18
Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

Embed Size (px)

Citation preview

Page 1: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

Universal Access Roadmap and Investment ProspectusInitial Results for the Investment Prospectus

Peter Hoogland, March 2014

Page 2: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

2

PRESENTATION OUTLINE

• What is an Investment Prospectus?

• The Financial Model that underpins the Investment Prospectus

• Interim Output from Chin and Kayin States

Page 3: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

What is an Investment Prospectus?

3

.

.

.

.

It is the basis for raising funds to achieve a reliable financing flow so that the entire electrification rollout can be achieved in a single co-ordinated, least cost program

It gives donors, government and investors a coherent plan that identifies their role and contribution.

It will accelerate the current rate of connections by ensuring full alignment between the least cost plan, its implementation and the funding and financing It will show stakeholders how their

development objectives will be achieved.

Page 4: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

4

Grid Rollout Plan for Kayin and Chin States

Kayin Chin

Total new connections to 2030 300,495 101,800

Grid percentage 99.9% 97%

Mini-grid percentage (Diesel based) 0.02% 2%

Individual system (Solar Home Systems) 0.01% 1%

Average cost of connection/household 815,100 kyat 1, 211,000 kyat

Initial assumption of equal number of connections in each year…

2015 2016 2017 2018 2019 Total (in first 5 yrs)

Kayin 20,033 20,033 20,033 20,033 20,033 100,165Chin 6,787 6,787 6,787 6,787 6,787 33,935

Source: interim results of geospatial analysis by Earth Institute

Page 5: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

5

Financial Model

Overview of the financial model…

Existing Infrastructure (Cash Costs) Generation Transmission Distribution

New Infrastructure (full economic costs)

Generation &Transmission

Distribution Rollout (All costs) Capital cost/connection Operating cost/connection Return on capital (financing cost)

—interest rate Return of capital (depreciation)

—useful life Total Annual Costs Generation Transmission Distribution

Costs are for total sector

Forecasts and Assumptions Number of connections pa Average consumption Growth rates in connections and

consumption

Additional Distribution Infrastructure (full economic costs)

33kV lines

= Cost/kWh

Page 6: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

6

Transmission:

Distribution:

Generation:

Costs are a blend of cash costs with full economic costs…

Existing Infrastructure

Cash costs onlyReplicates current practice

New Build Infrastructure

Full economic costs including financing and amortisation of loans

Ensures sector is financially sustainable over time

+

Page 7: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

7

Initial Investment Needs for Rollout in Chin and Kayin

Initial Investment needs for the distribution rollout for Kayin and Chin for the first 5 years is:

Kayin Kyat Millions

Chin Kyat Millions

LV lines initial cost 9,866 3,343

Service and meter initial cost 19,733 6,685

Transformer initial cost 22,492 10,036

MV lines initial cost 18,304 5,231

Mini Grid and Individual HH systems 346 4,020

Less: Connection Charges (50,000 kyat/connection)

5,008 1,697

Total 65,763 27,618

Page 8: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

8

Total Sector-wide Unit Costs

2015Kyat/kWh

2016Kyat/kWh

2017Kyat/kWh

2018Kyat/kWh

2019Kyat/kWh

Distribution Rollout Financial Costs34 33 33 33 32

Distribution O&M costs 4 4 4 4 4

LRMC of additional 33 KV distribution 10 10 10 10 10

LRMC of additional transmission 15 15 15 15 15

LRMC of blended generation 45 46 48 49 50Total Sector wide Unit Costs 108 108 109 110 111

Assuming all distribution rollout investment needs are financed by concessional loans at 3.5% interest and 30 year term

Page 9: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

9

These annual costs must be funded by matching annual revenue Revenue comes from:

­ Customers through tariffs­ Customers through connection charges

Any difference—the Funding Gap—must be met by subsidies or grants

To estimate revenue in our Financial Model we have developed two tariff scenarios:­ The Government Proposed tariff; and­ The Benchmark tariff

Revenue

Page 10: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

10

Initial tariff scenarios using for funding gap analysis

Unit 2013 Current

Kyat/kWh

Govt ProposedScenario

Kyat/kWh

BenchmarkScenario

Kyat/kWhHousehold first

100kWh/month35 35 60

> 100kWh/month 35 50 90

Business first 5000kWh/month

75 100 120

> 5000kWh/month

100 150 180

Benchmark tariff scenario is used for modeling purpose only.

