Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
1
CHAPTER ONE
UNIVERSITY O F NIGERIA, NSUKKA
DEPARTMENT OF ELECTRICAL ENGINEERING
A CRITICAL ANALYSIS OF TRANSIENT
STABILITY OF ELECTRICAL POWER SYSTEM
A CASE STUDY OF NIGERIAN 330KV POWER
SYSTEM:
A PROJECT WORK SUBMITTED IN PARTIAL
FULFILLMENT OF THE REQUIREMENT FOR THE
AWARD OF MASTER OF ENGINEERING DEGREE
(M. ENG) IN ELECTRICAL ENGINEERING.
BY:
IKELI, HYGINUS NDUBUISI
PG/M.ENG/O6/40613
NOVEMBER, 2009
UNIVERSITY O F NIGERIA, NSUKKA
2
DEPARTMENT OF ELECTRICAL ENGINEERING
A CRITICAL ANALYSIS OF TRANSIENT STABILITY OF
ELECTRICAL POWER SYSTEM:
A CASE STUDY OF NIGERIAN 330KV POWER SYSTEM .
A PROJECT WORK SUBMITTED IN PARTIAL FULFILLMENT OF
THE REQUIREMENT FOR THE AWARD OF MASTER OF
ENGINEERING DEGREE (M. ENG) IN ELECTRICAL
ENGINEERING.
BY:
IKELI, HYGINUS NDUBUISI
PG/M.ENG/O6/40613
NOVEMBER, 2009
AUTHOR: ………………………………………………
IKELI, HYGINUS NDUBUSISI
SUPERVISOR: ………………………………………………
VEN. ENGR. (PROF) T.C. MADUEME
HEAD OF DEPARTMENT: ………………………………………………
ENGR .DR. L.U. ANIH
EXTERNAL EXAMINER: ………………………………………………
ENGR. PROF. J.C. EKEH
TITLE PAGE
3
A CRITICAL ANALYSIS OF TRANSIENT STABILITY OF
ELECTRICAL POWER SYSTEM
A CASE STUDY OF NIGERIAN 330KV POWER SYSTEM.
4
DECLARATION PAGE
I, IKELI, HYGINUS NDUBUISI, a postugraduate student in
the Department of Electrical Engineering with Registration
Number, PG/M.ENG/06/40613, hereby declare that the work
embodied in this dissertation is Original and has not been
submitted in part or full for any other Diploma or Degree of this
University or other Institution to the best of my knowledge.
CERTIFICATION
5
IKELI, HYGINUS NDUBUISI, a postgraduate student in the Department of
Electrical Engineering with Registration Number, PG/M.ENG/06/40613,
has satisfactorily completed the requirement for course and research work
for the Degree of Master of Engineering(M.Eng) in the Department of
Electrical Engineering, University of Nigeria, Nsukka.
The work embodied in this dissertation is original and has not been
submitted in part or full for any other Diploma or Degree of this University
or other institution to the best of our knowledge.
…………………………….. ………………………………
Ven. Engr. (Prof) T.C. Madueme Engr. (Dr.) L.U. Anih
Supervisor Head of Department
DEDICATION
6
This work is dedicated to the Almighty God, the Giver of life, the author and
finisher of faith.
ACKNOWLEDGEMENT
7
I wish to express my profound gratitude to Almighty God, the Giver of life,
for his continuous guidance, I owe everything to his love and Grace upon my
life.
My sincere and humble thanks go to my able and wonderful
supervisor, Ven. Engr. Prof T.C. Madueme for his fatherly guidance, sincere
advice, encouragement and un-alloyed interest to seeing this work to
completion. I am highly indebted to him.
My special appreciation goes to Engr. Dr L.U. Anih, the Head of
Department Electrical Engineering for all his contributions and invaluable
support in my life.
I wish to also specially appreciate the efforts of Engr. Prof M.U. Agu,
Engr. Dr E.S. Obe, Engr. Prof O.I. Okoro and Engr.Dr. B.O. Anyaka for
their constant encouragement and enormous sacrifices they made in shaping
me to what I am today.
This work would have suffered serious setback if not for the
contributions of my very good friends and colleagues who assisted me at all
times with relevant information. They include Engr. (Prof) F.N. Okafor
UNILAG), Engr. A.J. Onah (PHCN, ENUGU), Engr. Emma Okonkwo
(PHCN, Delta power station), Engr. Iloma Davis, Engr. Chindo (both of
National Centre Oshogbo PHCN)
My special acknowledgement goes to my parents, Mr and Mrs
Hyacinth – Choma Ikeli for laying a good foundation for me in life. Long
life and prosperity shall be your portion in Jesus Name Amen. My special
thanks goes to my Uncle, Rev. Dr Godfrey Anyaka for his constant
encouragement, invaluable support and advice. I am indeed very grateful to
you.
8
I also remain grateful to the following as lecturers in this Department
for their encouragement, Engr. B.O. Nnadi, Engr. C. Nwosu, Engr. C. Odeh
and Engr. S.O. Oti.
Also not left out in my train of appreciation were my school mates,
Mbadiwe, Cosmas, Umuoh, Douglas, Nelson, Chinedu, Emeka, Samuel and
Benjamin for our cooperation cannot be forgotten in a hurry.
………………………………...
Ikeli, Hyginus Ndubuisi
November, 2009
U.N.N.
ABSTRACT
9
This work involves the investigation and analysis of critical clearing angle
and time of Protection System of Nigerian 330KV power system Network.
In the recent times, the importance of transient stability assessment
has been increasing since the electric power systems are being operated
closer to their stability limits. This poses a variety of challenging problems
at the planning and design stages as well as during the system operation.
In this work, the composition of the Nigerian 330KV Electric power
system (the national grid) is looked into and the critical clearing time and
angle evaluated and determined using fourth (4th) order Runge Kutta method
after obtaining power flow solution results with Ifnewton power flow
program(Newton-Raphson Method) and other programs such as Lfybus,
Busout, Trstab, Afpek, Dfpek, Ybusaf, Ybusbf and Ybusdf in Matlab software
package environment such that the probability of total system collapse is
reduced to the barest minimum.
The performance of protective system during transient period is
evaluated and the system critical clearing time and angle obtained.
Heavy Egbin – Ikeja West 330KV line was faulted and removed and
the system critical clearing time and angle determined such that the
Nigerian power system is transiently stable thereby averting widespread
black-out. The results so obtained is used to predict the transient stability of
the entire power system since Egbin – Ikeja West 330KV line is one of the
heaviest feeders in the National grid.
10
TABLE OF CONTENT
COVER PAGE- - - - - - - - - - - - - - - - - - - --------------------------------i
2ND
COVER PAGE- - - - - - - - - - - - - - - - - - ----------------------------ii
TITLE PAGE --- --- --- --- --- --- --- --- --- iii
DECLARATION ----- --- --- ---- ----- ---- ----- ---- ---- ---- -- iv
CERTIFICATION --- --- --- --- --- --- --- --- v
DEDICATION --- --- --- --- --- --- --- --- vi
ACKNOWLEDGEMENT --- --- --- --- --- --- --- vii-viii
ABSTRACT --- --- --- --- --- --- --- --- --- ix
TABLE OF CONTENT --- --- --- --- --- --- --- x-xii
LIST OF SYMBOLS AND ABBREVIATIONS --- --- --- --- xiii - xviii
LIST OF FIGURES AND DIAGRAMS --- --- --- --- xix-xx
LIST OF TABLES --- --- --- --- --- --- --- --- xxi
CHAPTER ONE: INTRODUCTION --- --- --- --- --- 1
1.1 PREAMBLE --- --- --- --- --- --- --- --- 1-2
1.2 OBJECTIVE OF THE STUDY --- --- --- --- --- 3
1.3 SCOPE OF STUDY --- --- --- --- --- --- --- 3
1.4 Methodology --- --- --- --- --- ---- ----- 3-4
1.5 Existing 330Kv National grid - - - - - - - - - 5
1.6 NEED FOR STABILITY STUDIES --- --- --- --- --- 6
CHARPTER TWO --- --- --- --- --- --- --- --- 7
2.1 CONCEPT OF ENERGY FUNCTION MODEL
IN TRANSIENT STABLITY ANALYSIS --- --- --- --- 7
2.2 MODELLING ISSUES --- --- --- --- --- --- 8
2.3 NUMBERICAL METHODS --- --- --- --- --- --- 9
2.3.1 STEADY STATE ANALYSIS --- --- --- --- --- ---- 9
2.3.2 DYNAMIC (TRANSIENT) STATE ANALYSIS --- --- --- 9-10
2.3.3 RUNGE-KUTTA METHOD --- --- --- --- --- --- 10-12
2.4 NIGERIAN NATIONAL GRID--- --- --- --- ---- ---- ---- ---- --- 12-13
2.5 BASIC CONCEPTS OF STABLITY STUDIES --- --- -- 13-14
11
2.6 ESSENTIAL FACTORS IN THE STABILITY PROBLEM --- --- 14
2.5.1 FACTORS AFFECTING STABILITY --- --- --- --- ---- 14-15
2.5.2 POWER CIRCLE DIAGRAM --- --- ---- ---- ---- ---- ---- --- 16-19
POWER ANGLE DIAGRAM --- --- --- --- --- ---- 17-19
2.5.3 FACTORS AFFECTING TRANSIENT STABILITY --- --- --- 19-20
2.5.4 STEADY-STATE STABILITY LIMIT --- --- --- --- ---- 20-21
2.5.5 TRANSIENT STABILITY LIMIT --- --- --- --- --- 22-24
2.6 THE SWING EQUATION --- --- --- --- --- --- 25-29
2.6.1 THE POWER-ANGLE EQUATION --- --- --- --- --- 30
2.6.2 TRANSIENT AND SUBTRANSIENT EFFECTS --- --- --- 30-31
2.7 EQUAL AREA CRITERION --- --- --- --- --- --- 31-39
2.8 MULTIMACHINE DYNAMIC MODEL --- --- --- --- 40
2.8.1 INTERCONNECTION OF SYNCHRONOUS
MACHINE DYNAMIC CIRCUIT AND THE
REST OF THE NETWORK --- --- --- --- --- --- 41
2.8.2 NETWORK EQUATIONS --- --- --- --- --- --- 42
2.9.0 POWER FLOW SOLUTION ---- ---- ----- ---- ---- ---- --- 43
2.9.1 POWER FLOW EQUATION --- ---- ---- ----- ---- ----- 44-45
CHAPTER THREE -- --- --- --- --- --- --- --- 46
3.1 PROJECT DESIGN --- --- --- --- --- --- --- 46
3.2 DATA SOURCES --- --- --- --- --- --- --- 47
3.3 DATA ANALYSIS TECHNIQUE --- --- --- --- --- 48
3.4 MULTIMACHINE TRANSIENT STABILITY
WITH MATLAB SOFTWARE PACKAGE --- --- --- --- 48-50
3.6 ASSUMPTION MADE FOR THIS WORK --- --- --- --- 51-52
3.7 PERFORMANCE OF PROTECTIVE RELAYING --- --- --- 51-52
3.7.1 FAULT CLEARING TIMES --- --- --- --- --- --- 52
3.7.2 FACTORS INFLUENCING TRANSIENT STABILITY --- --- 53
3.8 DATA FOR THE WORK --- --- --- --- --- --- 54-60
CHAPTER FOUR --- --- --- --- --- --- --- --- 61
12
4.1 EXISTING 330KV NATIONAL GRID DIAGRAM --- --- 61
4.2 SIMULATION AND DISCUSSION
OF RESULTS --- --- --- --- --- --- --- --- 62- 74
CHAPTER FIVE ---- ---- ----- ----- ------ ----- ------ ----- ----- ------ 75
5.0 CONCLUSION AND RECOMMENDATION --- --- --- --- 75- 76
REFERENCES 77 - 81
LIST OF APPENDICES
13
APPENDIX 1 82 -84
APPENDIX 2 85
APPENDIX 3 86
APPENDIX 4 87-88
APPENDIX 5 89
APPENDIX 6 90
APPENDIX 7 91
APPENDIX 8 92
APPENDIX 9 93
APPENDIX 10 94
APPENDIX 11 95
LIST OF SYMBOLS AND ABBREVIATIONS
O Code for the load buses
1 Code for the slack buses
14
2 Code for the voltage – controlled buses
Ra Generator’s armature resistances in per unit expressed on a
100 MVA base
Xa Transient reactance in per unit, expressed on a 100 MVA base.
( )
H Inertia constants in seconds expressed on a 100MVA base.
B Susceptance in per unit expressed on a 100mva base.
