Update on FCPS Construction/Renovation Projects. June 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date:$0 - PowerPoint PPT Presentation

Citation preview

Page 1: Update on FCPS  Construction/Renovation Projects

Update on FCPS Construction/Renovation Projects

June 2009

June 2009

Page 2: Update on FCPS  Construction/Renovation Projects

Cassidy Elementary – Renovation

Architect: Tate.Hill.Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010 Contract Sum: $9,061,000

Change Orders to Date: $0

Current Phase: 1 (On Schedule)

Estimated Completion: 14%

June 2009

Page 3: Update on FCPS  Construction/Renovation Projects

Cassidy Elementary – RenovationRendering of Final Façade

June 2009

Page 4: Update on FCPS  Construction/Renovation Projects

Cassidy Elementary – RenovationWork Completed in Last 30 Days:Primary electric conduit at new Cassidy parking lot.Foundations for 2-Story Admin/Classroom and Music Rm./Mech. Rm. Additions.Masonry mockup complete and block work begun on additions.Under slab plumbing and electrical rough-ins installed and inspected in 2-Story Admin/Classroom Addition.Under slab plumbing and electrical rough-ins begun in Music Rm./Mech. Rm. Addition.

Current Work Effort (June):Primary electric conduits to new transformer pad location.Site storm and sanitary sewer work will begin at front of building.Gas, water and fire protection utilities will begin into building.All Phase 1 foundation and ground floor slab concrete will be complete.Block masonry bearing wall installation to continue.

June 2009

Page 5: Update on FCPS  Construction/Renovation Projects

Cassidy Elementary – Renovation Current Work Effort (June - continued): Steel columns and beams in front 2-Story Addition to be complete. Underground primary plumbing rough-ins complete. Secondary

rough-ins to continue. Underground electrical work to be complete. Secondary rough-ins

to continue.

June 2009

Page 6: Update on FCPS  Construction/Renovation Projects

Cassidy Elementary – RenovationNew 2-Story Admin Addition Masonry Mockup

June 2009

Interior Corridor Barrier

Music Room Addition

Page 7: Update on FCPS  Construction/Renovation Projects

Russell Cave Elementary – Renovation

Architect: Pearson & Peters Architects

General Contractor: Congleton-Hacker

Construction

Substantial Completion Date: August, 2010

Contract Sum: $5,001,150

Change Orders to Date: $0

Current Phase: 1 (On Schedule)

Estimated Completion: 6%

June 2009

Page 8: Update on FCPS  Construction/Renovation Projects

Russell Cave Elementary – RenovationRendering of Final Façade

June 2009

Page 9: Update on FCPS  Construction/Renovation Projects

Russell Cave Elementary – RenovationWork Completed in Last 30 Days:Footing and foundation walls continue: 40 feet of footings poured and 38 feet of foundation wall have been pouredInterior wall footings: 200 feet have been poured.Footings at new mechanical enclosures have been poured. Pads for mech units at kitchen and new transformer and generator have been poured.

Current Work Effort (June):Additional work on footings and foundation at the new addition will continue. New floor slab will be poured in two weeks, weather permitting.Installation of the new leach fields for the septic system will begin installation in the front lawn of the building.Kitchen/Cafeteria demolition and renovation will begin.Renovation of (4) classrooms on the south side will begin.Masonry restoration on the existing building will begin the week of June 8th.

June 2009

Page 10: Update on FCPS  Construction/Renovation Projects

Russell Cave Elementary – RenovationFoundation Work 6.2.09 Foundation Work 6.2.09

June 2009

Foundation Work 6.2.09

Foundation Work 6.2.09

Page 11: Update on FCPS  Construction/Renovation Projects

Arlington Elementary – Renovation

Architect: RossTarrant Architects

General Contractor: W/S Construction

Substantial Completion Date: August, 2010

Contract Sum: $9,920,194

Change Orders: $36,900 (#1--Demo)

Current Phase: 1 (On Schedule)

Estimated Completion: Demo – 100%

June 2009

Page 12: Update on FCPS  Construction/Renovation Projects

Arlington Elementary – RenovationRendering of Final Façade

June 2009

Page 13: Update on FCPS  Construction/Renovation Projects

Arlington Elementary – RenovationWork Completed in Last 30 Days:WS-Construction has mobilized. Site preparation has begun, including erosion control adding engineered fill, and preliminary grading . Structural shoring of existing walls has also begun.

Current Work Effort (June):Selective demolition, additional site work and the laying out of the new building footprint.

June 2009

Page 14: Update on FCPS  Construction/Renovation Projects

Arlington Elementary – RenovationWS Construction Trailer Site Prep / Erosion Control

June 2009

Preliminary Grading

Page 15: Update on FCPS  Construction/Renovation Projects

Bryan Station Middle – Renovation

Architect: Clotfelter-Samokar Architects

General Contractor: Preston Construction Group

Substantial Completion Date: August, 2010

Contract Sum: $10,769,400

Change Orders to Date: $0

Current Phase: 1A (On Schedule)

Estimated Completion: 7%

June 2009

Page 16: Update on FCPS  Construction/Renovation Projects

Bryan Station Middle – RenovationRendering of Final Façade

June 2009

Page 17: Update on FCPS  Construction/Renovation Projects

Bryan Station Middle – RenovationWork Completed in Last 30 Days:General Contractor and sub-contractors are on site beginning demolition and preparing areas for new work. Phase 1A has begun.Barricade fencing, storage facilities and stored materials now on site.Owner-provided staff is on-site moving large amounts of furniture and equipment out of areas to be renovated.Owner-installed portable classroom units appear to be nearly complete. Electrical connections underway.Owner-provided asbestos abatement being performed in cafeteria. Nearly complete.