Page 11: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

0 2,000,000 4,000,000 6,000,000 8,000,000 10,000,000 12,000,000 0

50

100

150

200

250

300

Cambodia

Indonesia

Lao PDR

Malaysia

Myanmar (current)

Myanmar (Benchmark)

Pakistan

Philippines

Thailand Vietnam

GDP per Capita (Kyat)

Resid

entia

l Tar

iff

(Kya

t/kW

h)

Useful to compare to other countries with similar incomes

11

Benchmark residential tariff against neighboring countries

Page 12: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

12

Cambodia

Indonesia

Lao PDR

Malaysi

a

Myanmar

(Current)

Myanmar

(Bench

mark)

Pakist

an

Phillipines

Thail

and

Vietnam

0

50

100

150

200

250

Busin

ess K

yat/

kWh

Benchmark business tariff against neighboring countries

Page 13: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

Funding Gap for the First 5 Years: Interim Results

13

Proposed Tariff Scenario

(million kyats)

Benchmark Tariff Scenario

(million kyats)

Kayin State 12,145 3,439

Chin State 4,920 1,989

Page 14: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

14

Funding gap using concessional finance: Kayin

22,122

30,828

11,013

1,1293,194

4,800

15,295

1,164

1,16412,145

3,439

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Costs Proposed Tariff Revenue Benchmark TariffRevenue

Kyat

mill

ion

Funding Gap

Connection Charges

Generation

transmission

Additional Dist costs

Dist O & M

Dist Capital

Revenue

Revenue

Page 15: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

15

Funding gap using concessional finance: Chin

Chin 2015-2020

7,520

10,451

4,564

3831,082

1,626

5,181

396

3964,920

1,989

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

Coss Proposed Tariff Revenue Benchmark TariffRevenue

Kyat

mill

ion

Funding Gap

Connection Costs

Generation

transmission

Additional Dist costs

Dist O & M

Dist Capital

Revenue

Revenue

Page 16: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

16

If the distribution rollout was financed by grants—with no interest cost and no obligation to repay—then unit costs would be around 30 % lower than using concessional loans

If the distribution rollout was financed by commercial loans—high interest rate and short tenor—then unit costs could be double that of concessional loans

The funding gap is sensitive to the cost of financing

The Cost of Financing Matters….

Page 17: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

17

Next steps…

We will gather data for the remaining

states and refine cost information

We will fill the funding gap

(Budget funds and grants)

Final Prospectus for entire country

Syndicate the concessional finance

Sources include World Bank, ADB

Source Amount

Government kyat

Donor grants Kyat

Concessional finance (WB, ABD etc)

kyat

Customers—tariffs and connection charges

kyat

The Prospectus

Page 18: Universal Access Roadmap and Investment Prospectus Initial Results for the Investment Prospectus Peter Hoogland, March 2014

WellingtonLevel 2, 88 The Terrace

PO Box 10-225Wellington

New Zealand

Sydney36 -38 Young StreetSydney, NSW 2000

Australia

Washington1747 Pennsylvania Ave NW Suite

1200Washington DC

20006, USA

New York200 Park Avenue

Suite 1744New York, NY

10166, USA

BogotáCarrera 7 No. 99-53

Torre 1, Oficina 1424Bogotá

Colombia

Paris7 Rue Claude Chahu

75116 ParisFrance

Peter Hoogland

36-38 Young StreetSydney, NSW 2000

Australia

[email protected]

Contact Us