ω Angular speed rad/s
VA Phase voltage quantity, V
VB Voltage quantity, V
VC Phase voltage quantity, V
TDQOS Transformed Operator
ωS Synchronously speed rad/s
HIW Oshogbo T.S – Ikeja West T.S 330kv line
H7B Oshogbo T.S – Benin T.S 330kv line
O1W Olorunshogbo G.S – Ikeja West T.S 330kv line
NWIBS Sakete T.S – Ikeja West T.S 330kv line
W3L Ikeja West T.S – Akangba T.S 330kv line 1
W4L Ikeja West T.S – Akangba T.S 330kv line 2
E11 Ikeja West T.S – Egbin G.S 330kv line 4
E21 Ikeja West T.S – Egbin G.S 330kv line 2
N3J Aja T.S – Egbin G.S 330KV line 1
N4J Aja T.S – Egbin G.S 330KV line 2
E1A Egbin/Ikeja West line – AES G.S 330kv line 1
E2A Egbin/Ikeja West line – AES G.S 330kv line 2
A4J AES G.S line – AJA T.S 330KV line
M7W Ikeja West line – Omotosho G.S 330KV line
15
B5M Benin T.S – Omtosho G.S 330KV line
B6W Ikeja West line – Benin T.S 330KV line
B11J Benin T.S – Ajaokuta T.S 330KV line 1
B12J Benin T.S – Ajaokuta G.S 330KV line 2
AIS Ajaokuta T.S – Ascon G.S 330KV line 1
A2S Ajaokuta T.S – Ascon G.S 330KV line 2
AIG Ajaokuta T.S – Geregu G.S 330KV line 1
A2G Ajaokuta T.S – Geregu G.S 330KV line 2
BIT Benin T.S – Onitsha T.S 330KV line
T3H Onitsha T.S – (Enugu) New Heaven 330KV line
K3R Kainji – Benin Kebbi 330KV line
KIJ Kainji – Jebba T.S 330KVline 1
K2J Kainji – Jebba T.S 330KV line 2
RIM Shiroro T.S – Kaduna 330KV line
M6N Kaduna T.S – Kano 330KV line
R2M Shiroro T.S – Kaduna 330KV line
M2S Kaduna T.S – Jos 330KV line
SIE Jos T.S – Gombe 330KV line
B8J Jebba G.S – Jebba T.S 330KV line 1
B9J Jebba G.S – Jebba T.S 330KV line 2
J3R Jebba T.S – Shiroro T.S 330KV line 1
J7R Jebba T.S – Shiroro T.S 330KV line 2
R4B Shiroro T.S – Abuja T.S 330KV line 1
R5B Shiroro T.S – Abuja T.S 330KV line 2
P4A Shiroro T.S – Shiroro T.S 330KV line
JIH Jebba T.S – Oshogbo G.S 330KV line 1
J2H Jebba T.S – Oshogbo T.S 330KV line 2
J3H Jebba T.S – Oshogbo T.S 330KV line 3
16
H2A Ayede T.S – Oshogbo T.S 330KV line 1
W2A Ayede T.S – Ikeja-West T.S 330KV line 2
G3B Benin T.S – Delta G.S 330KV line
GIW Delta G.S – Aladja T.S 330KV line
S4W Sapele G.S – Benin T.S 330KV line
S3B Sapele G.S – Benin T.S 330KV line
KIT Onitsha T.S – Okpai G.S 330KV line 1
K2T Onitsha T.S – Okpai G.S 330KV line 2
T4A Alaoji T.S – Alaoji T.S 330KV line
FIA Alaoji T.S – Afam G.S 330KV line 1
F2A Alaoji T.S – Afam G.S 330KV line 2
MM6 Afam G.S line – Omoku G.S 330KV line
BUS 1 Kainji G.S (Slack bus)
BUS 2 Bernin Kebbi
BUS 3 Jebba G.S
BUS 4 Jebba T.S
BUS 5 Shiroro T.S
BUS 6 Abuja (katampe)
BUS 7 Shiroro G.S
BUS 8 Ayede T.S
BUS 9 Oshogbo T.S
BUS 10 Kaduna T.S
BUS 11 Olorunsongo G.S
BUS 12 Sakete T.S
BUS 13 Kano T.S
BUS 14 Jos T.S
BUS 15 Ikeja West T.S
BUS 16 Benin T.S
17
BUS 17 Gombe T.S
BUS 18 Delta G.S
BUS 19 Ajaokuta T.S
BUS 20 Akangba T.S
BUS 21 Omotosho T.S
BUS 22 Egbin G.S
BUS 23 Onitsha T.S
BUS 24 Sapele G.S
BUS 25 Aladja T.S
BUS 26 Geregu G.S
BUS 27 Ascon G.S
BUS 28 AES G.S
BUS 29 Aja T.S
BUS 30 New Heaven T.S
BUS 31 Okpai G.S
BUS 32 Alaoji T.S
BUS 33 Afam G.S
BUS 34 Omoku G.S
G.S Generating station
T.S Transmitting Station
Yij Transfer Admittance
Yii Self Admittance
X1d Transient Reactance
X11
d Sbtransient Reactance
E1 Voltage behind Transient Reactance
KG Kainji Generator
JG Jebba Generator
SG Shiroro Generator
18
OG Olorunsongo Generator
DG Delta Generator
OMG Omotosho Generator
EG Egbin Generator
SAG Sapele Generator
GG Geregu Generator
AG Ascon Generator
AEG AES Generator
OKG2 Okpai Generator
AFG Afam Generator
OMKG Omoku Generator
K1 is the slope @ the beginning of time step,
K2 is the first approximation to the slope @ midstep
K3 is the second approximation to the slope @ midstep
K4 is the slope @ the end step
Yn+1 is the incremental value of Y given by the weighted average of
estimates based on slopes @ the beginning, midstep, and end of time
step
Vi = voltage @ i bus
Vk= voltage @ k bus
Idi= current @ direct axis of i bus
Iqi = current @ quadrature axis of i bus
Pli= Real power @ i bus
Qli= Reactive power @ i bus
Yik = Admittance of k bus with reference to i bus
θi = Theta @ i bus
θk = Theta @ k bus
αik = phase angle difference between bus i and bus k
19
y = Rotor angle in radii
t = Time in seconds
LIST OF FIGURES AND DIAGRAMS
Figure 1.1 Existing 330KV National grid Network Diagram
Figure 2.1 Various elements of power system Network.
Figure 2.2 Power circle Diagram.
Figure 2.3 Power Angle Curve.
Figure 2.4 Single machine infinite bus system.
Figure 2.5 Generator prime mover and motor Dynamics.
20
Figure 2.6 Circuit diagram of a synchronous machine for transient
stability studies.
Figure 2.7 Plot of power against δ.
Figure 2.8 Plot of δ versus time for stable and unstable systems.
Figure 2.9 Synchronous machine and the rest of the network.
Figure 2.10 A typical bus of the power system.
Figure 4.1 Existing 330KV National grid Network Diagram.
Figure 4.2 Plot of rotor angle [radii] against time [s] for Nigerian
generators swing during fault for 0.025 seconds.
Figure 4.3 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.025seconds.
Figure 4.4 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.030 seconds.
Figure 4.5 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.035 seconds.
Figure 4.6 Plot of rotor angle [radii] against time [s] for fault
cleared @ 0.040 seconds.
Figure 4.7 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.045 seconds.
Figure 4.8 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.050 seconds.
Figure 4.9 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.055 seconds.
Figure 4.10 Plot of rotor angle [radii] against time [s] for system
fault cleared @ 0.060 seconds.
Figure 4.11 Plot of rotor angle [radii] against time [s] for system
Generators swinging in synchronism after the faulted
22
Table 3.1: Load Data ------------------------------------------------54-55
Table 3.2: Generation schedule------------------------------------56-57
Table 3.3 Machines and system vars-----------------------------57-58
Table 3.4: Line Data-----------------------------------------------58-59
Table 3.5: Machine Data -----------------------------------------59-60
23
INTRODUCTION
1.1 PREAMBLE
Electrical energy is an essential ingredient for the industrial and
all-round development of any country. The quality of life in any
country is highly dependent on a reliable electricity supply. The
frequent system collapses in the Nigerian power sector have severally
thrown or plunged the nation into darkness due to system instability in
the Nigeria electric power system. The epileptic nature of the supply
has led to low economic growth and dissatisfaction among the
citizenry. To assist in overcoming the instability problems, analysis of
the Nigerian electric power system transient stability is carried out
employing Newton-Raphson method of load flow solution and fourth
order Runge Kutta method in mat-lab software package environment
[1, 2, 3].
The objective of any electrical power system is to generate
electric energy in sufficient quantities at most suitable locality, transmit
it in bulk quantities to the load centre, which is then distributed to the
individual consumers. In carrying out the desired objectives, the electric
power system is faced with unforeseen circumstances such as faults.
Under this condition, the system voltage collapses resulting in a
dangerous high current. This causes instability within the system which
can result in system breakdown if adequate care is not taken [4, 5].
In order to avoid these undesirable situations, it becomes
necessary to, before hand; predict with a very good accuracy, the extent
of voltage, current and power distribution within the system at anytime
so as to know the protective devices to be incorporated to handle the
abnormal conditions. Hence under these dangerous situations, the
24
transformers, lines, generators, cables, bus-bars etc. need to be
protected [2, 6, and 7].
The transient stability analysis which is the main concern of this
work, deals with the state of the synchronous machine during a fault in
the system. It gives the state and position of the load. The digital
computer is an indispensable tool for power system analysis,
computational algorithms for various system studies such as load flow,
fault-level analysis, stability studies etc. It gives an acceptable working
accuracy to the ever widening complex power system of modern times
[8, 9].
1.2 THE OBJECTIVES OF THE STUDY.
These include the following:
i To determine the critical clearing angle and time of the Nigerian
330KV protection system.
ii To determine the behavior of the Nigerian power system during
large scale disturbance and make necessary recommendations.
iii To specify the circuit break speeds in the system
iv To determine the available transfer capability (ATC) of the
Nigerian 330KV grid system during fault and make
recommendation for improvement such that the system is
transiently stable.
25
1.3 SCOPE OF STUDY
The dissertation work covers the Nigerian 330KV power system. All
the thirty-four (34) buses in the network are critically examined and
analyzed with regard to transient stability .
1.4 Methodology
In this work, the composition of the Nigerian 330KV Electric power
system (the national grid) is looked into and the critical clearing time
and angle evaluated and determined using fourth (4th) order Runge
Kutta method after obtaining power flow solution results with
Ifnewton power flow program(Newton-Raphson Method) and other
programs such as Lfybus, Busout, Trstab, Afpek, Dfpek, Ybusaf,
Ybusbf and Ybusdf in Matlab software package environment such that
the probability of total system collapse is reduced to the barest
minimum.
Power holding company Plc. 330KV electrical network
single Line diagram is used for this study. The generators,
transmission lines and transformer parameters are taken from the most
up-to-date data from National control centre, Oshogbo System
Planning unit and system operations department. The subtransient
reactance X11
of the synchronous machines is used to give maximum
fault levels at the instant of fault.
The MATLAB function ode 23 will be employed to solve the 2m
first order swing equation to give the desired result.
The performance of protective system during transient period will be
Evaluated. Heavy Egbin – Ikeja West 330KV line will be faulted
26
And be removed and the system critical clearing time and angle
determined such that the Nigerian power system is transiently stable
thereby averting widespread black-out.
27
EXISITING 330KV NATIONAL GRID NETWORK
1
K3R
KIJ K2J
10
RIM R2M
M2S
M6N
SIE
13
17
14
7
P4A
R5B R4B J7R
J3R 5
6
B8J
B9J
4
JIH J2H J3H
9 H2A
W2A
01W
NWIBS
W3L
W4L
11
12
20
N3J
N4J
29
E21
22
E1A 15
E11
E2A
28
M7W
21
B5M
B6W
H7B
16
ABUJA
B11J
B12J AIG A2G
19
AIS
A2S
27
26
T3H
23 30
BIT
G3B
18
G1W
25
S4w
24
S3B
S4B KIT
K2T T4A
32
33
F1A F2A MM6
8
A4J
31
Figure 1.1 Existing 330kv National grid Network Diagram.
3
2
28
1.5 NEED FOR STABILITY STUDIES
In general, stability studies are very important primarily from
the stand point of determining the maximum amount of power that
can be transmitted without instability being incurred under steady
state conditions or as a result of load changes or faults. Potential
stability problems are still the most critical impediments to
maximizing power transfers across interconnected power systems like
the Nigerian national grid. Occurrence of transient instability
problems may result to large excursions of the system machines rotor
angle, and if corrective action fails, loss of synchronism among
generators may result in total system collapse. Recall that in the
summer of 1996, two major transient disturbances occurred in the
Western system co-ordinating council in United States of America
which resulted in partial black-outs that cost the power utilities and
their customers several Millions Dollars[13].
In Nigeria, two system collapses within a three-day interval in
March 2000, plunged the entire nation into darkness. The nation was
without electricity for up to 72 hours in some areas with serious
social, economic and security implications. This incident led to the
sacking of the power utility [NEPA] board and the appointment of a
Technical Board to oversee the day to day activities of the Authority
[13, 18].
The transient stability of a power system is normally taken as
very important and a major determinant of the stability of the power
system because of its non-linear character, its fast evolution and its
disastrous practical implications.
29
CHAPTER TWO
2.1 CONCEPT OF ENERGY FUNCTION MODEL IN TRANSIENT
STABILITY ANALYSIS
In 1892, A.M Lyapunov, in his famous ph.D. dissertation,
proposed that stability of the equilibrium of a non-linear dynamic
system of dimension n can be ascertained without numerical
integration.
According to this model, the critical clearing time of a circuit
breaker can be interpreted in terms of meaningful quantities such as
Maximum power transfer in the pre-fault state.
x = f (x), f (0) = 0 ………………………………………... (2.1)
He said that if there exists a scalar function V(x) for equation (1) that is
position definite, for V(x) > O around the equilibrium point “O” and
the derivative V(x) < O, then the equilibrium is asymptotically stable.
V(x) is obtained as Σi=1 ∂v xi =
∂xi
Σi=1 ∂v fi (x) = ------------(2.2) Where n is the order of the system in (2.1)
Furthermore, in 1948, the application of the energy function model to
power system stability actually began with the early work of
Magusson and Aylett, followed by a formal application of the more
general Lyapunov’s model by EL-Abad and Nagappan[19]
.
.
.
.
30
2.2 MODELLING ISSUES
A Power system undergoing a disturbance can be described by
a set of three differential equations:-
x (t) = f1 (x(t)) - ∞ < t < 0………………………(2.3)
x (t) = ff(x(t) ) O < t < tcl ……………………………..(2.4)
x (t) = f (x(t) ) tcl < t < ∞ ………………………….(2.5)
x (t) is the vector of state variable of the system at time t.
At t = 0, a fault occurs in the system and the dynamics change from fi
to ff .
During 0<t < tcl, called the faulted period, the system is
governed by the fault – on dynamics if actually, before the fault is
cleared at t = tcl, we may have several switching in the network, each
giving rise to a different ff.
For simplicity, we have taken a single ff, indicating that there
are no structural changes between t = 0 and t = tcl. When the fault is
cleared at t = tcl, we have the post fault system with its dynamics fi
(x(t)).
However, the energy function methods have proved to be
reliable after many decades of research for single machine system but
for multi-machine system with complex network like that of Nigerian
330KV power system network, the value of the tcl is not as reliable as
that got with numerical integration method with digital computer.
More research is still going on, on multi-machine system on this
concept. [19]
. .
.
31
2.3 NUMERICAL METHODS
Differential equations’ solution is highly restricted to the
employment of numerical methods since accuracy is needed. In
stability studies, non-linear highly-dimensional mathematical
problems are encountered hence engineers resort to using numerical
methods in their analysis. Numerical methods for the analysis of the
steady state and dynamic (transient) behaviour of power system
network are listed below:
2.3.1 STEADY STATE ANALYSIS.
This is done by four methods viz:
1. Gauss – Elimination Method.
2. Grammar’s rule.
3. Gauss – Jordan method.
4. Newton’s method.
The first three methods are suitable for linear expressions while the
last two methods are suitable for linear and non-linear expressions.
2.3.2 DYNAMIC (TRANSIENT) STATE ANALYSIS
Nine methods are available for this analysis namely:
1. Euler method.
2. Improved Euler method.
3. Euler-Cauchy.
4. Adams-Bash forth fourth-order method.
5. Adams-Moulton fourth-order.
32
6. Gear’s method.
7. Finite Difference method.
8. Fourth-order Runge-Kutta method.
9. Crank-Nicolson method.
Note: Crank-Nicolson and finite difference methods are mainly used
for the analysis involving partial differential equations, while the rest
seven methods are very suitable for analysis involving-ordinary
differential equations. [20]
2.3.3 RUNGE-KUTTA METHOD
One of the popular and most accurate, numerical procedures or
methods used in cracking a system of differential equation is the
fourth-order Runge-Kutta method. There are different orders of this
Runge-Kutta method but the interesting thing is that they are derived
using the Taylor’s series-expansion with remainder of function y(x).
