Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Unlocking the Value of a
World Class Resource Base
February 2018
BMO Global Metals & Mining Conference
Denis Alexandrov, Chief Executive Officer
AIM: HGM
Disclaimer
Certain statements within this presentation constitute forward looking statements. Such forward looking statements involve risks and
other factors which may cause the actual results, achievements or performance of the Group to be materially different from any future
results, achievements or performance expressed or implied by such forward looking statements. Such risks and other factors include,
but are not limited to, general economic and business conditions, changes in government regulations, currency fluctuations (including
the US$/RUR rate), the gold price, the Group’s ability to recover its reserves or develop new reserves, competition, changes in
development plans and other risks.
There can be no assurance that the results and events contemplated by the forward looking statements contained in this presentation
will, in fact, occur. These forward-looking statements are correct or represent honestly held views only as at the date of delivery of this
presentation.
The Company will not undertake any obligation to release publicly any revisions to these forward looking statements to reflect events,
circumstances and unanticipated events occurring after the date of this presentation except as required by law or by regulatory
authority.
***
Total cash costs include mine site operating costs such as mining, processing, administration, royalties and production taxes, but are
exclusive of depreciation, depletion and amortisation, capital and exploration costs. Total cash costs are then divided by ounces sold
to arrive at the total cash costs of sales. This data provides additional information and is a non-GAAP measure.
In line with guidance issued by the World Gold Council, the formula used to define all-in sustaining cash costs measure commences
with total cash costs per ounce sold and then adds sustaining capital expenditures, corporate general and administrative costs, mine
site exploration and evaluation costs and environmental rehabilitation costs. This data seeks to represent the total costs of producing
gold from current operations, and therefore it does not include capital expenditures attributable to projects or mine expansions,
exploration and evaluation costs attributable to growth projects, income tax payments, interest costs or dividend payments.
2
3
Highland Gold Highlights
Russia
Kekura
Klen
Mnogovershinnoye (MNV)
Belaya Gora
Blagodatnoye
Unkurtash
Novoshirokinskoye (Novo)
Kazakhstan Taseevskoye
Sredny Golgotay
ZIF-1 Tailings
- JORC-compliant measured, indicated & inferred Mineral
Resources and proven & probable Ore Reserves of gold
and gold equivalent as of 31 December 2017.
- TCC and AISC based on H1 2017 interim accounts
Annual Production 2017: 272 koz
2016: 261 koz
Total Cash Costs US$ 509/oz
All-In Sustaining Costs US$ 674/oz
Mineral Resources (Au + Au eq) 17.2 Moz
3.0 g/t
Ore Reserves (Au + Au eq) 5.1 Moz
3.3 g/t
EBITDA (FY 2016) US$ 162 M
Khabarovsk
Cluster
Baikal
Cluster
Chukotka
Cluster
Kyrgyzstan
Baley Hub
Operating mines
Development projects
Pre-development
4
Our Strategy: Unlocking Value
Maximise
the upside potential
of operating assets
Develop
assets at the
DFS/PFS stage
into production
De-risk and
convert additional
resources
into reserves
Focus development on
regions of presence
Maintain commitment to operating safety
and protecting the environment
Kekura
Klen
Taseevskoye
Unkurtash
MNV
Belaya Gora
Novo
DFS complete. Begin construction
New PFS + additional exploration
De-water pit + confirm reserves
Find partner + move to PFS stage
