Upload
sushike
View
217
Download
0
Embed Size (px)
Citation preview
8/14/2019 Unit 14 - System Analysis UML
1/39
OOAD 1/2550 .1
Unit 14: Project Management
.
2/2550
8/14/2019 Unit 14 - System Analysis UML
2/39
OOAD 1/2550 .2
Project Management
8/14/2019 Unit 14 - System Analysis UML
3/39
OOAD 1/2550 .3
Key Definitions
Project management is the process of planning andcontrolling the development of a system within aspecified timeframe at a minimum cost with the right
functionality.
A project manager has the primary responsibility formanaging the hundreds of tasks and roles that need
to be carefully coordinated.
8/14/2019 Unit 14 - System Analysis UML
4/39
OOAD 1/2550 .4
CREATING THE WORK PLAN
8/14/2019 Unit 14 - System Analysis UML
5/39
OOAD 1/2550 .5
A Workplan ExampleWork Plan Information Example
Name of task Perform economic feasibilityStart date ` Jan 05, 2001
Completion date Jan 19, 2001Person assigned Mary Smith, sponsorDeliverable(s) Cost-benefit analysisCompletion status OpenPriority High
Resources needed SpreadsheetEstimated time 16 hoursActual time 14.5 hours
8/14/2019 Unit 14 - System Analysis UML
6/39
OOAD 1/2550 .6
Identifying Tasks
Top-down approach
Identify highest level tasks
Break them into increasingly smaller units Methodology
Using standard list of tasks
8/14/2019 Unit 14 - System Analysis UML
7/39
OOAD 1/2550 .7
Top Down TaskIdentification
Phases Phases withhigh level steps
Work Plan Deliverab les Estima ted Ac tua l Assignedhours hours To
****
8/14/2019 Unit 14 - System Analysis UML
8/39
OOAD 1/2550 .8
Estimating a Project Based on
Industry Information
Planning Ana lysis Design Implementation
Industry
Standard
For Web 15% 20% 35% 30%
Applications
Tim e
Required 4 5.33 9.33 8in Person
Months
8/14/2019 Unit 14 - System Analysis UML
9/39
OOAD 1/2550 .9
Time Estimation Using a MoreComplex Approach
8/14/2019 Unit 14 - System Analysis UML
10/39
OOAD 1/2550 .10
Estimation Trade-offs
Size
Function points
Lines of code Effort
Person-months
Time Months
8/14/2019 Unit 14 - System Analysis UML
11/39
OOAD 1/2550 .11
Getting the Right Numbers forEstimation
Prior projects
Past experience
Industry standards Detailed analysis
8/14/2019 Unit 14 - System Analysis UML
12/39
OOAD 1/2550 .12
Function Point Estimation-- Step One
Complexity
Description Low Medium High Total
Inputs __x 3 __x 4 __x 6 ____
Outputs __x 4 __x 5 __x 7 ____
Queries __x 3 __x 4 __x 6 ____
Files __x 7 __x 10 __x 15 ____
Program __x 5 __x 7 __x 10 ____ Interfaces
TOTAL UNADJUSTED FUNCTION POINTS ____
8/14/2019 Unit 14 - System Analysis UML
13/39
OOAD 1/2550 .13
Function Points Estimation
-- Step Two
Scale of 1 to 5
Data Communications _____ Heavy Use Configuration _____ Transaction Rate _____ End-User efficiency _____ Complex Processing _____
Installation Ease _____ Multiple sites _____ Performance _____ Distributed functions _____ On-line data entry _____ On-line update _____
Reusability _____ Operational Ease _____ Extensibility _____
Project Complexity (PC) _____
8/14/2019 Unit 14 - System Analysis UML
14/39
OOAD 1/2550 .14
Function Point Estimation -- Step 3
Processing Complexity (PC): ________(From Step 2)
Adjusted ProcessingComplexity (PCA) = 0.65 + (0.001 * ____ )
Total Adjusted
Function Points: _____ * ____ =(TUFP -- From Step 1)
8/14/2019 Unit 14 - System Analysis UML
15/39
OOAD 1/2550 .15
Function Points Estimation
-- Step Four
Adjusted Project Complexity
= .065 + (0.01 * Project Complexity)
Total Adjusted Function Points
=
Adjusted Project Complexity * TUFP
8/14/2019 Unit 14 - System Analysis UML
16/39
OOAD 1/2550 .16
Converting Function Points toLines of Code
Source: Capers Jones, Software Productivity Research
Language LOC/Function Code Point
CCOBOLJAVAC++
Turbo PascalVisual BasicPowerBuilderHTMLPackages
(e.g., Access, Excel)
1301105550
50301515
10-40
8/14/2019 Unit 14 - System Analysis UML
17/39
OOAD 1/2550 .17
Your Turn
It takes time and effort to produce evenrough estimates of the function points for agiven project
What would you need to make it worthwhile?