The first order Runge-Kutta method is normally and basically the
same with basic Euler method. The second order Runge-Kutta method
is the same with improved Euler method. The fourth order Runge-
kutta solution to a system equation is as follows:
Y(x) = y(a) + y(a)1 x – a + y(a)
11 (x – a)
2 + … Y(c) (k+1) (x-a) k+1 …. (2.6)
1! 2! (k+1)!
Where c is some number between a and x boils down to:
Yn+1 = yn + ak1 + bk2 + ck3+ dk4 ………………… (2.7)
Where :
K1 = hf (Xn, Yn)
K2 = hf (Xn + 0.5h, Yn + 0.5K1)
K3 = hf (Xn + 0.5h, Yn + 0.5K2)
K4 = hf (Xn +h, Yn + K3)
33
This agrees with a Taylor Polynomial of degree 4.
The final solution formula for using in system analysis gives:
Yn+1 = Yn +1/6 [K1 + 2k2 + 2K3 + k4] ----------------- (2.8)
Careful look at the analysis of equation (6) shows that K2 depends on
K1, K3 depends on K2 and K4 depends on K3. This method amongst all
other methods allows usage of variable step size and this improves
accuracy of result. k1 is the slope @ the beginning of time step,
k2 is the first approximation to the slope @ midstep, k3 is the
second approximation to slope @ midstep While k4 is the slope
@ the end step. Yn+1 is the incremental value of Y given by the
weighted average of estimates based on slopes @ the beginning,
midstep, and end of the time step.
In this work, Runge-Kutta has been chosen for the stability
assessment of the Nigerian-Electric Power System based on the
following advantages it gives;
a. The method is inherently self-stating and this quality directly ceases
the handling of discontinuities and the adjustment of step length
where required (“easy for all automatic error control”)
b. It has high accuracy when the step can be made small.
Moreover, since this is a stability study which needs knowledge
of steady-state initial-condition values before starting transient-
stability integration, Runge-Kutta method was chosen.
c. Experiments have shown that several applications of a corrector say
three applications have to be made to match accuracy obtained using
Runge-Kutta method. This exhibits it’s time saving quality.
34
d. Easy to program for s digital computer and are always designed to
give greater accuracy [21], [23].
2.4 NIGERIAN NATIONAL GRID
The Nigerian National Grid is being run and controlled by
Power Holding Company of Nigerian PLC (PHCN), formally known
as National Electric Power Authority (NEPA). The Nigerian National
Grid System has a total of fourteen (14) Generating Power stations:
Namely:- Kanji, Jebba, Shiroro, Ascon, Egbin, AES, Delta, Okpai,
Afam, Sapele, Omotosho, Olorunsongo, Omoku and Geregu [10, 12,
13]. The national grid is made up of interconnected network of
5000km of 330KV transmission lines.
The control of the grid is affected by eight (8) Regional control
centers (RCC) located at Lagos, Oshogbo, Benin, Enugu,
PortHarcourt, Bauchi, Kaduna and Shiroro. Shiroro is normally taken
as sub-National control center (SNCC). The operations in these
regional control centers (RCC) are co-ordinated, directed and
supervised by the National control center at Oshogbo [14,15].
The radial nature of most stations in the National gid has made
some of the transmission lines very important and critical to the
integrity of the whole grid. These lines are Egbin – Ikeja West line,
Benin – Ikeja West line, Benin – Onitsha line, Jebba – Oshogbo line
and lastly the Oshogbo – Benin line. This could be clearly seen from
fig. 1.1. above. Records show that Lagos area consumes about 55%
of the total generated power [16]. These critical lines once disturbed,
reflect heavily on the whole power system most at times lead to a total
system outage. This situation critically affects the stability of the
system. The size of disturbance or fault distinguishes between
35
small disturbance stability and large disturbance stability. Small
disturbance stability is usually handled or solved by the linearization
of dynamic equations of motion while the large disturbance stability
requires non-linear approaches [17].
2.5 BASIC CONCEPTS OF STABILITY STUDIES
On commercial power systems, the large machines are of the
synchronous type; these include substantially all of the generators and
condensers, and a considerable part of motors
On such systems it is necessary to maintain synchronism
between the synchronous machines under steady-load conditions.
Also, in the event of transient disturbance, it is necessary to maintain
synchronism; otherwise a standard of service satisfactory to the user
will not be obtained.
These transient disturbances can be produced by load changes,
switching operations and particularly faults and loss of excitation.
Thus, maintenance of synchronism during steady-state conditions and
regaining of synchronism or equilibrium after a disturbance are of
prime-importance to the electrical utilities. Electrical manufacturers
are likewise concerned because stability considerations determine
many features of apparatus and under many conditions affect their
cost and performance. The characteristics of virtually every element
of the system have an effect on stability. It introduces important
problems in the co-ordination of electrical-apparatus and lines in order
to provide, at lowest cost, a system capable of carrying the desired-
36
loads and of maintaining a satisfactory-standard of service, both for
steady-state conditions and at times of disturbances [22], [23].
2.6 ESSENTIAL FACTORS IN THE STABILITY PROBLEM
The essential factors in the stability problem are illustrated in
connection with the two machine system shown schematically below in
figure 2.21.
The various elements of the system; prime mover synchronous
generator, reactance line, synchronous motor, and the shaft load, are
indicated:-
Figure 2.1: Various elements of Power System Network
PM - Prime Mover
G - Synchronous Generator
X - Reactance of the Line
M - Synchronous Motor
SL - Shaft Load
2.6.1 FACTORS AFFECTING STABILITY
These factors are the mechanical and electrical factors.
The essential mechanical factors include:
i. Prime Mover:- Turbine
Input
Torque
PM G X
M
SL
Output
Torque Inertia
37
ii. Inertial:- Mover of Turbine (crank shaft of the motor)
iii. Shaft:- Load out-put torque
The essential Electrical factors include:
i. Internal voltage of Synchronous generator
ii. Reactance of the system Viz: Generator, line and motor.
iii. Internal voltage of Synchronous motor [22]
38
θ11
θ1
P1
P11
Radius
Es Er
X
Receiver Circle
Centre
E2
X
θθ
P1
θ1
θ11
P11
Pmax
Es Er
X
Supply Circle
Centre
E2
O
O
X
Leading Reactive Power -
+ Lagging Reactive Power
2.6.2 POWER CIRCLE DIAGRAM AND POWER ANGLE CURVE.
Figure 2.2: Power Circle Diagram
39
Pmax
δ0 δ
O
Pe
pe
Pm
π/2
Figure 2.3: Power Angle Curve
The performance characteristics of the simple two-machine power
transmission system in figure 2.21 are shown by power-circle diagram and
power angle Curve as given in figure 2.22 and 2.23 respectively.
40
When a synchronous machine is in parallel with infinite bus bars, the
power generated equals the power received by the bus bars for a generator
in the absence of losses the system depends mainly on four factors namely:-
Eg, Em, θ and X.
The equation relating power transfer to the four factors in a three-phase
system is given by:-
P = Eg Em Sin θ ……………………………………………….……… (2.9)
X
P = three-phase power transferred in Watts
Eg = internal voltage of generator (line-to line in volts)
Em = internal voltage of motors (line-to-line in volts)
X = reactance between generator and motor internal voltages in OHMS
per phase.
θ = angle by which the internal voltage of generator leads the internal
voltage of the motor.
The maximum power is given by:-
Pmax = Eg Em ………………………………………………… (2.10)
X
(For θ = 900)
The radius of the circle is Pmax. The angle θ is varied between O and
1800. The relationship of the angle and the power is indicated in figure
2.23. As θ varies between O and 900, the power increases thus
reaching a maximum value at 900 and falling gradually from the
maximum to zero as θ increases from 900
to 1800.
The term “Stability” and “Maintenance of Synchronous” are
quite frequently used interchangeably. A system consisting of a
41
synchronous generator, a reactance line, and an induction motor may
become unstable but cannot loose synchronous. System stability is
ordinarily of importance only when it deals with the conditions of
stable operation between synchronous machines. The problem is of
importance, primarily from the stand-point of the maximum amount
of power that can be transmitted without instability being incurred
under steady-state conditions or as a result of circuit changes or faults.
Stability when used with reference to a power system is the attribute
of the system, or part of the system, which enables it to develop
restoring forces between the elements there of equal to or greater than
the disturbing forces so as to restore a state of equilibrium between the
elements. Stability applies to both steady state and transient conditions
in a power system [23],[24], [ 25].
2.5.3 FACTORS AFFECTING TRANSIENT STABILITY
Two factors which indicate the relative stability of a generating unit
are:
i. The angular swing of the machine during and following fault
condition.
ii. The critical clearing time.
H constant and the transient reactance X1d of the generating unit
have a direct effect on both of those factors.
Any development which lower the H constant and increase transient
reactance X1d of the machine causes the critical clearing time to
decrease and lessen the probability of maintaining stability under
transient conditions.
As power systems continually increase in size, there may be a
corresponding need for higher rated generating units. These larger
42
units have advanced cooling system which allows higher-rated
capacities without comparable increases in rotor size. As a result H
constants continue to decrease with potential adverse impact on
generating unit stability. Stability control techniques and transmission
system designs have also been evolving to increase overall system
stability in the modern times. The control schemes are
a. Excitation systems
b. Turbine valve control
c. Single-pole operation of circuit breakers
d. Faster fault clearing times
2.5.4 STEADY-STATE STABILITY LIMIT
A stability limit is the maximum power flow possible through
some point in the system when the entire system or part of the system
to which the stability limit refers is operating with stability. For the
two simple two-machine-transmission systems illustrated in figure
2.24 above, the steady-state stability is given by the maximum-power
obtained from either the power circle diagram or the power-angle
diagram of figures 2.22 and 2.23. The steady state stability of a
system without loss occurs at the angle of 90 degrees between the
sending and receiving ends as shown by these diagrams or reading
obtained from equation 8.
The steady-state limit for a three-phase system is given by:-
Pmax = Eg Em ………………………………………..(2.11)
X
Which gives the maximum power in watts when the voltages
are expressed as line-to-line voltage and reactance as ohms per phase.
43
If the criterion of stability is applied which states that the steady
limit for a three-phase system is given by the maximum power, then
the following exist.
i. For all load conditions with the power and angle less than those
corresponding to the 90 degrees limit, the system will be inherently
stable.
ii. For all loads at angle greater than 90 degrees the system will be
unstable. The 90 degrees-load point for a system without loss is the
critical load or the maximum value for all steady state operating
points that are inherently stable.
2.5.5 TRANSIENT STABILITY LIMIT
Transient stability refers to the amount of power that can be
transmitted with stability when the system is subjected to an
“aperiodic disturbance”. The three principal types of transient
disturbances that receive consideration in stability studies, in order of
increasing importance are:-
A. Load increases
B. Switching operation
C. Faults with subsequent circuit isolation.
44
A. LOAD INCREASE
Load increases can result in transient disturbances that are
important from the stability-standpoint if the following exist.
i. The total load exceeds the steady-state stability limit for specified
voltage and circuit reactance conditions.
ii. If the load increases set up an oscillation that causes the system to
swing beyond the critical point from which recovering would be
impossible.
If a large increment of load is added suddenly instead of
gradual, the synchronous machine may fall out of step even though
the steady-state stability limit has not been exceeded [22], [26], [27].
B. SWITCHING OPERATION
The transient-stability limits for switching- operations can be
investigated by looking at the initial condition and the final condition
after the switching operation has taken place.
The switching operation takes place the electrical out-put is
reduced. This change produces an increment power which is available
for accelerating the generator and decelerating the motor, both
changes tending to increase the angle between the sending and
receiving machines. Thus, the two machines depart from synchronous
speed, accelerating and decelerating forces increases the angle. At this
point, the generator rotor is traveling above the synchronous speed
with the result that both rotors tend to over shoot.
The amount of power transferable without loss of synchronous
depends upon the followings:-
45
i. The steady-state stability limit for the condition after switching
operation takes place.
ii. The difference between the initial and final state operating angles.
C. FAULTS
If short circuit faults of any degree occur within the systems,
the output power of the generator will be affected and become zero
while the mechanical input power to the generator remains constant
due to relating large time constant of the governor.
Consequently the speed of the synchronous machine decreases
thus, the machine will fall out of step.
The procedure of determining the stability of a system upon
occurrence of a disturbance followed by various switching off and on
actions is called a stability study. Steps to be followed in a stability
study are outlined below:-
46
G
Infinite
Busbar
Fault
Figure 2.4: Single machine infinite bus system
The fault is assured to be a transient one which is cleared by the time of first
reclosure of the circuit breaker. The steps listed below also apply to a system
of any size.
i. From the prefault loading, the voltage behind the transient reactance
and the torque angle δo of the machine with reference to the infinite
bus is determined.
ii. For the specified fault, the power transfer Pe (δ) is determined during
faults.
iii. From the swing equation, starting with δo as obtained in step i , δ is
calculated as a function of time using a numerical technique of
solving the non-linear differential equation.
iv. After the clearance of the fault, Pe(δ) is calculated and solved further
for (δ) (t).
47
v. After the switching on the transmission line, Pe((δ) ) is calculated and
likewise (δ)(t).
vi. If (δ)(t) goes through a maximum value and starts to reduce, the
system is regarded as stable. It is unstable if (δ)(t) continues to
increase. Calculation is ceased after a suitable length. [28, 29, 30].
2.6 THE SWING EQUATION
The swing equation describes the dynamics of a generator or motor.
Considering the generator in figure 2.25(a) .
It receives mechanical power Pim at torque at torque Ti and rotor speed
w via shaft from the prime mover. It delivers electrical power Pe to
the power system network via the bus bars. The generator develops
electromechemical torque Te in opposition to Ti. Assuming that
windage and frictional torque is negligible.
Figure 2.5: Generator, Prime Mover Diagram and Motor Dynamics.
Considering that the synchronous generator develops an electromagn etic
torque Te and running at the synchronous speed ωSm. If Tm is the driving
Generator Motor
Ti ω (a)
Pm
ω Te
Ti
(b)
Pe Pe Te
Pm
48
mechanical torque, then under steady-state operation with losses neglected
we have
Tm = Te -------------------------------------------------------------------------- (2.12)
A departure from stesy state due to a disturbance results in an accelerating
(Tm > Te) or decelerating (Tm< Te) torque Ta on the rotor.
Ta = Tm – Te --------------------------------------------------------------(2.13)
If J is the combined moment of inertia of the prime miver and generator,
neglecting the frictional and damping torques, from law’s of relation we
have
J = Ta = Tm – Te------------------------------------------- (2.14)
Where θm is the angular displacement of the rotor with respect to the
stationary reference axis on the stator. Since we are interested in the rotor
speed relative to synchronous speed, the angular reference is chosen relative
to a synchronously rotating reference frame moving with constant angular
velocity ωsm, that is:
θm = ωSmt + δm --------------------------------------------------------- (2.15)
Where δ is the rotor position before disturbance at time t = 0, measured from
the synchronously rotating reference frame. Derivative of (14) gives the
rotor angular velocity.
