been poured. Pads for mech units at kitchen and new transformer and generator have been poured.
Current Work Effort (June):Additional work on footings and foundation at the new addition will continue. New floor slab will be poured in two weeks, weather permitting.Installation of the new leach fields for the septic system will begin installation in the front lawn of the building.Kitchen/Cafeteria demolition and renovation will begin.Renovation of (4) classrooms on the south side will begin.Masonry restoration on the existing building will begin the week of June 8th.
June 2009
Russell Cave Elementary – RenovationFoundation Work 6.2.09 Foundation Work 6.2.09
June 2009
Foundation Work 6.2.09
Foundation Work 6.2.09
Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: W/S Construction
Substantial Completion Date: August, 2010
Contract Sum: $9,920,194
Change Orders: $36,900 (#1--Demo)
Current Phase: 1 (On Schedule)
Estimated Completion: Demo – 100%
June 2009
Arlington Elementary – RenovationRendering of Final Façade
June 2009
Arlington Elementary – RenovationWork Completed in Last 30 Days:WS-Construction has mobilized. Site preparation has begun, including erosion control adding engineered fill, and preliminary grading . Structural shoring of existing walls has also begun.
Current Work Effort (June):Selective demolition, additional site work and the laying out of the new building footprint.
June 2009
Arlington Elementary – RenovationWS Construction Trailer Site Prep / Erosion Control
June 2009
Preliminary Grading
Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
Contract Sum: $10,769,400
Change Orders to Date: $0
Current Phase: 1A (On Schedule)
Estimated Completion: 7%
June 2009
Bryan Station Middle – RenovationRendering of Final Façade
June 2009
Bryan Station Middle – RenovationWork Completed in Last 30 Days:General Contractor and sub-contractors are on site beginning demolition and preparing areas for new work. Phase 1A has begun.Barricade fencing, storage facilities and stored materials now on site.Owner-provided staff is on-site moving large amounts of furniture and equipment out of areas to be renovated.Owner-installed portable classroom units appear to be nearly complete. Electrical connections underway.Owner-provided asbestos abatement being performed in cafeteria. Nearly complete.
Current Work Effort (June):Sanitary sewer extensions also underway.Roof being demolished and new roofing installed throughout the month of June.Floor demolition complete in kitchen and cafeteria and under-slab plumbing installation has begun.Earthwork and site demolition of paving and concrete has begun.Duct work and electrical work has begun.
June 2009
Bryan Station Middle – RenovationKitchen Demolition Cafeteria Asbestos Abatement
June 2009
Rear Entry Wall Demo Portable Classrooms
Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
Contract Sum: $11,182,000
Change Orders to Date: $0
Current Phase: 1, 1a, 1b (On Schedule)
June 2009
Leestown Middle – RenovationRendering of Final Façade
June 2009
Leestown Middle – RenovationWork Completed in Last 30 Days:D.W. Wilburn mobilized on-site.Phase 1demolition efforts commenced. Asbestos abatement started.
Current Work Effort (June):Interior and exterior demolition in Phases 1, 1a & 1b will continue.Structural shoring to be erected.Foundations for the new Kitchen will be poured.Electrical and Plumbing rough-ins to begin.Interior and load bearing masonry to start.
June 2009
Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Set to bid July 6
Substantial Completion Date: July, 2010
Contract Sum: TBD
Change Orders to Date: $0
Current Phase: Construction Documents
June 2009
Lafayette High Stadium – Replacement
Existing Campus
June 2009
Lafayette High Stadium – Replacement
Existing Football Stadium
June 2009
Lafayette High Stadium – Replacement
New Football Stadium
June 2009
Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: James R. Leake & Sons, Inc.
Substantial Completion Date: August, 2009
Contract Sum: $2,782,000
Change Orders to Date: $0
Current Phase: Construction
June 2009
Central Bus Garage – Adaptive ReuseFaçade
June 2009
Central Bus Garage – Adaptive ReuseProposed Floor Plan
June 2009
Central Bus Garage – Adaptive ReuseWork Completed in Last 30 Days:All concrete has been sawn and approximately 85% has been removed.All out buildings scheduled to be removed have been removed.Interior doors/windows have been removed.Electric demo 70% complete.HVAC demo complete.Specialty equipment overhead work complete.Mason has completed wall construction.90% of overhead electric complete.70% of exterior underground piping complete.100% of primary is complete.Grading is proceeding on new parking lot.
June 2009
Central Bus Garage – Adaptive ReuseCurrent Work Effort (June):Interior concrete to be demolished.Equipment pits to be dug.Footing for addition to be completed.Parking lot pole bases/bollards to be installed.Concrete patching to be completed.Storm lines to be installed.
June 2009
Central Bus Garage – Adaptive Reuse Interior Pit at Paint Booth Exterior Excavation – Sanitary Line
June 2009
Exterior Slab Replacement – Parking Area
Tonight’s Agenda ItemsProject Agenda Item
Henry Clay High – Softball Field
Approval of Construction Documents & Advertisement for Bids Total Estimated Cost: $798,786
Agriscience Center Approval BG-1 Project Application Total Estimated Cost: $7,225,724
Clays Mill Elementary Approval BG-1 Project Application Total Estimated Cost: $13,393,104
Yates Elementary Approval BG-1 Project Application Total Estimated Cost: $12,029,153
Tates Creek Middle Approval BG-1 Project Application Total Estimated Cost: $20,242,042
Cassidy Elementary Approval of Change Order #1 Total Cost: $3,152.42
Russell Cave Elementary Approval of Change Order #1 Total Cost: $0
Miles Point Way (Bus Garage)
Approval of Change Order #1 Total Cost: $4,346.17
June 2009
Tonight’s Agenda Items - continuedProject Agenda Item
Veterans Park Elementary – Roof Replacement
Approval of Bid, Proposed Contract and Revision to BG-1 Project Application Intech Construction: $948,990 Total Project Cost: $1,089,079
June 2009