8/14/2019 Unit 14 - System Analysis UML
18/39
OOAD 1/2550 .18
Estimating Effort
Function of size and production rate
COCOMO model
8/14/2019 Unit 14 - System Analysis UML
19/39
OOAD 1/2550 .19
COCOMO Estimation Calculation
Effort = 1.4 * thousands-of-(in Person- lines-of-code
Months)
Example:
If LOC = 2000 Then...Effort = (1.4 * 2000) = 28 Person Months
8/14/2019 Unit 14 - System Analysis UML
20/39
OOAD 1/2550 .20
Estimating Schedule Time
Rule of thumb for estimation
Schedule Time (months)
=
3.0 * person-months1/3
8/14/2019 Unit 14 - System Analysis UML
21/39
OOAD 1/2550 .21
Staffing Attributes
Staffing levels will change over a projectslifetime
Adding staff may add more overhead thanadditional labor
Using teams of 8-10 reporting in a
hierarchical structure can reduce complexity
8/14/2019 Unit 14 - System Analysis UML
22/39
OOAD 1/2550 .22
Increasing Complexity with LargerTeams
8/14/2019 Unit 14 - System Analysis UML
23/39
OOAD 1/2550 .23
Timeboxing
Fixed deadline
Reduced functionality, if necessary
Fewer finishing touches
8/14/2019 Unit 14 - System Analysis UML
24/39
OOAD 1/2550 .24
Timeboxing Steps
Set delivery date
Deadline should not be impossible
Should be set by development group
Prioritize features by importance
Build the system core
Postpone unfinished functionality
Deliver the system with core functionality
Repeat steps 3-5 to add refinements and enhancemen
8/14/2019 Unit 14 - System Analysis UML
25/39
OOAD 1/2550 .25
STAFFING THE PROJECT
8/14/2019 Unit 14 - System Analysis UML
26/39
OOAD 1/2550 .26
Key Definitions
The staffing plandescribes the kinds of people working onthe project
The project charterdescribes the projects objectives and
rules A functional leadmanages a group of analysts
A technical leadoversees progress of programmers andtechnical staff members
8/14/2019 Unit 14 - System Analysis UML
27/39
OOAD 1/2550 .27
Motivation
Use monetary rewards cautiously
Use intrinsic rewards
Recognition
Achievement
The work itself
Responsibility
Advancement
Chance to learn new skills
8/14/2019 Unit 14 - System Analysis UML
28/39
OOAD 1/2550 .28
Conflict Avoidance Strategies
Clearly define roles and project plans
Hold individuals accountable
Project charter listing norms and groundrules
Develop schedule commitments ahead of time Forecast other priorities and their possible impact on the project
8/14/2019 Unit 14 - System Analysis UML
29/39
OOAD 1/2550 .29
CONTROLLING ANDDIRECTING THE PROJECT
8/14/2019 Unit 14 - System Analysis UML
30/39
OOAD 1/2550 .30
Margins of Error inCost and Time Estimates
Typ ic a l marg ins of Error forWell-done Estima tes
Phase Deliverab le Cost (%) time (%)
Planning System Request 400 60Projec t Plan 100 25
Ana lysis System Proposa l 50 15
Design System Spec ific a tion 25 10
Sourc e: Boehm et a l. (1995)
8/14/2019 Unit 14 - System Analysis UML
31/39
OOAD 1/2550 .31
Tracking Tasks Using Gantt Chart
Go to Library
Go to Bookstore
Select and Purchase Book
Skim Book
Write Phase One
Read Book Carefully
Write Phase Two
Action Week
2 3 4 5 6 7 8 9 10 11 12 13
8/14/2019 Unit 14 - System Analysis UML
32/39
OOAD 1/2550 .32
CASE Tools
Initiation Analysis Design Implementation
Upper CASE Lower CASE
Integrated CASE (I-CASE)
8/14/2019 Unit 14 - System Analysis UML
33/39
OOAD 1/2550 .33
Procedural MetadataLogic
Diagrams ScreenDesigns
CASE Repository
CASE Components
8/14/2019 Unit 14 - System Analysis UML
34/39
OOAD 1/2550 .34
Standards
Examples
Formal rules for naming files
Forms indicating goals reached
Programming guidelines
Can you think of more examples?
8/14/2019 Unit 14 - System Analysis UML
35/39
OOAD 1/2550 .35
Documentation
Project binder
Table of contents
Continual updating
8/14/2019 Unit 14 - System Analysis UML
36/39
OOAD 1/2550 .36
Managing Scope
Scope creep -- a major cause ofdevelopment problems
JAD and prototyping
Formal change approval
Charging for changes
8/14/2019 Unit 14 - System Analysis UML
37/39
OOAD 1/2550 .37
Managing Risk
Risk assessment
Actions to reduce risk
Revised assessment
8/14/2019 Unit 14 - System Analysis UML
38/39
OOAD 1/2550 .38
Classic Mistakes
Overly optimistic schedule
Failing to monitor schedule
Failing to update schedule Adding people to a late project
8/14/2019 Unit 14 - System Analysis UML
39/39
OOAD 1/2550 .39
Summary
Project management is critical to successfuldevelopment of new systems
Project management involves planning,controlling and reporting on time, labor, andcosts.