ωm = dθm = ωmS + dδm --------------------------------------------------- (2.16)
dt dt
and the rotor acceleration is
d2θ m = d
2δm ----------------------------------------------------------- (2.17)
dt2 dt
2
dt2
d2 θm
49
Substituting (16) into (13), we have
J = Tm – Te---------------------------------------------- (2.18)
Multiplying (17) by ωm, results in
Jωm d2δm = ωm Tm – ωm Te-------------------------------------- (2.19)
dt2
Since angular velocity times torque is equal to the power, we write the abo
ve equation in terms of power
Jωm = Pm - Pe ------------------------------------------- (2.20)
The quantity Jωm is called the inertia constant and is denoted by M. It is
related to Kinetic energy of the rotating masses, Wk.
Wk = ½ Jω2
m = ½ Mωm ----------------------------------------------- (2.21)
or
M = 2Wk -----------------------------------------------------------------(2.22)
ωm
Although M is called inertia constant, it is not really constat when the roror
speed deviates from the synchrounous speed. However, since Wm does not
change by a large amount before stability is lost, M is evaluated at the
synchrounous speed and is considered to reamain constant, ie,
M = 2Wk -----------------------------------------------------------------(2.23)
ωsm
The swing equation in terms of the inertia constant becomes:
M d2δm = Pm – Pe ------------------------------------------------------ (2.24)
dt2
dt2
d2δm
dt2
d2δ m
50
It is more convenient to write the swing equation in terms of the electrical
power angle δ . If P is the number of poles of a synchronous generator, the
electrical power angle δ is related to the mechanical power angle δm by:
δ = P/2 δm -------------------------------------------------------------- (2.25)
also, ω = P/2 ωm ------------------------------------------------------------(2.26)
Swing equation in terms of electrical power angle is
2/p M d2 δ = Pm – Pe ------------------------------------------------- (2.27)
dt2
Since power system analysis is done in per unit system, the swing equation
is usually expressed in per unit. Dividing (26) by the base power Sb, and
substituting for M from (22) results in
2/P 2 W k d2 δ = Pm – Pe ---------------------------------------- (2.28)
ω sm sb dt2 Sb Sb
We now define the important quantity known as the H constant or per unit
inertia constant.
H = Kinetic energy in MJ at rated speed = W k ------------------------- (2.29)
Machine rating in MVA Sb
The unit of it is seconds. The val ue of H ranges from I to 10 seconds,
depending on the size and type of machine. Substituting in (2.28), we get
2/p 2H d2 δ = Pm(p.u) – Pe(pu) -------------------------------------- (2.30)
ωsm dt2
Where Pm(pu) and Pe(pu) are the per unit mechanical power and electrical
power, respectively. The electrical angular velocity is related to the
mechanical angular velocity by ωsm = (2/p) ωs. Writing (2.30) in terms of
electrical angular velocity is
2H d2δ = Pm(p.u) - Pe(p.u) ----------------------------------- (2.31)
ωs dt2
51
Exressing the above equation in terms of frequency fo and simplifying the
notation, the subscript p.u is omitted and the powers are understood to be in
per unit.
H d2 δ = Pm - Pe --------------------------------------------- (2.32)
πfo dt2
Where δ is in electrical radian. If δ is expressed in electrical degrees, the
swing equation becomes
H d2 (δ) = Pm - Pe ------------------------------------------ (2.33)
180fo dt2
The above equation is called the swing equation and describes the
dynamics of a generator or a motor. It is strictly a non-linear equation where
accelerated power (Pa) has a non-linear functional dependence on δ, the
internal angle of machine with respect to busbar [31], [32], and [33].
Equation (2.32) is transformed into state variable model as follows:
dδi = Δωi ---------------------------------------------------------------------------------------------- (2.34)
dt
dΔωi = πf0 (pm - pe) ------------------------------------------------ (2.35)
dt Hi
This is the two state equation for each generator, with initial
power angle δ0i, Δω0i = 0.
The MATLAB function ode 23 is employed to solve the above 2m
first order differential equation.
52
2.6.1 THE POWER-ANGLE EQUATION
In the swing equation, for generator, the input-mechanical
power from the prime mover, Pm is assured to be constant.
Considering equation (2.31) Pm is constant and the electrical power
output Pe will be determined whether rotor accelerates, decelerates, or
remains at synchronous speed. When Pe changes from this value, the
rotor deviates from synchronous speed; when Pe equals Pm the
machine operates at steady-state synchronous speed. Changes in Pe are
deter mined by conditions on the transmission and distribution
networks, the loads on the system to which the generator supplies
power. Electrical network disturbance resulting from severe load
changes, network faults, or circuit breaker operations may cause the
generator out-put Pe to change rapidly in which case
electromechanically transients exists. Each synchronous machine is
represented for transient stability studies by its transient internal
voltage E; in senses with the transient reactance X1d, as show in figure
2.26 in which Vt is the terminal voltage.
2.6.2 TRANSIENT AND SUBTRANSIENT EFFECTS
When a fault occurs in a power system networks, the current
flowing is deter mined by the internal e.m.f of the machines in the
network; by their impedances, and by the impedances in the network
between the machines and the fault. The current flowing in a
synchronous machine immediately after the occurrence of a fault
differs from that flowing a few cycles later and from the sustained or
steady-state value of the fault current. This is because of the effect of
53
the fault current in the armature on the flux generating the voltage in
the machine. The current changes relatively slowly from its initial
value to its steady-state value owing to the changes in reactance of the
synchronous machine [31], [32], [33].
Figure 2.6: Circuit diagram of a synchronous machine for stability
studies.
2.7 EQUAL AREA CRITERION
To determine whether a power system is stable after a
disturbance, it is necessary, in general, to plot and to inspect the swing
curves. If these curves show that the angle between any two machines
tends to increase without limit, the system, of course is unstable. If,
on the other hand, after all disturbances, the angle reaches a maximum
and then diminishes, it is probable, although not certain, that the
system is stable.
jX1
d
+
Ei
-
Vt
i
54
Considering the swing equation below
M δ 2 = Pa = Pm - Pe ------------------------------------------ (2.34)
dt2
Where M is the inertia constant of the finite machine and δ is the
angular displacement of this machine with respect to infinite bus.
Multiplying each member of the equation by 2d δ
Mdt
gives:
M d2 δ . 2 d δ = Pa . 2d δ ------------------------------------- (2.35)
dt2 Mdt Mdt
Simplifying (34) gives
2 d2 δ . d δ = 2 . Pa . d δ
dt2 dt M dt
or
d dδ 2 = 2 . Pa . d δ ----------------------------- (2.36)
dt dt 2 M dt
Multiplying both sides of (2.36) by dt we obtain differential instead of
derivatives
d d δ 2 = P a d δ--------------------------------------- (2.37)
dt M
Integrating equation (2.37) gives:
55
d δ 2 = 1/m ∫ Pa . d δ
dt
d δ = ω = 1/m ∫ pa.dδ -------------------- 2.38)
dt
Where δo is the initial rotor angle before it begins to swing due to
disturbance.
When machine comes to rest with respect to the infinite bus, ω
becomes zero (ω = 0)
1/m ∫ Pa . d δ = 0
or
∫ pa.dδ= 0--------------------------- (2.39)
δm
δo
δm
δo
1/2
δm
δo
1/2 δm
δo
56
The integral is the area under a curve of Pa plotted against δ between
limits δo, the initial angle, and δm, the final angle.
Since Pa = Pm –Pe, the integral may be interpreted also as the area between
the curve of Pm versus δ. the curve of Pm versus δ is a horizontal line, since
Pm is assumed to be constant. The curve of Pe versus δ is known as a power
angle curve and it is a sinusoidal if the network is linear and if the machine
is represented by a constant reactance.
58
Figure 2.8: plot of δ versus time for stable and unstable systems
The area, to be equal to zero must consist of a positive portion A1, for which
Pm > Pe, and an equal and opposite negative portion A2, for which Pm < Pe.
For a stable system, indication of stability will be given by observation of
the first swing where δ will go to a maximum and start to reduce. The
system is stable if at sometime d δ = 0 and
t
Unstable
dδ = 0
dt
Stable
δ
δmax
59
dt
is Unstable , if d δ
dt
The equal – area criterion cannot be used directly in multimachine
systems because the complexity of the numerical computations increases
with the number of machines considered in a transient stability study. When
a multi-machine system operates under electromechanical transient
conditions, inter-machine Oscillations occur through the medium of the
transmission system connecting the machines.
P1 = E1
2 G11 + E
11 E
12 Y12 Cos (δ 1 – δ2 -θ12) -------------------- (2.40)
Q1 = - E1
2 B11 + E
11 E
12 Y12 Sin (δ 1 – δ 2 -θ12) -------------------- (2.41)
Letting δ = δ 1 – δ 2 ---------------------------------------------------- (2.42)
and
defining a new angle which is temperature dependent such that
= θ12 - π/2 -------------------------------------------------------------- (2.43)
Therefore θ12 = +
Equations (2.40) & (2.41) give or transformed into the following:
P1 = E1
1 2 G11 + E
11 E
12 Y12 Sin (δ- - )- --------------------------- (2.44)
Q1 = - E1
1 2 B11 - E
11 E
12 Y12 Cos (δ- )--------------------------- (2.45)
> 0 (for a Sufficiently longtime, say one second).
60
Equations (43) can be written more simply as:
Pe = Pc + Pmax Sin (δ - ) -------------------------------------------- (2.46)
Where, Pc = E1
1 2 G11 and
Pmax = E1
1 E1
2 Y12
The parameters Pc, Pmax and are constants for a given network
configuration and constant voltage magnitudes E1
1 and E12 . When the
network is considered without resistance, all the elements of Ybus are
susceptance and G11 and are both zero. The power-angle equation which
then applies for the pure reactance network is simply the familiar equation
shown below.
Pe = Pmax Sin δ ----------------------------------------------------------------- (2.47)
Where Pmax = E1
1 E1
2 and
X
X is the transfer reactance between E11 and E
12. The in-phase component of
the admittance is the conductance G, and the quadrant component is the
susceptance [34, 35, 36].
Modern excitation systems employing thyristor controls can respond
rapidly to bus – voltage reduction and can affect from 0.5 to 1.5 cycles gain
in critical clearing times for three phase faults on the high side bus of the
generator step-up transformer. Modern electrohydraulic turbine governing
systems have the ability to close turbine valves to reduce unit acceleration
during severe system faults near the unit. A gain of 1 to 2 cycles in critical
clearing time can be achieved.
61
Reducing the reactance of the system during fault conditions increases Pmax
and decreases the acceleration area. Reducing the reactance of a
transmission line is another way of raising Pmax. Compensating for line
reactance by series capacitors is often an economical means of increasing
stability. Increasing the number of parallel lines between two points is a
common means of reducing reactance. When parallel transmission lines are
used instead of a single line, some power is transferred over the remaining
line even during a three-phase fault on one of the lines unless the fault
occurs at a paralleling bus. For more than two lines in parallel the power
transferred during the fault is even greater. Thus, the more power is
transferred into the system during a fault, the lower the acceleration of the
machine rotor and the greater the degree of stability [34] - [36].
62
2.8 MULTIMACHINE DYNAMIC MODEL
There is probably more literature on synchronous machines
than any other devices in-electrical engineering. Unfortunately, this
vast amount of material often makes the subject complex and
confusing.
In addition, most of the work on reduced order modeling is
based primarily on physical intuition, practical experience, and years
of experimentation. This model considers many synchronous
machines interconnected by transformers and transmission lines.
Here, loads are considered balanced symmetrical R-L elements. For
symbol notation, we have the followings:-
m = number of synchronous machines (if there is an infinite
bus, it is machine number 1).
n = number of system three-phase buses (excluding the datum
or reference bus).
b = total number of machines plus transformers plus lines plus
load (total branches).
63
PLm+1 (Vm+1) +
jQLm+1 (Vm+1) +
-
+
-
PLi (Vi) +
jQLi (Vi)
Network
I= YN V
m+1
PLn (Vn) + jQLn (Vn)
PLm (Vm) +
jQLm Vm
m
i
2.8.1 INTERCONNECTION OF SYNCHRONOUS MACHINE
DYNAMIC CIRCUIT AND THE REST OF THE NETWORK
Jx1
di Rsi
Jx1
dm Rsm
n
Figure: 2.9: Synchronous machine and the rest of the network
(Idi + jIqi) ej(δi -
π/2) = IGie
jγi = IDi + jIQi
64
2.8.2 NETWORK EQUATIONS
The network equations written at n buses are in complex form.
Network equations are represented as:
i GENERATOR BUSES
Vi ejθi
(Idi – jIqi) e-j(δi -
π/2) + PLi(Vi) + jQLi(Vi)
= n
ViVk Yik ej (θi - θk - ik)
k = 1 i = 1, ------------, m
---------------(2.48)
ii LOAD BUSES
PLi(Vi) + jQLi(Vi) = n
ViVk Yik ej (θi - θk - ik)
k = 1 ------------------------------ (2.49)
i = m + 1, ---------, n
In equation (47)
Vi ejθi
(Idi – jIqi) e-j(δi -
π/2)
PGi + jQGi
and it is the complex power “Injected” into bus i due to the generator.
Equations (2.47) and (2.48) represent the real and reactive power
balance equation at the n buses [19],[ 34], [35],[ 36].
65
2.9 POWER FLOW SOLUTION
Power flow studies, commonly known as load flow, form an important
part of power system analysis.
In solving a power flow problem, the system is assumed to be
operating under balanced conditions. Four quantities are associated with
each bus. These are voltage magnitude /V/, phase angle δ, real power P,
and reactive power Q. The system buses are generally classified into
three types, namely:
(i) Slack bus:- This is taken as reference bus where the
magnitude and phase angle of the voltage are specified. This
bus makes up the difference between the scheduled loads and
generated power that are caused by the losses in the network.
The bus is known by other names such as, reference bus, swing
bus, etc.
(ii) Load buses:- At these buses the active and reactive powers
are specified. The magnitude and the phase angle of the bus
voltages are unknown. These buses are called P-Q buses.
(iii ) Regulated buses:- These buses are the generator buses. They
are also known as voltage controlled buses. At these buses, the real
power and voltage magnitude are specified. The phase angles of the
voltages and the reactive power are to be determined. The limits on
the value of the reactive power are also specified. These buses are
called P-V buses [37]- [40].
66
2.9.1 POWER FLOW EQUATION
Consider a typical bus of power system shown in figure 2.10 below.
Vi
yi1 V1
yi2 V2
Ii
yin Vn
yio
Figure : 2.10: A typical bus of the power system.
