Underground Mine MappingItasca County, Minnesota
Peter Clevenstine, P.E. Manager of Engineering & Mineral Development
DisclaimerDisclaimer
The Minnesota Department of Natural Resources The Minnesota Department of Natural Resources makes no representation or warranties, express or makes no representation or warranties, express or implied, with respect to the reuse of data provided implied, with respect to the reuse of data provided herewith, regardless of its format or the means of its herewith, regardless of its format or the means of its transmission. There is no guarantee or transmission. There is no guarantee or representation to the user as to the accuracy, representation to the user as to the accuracy, currency, suitability, or reliability of this data for any currency, suitability, or reliability of this data for any purpose. The user accepts the data 'as is', and purpose. The user accepts the data 'as is', and assumes all risks associated with its use. By assumes all risks associated with its use. By accepting this data, the user agrees not to transmit accepting this data, the user agrees not to transmit this data or provide access to it or any part of it to this data or provide access to it or any part of it to another party unless the user shall include with the another party unless the user shall include with the data a copy of this disclaimer. The Minnesota data a copy of this disclaimer. The Minnesota Department of Natural Resources assumes no Department of Natural Resources assumes no responsibility for actual or consequential damage responsibility for actual or consequential damage incurred as a result of any user's reliance on this incurred as a result of any user's reliance on this data.data.
Three PhasesThree Phases
Phase 3 Work TasksPhase 3 Work Tasks Research the study areaResearch the study area Collect and organize maps of known Collect and organize maps of known
underground mine workings.underground mine workings. Scan plan maps and sectionsScan plan maps and sections Develop GIS coveragesDevelop GIS coverages Link the scanned images to specific Link the scanned images to specific
mine parcels.mine parcels. Identify other potential areasIdentify other potential areas
Phase 3 BudgetPhase 3 Budget
Category Description Cost
DNR Staff Geologist, Mining Engineer, Information Technologist
$183,000
Contract worker
Geological Scientist from NRRI 105,000
Other Equipment, supplies and travel 2,000
Total $290,000
Phase FundingPhase FundingFunding Source Phase 1 Phase 2 Phase 3
State Bonding CIRSSD)
$304,000
IRR Innovation Grant
$150,000
DNR 60,000 125,000
Private 60,000 30,000
State MN/DOT 25,000 25,000
County 0
5,000 5,000
Unfunded $105,000
Total $304,000 $300,000 $290,000
I’m asking for your I’m asking for your endorsement?endorsement?