UPDATE of RFCC MOUDLE Derun Li, Steve Gourlay Lawrence Berkeley National Laboratory MICE MICO Meeting December 21, 2011

UPDATE of RFCC MOUDLE

  • Upload
    ogden

  • View
    61

  • Download
    0

Embed Size (px)

DESCRIPTION

UPDATE of RFCC MOUDLE. Derun Li, Steve Gourlay Lawrence Berkeley National Laboratory MICE MICO Meeting December 21, 2011. CC Magnets. 1 st CC magnet Cold mass at LBNL First physical (CMM) and electrical measurements complete; - PowerPoint PPT Presentation

Citation preview

Page 1: UPDATE of RFCC MOUDLE

UPDATE of RFCC MOUDLE

Derun Li, Steve GourlayLawrence Berkeley National Laboratory

MICE MICO MeetingDecember 21, 2011

Page 2: UPDATE of RFCC MOUDLE

CC Magnets

• 1st CC magnet– Cold mass at LBNL

• First physical (CMM) and electrical measurements complete;• Design of the cooling circuit finalized for Fermilab testing;• Vacuum potting prep underway;• Thermal stress analysis during cool-down complete;• PID (Piping and Instrumentation Diagram) in progress.

– Quench protection• Contract signed with MIT;• Preliminary analysis of QP indicated 4 sub-divisions may be adequate

(original design has 8);• Design of the stabilization of HTS and SC current and QP leads

underway at MIT.

Page 3: UPDATE of RFCC MOUDLE

Cold Mass at LBNLCMM measurements completeLH pipe bending completeReady for machining pipe groove and cold mass support brackets

1st Electrical measurementcomplete: measured resistance between in-out and QP leads consistent with the design

Page 4: UPDATE of RFCC MOUDLE

Update of LH Cooling Pipe Design for the 1st Cold Mass Testing in Progress

Page 5: UPDATE of RFCC MOUDLE

CC Magnets• 1st CC magnet

– Testing preparation at Fermilab• FSU cryostat;• Testing location identified;• …

– SC wires (261 km) ready to be ordered – Review of the cryostat drawings nearly complete;– Modification/updating of the drawings in progress at LBNL

• Cryostat fabrication readiness review after next MICE Collaboration meeting (Feb. 8-11, 2012)

• Winding procedure review in China (Mar. - Apr. 2012)• Winding of the 2nd coil could start June 2012 or earlier if we

decide to mix two different SC wires

Page 6: UPDATE of RFCC MOUDLE

MICE RF Cavities• Electro-polishing (EP) set up at LBNL ready;• Waiting for ES&H approval;• Expect to start early 2012.

Design

Page 7: UPDATE of RFCC MOUDLE

MICE RF Cavities• RF coupler design updated;• Additional welding of cavity support struts

complete;• Single cavity vessel fabrication complete and expect

to arrive Fermilab this month;• Fabrication of six tuner arms in progress at

Fermilab;• Discussions on potential assistance from LBNL on