Ii = yioVi + yi1(Vi - V1) + y12(Vi - V2) + ……+ yin(Vi - Vn)
=(yio + yi1 + yi2 + …….+ yin)Vi - yi1V1 – yi2V2 -------yinVn ----------- (2.50)
Equation (2.51) can be written as
Ii = Vi Σyij - ΣyijVj -------------------------------------------------- (2.51)
The real and reactive power @ bus i is
pi + jQi = ViIi* ---------------------------------------------------------------------------------------------------------- (2.52)
n
J=0
n
J=1
67
or
Ii = pi + jQi ------------------------------------------------------------------------------------------------------------ (2.53)
Vi*
Substituting for Ii in Equation (51) yields
pi + jQi = Vi Σyij - ΣyijVj ----------------------------------- (2.54)
Vi*
n
n
68
CHAPTER THREE
Data Analysis and Simulation
3.1 PROJECT DESIGN
The quality of life in any country is highly dependent on
a reliable electricity supply. In Nigeria, the electricity supply authority
is unable in most cases to meet up with a reliable and efficient power
supply to its consumers. The epileptic nature of the supply has led to
low economic growth and dissatisfaction among the citizenry.
As the size and complexity of electric power system increase
because of pressing economics and population, the desire to predict
system behaviour more accurately will also increase. The digital
computer has given the engineers the ability to predict in situations
where complexity would have been two great before.
For multi-machine system like that of Nigerian power system,
synchronism poses a great problem, when a machine or generator is
out of synchronism within an electric power system. This affects the
quality of supply to the consumers if it does not cause total collapse of
such a system. These undesirable occurrences usually cause a great
loss of revenue to the supplying authority and hardship to consumers
because of the inability of the system to fulfill requirement of its
customers. The undesirable factor of instability can be eliminated by
carrying out the stability studies of the system so that the transient
stability limit of the system loading can be determined.
69
Short circuit studies and load flow studies are carried out. These
results are used in the stability analysis.
3.2 DATA SOURCES
Power holding company Plc. 330KV electrical network single
Line diagram is used for this study. The generators, transmission
lines and transformer parameters are taken from the most up-to-date
data from National control centre, Oshogbo System Planning unit and
system operations department. The subtransient reactance X11
of the
synchronous machines is used to give maximum fault levels at the
instant of fault.
In a station where the number of machines is more than one, the
machines are represented with a single unit by paralleling transient
reactance and adding Inertia.
Line data for the equivalent system are used which contains a
complex tap ratio.
There are two types of bus bars namely:
i) Load bus bar
ii) Generator bus bar
iii) At each bus bar the voltage is assumed to be (1.0 + j0.0)
70
3.3 DATA ANALYSIS TECHNIQUE
The tool used for the data analysis is MAT-LAB software
package. MAT-LAB is a matrix-based software package, with its
extensive numerical resources, it can be used to obtain numerical
solutions that involve various types of vector-matrix-operations. My
choice of mat-lab for this work is as result of it’s high
performance COMPUTATION and VISUALIZATION. The
combination of analysis capabilities, flexibilities, reliability and
powerful graphics makes MAT-LAB the premier software
package for engineers and scientists.
3.4 MULTIMACHINE TRANSIENT STABILITY WITH MAT-LAB
SOFTWARE PACKAGE
The classical transient stability study is based on the application
of a three-phase fault. A solid three-phase fault at bus k in the network
results in Vk = 0. This is simulated by removing admittance matrix.
The new bus admittance matrix is reduced by eliminating all nodes
except the internal generator modes.
The generator excitation voltages during the fault and post fault
modes are assumed to remain constant.
The Electrical power of the ith generator in terms of the new
reduced bus admittance machines are obtained from the equation (43)
The swing equation with damping neglected is given as:
Hi d2δi = Pmi - m Ei
1 Ej
1 Yij Sin (δi - ) ------------ (3.1)
πfo dt2
j = 1
71
Where Yij are the elements of the faulted reduced bus admittance matrix, and
Hi is the inertia constant of machine i expressed on the common MVA base
SB. If HGi is the inertia constant of the machine i expressed on the machine
rated MVA SGi, then:
Hi is given as:
Hi = SGi HGi ------------------------------------------------------------ (3.2)
SB
Representing the electrical power of the ith generator by P
fe and transforming
equation (49) into state variable model yields:
dδi = ωi -------------------------------------------------------- (3.3)
dt
d ωi = fo (Pm - Pfe) --------------------------------------- (3.4)
dt Hi
i = 1-------------m
There are two state equation for each generator, with initial power
angle δo, ωoi = 0.
The mat lab function Ode 23 is employed to solve the above 2 – machine
first order differential equation.
When the fault is cleared, which may involve the removal of the
faulty line, the bus admittance matrix is recomputed to reflect the change in
the network.
Furthermore, the post fault reduced bus admittance matrix is evaluated
and the post fault Electrical Power of the ith generator shown by Pi
pf is
readily determined from equation (43).
72
Using the post fault power Pipf
, the simulation is continued to
determine the system stability, until the plots reveal a definite trend as to
stability or instability. Usually, the slack generator is selected as the
reference, and the phase angle difference of all other generators with respect
to the reference machine are plotted. Usually, the solution is carried out for
two swings to slow that the second is not greater than the first one.
If the angle differences do not increase, the system is stable but if any
of the angle differences increase indefinitely, the system is unstable.
Based on the procedure, a program named trstab is developed for the
transient stability analysis of a multi-machine network subjected to a
balanced three-phase fault. The program trstab must be preceded by the
power flow program. Ifnewton power flow program is used for this work.
In addition to the power flow data, generator data must be specified in
a matrix named gendata. The first column contains the generator bus
number terminal. Column 2 and 3 contain resistance and transient reactance
in per unit on the specified common MVA base. The program trstab
automatically adds additional buses to include the generator impedances in
the power flow line data.
Also, the bus admittance matrix is modified to include the load
admittances y load, returned by the power flow program. The program
prompts the user to enter the faulted bus number, fault clearing time, and the
line number of the removed faulty line.
The program displays the prefault, faulted, and post fault reduced bus
admittances matrices. The machine phase angles are tabulated and a plot of
the swing curves is obtained. The program inquires for other fault clearing
times and fault locations [3], [33], [38].
73
3.6 ASSUMPTIONS MADE FOR THIS WORK
1. Each synchronous machine is represented by a constant voltage source
behind the direct axis transient reactance. This representation neglects the
effect of saliency and assumes constant flux linkages.
2. The governor’s actions are neglected and the input powers are assumed
to remain constant during the entire period of simulation.
3. Using the prefault bus voltages, all loads are converted to equivalent
admittance to the ground and are assumed to remain constant.
4. Damping or asynchronous powers are ignored
5. The mechanical rotor angle of each machine coincides with the angle of
the voltage behind the machine reactance.
6. Machines belonging to the same station swing together and are said to be
coherent. A group of coherent machines is represented by one equivalent
machine.
3.7 PERFORMANCE OF PROTECTIVE RELAYING
Protective relays detect the existence of abnormal system
conditions by monitoring appropriate system quantities, determine
which circuit breakers should be opened, and energize trip circuits of
those breakers. In order to perform their functions satisfactorily,
relays should satisfy three basic requirements: selectivity, speed and
reliability.
Since transient stability is concerned with the ability of the
power system to maintain synchronism when subjected to a severe
disturbance, satisfactory performance of certain protection system is
of paramount importance in ensuring system stability.
Protective relays must be able to distinguish among fault
conditions, stable power swings and out-of-step condition. While the
74
relays should initiate circuit-breaker operations to clear faulted
elements, it is important to ensure that there are no further relaying
operations that cause unnecessary opening of unfaulted elements
during stable power swings. Tripping of unfaulted element would
weaken the system further and could lead to system instability.
One of the important aspects of transient stability analysis is the
evaluation of the performance of protective systems during the
transient period, particularly the performance of relaying used for
protection of transmission lines and generators [38].
3.7.1 FAULT – CLEARING TIMES
The critical clearing time is the maximum elapsed time from the
initiation of fault until its isolation such that the power system is
transiently stable.
The removal of a faulted element requires a protective relay
system to detect that a fault has occurred and to initiate the opening of
circuit breakers which will isolate the faulted element from the
system.. The total fault-clearing time is, therefore, made up of the
relay time and breaker-interrupting time. The relay time is the time
from the initiation of the short-circuit current to the initiation of the
trip signal to the circuit breaker. The interrupting time is the time from
initiation of the trip signal to the interruption of the current through
the breaker.
On High voltage (HV) and Extra-high voltage (EHV)
transmission systems, the normal relay times range from 15 to 30ms
(1 to 2 cycles) and circuit breaker interrupting times range from 30 to
40ms (2 to 2.5 cycles). [34]
75
3.7.2 FACTORS INFLUENCING TRANSIENT STABILITY
Transient stability of the generator is dependent on the
following:
i How heavily the generator is loaded.
ii The generator output during the fault. This depends on the fault
location and type.
iii The fault- clearing time.
iv The post fault transmission system reactance.
v The generator reactance. A lower reactance increases peak power
and reduces initial rotor angle.
vi The generator inertia. The higher the inertia, the slower the rate of
change in angle. This reduces the Kinetic energy gained during
fault ie, area A1 is reduced.
vii The generator internal voltage magnitude ( E ).
This depends on the field excitation.
viii The infinite bus voltage magnitude EB [37], [38]
76
3.8 DATA FOR THE WORK
The data for this work is obtained from the up to date records of the
power Holding company of nigerian's National Control Centre, Oshogbo.
The departments visited inlude:
(1) system planing.
(2) system operations.
(3) SCADA sections.
( 4) Protection division.
Verbal interaction was also carried out with the most senior and principal
Engineers of the departments. These Data are shown below:
TABLE 3.1 LOAD DATA
LOAD DATA
BUS NO LOAD
MW MVar
1 00.00 00.00
2 40.00 - 10.00
3 00.00 00.00
4 140.00 30.00
5 90.00 30.00
6 160.00 70.00
7 00.00 00.00
8 130.00 70.00
9 300.00 90.00
10 210.00 40.00
77
11 00.00 00.00
12 50.00 -20.00
13 100.00 -30.00
14 120.00 60.00
15 500.00 50.00
16 250.00 43.00
17 70.00 38.00
18 00.00 00.00
19 200.00 55.00
20 150.00 35.00
21 00.00 00.00
22 00.00 00.00
23 300.00 45.00
24 00.00 00.00
25 100.00 58.00
26 00.00 00.00
27 00.00 00.00
28 00.00 00.00
29 120.00 80.00
30 130.00 -78.00
31 00.00 00.00
32 200.00 67.00
33 00.00 00.00
34 00.00 00.00
78
TABLE 3.2 GENERATION SCHEDULE
Bus
No
Voltage Magnitude Generation MW MVar Limits
Min Max
1 1.06 00.00 0 0
2 1.0 00.00 0 0
3 1.04 300.00 0 110
4 1.0 00.00 0 0
5 1.0 00.00 0 0
6 1.04 20.00 0 0
7 1.0 400.00 0 140
8 1.0 00.00 0 0
9 1.0 00.00 0 0
10 1.02 00.00 0 0
11 1.0 150.00 0 114
12 1.0 00.00 0 0
13 1.0 00.00 0 0
14 1.0 00.00 0 0
15 1.0 000.00 0 0
16 1.0 00.00 0 0
17 1.0 00.00 0 0
18 1.03 280.00 0 100
19 1.0 00.00 0 0
20 1.0 00.00 0 0
21 1.02 240.00 0 104
22 1.05 700.00 0 108
23 1.0 00.00 0 0
24 1.04 180.00 0 132
79
25 1.0 00.00 0 0
26 1.01 190.00 0 126
27 1.03 150.00 0 100
28 1.02 130.00 0 150
29 1.0 00.00 0 0
30 1.0 00.00 0 0
31 1.03 150.00 0 100
32 1.0 00.00 0 146
33 1.04 200.00 0 140
34 1.02 300.00 0 125
TABLE 3.3: MACHINES AND SYSTEM VARS
Bus No Machine Vars System Injected Vars
1 00.00 0
2 00.00 0
3 40.00 0
4 00.00 0
5 00.00 0
6 00.00 0
7 60.00 0
8 00.00 0
9 00.00 0
10 00.00 0
11 50.00 0
12 00.00 0
13 00.00 0
14 00.00 0
15 00.00 0
80
16 00.00 0
17 00.00 0
18 45.00 0
19 00.00 0
20 00.00 0
21 55.00 0
22 68.00 0
23 00.00 0
24 00.00 0
25 00.00 0
26 -35.00 0
27 51.00 0
28 80.00 0
29 00.00 0
30 00.00 0
31 00.00 0
32 00.00 0
33 59.00 0
34 65.00 0
TABLE 3.4: LINE DATA
Bus No Bus No R (P.U) X (P.U) B( P.U) TRANSFORMER
TAP SETTING
PER UNITY
1 2 0.0121836 0.0916336 1.21 1.0
1 4 0.0015918 0.0119716 0.31 1.0
3 4 0.0001572 0.0094178 0.00 1.0
4 5 0.0047827 0.0360219 0.09 1.0
4 9 0.0020565 0.0154692 0.07 1.0
5 6 0.0018864 0.0141884 0.36 1.0
5 7 0.0003144 0.0188355 0.00 1.0
5 10 0.0018864 0.0141884 0.37 1.0
8 9 0.0053843 0.0404961 0.33 1.0
8 15 0.0053343 0.0405651 0.45 1.0
9 15 0.0065432 0.0426547 0.55 1.0
9 16 0.0098648 0.0741936 0.98 1.0
10 13 0.0090394 0.0679862 0.52 1.0
81
10 14 0.0077425 0.0582316 0.77 1.0
11 15 0.0020643 0.0103951 0.31 1.0
12 15 0.0040534 0.0305160 0.41 1.0
14 17 0.0104150 0.0783319 0.01 1.0
15 16 0.0110045 0.0827653 0.09 1.0
15 20 0.0003527 0.0026574 0.05 1.0
15 21 0.0055023 0.0413829 0.35 1.0
15 22 0.0012184 0.0091634 0.20 1.0
16 18 0.0063843 0.0404961 0.15 1.0
16 19 0.0038336 0.0288242 0.76 1.0
16 21 0.0055023 0.0413829 0.55 1.0
16 23 0.0053843 0.0404961 0.38 1.0
16 24 0.0009826 0.0073898 0.19 1.0
18 25 0.0010218 0.0076553 0.10 1.0
19 26 0.0005109 0.0038427 0.38 1.0
19 27 0.0006105 0.0038427 0.40 1.0
22 28 0.0005109 0.0036458 0.30 1.0
22 29 0.0002749 0.0020654 0.20 1.0
23 30 0.0037730 0.0283768 0.37 1.0
23 31 0.004913 0.0036949 0.09 1.0
23 32 0.00605225 0.0455212 0.02 1.0
24 25 0.0024760 0.0186223 0.24 1.0
28 29 0.0034640 0.0206114 0.30 1.0
32 33 0.0009825 0.0073898 0.09 1.0
33 34 0.0005109 0.0038427 0.30 1.0
TABLE 3.5: MACHINE DATA
GENERATOR
NUMBER
Ra(Ω)) X1d H
1 0.0020 0.0901 9.920
3 0.0080 0.3000 3.390
7 0.0240 0.3000 3.240
11 0.0036 0.2200 4.000
18 0.0020 0.1240 12.400
21 0.0036 0.2200 4.000
22 0.0040 0.3080 3.090
24 0.0030 0.1060 12.690
26 0.0061 0.3400 1.245
27 0.0036 0.3000 1.242
28 0.0051 0.2100 1.249
83
CHAPTER FOUR
4.1 EXISTING 330KV NATIONAL GRID NETWORK
1
K3R
KIJ K2J
10
RIM R2M
M2S
M6N
SIE
13
17
14
7
P4A
R5B R4B J7R
J3R 5
6
B8J
B9J
4
JIH J2H J3H
9 H2A
W2A
01W
NWIBS
W3L
W4L
11
12
20
N3J
N4J
29
E21
22
E1A 15
E11 E2A
28
M7W
21
B5M
B6W
H7B
16
ABUJA
B11J
B12J AIG A2G
19
AIS
A2S
27
26
T3H
23 30
BIT
G3B
18
G1W
25
S4w
24
S3B
S4B KIT
K2T T4A
32
33
F1A F2A MM6
8
A4J
31
Figure 4.11 Existing 330kv National grid Network Diagram.
