Union Square Utility andStreetscape Improvements Study and Design
April 13, 2015
Agenda
6:30-6:40 . . . . . . . IntroductionJennifer Molina, Transportation Planner, City of Somerville
6:40-6:50 . . . . . . . Overview and Project UpdateRachel Burckardt, PE, Parsons Brinckerhoff
6:50-7:20 . . . . . . . Early Action Plan: Interim DesignUtilities - Rachel Burckardt, PE, Parsons BrinckerhoffTraffic - Kristen Torrance Clarke, PE, PTOE, Parsons BrinckerhoffQ&A/Discussion
7:20-8:00 . . . . . . . Small Group DiscussionQ&A/Discussion
City of Somerville Team
Mayor Joseph A. Curtatone
Ward 2 Alderman Maryann M. Heuston
Ward 3 Alderman Robert McWattersDepartment of Public Works City EngineeringOffice of Strategic Planning & DevelopmentMichael Glavin, Executive DirectorJennifer Molina, Transportation and InfrastructureBrad Rawson, Senior Planner, Planning DivisionTraffic and Parking Department
Civic Advisory Committee
Wig Zamore, ChairmanJoe BeckmannAngelica BennattiJennifer BlundellSusan CallahanPokye CasserlyRobyn ChampionFr. Richard CurranMike DaceyErik FellingerIrma FloresGregore Jenkins
Angelina JockovichShaina Korman-HoustonChris ManciniPat McCormickErik NeuPhilip ParsonsEmily ReichertKat RutkinRebecca SchrummShu TalunAnne TateGordon Wong
The PB TeamParsons Brinckerhoff Project Management
Civil, Structural & Traffic EngineeringPublic Outreach
Team Better Block
Crosby Schlessinger Smallridge, Inc.
Toole Design Group, Inc.
Bryant Associates, Inc.
PEER Consultants, Inc.
Experiential Community Engagement
Streetscape & Urban Design
Bicycle & Pedestrian Facilities
Surveying
LSP Services
Project Overview and Update
Study Area
Project Objectives
Recognize the unique history of Union Square
Build on foundation of previous work
Coordinate with ongoing and future projects
Develop utility and transportation solutions
Integrate all modes of transportation(pedestrians, bicyclists, transit, vehicles)
Design for improvements that can be built
ScopeUtilities
Transportation
Public Space
Development Impacts
Public Outreach
Public OutreachPreliminary Streetscape Design
Nov 2013 Spring 2015
Meeting #1: Nov. 18, 2013
Meeting #2- Jan. 29, 2014
Meeting #3- March 25, 2014
Ongoing Advisory Committee Meetings/Coordination
Team Better Block Demonstration-May 30, 2014
Meeting #4-Oct. 20, 2014
Meeting #5- Jan. 8, 2015
Meeting #6- Apr. 13, 2015
Somerville by Design Survey
72% of Respondents Stated that Being Ableto Safely Bicycle Through the Square was“very important”81% of Respondents Stated that Being Ableto Safely Walk Through the Square was “veryimportant”These sentiments are reflected in the ideaspresented in this presentation
Project UpdateSurvey – CompleteSoils Investigation – Fieldwork done; draft reportpreparedTraffic counts and data – CompleteWater System Improvements – Concept completeSewer/Storm Drain Improvements – Conceptdeveloped; modeling underwayCoordination with US2 – OngoingInterim Improvements: 25% Plans Winter 2015Interim Improvements: Final Design- Spring 2015
Water System Improvements
Yellow = NewWater MainsGreen =Clean & Line(by others)
Sanitary/Storm System Improvements
SewerseparationAdded capacity& off-linestorage:Union Sq. toCMI viaSomerville Ave.
