24
UNIVERSITY CAMPUS CHILLER PLANTS – ASHRAE GUIDELINE 22 AND STANDARD 184P IN OPERATION Presented by John Vucci Associate Director, HVAC Systems University of Maryland College Park ASHRAE Winter meeting Chicago, Il. January 21, 2018

UNIVERSITY CAMPUS CHILLER PLANTS ASHRAE ... 1...UNIVERSITY CAMPUS CHILLER PLANTS –ASHRAE GUIDELINE 22 AND STANDARD 184P IN OPERATION Presented by John Vucci Associate Director, HVAC

  • Upload
    others

  • View
    18

  • Download
    1

Embed Size (px)

Citation preview

UNIVERSITY CAMPUS CHILLER

PLANTS – ASHRAE GUIDELINE

22 AND STANDARD 184P IN

OPERATIONPresented by John Vucci

Associate Director, HVAC Systems

University of Maryland College Park

ASHRAE Winter meeting Chicago, Il.

January 21, 2018

LEARNING OBJECTIVES

Provide overview of Guideline 22 as is being used for installation & operation monitoring

Chilled Water Plant Efficiency.

Provide understanding of benefit of measuring chiller Plant Performance through a dash board

at a multi use Facility.

Obstacles to over come found when identifying Guideline 22 for design and installation.

Sample Plants utilizing Guideline 22 with potential takeaway benefits & ideas.

Overview of STD 184P.

ASHRAE is a Registered Provider with the American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to ASHRAE records for AIA members. Certificates for completion for non-AIA members are available on request.

This program is registered with the AIA/ASHRAE for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any method or manner of handling, using, distributing or dealing in any material or product. Questions related to specific materials, methods and services will be addressed at the conclusion of this presentation.

TABLE OF CONTENTS

• General information identifying the need

• General Information Guideline 22

• Potential Uses from and Owner Perspective

• Implementation Obstacles

• Methods of control for retrofits

• Equipment inclusion

• Case study sample utilization

• Standard 184P potential uses and Committee Beta test

UNIVERSITY INFORMATION

1305 Acres with > 305 Buildings

$70M F&U Budget

Nominally 30,000 Tons refrigeration comprised of 13

Satellite Central Plants with other Plants (approx. 12,300

Tons) singularly dedicated for stand alone buildings,

most central plants are available year round.

Campus functions range from High end specific research

of 100% Outdoor air labs, clean rooms, BSL-3 , computer

facilities, academic teaching theatres, classrooms

offices, Residence halls and dining facilities.

+/- 39,000 Undergraduates, 9,000 Graduate Students

with 10,000 faculty and staff .

UNIVERSITY INFRASTRUCTURE UTILITY

COST INFORMATION AS OF FY-16

Electric Peak Demand: 43 MW

Electric F&U: $16M / All-in cost $72/MWh

Steam Peak Demand: 248 KLbs./Hr.

Steam Utility Cost: $10M

Water Costs: $8.20/1,000 gal

Sanitary Cost: $11.20/1,000 gal

Annual water & Sewer Cost: $8.2M

Note: Approximately 50% of campus CT makeup water is sub

metered by Public Utility. Agreements with Public Utility credits

73% of makeup water sewer charge and attributes 27% of

makeup water to sanitary sewer blowdown

CHILLER PLANTS

With Multiple Chiller Plants across the campus understanding and control

of energy becomes increasingly important as building inventory

expands.

Utilization of Guideline 22 has become a means for monitoring oversight

to standardize measurement & verification through the Central Control

and Monitoring System (CCMS) or Campus BAS.

GUIDELINE 22 – SCOPE NOTES

The procedures identified are for site-specific. Within the Guideline

they do not discuss the comparison of collected data between

different sites, nor do they recommend that data obtained be

applied in this manner.

Section 2.3 The procedures also do not discuss:

(a) Any Plants except electrically driven Chilled Water Plants

(b) The design and operation of Central Chilled Water Plants,

except for recommending the instrumentation, used to

determine Plant Efficiency, or

(c) The selection, application , or operation of the system

components

POTENTIAL USES FROM AN OWNERS

PERSPECTIVE

BTUH metering and power consumption, integration of plant

automation to achieve best operating performance.

Comparative evaluation of different plants to evaluate various

design criteria, maintenance and performance upgrades.