New reserves
Plant upgrade +
Increase throughput
Blagodatnoye
Share Price Performance
Shareholder Structure
Corporate Overview
5
Listed on London AIM
Incorporated in Jersey in 2002
15-year track record as a public company
Shareholders include a broad range of high-quality
UK, European and N. American institutional investors
Committed to Best Practice in Corporate
Governance
Led by an experienced Board of Directors and
management team
Seven directors – executive chairman, one executive
director, and five non-executive (three independent)
Shares 325,222,098
Market Cap* US$ 656M
Enterprise Value* US$ 855M
Net Debt** US$ 199M
Net Debt/EBITDA (LTM)** 1.3x
2016 Earnings/Share US$ 0.145
* On 21 Feb 2017 ** Estimated as of 31 Dec 2017
20%
10%
53%
17%
Prosperity
Capital
Management
Board &
Management
Institutions
& Retail
Core
Shareholder
Group
63%
Free
Float
HGM Gold Price FTSE All Share Mining
HGM
50
100
150
Feb’17 May’17 Jul’17 Oct’17 Feb’18
Commitment to Dividends
6
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
0
2
4
6
8
10
12
2011 2012 2013 2014 2015 2016 H1 2017
GB
X
Dividend per share (pence) Yield (%) Total Payout (US$)
$25.7M $40.3M $26.7M $23.2M $21.9M $41.8M
- Yield based on average share price for the period
- Yield calculated for H1 2017 on annualised basis
$21M
35 36 36 45 47 50 50
63
Low Cost, High Margin Producer
7
(%)
All-In Sustaining Costs Total Cash Costs
EBIDTA Margin
(US$/oz) (US$/oz)
International Majors
Russian Peers
Figures based on company filings and street consensus estimates for FY 2017 Highland Gold figures based on H1 2017 interim results
1054 954
875 860 824 750
674 621
792
669 660 663 632 526 509
379
$291
$205 $198
$134 $129 $106
$82 $70 $67 $50 $46 $44
$29
8
Attractively Valued with Upside Remaining
10.8x
7.6x 7.4x 7.0x6.1x 5.8x 5.5x 5.5x 5.2x
4.3x 4.2x3.4x 3.3x
Figures based on company filings, street consensus estimates and share price as of 20 Feb 2018 Source: BMO
EV / 2018E EBITDA
EV / Resources
Ore Reserves (proven and probable) increased by
56% year-on-year
Average grade lowered to 3.3 g/t, reflecting lower cut-
off grades and increased ore tonnage at Novo and
Belaya Gora, plus the addition of Blagodatnoye.
Reserves added from:
– Extensive MNV near-mine exploration
– Conversion of Blagodatnoye resources to
reserves following 2016-2017 drilling programme
– New exploration and lower cut-off grade at
Belaya Gora
– Re-estimation of Novo reserves with substantial
increase in ore tonnage
– Updated reserve estimate for Kekura as part of
DFS
9
Converting Resources to Reserves
31 December 2016
Ore
(tonnes)
Grade
(g/t)
Gold
oz
Proven 4 041 747 5.5 710 576
Probable 8 727 888 9.1 2 549 548
Proven + Probable 12 769 635 8.0 3 260 124
31 December 2017
Ore
(tonnes)
Grade
(g/t)
Gold
oz
Proven 15 049 783 3.5 1 697 888
Probable 33 724 397 3.1 3 402 184
Proven + Probable 48 774 180 3.3 5 100 072
Highland Gold Ore Reserves
JORC-compliant Resources and Reserves of gold and
gold equivalent as of 31 Dec 2016 and 31 Dec. 2017
3.26
5.10
31 Dec 2016 31 Dec 2017
(Moz Au)
MNV Snapshot
94.6 90.4 96.2
91.5
102.5
91.4
Production(koz)
Recovery(%)
Grade(g/t)
TCC(US$)
Khabarovsk Cluster
2.29 2.36
691
607 595
2.55
2015 2016 2017
Gold production increased by 7% in 2017
Updated MNV JORC reserve statement completed and published
in May, with Life of Mine extended to 2022 (was 2018)
Ongoing near-mine exploration programme on existing MNV
licences, focusing on areas around previously-mined ore bodies
Historic waste dumps being re-evaluated, adding over 1M tonnes
of ore with grades of ~1.1 g/t Au since 2016
Two new licences received in 2017 for greenfield sites directly
adjacent to MNV – Zamanchivaya (4.2 sq km) and
Kulibinskaya (38 sq km) – with initial exploration work underway