3
2
84
4.2. SIMULATION AND DISCUSSION OF RESULTS
The classical transient stability study is based on the application of a
three-phase fault. A solid three-phase fault at bus k in the network results in
Vk = 0.
Simulations were carried out using raw data on pages 51,52,53,54,
55, & 56 respctively in MATLAB software package environment to
examine the behaviour of Nigeria 330KV power system network during
large scale disturbance and hence, determine the actual critical clearing time
and angle of the system such that the grid is transiently stable.
Egbin – Ikeja West 330KV line was faulted and removed from
the system. This is simulated for a period of 0.025 (25 milliseconds)
and was observed that the phase angle difference of all the fourteen
(14) machine increase with out limit as shown in figure 4.2 until the
fault was cleared at 0.025 seconds as shown in figure 4.3. The
simulation is continued until the Critical Clearing time and angle are
Obtained as shown in figures 4.4, 4.5, 4.6, 4.7, 4.8, 4.9, 4.10 and 4.11
respectively. It was observed that the phases angle difference, after
reaching a maximum, start to decrease and the machines regain their
synchronism and start swinging together in unison.
85
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.50
1
2
3
4
5
6
7
Time[s]
Roto
r angle
[radii]]
GENERATORS SWING DURING FAULT FOR 0.025 SECONDS
KG
JG
SG
OG
DG
OMG
EG
SAG
GG
AG
AEG
OKG
AFG
OMKG
Figure 4.2 : Plot of rotor angle against time
86
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7-1
-0.5
0
0.5
1
1.5
2
Time[s]
Roto
r angle
[radii]]
System fault cleared @ 0.025seconds
KG
JG
SG
OG
DG
OMG
EG
SAG
GG
AG
AEG
OKG
AFG
OMKG
Figure 4.3: Plot of rotor angle against time
87
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -1
-0.5
0
0.5
1
1.5
2
Time[s]
Rotor angle[radii]]
System fault cleared @ 0.030 seconds
KG JG SG OG DG OMG EG SAG GG AG AEG OKG AFG OMKG
Figure 4.4: Plot of rotor angle against time
88
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7-1.5
-1
-0.5
0
0.5
1
1.5
2
Time[s]
R
otor angle
[radii]]
System fault cleared @ 0.035 seconds
KG
JG
SG
OG
DG
OMG
EG
SAG
GG
AG
AEG
OKG
AFG
OMKG
Figure 4.5: Plot of rotor angle against time
89
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -1
-0.5
0
0.5
1
1.5
2
Time[s]
Rotor angle [radii]]
System fault cleared @ 0.040seconds
KG JG SG OG DG OMG EG SAG GG AG AEG OKG AFG OMKG
Figure 4.6: Plot of rotor angle against time
90
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -2
-1.5
-1
-0.5
0
0.5
1
1.5
2
2.5
Time[s]
Rotor angle [radii]]
System generators swinging in synchronism after the fault clearing time of 0.045 seconds
Figure 4.7: Plot of rotor angle against time
KG JG SG OG DG OMG EG SAG GG AG AEG OKG AFG OMKG
91
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -2
0
2
4
6
8
10
12
14
Time[s]
Rotor ange[radii]]
faulted machine 6 removed @ clearing time of 0.050 seconds
Figure 4.8: Plot of angle against time
KG JG SG OG DG OMG EG SAG GG AG AEG OKG AFG OMKG
92
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -3
-2
-1
0
1
2
3
Time[s]
Rotor angle[radii]]
System fault cleared @ 0.055 seconds after faulted machine 6 has been removed from the System
KG JG SG OG DG EG SAG GG AG AEG OKG AFG OMKG
Figure 4.9: Plot of angle against time
93
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -10
0
10
20
30
40
50
Time[s]
Rotor angle [radii]]
Faulted machine 11 removed @ 0.060 seconds which is the critical clearing time of the system
Figure 4.10: Plot of rotor angle against time
KG JG SG OG DG OMG EG SAG GG AG AEG OKG AFG OMKG
94
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 -1
-0.5
0
0.5
1
1.5
2
2.5
Time[s]
Rotor angle[radii]]
Healthy System after faults have been completely removed @ 0.065 seconds
Figure 4.11: Plot of rotor angle against time
KG JG SG OG DG EG SAG GG AG AEG AFG OMKG
95
The simulations were repeated for fault clearing times of
0.030s, 0.035s, 0.040s, 0.045s, 0.050s, 0.055s & 0.065s. It was
observed that at 0.050s, faulted machine six (6) was removed from
the system. At the fault clearing time of 0.060s, faulted machine 11
was removed from the rest of the other generators in the system.
Simulation was continued, system generators continue to swing
in synchronism after machines 6 and 11 were removed from the
system.
The critical clearing time of the system is 0.060s and the
corresponding clearing angle is 2.5 radii or 143.20 in degree. This
fault clearing time is used to predict the entire Nigerian 330KV grid
network since the Egbin – Ikeja West 330KV line is the one of the
heaviest feeder in the national grid.
The PHCN protection Engineers need to set their relay and
circuit breaker operating time at 0.060s or less such that the entire
network will be transiently stable after the occurrence of a fault
thereby reducing the probability of total system collapse to the barest
minimum.
According to the annual technical report released by the
National Control Center Oshogbo, PHCN on 5th
March, 2006,
73.33% of all the system disturbances were due to the transmission
faults, mainly from Egbin – Ikeja West 330KV line.
Analysis of the events leading to the system disturbances
generally revealed inadequacy of protection schemes in the national
grid network. Some of the protection problems on the grid are
traceable to the lack of proper coordination of distance relays, failure
96
and spurious relay operations [39, 40, 41, 42, 43, 44]. This work
serves as a guide to the PHCN Protection Engineers to set their
relays and circuit breakers operating time to act at 0.060s (60
millisecond) or less in the event of a three phase fault in the grid, so
that the system regains its synchronising power fast such that the
network is transiently stable and integrity of the national grid network
maintained. Also, customer’s inconvinences are reduced to the barest
minimum.
97
Chapter Five
4.2 CONCLUSION AND RECOMMENDATIONS
In this work, a suitable critical clearing time and angle has been
achieved or obtained for Nigerian Power System so that our
system will be able to survive any severe disturbance.
PHCN protection Engineers should endeavour to set their relay
and circuit breaker operating time to clear fault at 60 milliseconds
and it's corresponding angle of 143.20 or less than this time and angle.
If this is done the incidence of power system collapse will be
minimized to the barest minimum.
The persistent system collapse in the National grid is traceable
to the inappropriate relay and circuit breakers operating time which is
higher than 120 milliseconds [41],[42]. If the system is allowed to
collapse, it takes time for the system to be revived and this leads to the
customer’s frustrations and loss in revenue to PHCN.
RECOMMENDATION: It is very important to point out here that
increasing the number of parallel lines between two points is a common
means of reducing reactance. When a parallel transmission lines are used
instead of a single line, some power is transferred over the remaining line
even during a three – phase fault on one of the lines unless the fault occurs at
a paralleling bus. Thus, the more power is transferred into the system during
a fault, the lower the acceleration of the machine rotor and the greater the
98
degree of stability, hence, a gain in critical clearing time can be achieved.
Benin – Onitsha – Alaoji 330KV line is limited by a single line contingency.
There is an urgent need to construct the second Benin – Onitsha 330KV
circuit which had been under plan for some years past [40], [41], [42]. Also,
construction of the proposed Alaoji – New Heaven – Markurdi – Jos 330KV
circuit configuration should be expedited.
The results obtained from this work are used to predict the transient
stability of the entire Nigerian power system since Egbin – Ikeja West is
one of the heavily loaded 330KV line in the National grid.
99
REFERENCES
(1) W.J. Stevenson, “Elements of Power System Analysis”, 4th
Edition,
McGraw – Hill Inc, New York 1990
(2) Central Station Engineers, “Electrical Transmission and
Distribution References book”, Westinghouse Electric Corporation,
East Rittsburgh, Pennsylvania 1985.
(3) G. Gross, “A tool for the comprehensive analysis of power system
dynamic stability”, IEE Transaction on power Apparatus and system
Vol. 101, No. 1, pp. 226 – 234, April, 1982.
(4) A.A Fouad and S.E. Starton, “Transient stability of a multi-
machine power system”, part 1 &
11, IEE Transaction on power systems vol. 100, No. 7, pp. 3408 –
3424, March, 1981.
(5) E.O. Okwu, “Power Distribution in Developing Economy; The
Nigerian Perspective”, Newletter of the Nigerian Society of
Engineers, Vol. No. 2, pp. 4-5 February, 2007.
(6) C.O.A. Awosope, C.C. Okoro & B.A.O. Ezeobi “An Assessment
of the stability of the fault separated Nigerian Grid”, the Nigerian
Engineer Vol. 23 No. 3, PP 75 – 91, I986.
(7) M. Ernest, Pavella & D. Ruiz – Vega, “Transient stability of power
system: A unified Approach to Assessment and control”, Kluwer
Academic Publishers, Boston, September, 2000.
100
(8) J.D. Glover and Sarma “Power System Analysis and Design”, 3rd
Edition, Wadsworth Group, Brooks Cele, a division of Thomson
learning Inc, 2002.
(9) A. Odibiyi, I.E. Davidson, M.O Kachienga and B. Manhive “
Technical loss computation and Economic Dispatch model for T &
D. System in a deregulated ESI” I.E.E.E Power Engineering Journal
Vol. 20 No 8 pp. 40 April, 2002.
(10) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 1997.
(11) National PHCN Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 1998.
(12) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 1999.
(13) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2000
(14) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2001
(15) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2002
(16) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2003
(17) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2004
(18) L.K. Kirchimayar “Economic Operation of Power Systems”
System Generation Analytical Engineering Electric Utility
Engineering Section, General Electric Company, Schenectady, New
York July, 1958.
101
(19) P.W. Sauer, “Power System Dynamics and Stability”,
Department of Electrical and Computer Engineering, University of
Illinois at Urbana – Champaign, 1998.
(20) E.O. Norinder, “A Rational Method for the step-by-step
Calculations in Power System Transient Stability Studies”. AIEE
Trans, 1955, 48, pp. 61 – 67.
(21) S.S. Sastry “Engineering Mathematics” Vol. 2, Prentice – Hall
Publishers, India, 1986.
(22) W.D. Humpage and B. Stott “Preduictor – Corrector Method of
numerical integration in digital computer analysis of Power –
System transient stability”. Proc. IEE. Vol. 112 No 8, 1965.
(23) J.F. Traub, “Interative methods for the solution of Equations”
(Prentice – Hall) 1988.
(24) Stagg and El – Abiod “Computer Methods in power system
Analysis”. (McGraw – Hill) 1980.
(25) E.W. Kimbank “Power System stability; Vol 1, Element of stability
calculations”. (John Wiley & Sons) 1975.
(26) G. Dennis, Z. Micheal and R. Cullen, (Advanced Engineering
Mathematics” 2nd
Edition, CBC publishers New Delhi India, 2000.
pp. 269 -290
(27) B.M. Weedly and B.J. Cory, “Electric Power Systems Analysis”,
Fourth Edition. 1998
(28) M.V. Deshpande “Electric Power System Design” Tata McGraw –
Hill publishing company limited New Delhi 2006.
(29) M.S. Naidu and V. Kamaraju, “High Voltage Engineering”, Third
Edition. Tata McGraw – Hill publishing company limited New
Delhi, 1995.
102
(30) S.I. Jang, M. Chulshine, C. Dae Yoon and R.C. Campbell, “A
study on Adaptive Autoreclosure scheme with real – time Transient
stability”, A journal of Electrical Engineering and Technology, Vol
1, No. 1 pp. 8 -15, 2006.
(31) V.A. Levi, J.M. Nahman and D.P. Nedic, “security modeling for
power system reliability, Evaluation”, I.E.E Transactions on Power
Systems, Vol 16, No 1, February 2001, pp. 29 – 169.
(32) H. Saadat, “Power System Analysis”, Tata McGraw – Hill
Publishing company limited New – Delhi, Milwaukee School of
Engineering 2002.
(33) J.J. Grainger and W.D. Stevenson, Jr; “Power System Analysis”
McGraw – Hill Inc. New York 1994.
(34) H. Kim and S. Hyuk Kwon, “The study of facts impacts for
probabilistic Transient stability”, A Journal of Electrical
Engineering & Technology Vol. 1, No.2, pp. 129 – 133, 2006.
(35) S. Seung Lee, S. Heekang, G. SooJang, S. Yimg Li, J. Keun
park, S.H. Moon and Y. Tae Yoon; “Damping Analysis using
I.E.E.E.S.T PSS and PSS2A PSS”, A Journal of Electrical
Engineering and Technology, Vol 1, No. 3, pp. 271 – 278, 2006.
(36) C. Mun ong, “Dynamic simulation of Electric Machinery using
Matlab/simulink”, School of Electrical and Computer Engineering
Purdue University West Lafayette, Indiana, Prentice Hall PTR 1998.
(37) P. Kundur, N.J. Balu and M.G. Lauby, “Power System stability
and control”,. McGraw – Hill, Inc. New York San Francisco
Wastington, D.C. Auckland Bogota, 1993.
(38) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2005
103
(39) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 2006.
(40) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 2007.
(41) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 2008.
(42) ALSTOM, “Protection and Automation Network Guide”.