Advanced troubleshooting tool.

Assessment tool for connected buildings.

POTENTIAL USES FROM AN OWNERS

PERSPECTIVE (CONT’D.)

Assistance to owner staff working through Cx start up process

identifying deficiencies.

Owner clearly identifying design and performance expectation

criteria to the engineer throughout the design, working with

installation intent and requirements.

Owner modifications and additions to chiller plant M&V to utilize

G-22 philosophy include replacement of metering, additional

BAS programing, additional data points, (e.g., KWH power

metering of constant volume pumps and inclusion of total KWH

components).

IMPLEMENTATION OBSTACLES

BAS and/or Engineers interpretation of design intent of utilizing a

summary dashboard for installation.

BAS contractors interpretation of engineers criteria identified in the

specification narrative.

Vague design specifications lead to communication interpretation

errors. Reduced cost interpretations or “value engineering” to meet

the design intent can plague Cx and effective installation to meet the

Owner’s program intent.

METHODS OF CONTROLLING

RETROFITS FOR FUTURE UTILIZATION

Design and retrofit of Automation Upgrades needs to consider:

Owner design direct involvement of control system integration.

Owner project management oversight of BAS contractor interpretation and installation.

Potentially owner installation of flow meters and power meters to provide accuracy and real time measurement.

Where owner is not directly involved the owners contract liaison needs to be intimately familiar with both meter installation requirements as well as BAS integration.

MAJOR EQUIPMENT TO CONSIDER

Chiller Power and BTUH

CHW Pump Power

Plant design consideration to include Primary CHW Pump for variable Flow Primary or both Primary CHW Pump and Secondary CHW Pump.

CW Pump Power

Cooling Tower fan Power and total rejected BTUH

Though not directly related to G-22 principles of G-22 can be considered for Heating water plant operational dash boarding.

SCUB MM 12-1-17

Oakland Hall SCUB 12-1-17

MEASUREMENT & VERIFICATION

What plants are the most efficient?

B425 Prince Frederick Hall

B224 Wing 2 Computer Space

Science SCUB

B416 SCUB 5

B046 Marie Mount SCUB

B224 Wing 4 Computer Space

Science SCUB

0

0.5

1

1.5

2

2.5

B425 Prince

Frederick

Hall SCUB

B224 Wing 2

Computer

Space

Science

SCUB

B416 SCUB 5 B046 Marie

Mount SCUB

B224 Wing 4

Computer

Space

Science

SCUB

2015 KW/Ton

STANDARD 184P The STD-184P is available for purchase

There is to be an accompanying Excel Worksheet to assist in developing the

Uncertainty of field effect on the accuracy of the Field Performance Test.

The Standard does not take the place of the AHRI-550/590 factory certification

Where are there opportunities to utilize a Field Performance Test of a Chiller.

Where the chiller is erected in the field

For field commissioning of chiller Plants to understand the “field installation

impacts”

For baseline measurement of chiller performance prior to and after potential

upgrades occur within an Energy Performance Contract

Baseline testing for owners building a Chiller Plant, measuring the chiller

performance to then re-measure the chiller performance following upgrades or

after length of service operation

STANDARD 184P BETA TEST SEPTEMBER 2016 Prior to publishing the committee wanted to “walk

through” the process to test the viability of the

Standard protocols.

A site was identified that measured Chiller Plant

Performance through the principles of Guideline 22.

The committee brought field testing tools by one of the

manufacturers on the committee.

On the date of the testing field metering was installed

and trended in parallel with the facilities installed

metering.

As the Standard is for an individual chiller a single

chiller (800 Ton) was operated in the Primary variable

flow plant design.

STANDARD 184P BETA TEST SEPTEMBER 2016

To complete the test two days were required, 1 day to discuss protocols as identified in the STD with an owner/Testing Authority/Manufacturer mock meeting. The 2nd full day included set up of instrumentation as well as testing set up to measure the chiller performance at various load points previously established where operation could be maintained without compromise to connected facilities.

The process determined there are benefits and detriments to utilizing certain types of metering and where the metering is installed.

Proved the viability of the uncertainty analysis in the overall impact of the testing protocols.

Ultimately both Guideline 22 and STD-184P provided similar results

QUESTIONS

John Vucci

[email protected]