Update on FCPS
Construction/Renovation Projects
December 2015
Squires Elementary -- Renovation
Architect: JRA Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $12,166,000
Total Project Cost: $15,207,000
Change Orders to Date (8): $52,818
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 70.0%
Revised Completion Date per GC: No Change
December 2015
Squires Elementary -- Renovation
Rendering of Final Façade
December 2015
Squires Elementary -- Renovation
Work Completed to Date:
Area “B” plumbing rough-in and fixtures are complete (Phase 2).
Area “B” ceramic tile is complete (Phase 2).
Area “B” casework is complete (Phase 2).
Area “B” interior masonry partition walls are complete (Phase 2A).
Area “B” roof joists and decking are complete (Phase 2A).
Current Work Effort (December):
Area “B” terrazzo to complete (Phase 2).
Area “B” doors and hardware to complete (Phase 2).
Area “B” exterior spray insulation to complete (Phase 2A).
Area “B” brick to continue (Phase 2A).
Area “D” selective demolition to begin (Phase 3).
December 2015
Squires Elementary -- Renovation
December 2015
Completed Restroom VCT Flooring
Completed Casework Terrazzo Base
Squires Elementary -- Renovation
December 2015
Supply Ducts Exterior Doors
Prepping CMU Walls Exterior Spray Insulation
New Elementary at Passage Mound
Architect: Moody-Nolan Architects
General Contractor: Griggs Enterprises, Inc.
GC Contract Sum: $14,980,350
Total Project Cost: $19,478,511
Change Orders to Date (6): $143,211
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 50.93%
Revised Completion Date per GC: No Change
December 2015
New Elementary at Passage Mound
Rendering of Final Façade
December 2015
New Elementary at Passage Mound
Work Completed to Date:
Install metal studs & drywall in Administration Area.
Start Media Center metal Studs.
Install ceiling grid - Area A Classrooms.
Start metal roof panels - Area A.
Start windows - Area A.
Current Work Effort (December):
Continue with above-ceiling MEP installation.
Continue with window installation Area A and Area B.
Complete brick on the Media Center.
Permanent power on to the building.
Start ceiling grid in Area B - Classrooms.
December 2015
New Elementary at Passage Mound
December 2015
Site – Towards Area B Entrance
Typical Classroom Media Center - Exterior
New Elementary at Passage Mound
December 2015
Media Center -- Interior Kitchen
Street View Last Corridor Cap
New Elementary at Georgetown Road
Architect: Clotfelter-Samokar Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $14,874,000
Total Project Cost: $19,848,291
Change Orders to Date (6): $48,441
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 49.0%
Revised Completion Date per GC: No Change
December 2015
New Elementary at Georgetown Road
Rendering of Final Façade
December 2015
New Elementary at Georgetown Road
Work Completed to Date:
Fine grading behind installed curb & gutter continues.
Installation of DGA base for parking lots and drive lanes on-going.
Begin exterior window installation starting in Area C.
CMU in Areas A & D are around 95% complete. Brick veneer is on-going.
Mechanical, Plumbing & Electrical are on-going
Tectum Roof deck installation complete. Area A & D roof insulation on-going.
Current Work Effort (December):
Site contractor to continue grading parking lot and begin binder installation.
Exterior window installation on-going.
Structural steel framing and roof decking will complete.
Foam cavity insulation to begin in Area D & complete in Area A.
CMU and brick veneer installation will continue.
Installation of above deck roof insulation and dry-in will continue.
December 2015
New Elementary at Georgetown Road
December 2015
Entrance Front
Gym Roof Base Sheet Mezzanine Sprinkler Piping
New Elementary at Georgetown Road
December 2015
Mezzanine Raceway Roof Deck Installation
South End South Wall Gym
New High at Winchester Road
Architect: Tate Hill Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $62,044,000
Total Project Cost: $81,511,696
Change Orders to Date (2): ($16,111)
Scheduled Contract Completion Date: July 2017
% of Contract Completed: 21.13%
Revised Completion Date per GC: No Change
December 2015
New High at Winchester Road
Rendering of Final Façade
December 2015
New High at Winchester Road
Work Completed to Date:
Fill at the Athletic Fields has continued. Storm drain installation has continued in
parking lot. Geothermal wells have continued.
Field house foundations have begun. Foundations are 99% complete for academic
building. ICF walls are to roof bearing height in Area C. ICF walls are to second
floor bearing height in Area B. Floor slabs have begun in Area D.
Masonry is up to roof bearing height in the Main Gym. Masonry is up to roof
bearing height in Area C. Masonry is up to second floor bearing height in Area B
and Area E3. Area E2 masonry has begun. Stem wall CMU has been completed in
Areas E1 and D and has begun in Area A.
Steel joist and metal deck work has begun on the second floor of Area B and at
the roof of Area C.
Mechanical rough-ins have continued above ceiling in Area C on the first floor.
Underground plumbing in Areas A, D, and E1 has continued and is near
completion. Underslab electrical rough-ins have been completed in Area E1 and
have begun in Area D. Electric primaries have been roughed-in at the mechanical
room. December 2015
New High at Winchester Road
Current Work Effort (December):
Fill at athletic fields will be completed. Storm drains will continue at the parking
lot. Geothermal drilling and tie-ins will continue.
Foundations will be completed at the field house. Foundations will begin at the
grandstand bleachers and restrooms at the bleachers. Floor slabs will be
completed in Area D. Floor slabs will be placed on the second floor in Areas E3,
E4, and B. Floor slabs will begin in Area A.
Masonry will begin in Area B on the second floor and on the first floor in Area E1
and D. Foundation CMU will be completed in Area A. Second floor masonry will
begin in Areas E3 and E4. All CMU masonry will be completed in Area C.
Roof Joist and metal deck will continue in Area C. Second floor joist/deck will be
completed in Area E3 and E4 and will begin in the Main Gym.
Above ceiling MEP work on the first floor of Area C will continue and will begin
in Area E4. Underground plumbing will be complete in all areas of the academic
building. Underslab electrical will continue in Areas A, D, & E1. Underground
plumbing will begin in the Field House. Secondary electrical rough-ins will begin
in the Field House. December 2015
New High at Winchester Road
December 2015
Area A Progress Area D Progress
Area E1 Progress Area E4 and C
New High at Winchester Road
December 2015
Area C Ductwork Stored Ductwork
Gym CMU Gym Upper Bleachers