(43) JIYODA Engineering Nigeria Limited, “Power Holding Company
of Nigeria, Power System Protection Courses” Held at National
Control Centre Oshogbo (from 12th
– 23rd
March and 28 March –
10th April, 2001)
104
APPENDIX 1
% Power flow solution by Newton-Raphson
method
ns=0; ng=0; Vm=0; delta=0; yload=0; deltad=0; nbus = length(busdata(:,1)); for k=1:nbus n=busdata(k,1); kb(n)=busdata(k,2); Vm(n)=busdata(k,3); delta(n)=busdata(k, 4); Pd(n)=busdata(k,5); Qd(n)=busdata(k,6); Pg(n)=busdata(k,7); Qg(n) =
busdata(k,8); Qmin(n)=busdata(k, 9); Qmax(n)=busdata(k, 10); Qsh(n)=busdata(k, 11); if Vm(n) <= 0 Vm(n) = 1.0; V(n) = 1 + j*0; else delta(n) = pi/180*delta(n); V(n) = Vm(n)*(cos(delta(n)) + j*sin(delta(n))); P(n)=(Pg(n)-Pd(n))/basemva; Q(n)=(Qg(n)-Qd(n)+ Qsh(n))/basemva; S(n) = P(n) + j*Q(n); end end for k=1:nbus if kb(k) == 1, ns = ns+1; else, end if kb(k) == 2 ng = ng+1; else, end ngs(k) = ng; nss(k) = ns; end Ym=abs(Ybus); t = angle(Ybus); m=2*nbus-ng-2*ns; maxerror = 1; converge=1; iter = 0; % Start of iterations clear A DC J DX while maxerror >= accuracy & iter <= maxiter % Test for max. power
mismatch for i=1:m for k=1:m A(i,k)=0; %Initializing Jacobian matrix end, end iter = iter+1; for n=1:nbus nn=n-nss(n); lm=nbus+n-ngs(n)-nss(n)-ns; J11=0; J22=0; J33=0; J44=0; for i=1:nbr if nl(i) == n | nr(i) == n if nl(i) == n, l = nr(i); end if nr(i) == n, l = nl(i); end J11=J11+ Vm(n)*Vm(l)*Ym(n,l)*sin(t(n,l)- delta(n) + delta(l)); J33=J33+ Vm(n)*Vm(l)*Ym(n,l)*cos(t(n,l)- delta(n) + delta(l)); if kb(n)~=1 J22=J22+ Vm(l)*Ym(n,l)*cos(t(n,l)- delta(n) + delta(l)); J44=J44+ Vm(l)*Ym(n,l)*sin(t(n,l)- delta(n) + delta(l)); else, end
105
if kb(n) ~= 1 & kb(l) ~=1 lk = nbus+l-ngs(l)-nss(l)-ns; ll = l -nss(l); % off diagonalelements of J1 A(nn, ll) =-Vm(n)*Vm(l)*Ym(n,l)*sin(t(n,l)- delta(n) +
delta(l)); if kb(l) == 0 % off diagonal elements of J2 A(nn, lk) =Vm(n)*Ym(n,l)*cos(t(n,l)- delta(n) +
delta(l));end if kb(n) == 0 % off diagonal elements of J3 A(lm, ll) =-Vm(n)*Vm(l)*Ym(n,l)*cos(t(n,l)-
delta(n)+delta(l)); end if kb(n) == 0 & kb(l) == 0 % off diagonal elements of
J4 A(lm, lk) =-Vm(n)*Ym(n,l)*sin(t(n,l)- delta(n) +
delta(l));end else end else , end end Pk = Vm(n)^2*Ym(n,n)*cos(t(n,n))+J33; Qk = -Vm(n)^2*Ym(n,n)*sin(t(n,n))-J11; if kb(n) == 1 P(n)=Pk; Q(n) = Qk; end % Swing bus P if kb(n) == 2 Q(n)=Qk; if Qmax(n) ~= 0 Qgc = Q(n)*basemva + Qd(n) - Qsh(n); if iter <= 7 % Between the 2th & 6th
iterations if iter > 2 % the Mvar of generator buses
are if Qgc < Qmin(n), % tested. If not within limits
Vm(n) Vm(n) = Vm(n) + 0.01; % is changed in steps of 0.01
pu to elseif Qgc > Qmax(n), % bring the generator Mvar
within Vm(n) = Vm(n) - 0.01;end % the specified limits. else, end else,end else,end end if kb(n) ~= 1 A(nn,nn) = J11; %diagonal elements of J1 DC(nn) = P(n)-Pk; end if kb(n) == 0 A(nn,lm) = 2*Vm(n)*Ym(n,n)*cos(t(n,n))+J22; %diagonal elements of
J2 A(lm,nn)= J33; %diagonal elements of J3 A(lm,lm) =-2*Vm(n)*Ym(n,n)*sin(t(n,n))-J44; %diagonal of elements
of J4 DC(lm) = Q(n)-Qk; end end
gx=A; DX=A\DC'; for n=1:nbus nn=n-nss(n); lm=nbus+n-ngs(n)-nss(n)-ns;
106
if kb(n) ~= 1 delta(n) = delta(n)+DX(nn); end if kb(n) == 0 Vm(n)=Vm(n)+DX(lm); end end maxerror=max(abs(DC)); if iter == maxiter & maxerror > accuracy fprintf('\nWARNING: Iterative solution did not converged after ') fprintf('%g', iter), fprintf(' iterations.\n\n') fprintf('Press Enter to terminate the iterations and print the
results \n') converge = 0; pause, else, end
end
if converge ~= 1 tech= (' ITERATIVE SOLUTION DID NOT CONVERGE');
else, tech=(' Newton-Raphson Power Flow Solution'); end V = Vm.*cos(delta)+j*Vm.*sin(delta); deltad=180/pi*delta; i=sqrt(-1); k=0; for n = 1:nbus if kb(n) == 1 k=k+1; S(n)= P(n)+j*Q(n); Pg(n) = P(n)*basemva + Pd(n); Qg(n) = Q(n)*basemva + Qd(n) - Qsh(n); Pgg(k)=Pg(n); Qgg(k)=Qg(n); %june 97 elseif kb(n) ==2 k=k+1; S(n)=P(n)+j*Q(n); Qg(n) = Q(n)*basemva + Qd(n) - Qsh(n); Pgg(k)=Pg(n); Qgg(k)=Qg(n); % June 1997 end yload(n) = (Pd(n)- j*Qd(n)+j*Qsh(n))/(basemva*Vm(n)^2); end busdata(:,3)=Vm'; busdata(:,4)=deltad'; Pgt = sum(Pg); Qgt = sum(Qg); Pdt = sum(Pd); Qdt = sum(Qd); Qsht =
sum(Qsh); inv(A); Vm(4); deltad(4); Vm(2)*YL(1,2) Vm(3)*gx; plot(Vm) grid on %clear A DC DX J11 J22 J33 J44 Qk delta lk ll lm %clear A DC DX J11 J22 J33 Qk delta lk ll lm
107
APPENDIX 2
% This program obtains th Bus Admittance Matrix
for power flow solution
j=sqrt(-1); i = sqrt(-1); nl = linedata(:,1); nr = linedata(:,2); R = linedata(:,3); X = linedata(:,4); Bc = j*linedata(:,5); a = linedata(:, 6); nbr=length(linedata(:,1)); nbus = max(max(nl), max(nr)); Z = R + j*X; y= ones(nbr,1)./Z; %branch admittance for n = 1:nbr if a(n) <= 0 a(n) = 1; else end Ybus=zeros(nbus,nbus); % initialize Ybus to zero % formation of the off diagonal elements for k=1:nbr; Ybus(nl(k),nr(k))=Ybus(nl(k),nr(k))-y(k)/a(k); Ybus(nr(k),nl(k))=Ybus(nl(k),nr(k)); end end % formation of the diagonal elements for n=1:nbus for k=1:nbr if nl(k)==n Ybus(n,n) = Ybus(n,n)+y(k)/(a(k)^2) + Bc(k); elseif nr(k)==n Ybus(n,n) = Ybus(n,n)+y(k) +Bc(k); else, end end end clear Pgg
108
APPENDIX 3
% This program prints the power flow solution in a
tabulated form on the screen.
%clc disp(tech) fprintf(' Maximum Power Mismatch = %g \n',
maxerror) fprintf(' No. of Iterations = %g \n\n',
iter) head =[' Bus Voltage Angle ------Load------ ---Generation---
Injected' ' No. Mag. Degree MW Mvar MW Mvar
Mvar ' '
']; disp(head) for n=1:nbus fprintf(' %5g', n), fprintf(' %7.3f', Vm(n)), fprintf(' %8.3f', deltad(n)), fprintf(' %9.3f', Pd(n)), fprintf(' %9.3f', Qd(n)), fprintf(' %9.3f', Pg(n)), fprintf(' %9.3f ', Qg(n)), fprintf(' %8.3f\n', Qsh(n)) end fprintf(' \n'), fprintf(' Total ') fprintf(' %9.3f', Pdt), fprintf(' %9.3f', Qdt), fprintf(' %9.3f', Pgt), fprintf(' %9.3f', Qgt), fprintf('
%9.3f\n\n', Qsht)
109
APPENDIX 4
% TRANSIENT STABILITY ANALYSIS OF A MULTIMACHINE
POWER SYSTEM NETWORK
f=50; %zdd=gendata(:,2)+j*gendata(:,3); ngr=gendata(:,1); %H=gendata(:,4); ngg=length(gendata(:,1)); %% for k=1:ngg zdd(ngr(k))=gendata(k, 2)+j*gendata(k,3); %H(ngr(k))=gendata(k, 4); H(k)=gendata(k,4); % new end %% for k=1:ngg I=conj(S(ngr(k)))/conj(V(ngr(k))); %Ep(ngr(k)) = V(ngr(k))+zdd(ngr(k))*I; %Pm(ngr(k))=real(S(ngr(k))); Ep(k) = V(ngr(k))+zdd(ngr(k))*I; % new Pm(k)=real(S(ngr(k))); % new
end E=abs(Ep); d0=angle(Ep); for k=1:ngg nl(nbr+k) = nbus+k;
nr(nbr+k) = gendata(k, 1);
%R(nbr+k) = gendata(k, 2); %X(nbr+k) = gendata(k, 3);
R(nbr+k) = real(zdd(ngr(k))); X(nbr+k) = imag(zdd(ngr(k)));
Bc(nbr+k) = 0; a(nbr+k) = 1.0; yload(nbus+k)=0; end nbr1=nbr; nbus1=nbus; nbrt=nbr+ngg; nbust=nbus+ngg; linedata=[nl, nr, R, X, -j*Bc, a]; [Ybus, Ybf]=ybusbf(linedata, yload, nbus1,nbust); fprintf('\nPrefault reduced bus admittance matrix \n') Ybf Y=abs(Ybf); th=angle(Ybf); Pm=zeros(1, ngg); disp([' G(i) E''(i) d0(i) Pm(i)']) for ii = 1:ngg for jj = 1:ngg Pm(ii) = Pm(ii) + E(ii)*E(jj)*Y(ii, jj)*cos(th(ii, jj)-d0(ii)+d0(jj));
110
end, fprintf(' %g', ngr(ii)), fprintf(' %8.4f',E(ii)), fprintf('
%8.4f', 180/pi*d0(ii)) fprintf(' %8.4f \n',Pm(ii)) end respfl='y'; while respfl =='y' | respfl=='Y' nf=input('Enter faulted bus No. -> '); fprintf('\nFaulted reduced bus admittance matrix\n') Ydf=ybusdf(Ybus, nbus1, nbust, nf) %Fault cleared [Yaf]=ybusaf(linedata, yload, nbus1,nbust, nbrt); fprintf('\nPostfault reduced bus admittance matrix\n') Yaf resptc='y'; while resptc =='y' | resptc=='Y' tc=input('Enter clearing time of fault in sec. tc = '); tf=input('Enter final simulation time in sec. tf = ');
111
APPENDIX 5
% This function forms the bus admittance matrix
including load admittances before fault. The
corresponding reduced bus admittance matrix is
obtained for transient stability study.
function [Ybus, Ybf] = ybusbf(linedata, yload, nbus1, nbust) global Pm f H E Y th ngg
lfybus for k=1:nbust Ybus(k,k)=Ybus(k,k)+yload(k); end YLL=Ybus(1:nbus1, 1:nbus1); YGG = Ybus(nbus1+1:nbust, nbus1+1:nbust); YLG = Ybus(1:nbus1, nbus1+1:nbust); Ybf=YGG-YLG.'*inv(YLL)*YLG;
112
APPENDIX 6
% This function forms the bus admittance matrix
including load admittances during fault. The
corresponding reduced bus admittance matrix is
obtained for transient stability study.
function Ypf=ybusdf(Ybus, nbus1, nbust, nf) global Pm f H E Y th ngg nbusf=nbust-1; Ybus(:,nf:nbusf)=Ybus(:,nf+1:nbust); Ybus(nf:nbusf,:)=Ybus(nf+1:nbust,:); YLL=Ybus(1:nbus1-1, 1:nbus1-1); YGG = Ybus(nbus1:nbusf, nbus1:nbusf); YLG = Ybus(1:nbus1-1, nbus1:nbusf); Ypf=YGG-YLG.'*inv(YLL)*YLG;
113
APPENDIX 7
% This function forms the bus admittance matrix
including load admittances after fault. The
corresponding reduced bus admittance matrix is
obtained for transient stability study.