Current Work Effort (June):Sanitary sewer extensions also underway.Roof being demolished and new roofing installed throughout the month of June.Floor demolition complete in kitchen and cafeteria and under-slab plumbing installation has begun.Earthwork and site demolition of paving and concrete has begun.Duct work and electrical work has begun.

June 2009

Page 18: Update on FCPS  Construction/Renovation Projects

Bryan Station Middle – RenovationKitchen Demolition Cafeteria Asbestos Abatement

June 2009

Rear Entry Wall Demo Portable Classrooms

Page 19: Update on FCPS  Construction/Renovation Projects

Leestown Middle – Renovation

Architect: Lucas/Schwering Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010

Contract Sum: $11,182,000

Change Orders to Date: $0

Current Phase: 1, 1a, 1b (On Schedule)

June 2009

Page 20: Update on FCPS  Construction/Renovation Projects

Leestown Middle – RenovationRendering of Final Façade

June 2009

Page 21: Update on FCPS  Construction/Renovation Projects

Leestown Middle – RenovationWork Completed in Last 30 Days:D.W. Wilburn mobilized on-site.Phase 1demolition efforts commenced. Asbestos abatement started.

Current Work Effort (June):Interior and exterior demolition in Phases 1, 1a & 1b will continue.Structural shoring to be erected.Foundations for the new Kitchen will be poured.Electrical and Plumbing rough-ins to begin.Interior and load bearing masonry to start.

June 2009

Page 22: Update on FCPS  Construction/Renovation Projects

Lafayette High Stadium – Replacement

Architect: Strand & Associates

General Contractor: Set to bid July 6

Substantial Completion Date: July, 2010

Contract Sum: TBD

Change Orders to Date: $0

Current Phase: Construction Documents

June 2009

Page 23: Update on FCPS  Construction/Renovation Projects

Lafayette High Stadium – Replacement

Existing Campus

June 2009

Page 24: Update on FCPS  Construction/Renovation Projects

Lafayette High Stadium – Replacement

Existing Football Stadium

June 2009

Page 25: Update on FCPS  Construction/Renovation Projects

Lafayette High Stadium – Replacement

New Football Stadium

June 2009

Page 26: Update on FCPS  Construction/Renovation Projects

Central Bus Garage – Adaptive Reuse

Architect: Lucas/Schwering Architects

General Contractor: James R. Leake & Sons, Inc.

Substantial Completion Date: August, 2009

Contract Sum: $2,782,000

Change Orders to Date: $0

Current Phase: Construction

June 2009

Page 27: Update on FCPS  Construction/Renovation Projects

Central Bus Garage – Adaptive ReuseFaçade

June 2009

Page 28: Update on FCPS  Construction/Renovation Projects

Central Bus Garage – Adaptive ReuseProposed Floor Plan

June 2009

Page 29: Update on FCPS  Construction/Renovation Projects

Central Bus Garage – Adaptive ReuseWork Completed in Last 30 Days:All concrete has been sawn and approximately 85% has been removed.All out buildings scheduled to be removed have been removed.Interior doors/windows have been removed.Electric demo 70% complete.HVAC demo complete.Specialty equipment overhead work complete.Mason has completed wall construction.90% of overhead electric complete.70% of exterior underground piping complete.100% of primary is complete.Grading is proceeding on new parking lot.

June 2009

Page 30: Update on FCPS  Construction/Renovation Projects

Central Bus Garage – Adaptive ReuseCurrent Work Effort (June):Interior concrete to be demolished.Equipment pits to be dug.Footing for addition to be completed.Parking lot pole bases/bollards to be installed.Concrete patching to be completed.Storm lines to be installed.

June 2009

Page 31: Update on FCPS  Construction/Renovation Projects

Central Bus Garage – Adaptive Reuse Interior Pit at Paint Booth Exterior Excavation – Sanitary Line

June 2009

Exterior Slab Replacement – Parking Area

Page 32: Update on FCPS  Construction/Renovation Projects

Tonight’s Agenda ItemsProject Agenda Item

Henry Clay High – Softball Field

Approval of Construction Documents & Advertisement for Bids Total Estimated Cost: $798,786

Agriscience Center Approval BG-1 Project Application Total Estimated Cost: $7,225,724

Clays Mill Elementary Approval BG-1 Project Application Total Estimated Cost: $13,393,104

Yates Elementary Approval BG-1 Project Application Total Estimated Cost: $12,029,153

Tates Creek Middle Approval BG-1 Project Application Total Estimated Cost: $20,242,042

Cassidy Elementary Approval of Change Order #1 Total Cost: $3,152.42

Russell Cave Elementary Approval of Change Order #1 Total Cost: $0

Miles Point Way (Bus Garage)

Approval of Change Order #1 Total Cost: $4,346.17

June 2009

Page 33: Update on FCPS  Construction/Renovation Projects

Tonight’s Agenda Items - continuedProject Agenda Item

Veterans Park Elementary – Roof Replacement

Approval of Bid, Proposed Contract and Revision to BG-1 Project Application Intech Construction: $948,990 Total Project Cost: $1,089,079

June 2009