Exploration budget of US$ 3-5 M per year
Updated JORC reserve estimate expected in Q3 2018
10
Mnogovershinnoye (MNV)
2017 Highlights
Significant Exploration Potential
TCC as of H1 2017. JORC-compliant Resources and Reserves as of 31 Dec. 2017
Opened 1991 (HGM 1999)
Life of Mine 2022
Mine Type Open pit & underground
Processing Gravity + cyanide leaching
Processing Capacity 1.4 Mtpa
Au Resources (M,I&I) 578 koz @ 7.7 g/t
Au Reserves (P&P) 453 koz @ 5.5 g/t
Au Production (2017) 103 koz
Avg Head Grade 2.55 g/t
Total Cash Costs* US$ 595/oz
61.3
75.4
45.9
71.4
43.2
72.5
Production(koz)
Recovery(%)
Grade(g/t)
TCC(US$)
11
Belaya Gora
1.21 1.64
1.11
465
678
880
Opened 2014
Life of Mine* 2032
Mine Type Open pit
Processing Gravity
Processing Capacity 1.6 Mtpa
Au Resources (M,I&I)* 1.38 Moz@ 1.4 g/t
Au Reserves (P&P)* 932 koz @ 1.4 g/t
Au Production (2017) 43 koz
Avg Head Grade 1.11 g/t
Total Cash Costs US$ 880/oz
Belaya Gora Snapshot Khabarovsk Cluster
2017 operations focussed on processing low-grade ore stockpiles
in advance of expected new mining plan and processing plant
upgrades
Lower mined ore grade during the year due to the re-classification
of some waste stripping following a decision by regulators to
reduce the mine's cut-off grade from 0.7 g/t to 0.3 g/t
A pre-feasibility study was completed in early 2018, including:
– Upgrades to the processing plant, adding a carbon-in-pulp
(CIP) circuit to improve recoveries from 72% to a range of 86-
91% for Belaya Gora ore and 90% for Blagodatnoye ore
– New mining plans for Belaya Gora and Blagodatnoye (both
open pit), envisioning the processing of Blagodatnoye ore at
the Belaya Gora mill and a combined life of mine extending
until the year 2032
– Estimated capex of US$ 15M for the plant upgrade and
US$ 21M to move mining activity from Belaya Gora to
Blagodatnoye in 2023 (crushing circuit, road construction and
upgrades, and equipment replacement)
– Updated resource estimates incorporating results from 2016-
2017 drilling on the Belaya Gora northeast flank and at
Blagodatnoye, tripling gold reserves for the operation
– Average annual production of 55 koz over LoM at an average
total cash cost of US$ 802/oz and all-in sustaining costs of
US$ 848/oz
2017 Highlights
Plant Upgrade + Blagodatnoye
2015 2016 2017
TCC as of H1 2017. JORC-compliant Resources and Reserves as of 31 Dec. 2017
* with Blagodatnoye
106
86.0
118
85.9
127
85.0
Production(koz)
Recovery(%)
Grade(g/t)
TCC(US$)
12
Novoshirokinskoye (Novo)
5.58 5.62
305 302 254
5.61
* Adjusted for processing costs as if producing dore.
Opened 2009
Life of Mine 2032
Mine Type Polymetallic, underground
Processing Gravity-flotation circuit
Processing Capacity 0.8 Mtpa
Au eq Resources (M,I&I) 2.87 Moz @ 3.9 g/t
Au eq Reserves (P&P) 1.71 Moz @ 3.1 g/t
Au Eq Production (2017) 127k oz
Avg Head Grade 5.61 g/t
Total Cash Costs US$ 305/oz (US$ 450/oz*)
Novo Snapshot Baikal Cluster
Novo continues to be our lowest cost, highest margin production
asset
Gold equivalent production rose by 7.7% in 2017
Updated JORC reserve audit completed in November 2017 with a
lower cut-off grade and 430% increase in ore tonnage.
– Ore reserves rose to 1.9 Moz Au Eq. (as of 31 Dec 2016) from
the previously-estimated 1.1 Moz, at an average grade of
3.3 g/t versus 9.8 g/t reported earlier and the current 5.6 g/t
average grade at the mill
To compensate for expected lower grades, the Company is in the
process of expanding Novo’s mining and milling capacity to
1.3 Mtpa
Stage 1 – upgrades to the mining complex including a skip hoist
overall, ventilation and heating systems – scheduled for
completion by year-end 2018
Stage 2 – processing plant upgrades – currently in the design
phase.