function [Yaf]=ybusaf(linedata, yload, nbus1,nbust, nbrt); global Pm f H E Y th ngg
nl=linedata(:, 1); nr=linedata(:, 2); remove = 0; while remove ~= 1 fprintf('\nFault is cleared by opening a line. The bus to bus nos. of
the\n') fprintf('line to be removed must be entered within brackets, e.g. [5,
7]\n') fline=input('Enter the bus to bus Nos. of line to be removed -> '); nlf=fline(1); nrf=fline(2); for k=1:nbrt if nl(k)==nlf & nr(k)==nrf remove = 1; m=k; else, end end if remove ~= 1 fprintf('\nThe line to be removed does not exist in the line
data. try again.\n\n') end end linedat2(1:m-1,:)= linedata(1:m-1,:); linedat2(m:nbrt-1,:)=linedata(m+1:nbrt,:);
linedat0=linedata; linedata=linedat2; lfybus for k=1:nbust Ybus(k,k)=Ybus(k,k)+yload(k); end YLL=Ybus(1:nbus1, 1:nbus1); YGG = Ybus(nbus1+1:nbust, nbus1+1:nbust); YLG = Ybus(1:nbus1, nbus1+1:nbust); Yaf=YGG-YLG.'*inv(YLL)*YLG; linedata=linedat0;
114
APPENDIX 8
% State variable representation of the multimachine
system during fault. (for use with trstab) function xdot = dfpek(t,x) global Pm f H E Y th ngg Pe=zeros(1, ngg); for ii = 1:ngg for jj = 1:ngg Pe(ii) = Pe(ii) + E(ii)*E(jj)*Y(ii, jj)*cos(th(ii, jj)-x(ii)+x(jj)); end, end for k=1:ngg xdot(k)=x(k+ngg); xdot(k+ngg)=(pi*f)/H(k)*(Pm(k)-Pe(k)); end xdot=xdot'; % use with MATLAB 5 (remove for MATLAB 4)
115
APPENDIX 9
% State variable representation of the multimachine
system
after fault. (for use with trstab)
function xdot = afpek(t,x) global Pm f H E Y th ngg
Pe=zeros(1, ngg); for ii = 1:ngg for jj = 1:ngg Pe(ii) = Pe(ii) + E(ii)*E(jj)*Y(ii, jj)*cos(th(ii, jj)-x(ii)+x(jj)); end, end for k=1:ngg xdot(k)=x(k+ngg); xdot(k+ngg)=(pi*f)/H(k)*(Pm(k)-Pe(k)); end xdot=xdot'; % use with MATLAB 5 (remove for MATLAB 4)
116
APPENDIX 10
Plotting Program 1
f=50; a2=0; H2=30.390; Pm2=11.6670; Pc2=0; Pmax2=9.5646; % y2''=((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2-a2) t0=0 y20=(14/180)*pi dy20=0.1; h=0.005; k=1; ddy20(k)=((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y20-a2)); k1(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y20-a2)); t01(k)=t0+(h/2); y201(k)=y20+(h/2)*dy20+(k1(k)/4); k2(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y201(k)-a2)); k3(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y201(k)-a2)); t011(k)=t0+h; y2011(k)=y20+(h*dy20)+k3(k); k4(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2011(k)-a2)); P(k)=(1/3)*(k1(k)+k2(k)+k3(k)); Q(k)=(1/3)*(k1(k)+2*k2(k)+2*k3(k)+k4(k)); t(k)=t0+h; y2(k)=y20+h*dy20+P(k) yy2=(y2(k)/pi)*180; dy2(k)=dy20+(Q(k)/h); ddy2(k)=((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2(k)-a2));
for k=2:100; ddy20(k)=((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2(k-1)-a2)); k1(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2(k-1)-a2)); t01(k)=t(k-1)+(h/2); y201(k)=y2(k-1)+(h/2)*dy2(k-1)+(k1(k)/4); k2(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y201(k)-a2)); k3(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y201(k)-a2)); t011(k)=t(k-1)+h; y2011(k)=y2(k-1)+(h*dy2(k-1))+k3(k); k4(k)=(1/2)*(h)^2*((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2011(k)-a2)); P(k)=(1/3)*(k1(k)+k2(k)+k3(k)); Q(k)=(1/3)*(k1(k)+2*k2(k)+2*k3(k)+k4(k)); t(k)=t(k-1)+h y2(k)=y2(k-1)+h*dy2(k-1)+P(k) yy2=(y2(k)/pi)*180 dy2(k)=dy2(k-1)+(Q(k)/h); ddy2(k)=((pi*f)/H2)*(Pm2-Pc2-Pmax2*sin(y2(k)-a2)); end figure(1) plot(t,y2,'r') grid on
117
APPENDIX 11
Plotting Program 2
f=50; H2=9.920; a2=0; Pmax2=7.2298; P2=0.4618; % y2''=((pi*f)/H2)*(P2-Pmax2*sin(y2-a2) t0=0.060; y20=0.3075; dy20=0.1; h=0.005; k=1; ddy20(k)=((pi*f)/H2)*(P2-Pmax2*sin(y20-a2)); k1(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y20-a2)); t01(k)=t0+(h/2); y201(k)=y20+(h/2)*dy20+(k1(k)/4); k2(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y201(k)-a2)); k3(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y201(k)-a2)); t011(k)=t0+h; y2011(k)=y20+(h*dy20)+k3(k); k4(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y2011(k)-a2)); P(k)=(1/3)*(k1(k)+k2(k)+k3(k)); Q(k)=(1/3)*(k1(k)+2*k2(k)+2*k3(k)+k4(k)); t(k)=t0+h y2(k)=y20+h*dy20+P(k) yy2=(y2(k)/pi)*180; dy2(k)=dy20+(Q(k)/h); ddy2(k)=((pi*f)/H2)*(P2-Pmax2*sin(y2(k)-a2));
for k=2:100; ddy20(k)=((pi*f)/H2)*(P2-Pmax2*sin(y2(k-1)-a2)); k1(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y2(k-1)-a2)); t01(k)=t(k-1)+(h/2); y201(k)=y2(k-1)+(h/2)*dy2(k-1)+(k1(k)/4); k2(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y201(k)-a2)); k3(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y201(k)-a2)); t011(k)=t(k-1)+h; y2011(k)=y2(k-1)+(h*dy2(k-1))+k3(k); k4(k)=(1/2)*(h)^2*((pi*f)/H2)*(P2-Pmax2*sin(y2011(k)-a2)); P(k)=(1/3)*(k1(k)+k2(k)+k3(k)); Q(k)=(1/3)*(k1(k)+2*k2(k)+2*k3(k)+k4(k)); t(k)=t(k-1)+h y2(k)=y2(k-1)+h*dy2(k-1)+P(k) yy2=(y2(k)/pi)*180; dy2(k)=dy2(k-1)+(Q(k)/h); ddy2(k)=((pi*f)/H2)*(P2-Pmax2*sin(y2(k)-a2)); end figure(1) plot(t,y2,'r') grid on
193
The simulations were repeated for fault clearing times of
0.030s, 0.035s, 0.040s, 0.045s, 0.050s, 0.055s & 0.065s. It was
observed that at 0.050s, faulted machine six (6) was removed from
the system. At the fault clearing time of 0.060s, faulted machine 11
was removed from the rest of the other generators in the system.
Simulation was continued, system generators continue to swing
in synchronism after machines 6 and 11 were removed from the
system.
The critical clearing time of the system is 0.060s and the
corresponding clearing angle is 2.5 radii or 143.20 in degree. This
fault clearing time is used to predict the entire Nigerian 330KV grid
network since the Egbin – Ikeja West 330KV line is the one of the
heaviest feeder in the national grid.
The PHCN protection Engineers need to set their relay and
circuit breaker operating time at 0.060s or less such that the entire
network will be transiently stable after the occurrence of a fault
thereby reducing the probability of total system collapse to the barest
minimum.
According to the annual technical report released by the
National Control Center Oshogbo, PHCN on 5th
March, 2006,
73.33% of all the system disturbances were due to the transmission
faults, mainly from Egbin – Ikeja West 330KV line.
Analysis of the events leading to the system disturbances
generally revealed inadequacy of protection schemes in the national
grid network. Some of the protection problems on the grid are
194
traceable to the lack of proper coordination of distance relays, failure
and spurious relay operations [39, 40, 41, 42, 43, 44]. This work
serves as a guide to the PHCN Protection Engineers to set their
relays and circuit breakers operating time to act at 0.060s (60
millisecond) or less in the event of a three phase fault in the grid, so
that the system regains its synchronising power fast such that the
network is transiently stable and integrity of the national grid network
maintained. Also, customer’s inconvinences are reduced to the barest
minimum.
195
Chapter Five
4.2 CONCLUSION AND RECOMMENDATIONS
In this work, a suitable critical clearing time and angle has been
achieved or obtained for Nigerian Power System so that our
system will be able to survive any severe disturbance.
PHCN protection Engineers should endeavour to set their relay
and circuit breaker operating time to clear fault at 60 milliseconds
and it's corresponding angle of 143.20 or less than this time and angle.
If this is done the incidence of power system collapse will be
minimized to the barest minimum.
The persistent system collapse in the National grid is traceable
to the inappropriate relay and circuit breakers operating time which is
higher than 120 milliseconds [41],[42]. If the system is allowed to
collapse, it takes time for the system to be revived and this leads to the
customer’s frustrations and loss in revenue to PHCN.
RECOMMENDATION: It is very important to point out here that
increasing the number of parallel lines between two points is a common
means of reducing reactance. When a parallel transmission lines are used
instead of a single line, some power is transferred over the remaining line
even during a three – phase fault on one of the lines unless the fault occurs at
a paralleling bus. Thus, the more power is transferred into the system during
a fault, the lower the acceleration of the machine rotor and the greater the
196
degree of stability, hence, a gain in critical clearing time can be achieved.
Benin – Onitsha – Alaoji 330KV line is limited by a single line contingency.
There is an urgent need to construct the second Benin – Onitsha 330KV
circuit which had been under plan for some years past [40], [41], [42]. Also,
construction of the proposed Alaoji – New Heaven – Markurdi – Jos 330KV
circuit configuration should be expedited.
The results obtained from this work are used to predict the transient
stability of the entire Nigerian power system since Egbin – Ikeja West is
one of the heavily loaded 330KV line in the National grid.
197
REFERENCES
(44) W.J. Stevenson, “Elements of Power System Analysis”, 4th
Edition,
McGraw – Hill Inc, New York 1990
(45) Central Station Engineers, “Electrical Transmission and
Distribution References book”, Westinghouse Electric Corporation,
East Rittsburgh, Pennsylvania 1985.
(46) G. Gross, “A tool for the comprehensive analysis of power system
dynamic stability”, IEE Transaction on power Apparatus and system
Vol. 101, No. 1, pp. 226 – 234, April, 1982.
(47) A.A Fouad and S.E. Starton, “Transient stability of a multi-
machine power system”, part 1 &
11, IEE Transaction on power systems vol. 100, No. 7, pp. 3408 –
3424, March, 1981.
198
(48) E.O. Okwu, “Power Distribution in Developing Economy; The
Nigerian Perspective”, Newletter of the Nigerian Society of
Engineers, Vol. No. 2, pp. 4-5 February, 2007.
(49) C.O.A. Awosope, C.C. Okoro & B.A.O. Ezeobi “An Assessment
of the stability of the fault separated Nigerian Grid”, the Nigerian
Engineer Vol. 23 No. 3, PP 75 – 91, I986.
(50) M. Ernest, Pavella & D. Ruiz – Vega, “Transient stability of power
system: A unified Approach to Assessment and control”, Kluwer
Academic Publishers, Boston, September, 2000.
(51) J.D. Glover and Sarma “Power System Analysis and Design”, 3rd
Edition, Wadsworth Group, Brooks Cele, a division of Thomson
learning Inc, 2002.
(52) A. Odibiyi, I.E. Davidson, M.O Kachienga and B. Manhive “
Technical loss computation and Economic Dispatch model for T &
D. System in a deregulated ESI” I.E.E.E Power Engineering Journal
Vol. 20 No 8 pp. 40 April, 2002.
(53) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 1997.
(54) National PHCN Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 1998.
(55) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 1999.
(56) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2000
(57) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2001
(58) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2002
199
(59) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2003
(60) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2004
(61) L.K. Kirchimayar “Economic Operation of Power Systems”
System Generation Analytical Engineering Electric Utility
Engineering Section, General Electric Company, Schenectady, New
York July, 1958.
(62) P.W. Sauer, “Power System Dynamics and Stability”,
Department of Electrical and Computer Engineering, University of
Illinois at Urbana – Champaign, 1998.
(63) E.O. Norinder, “A Rational Method for the step-by-step
Calculations in Power System Transient Stability Studies”. AIEE
Trans, 1955, 48, pp. 61 – 67.
(64) S.S. Sastry “Engineering Mathematics” Vol. 2, Prentice – Hall
Publishers, India, 1986.
(65) W.D. Humpage and B. Stott “Preduictor – Corrector Method of
numerical integration in digital computer analysis of Power –
System transient stability”. Proc. IEE. Vol. 112 No 8, 1965.
(66) J.F. Traub, “Interative methods for the solution of Equations”
(Prentice – Hall) 1988.
(67) Stagg and El – Abiod “Computer Methods in power system
Analysis”. (McGraw – Hill) 1980.
(68) E.W. Kimbank “Power System stability; Vol 1, Element of stability
calculations”. (John Wiley & Sons) 1975.
(69) G. Dennis, Z. Micheal and R. Cullen, (Advanced Engineering
Mathematics” 2nd
Edition, CBC publishers New Delhi India, 2000.
pp. 269 -290
200
(70) B.M. Weedly and B.J. Cory, “Electric Power Systems Analysis”,
Fourth Edition. 1998
(71) M.V. Deshpande “Electric Power System Design” Tata McGraw –
Hill publishing company limited New Delhi 2006.
(72) M.S. Naidu and V. Kamaraju, “High Voltage Engineering”, Third
Edition. Tata McGraw – Hill publishing company limited New
Delhi, 1995.
(73) S.I. Jang, M. Chulshine, C. Dae Yoon and R.C. Campbell, “A
study on Adaptive Autoreclosure scheme with real – time Transient
stability”, A journal of Electrical Engineering and Technology, Vol
1, No. 1 pp. 8 -15, 2006.
(74) V.A. Levi, J.M. Nahman and D.P. Nedic, “security modeling for
power system reliability, Evaluation”, I.E.E Transactions on Power
Systems, Vol 16, No 1, February 2001, pp. 29 – 169.
(75) H. Saadat, “Power System Analysis”, Tata McGraw – Hill
Publishing company limited New – Delhi, Milwaukee School of
Engineering 2002.
(76) J.J. Grainger and W.D. Stevenson, Jr; “Power System Analysis”
McGraw – Hill Inc. New York 1994.
(77) H. Kim and S. Hyuk Kwon, “The study of facts impacts for
probabilistic Transient stability”, A Journal of Electrical
Engineering & Technology Vol. 1, No.2, pp. 129 – 133, 2006.
(78) S. Seung Lee, S. Heekang, G. SooJang, S. Yimg Li, J. Keun
park, S.H. Moon and Y. Tae Yoon; “Damping Analysis using
I.E.E.E.S.T PSS and PSS2A PSS”, A Journal of Electrical
Engineering and Technology, Vol 1, No. 3, pp. 271 – 278, 2006.
201
(79) C. Mun ong, “Dynamic simulation of Electric Machinery using
Matlab/simulink”, School of Electrical and Computer Engineering
Purdue University West Lafayette, Indiana, Prentice Hall PTR 1998.
(80) P. Kundur, N.J. Balu and M.G. Lauby, “Power System stability
and control”,. McGraw – Hill, Inc. New York San Francisco
Wastington, D.C. Auckland Bogota, 1993.
(81) PHCN National Control Centre Oshogbo “ Generation and
Transmission Grid Operations, Annual Technical Report 2005
(82) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 2006.
(83) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 2007.
(84) PHCN National Control Centre Oshogbo “Generation and
Transmission Grid Operations, Annual Technical Report 2008.
(85) ALSTOM, “Protection and Automation Network Guide”.
(86) JIYODA Engineering Nigeria Limited, “Power Holding Company
of Nigeria, Power System Protection Courses” Held at National
Control Centre Oshogbo (from 12th
– 23rd
March and 28 March –
10th April, 2001)