Somerville Ave. StormDrain (completed)
Early Action Plan: InterimImprovements
Early Action - Interim Improvements
Goal: Identify short-term roadwayimprovements that could be accommodatedwithin the existing curb lines
Design Completion: Spring 2015Estimated Construction Period: JulyDecember 2015Include utility work in Prospect Street
Prospect Street: Sewer & WaterNew sewer and water mainto serve MBTA station andD2 developmentNew fire hydrants
Improve Traffic Flow & Safety at SignalizedIntersections
Reduce Overall Intersection DelayReduce Circuitous Traffic Movements
• One-Way vs. Two-Way Webster + Prospect
Evaluate Turn Lanes at Intersections
Goals of Interim TransportationImprovements
Goals of Interim TransportationImprovements
Improve Pedestrian ConnectivitySignal Timing/Phasing
• Exclusive vs. Concurrent Phasing• Leading Pedestrian Interval
Goals of Interim TransportationImprovements
Improve Pedestrian ConnectivityCrosswalk Locations
• Shorten CrosswalkLocations where Possible
– Modify Alignment– Adding Bump-out
• Add any MissingPedestrian Links
Improve BicycleConnectivity
Painted Bicycle Lanes
Bike Boxes• Increase Visibility of Cyclist• Reduces Signal Delay• Facilities Left Turn Position• Helps Prevent Left Hook
Conflicts
Goals of Interim TransportationImprovements
Improve Bicycle ConnectivityTwo Stage Turn Queue Box
• Left Turn Safety• Formal Queue Space• Reduces Turning conflicts• Separates Turning &
Thru Bicyclists
Goals of Interim TransportationImprovements
Prospect/Somerville/WashingtonRecommendations from 25% DesignAdd bicycle boxes on all approachesAdd bicycle lane on Washington St NBBicycle striping thru the intersectionCrosswalk StripingSharrows on Prospect SB‘Do Not Block’ Intersection Striping onWashington Street at Municipal LotModify Turn Radius on NW CornerIncrease Leading Pedestrian Interval from 3 to 5seconds
Prospect/Somerville/WashingtonConcept
Prospect/Somerville/WashingtonSignal Operations
Webster/Somerville/WashingtonRecommendations from 25% DesignEliminate Webster NB left turn lane to allow full bicyclelane SB thru intersectionAdd bicycle boxes on all approachesBicycle lane on Somerville Avenue WB approaching theintersectionSharrows on Webster Avenue SBCrosswalk StripingModify lane alignment on Somerville Avenue WB tocreate left turn pocket with thru and right turn lanesShorten crosswalk distance on east side of intersectionIncrease Leading Pedestrian Interval from 3 to 5 seconds
Webster/Somerville/WashingtonConcept
Webster/Somerville/WashingtonSignal Operations
Webster/ProspectRecommendations from 25% Design
Add bicycle box on Webster Ave SBAdd sharrows on Webster Ave NB andProspect SBAdd bicycle facilities south of intersectionUpdate phasing to have an exclusive phasewhen crossing the north side of ProspectStreetExtend Prospect St bicycle striping intointersection
Webster/ProspectConcept
Webster/Prospect Signal Operations
Additional Recommendationsfrom 25% Design
Reduce cut thru traffic on Newton StreetTwo-way bicycle traffic on Newton StreetProvide additional safety measures formidblock crosswalk on Somerville AvenueImprove sight lines for pedestrian crosswalkon Webster Street at Newton Street
DiscussionUtilitiesProspect St. & Webster Ave.Bicycle accommodationsPedestrian crossingsConnection with Green Line StationBus stop relocations
Next StepsUtility improvements:
Advance concept plans & modeling for sewer separationEarly Action – Interim Improvements:
Finish designAdvertise for bids
Street improvements– Refine concept plansBicycle accommodationsImproved pedestrian crossingsConnection with Green Line stationBus stop relocations
Streetscape Design:Plaza alternativesStreetscape concepts
Explore Federal Funding- 2015 TIGER Grant
Contact UsJennifer MolinaCity of SomervilleTransportation [email protected] x2514