2017 Highlights
1.3 Mtpa Expansion
TCC as of H1 2017. JORC-compliant Resources and Reserves as of 31 Dec. 2017
2015 2016 2017
2017 Highlights
Kekura
Est. Start Date 2021
LoM 16 years
Mine Type Open pit & underground
Processing Gravity + cyanide leaching
Processing Capacity 0.8 Mtpa
Au Resources (M,I&I) 2.46 Moz @ 8.1 g/t
Au Reserves (P&P) 2.00 Moz @ 7.0 g/t
Au Production
(est. annual)
172k oz (years 1-8)
46k oz (years 9-16)
Total Cash Costs (est.) US$ 511/oz
Kekura Snapshot Chukotka Cluster
Mayskoye
Kupol
Klen Dvoinoye Kekura
Chukotka
Polymetal
Kinross
Valunisty
Pevek
Anadyr
2017 exploration programme of 11,000 metres of RC-drilling and 4,750 m of core drilling for reserve confirmation, as well 4,350 m of drilling to confirm sterile ground
Government approval granted for the development of a deposit of “federal significance”, a requirement for deposits of this size
Work began on a state-funded power line to connect Kekura to the regional electrical grid
DFS completed in early 2018, envisaging:
– Sequential and combined open-pit and underground operation with an estimated total mine life of 16 years, compared to eight years projected in the PFS
– Processing plant capacity of 800 ktpa with 85% recovery
– Capex of US$ 229 M (pre-commissioning, excl. underground)
– Average annual gold production of 172 koz for the first eight years of operation and 46 koz for the final eight years
– Average total cash costs of US$ 511/oz and all-in sustaining costs of US$ 541/oz
Preliminary construction work is already underway at Kekura, with the bulk of construction due to take place in 2019-2020.
Upside potential in additional targets within licence area
– 12 additional targets in the broader Kekura licence area (nearly 1500 sq km.).
– Exploration drilling in progress on the Granat ore body
Definitive Feasibility Study
Figures based on 2018 Definitive Feasibility Study 13
A scoping study for Unkurtash was completed and published in
March 2017, envisaging:
– Two open pits and an 18-year life of mine
– Processing plant utilizing gravity concentration and gravity
tailings CIL with an annual throughput of 4 million tonnes and
recoveries of over 80%
– Annual production of 133k oz of gold at an average operating
cost of US$ 616/oz
– Total capital expenditure to start production is estimated at
US$ 322 million
Highland Gold is considering partnership opportunities to develop
this promising resource and has had preliminary discussions with
potential partners
14
Unkurtash
Unkurtash
Sarytube
Karatube
Baikonur 0 1000 m
Unkurtash
Kazakhstan
Kyrgyzstan
Kumtor
Bishkek
Bozymchak
Ishtamberdy
KAZ Minerals
Centerra
Full Gold Mining
China
Unkurtash Licence Area
Figures based on March 2017 Scoping Study
LoM 18 years
Mine Type Open pit
Processing Gravity + cyanide leaching
Processing Capacity 4 Mtpa
Resources (M,I&I) 3.70 Moz @ 1.7 g/t
Au Production (est. annual) 133k oz
Avg. Operating Costs (est.) US$ 616/oz
Capex Required US$ 322 M
NPV (10%) US$ 200 M
Unkurtash Snapshot Kyrgyzstan Scoping Study
The Highland Gold Investment Case
Upside Potential in Existing
Operating Assets
Growth Potential in High
Grade Deposits
Development Strategy
Focused on Regional Hubs
Disciplined Capital
Allocation
Commitment to Dividend
15-Year Track Record
as a Public Company
15
Unlocking the Value of
Highland Gold’s
Resource Base
www.highlandgold.com [email protected] +7 495 424-95-21
0 Thank You